Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 70

 

  Главная      Manuals     Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     68      69      70      71     ..

 

 

 

Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 70

 

 

Soil Nail Walls 

6-15

The Engineer will evaluate the results of each verification test and make a determination 
of the suitability of the test and of the Contractor’s proposed production nail design 
and installation system. Tests that fail to meet the design criteria will require additional 
verification testing or an approved revision to the Contractor’s proposed production nail 
design and installation system. If a nail fails in creep, retesting will not be allowed.

A verification tested nail with a 60-minute load hold at 1.50TL is acceptable if:
1.  The nail carries the test load with a creep rate that does not exceed 0.08 inch per log 

cycle of time and is at a linear or decreasing creep rate.

2.  The total movement at the test load exceeds 80 percent of the theoretical elastic 

elongation of the non-bonded length.

Furthermore, a pullout failure shall not occur for the verification test anchor at the 2.0TL 
maximum load. Pullout failure load is defined as the load at which attempts to increase 
the test load result only in continued pullout movement of the test nail without a 
sustainable increase in the test load.

6-15.3(8)B 

Proof Testing

Proof tests shall be performed on proof test soil nails installed within the pattern of 
the production soil nails at the locations shown in the Plans. Proof test soil nails shall 
be installed using the same equipment, methods, nail inclination, nail length, and hole 
diameter as for adjacent production nails. The Contractor shall maintain the side-wall 
stability of the drill hole for the non-grouted portion during the test. The bond length 
shall be determined from the Nail Schedule and Test Nail Detail shown in the Plans. Prior 
to beginning proof testing, the Contractor shall measure and record the length of the 
nonbonded zone for each proof test soil nail.

Proof tests shall be performed by incrementally loading the nail in accordance with the 
schedule below. The anchor movement shall be measured and recorded to the nearest 
0.001 inch with respect to an independent fixed reference point in the same manner as 
for the verification tests at the alignment load and at each increment of load. The load 
shall be monitored in accordance with 

Section 6-15.3(8)

. The scheduling of hold times 

shall be as follows:
 

AL 

1 minute 

0.25TL 

5 minutes 

0.50TL 

5 minutes 

0.75TL 

5 minutes 

1.00TL 

5 minutes 

1.25TL 

5 minutes 

1.50TL 

10 minutes 

AL = Nail Alignment Load  
TL = Nail Test Load

Page 6-304 

Soil Nail Walls

The maximum load in a proof test shall be held for 10 minutes. The load hold period 
shall start as soon as the maximum load is applied and the nail movement with respect 
to an independent fixed reference shall be measured and recorded at 1, 2, 3, 4, 5, 6, and 
10 minutes. The nail movement between 1 and 10 minutes shall not exceed 0.04 inches. 
If the nail movement between 1 and 10 minutes exceeds 0.04 inches, the maximum load 
shall be held an additional 50 minutes. If the load hold is extended, the nail movement 
shall be recorded at 20, 30, 40, 50, and 60 minutes. If a nail fails in creep, retesting will 
not be allowed.

A proof tested nail is acceptable if:
1.  The nail carries the maximum load with less than 0.04 inches of movement between 

1 and 10 minutes, unless the load hold extended to 60 minutes, in which case the 
nail would be acceptable if the creep rate does not exceed 0.08 inches per log cycle 
of time.

2.  The total movement at the maximum load exceeded 80 percent of the theoretical 

elastic elongation of the non-bonded length.

The creep rate is not increasing with time during the load hold period.

If a proof test fails, the Engineer may direct the Contractor to replace some or all of the 
installed production nails between the failed test and an adjacent proof test nail that has 
met the test criteria. The Engineer may also require additional proof testing. All additional 
proof tests, and all installation of additional or modified nails, shall be performed at no 
additional expense to the Contracting Agency.

6-15.3(9)  Concrete Fascia Panels

The Contractor shall construct the concrete fascia panels in accordance with 

Section 6-02

 

and the details in the Plans. The concrete fascia panels shall be cured in accordance with 
the 

Section 6-02.3(11)

 requirements specified for retaining walls. The Contractor shall 

provide the specified surface finish as noted, and to the limits shown, in the Plans to the 
exterior concrete surface. When noted in the Plans, the Contractor shall apply pigmented 
sealer to the limits shown in the Plans.

