Document No:
Chapter –3 Infra. Facilities of Diesel Loco Shed
Version No: 1.0-d0
Date Issued: dd/mm/yyyy
Document Title: MANUAL MAINTENANCE FOR DIESEL LOCOMOTIVES
Revised 2013
Printed: 2015/03/08
Page 28 of 303
(viii) More over the depot in-charge should keep watch on the trips performed by a
particular crew so that if any crew has not operated in a particular section for
about two or two and half months, such crew should be identified immediately
and booked to such section. This will avoid expiry of Road Learning of the crew.
2.10.1.8 Training as Co-LP:- It is normally a good practice to allow the newly promoted
LP to work as Co-LP for a month along with the experienced goods LP. This
helps to get the feel of driving and absorbing the driving technique by newly
promoted candidate and clarify his doubts. During this period of working as a
Co-LP, the nominated loco inspector keeps a watch on the performance of the
LP, guides and counsels him suitably.
2.10.2 System of monitoring and counseling of running staff:- The working of running
staff needs to be continuously monitored to ensure safe train operation. The running
staff, i.e., LPs / ALPs belong to a category of staff who are not available at a time on
a given workplace. In other types of working, like workshops and sheds, the work
place of the staff is definite and therefore, any instruction can be given to the staff in
a planned manner. On the contrary, the running staff, moves from one place to
another and working is round the clock, with no fixed period of duty and rest.
Therefore, giving instructions, counseling and taking the feedback on their working
becomes very difficult and cumbersome. Running staff either remains on line or
takes rest in running room / at their HQ station. Therefore, they can be counseled /
monitored only when they come for duty at the time of sign on and also during their
journey by way of foot plate inspection. The system is as under:
2.10.2.1 Categorization of LPs: On the basis of monitoring done by LI of their nominated
LPs, they will be assigned/reviewed Categories :A, B, C & D, as per Board’s
guidelines contained in letter no. 97/Safety-I/23/15 dated 29/03/2007.
2.10.2.2 Monitoring and counseling by Loco Inspector:
a) Division has certain number of loco inspectors. Each loco inspector should be
allotted 15 LPs. These nominated LPs are monitored and counseled by loco
inspector during their foot plate inspection and their visit to lobbies. The
periodicity of monitoring of the LP as per their category is: ‘A’ are once in 2
months, ‘B’ once in a month and ‘C’ once in a fortnight by their nominated loco
inspector. Monitoring should include both up and down directions, all sections, as
per crew beat, in night also and for all types of stock.
b) It has become important to formally monitor Shunters and ALPs as they also play
an important part in ensuring safe train operations. Hence, one LI should be
nominated to monitor 45 shunters or 45 ALPs. These Shunters and ALPs should
be monitored, at least once in 3 months. No categorization of Shunters/ALPs is
considered necessary.
c) One LI can be assigned mix of LPs/Shunters/ALPs, keeping the overall workload
same e.g. 3 Shunters/ALPs can be assigned to a LI, in place of one LP. So, LIs can
be assigned: 15 LPs or 45 Shunters or 45 ALPs or 10 LPs + 15 Shunters/ALPs or
10 LPs + 6 Shunters + 9 ALPs, etc.
Home
Ch-2
Draft