Soil Nail Walls
6-15
The Engineer will evaluate the results of each verification test and make a determination
of the suitability of the test and of the Contractor’s proposed production nail design
and installation system. Tests that fail to meet the design criteria will require additional
verification testing or an approved revision to the Contractor’s proposed production nail
design and installation system. If a nail fails in creep, retesting will not be allowed.
A verification tested nail with a 60-minute load hold at 1.50TL is acceptable if:
1. The nail carries the test load with a creep rate that does not exceed 0.08 inch per log
cycle of time and is at a linear or decreasing creep rate.
2. The total movement at the test load exceeds 80 percent of the theoretical elastic
elongation of the non-bonded length.
Furthermore, a pullout failure shall not occur for the verification test anchor at the 2.0TL
maximum load. Pullout failure load is defined as the load at which attempts to increase
the test load result only in continued pullout movement of the test nail without a
sustainable increase in the test load.
6-15.3(8)B
Proof Testing
Proof tests shall be performed on proof test soil nails installed within the pattern of
the production soil nails at the locations shown in the Plans. Proof test soil nails shall
be installed using the same equipment, methods, nail inclination, nail length, and hole
diameter as for adjacent production nails. The Contractor shall maintain the side-wall
stability of the drill hole for the non-grouted portion during the test. The bond length
shall be determined from the Nail Schedule and Test Nail Detail shown in the Plans. Prior
to beginning proof testing, the Contractor shall measure and record the length of the
nonbonded zone for each proof test soil nail.
Proof tests shall be performed by incrementally loading the nail in accordance with the
schedule below. The anchor movement shall be measured and recorded to the nearest
0.001 inch with respect to an independent fixed reference point in the same manner as
for the verification tests at the alignment load and at each increment of load. The load
shall be monitored in accordance with
Section 6-15.3(8)
. The scheduling of hold times
shall be as follows:
AL
1 minute
0.25TL
5 minutes
0.50TL
5 minutes
0.75TL
5 minutes
1.00TL
5 minutes
1.25TL
5 minutes
1.50TL
10 minutes
AL = Nail Alignment Load
TL = Nail Test Load