Asphalt or cement concrete gutter shall be constructed as shown in the Plans and as 
specified in 

Section 8-04

.

6-15.4 Measurement

Prefabricated drainage mat will be measured by the square yard of material furnished 
and installed.

Soil nails will be measured per each for each soil nail installed and accepted.

Soil nail verification test and soil nail proof test will be measured per each for each 
successfully completed soil nail verification test and soil nail proof test at the locations 
specified in the Special Provisions and shown in the Plans.

Soil Nail Walls 

6-15

Shotcrete facing and concrete fascia panel will be measured by the square foot surface 
area of the completed facing or fascia panel, measured to the neat lines of the facing or 
panel as shown in the Plans.

6-15.5 Payment

Payment will be made for each of the following Bid items when they are included in the 
Proposal:

“Soil Nail – Epoxy Coated”, per each.
 “Soil Nail – Encapsulated”, per each.
All costs in connection with furnishing and installing the soil nails as specified shall 
be included in the unit Contract price per each for “Soil Nail - ___”, including all 
drilling, grouting, centralizers, bearing plates, welded shear connectors, nuts, and 
other Work required for installation of each soil nail.
“Prefabricated Drainage Mat”, per square yard.
“Soil Nail Verification Test and Soil Nail Proof Test”, per each.
All costs in connection with successfully completing soil nail verification tests 
and soil nail proof tests as specified shall be included in the unit contract price 
per each for “Soil Nail Verification Test and Soil Nail Proof Test”, including removal 
of the exposed portion of the test nail and backfilling the drilled hole with grout 
or nonstructural filler.
“Concrete Fascia Panel”, per square foot.
All costs in connection with constructing the concrete fascia panels as specified shall 
be included in the unit Contract price per square foot for “Concrete Fascia Panel”, 
including all steel reinforcing bars, premolded joint filler, polyethylene bond breaker 
strip, joint sealant, PVC pipe for weep holes, exterior surface finish, and pigmented 
sealer (when specified).
Shotcrete facing will be paid for in accordance with 

Section 6-18.5

.

Unless otherwise specified, all costs in connection with excavation in front of the 
back face of the shotcrete facing shall be included in the unit Contract price per 
cubic yard for “Roadway Excavation” or “Roadway Excavation Incl. Haul” as specified 
in 

Section 2-03.5

.

Page 6-306 

Soldier Pile and Soldier Pile Tieback Walls

6-16 

Soldier Pile and Soldier Pile Tieback Walls

6-16.1 Description

This Work consists of constructing soldier pile walls and soldier pile tieback walls.

6-16.2 Materials

Materials shall meet the requirements of the following sections:
 

Controlled Density Fill 

2-09.3(1)E

 

Cement 

9-01

 

Aggregates for Concrete 

9-03.1

 

Gravel Backfill 

9-03.12

 

Premolded Joint Filler 

9-04.1(2)

 

Welded Shear Studs 

9-06.15

 

Steel Reinforcing Bar 

9-07.2

 

Epoxy-Coated Steel Reinforcing Bar 

9-07.3

 

Paints 

9-08 

Timber Lagging 

9-09.2 

Preservative Treatment for Timber Lagging 

9-09.3(1)

 

Soldier Piles 

9-10.5 

Concrete Curing Materials and Admixtures 

9-23 

Fly Ash 

9-23.9

 

Water 

9-25

 

Prefabricated Drainage Mat 

9-33.2(3)

Other materials required shall be as specified in the Special Provisions.

6-16.3 

Construction Requirements

6-16.3(1)  Quality Assurance

The steel soldier piles shall be placed so that the centerline of the pile at the top is within 
1 inch of the Plan location. The steel soldier pile shall be plumb, to within 0.5 percent of 
the length based on the total length of the pile.

Welding, repair welding, and welding inspection shall conform to the 

Section 6-03.3(25) 

requirements for welding, repair welding, and welding inspection for all other steel 
fabrication.

6-16.3(2) Submittals

The Contractor shall submit Type 2 Working Drawings consisting of shop plans as 
specified in 

Section 6-03.3(7)

 for all structural steel, including the steel soldier piles, 

and shall submit Type 2 Working Drawings consisting of shop plans and other details as 
specified in 

Section 6-17.3(3)

 for permanent ground anchors.

The Contractor shall submit Type 1 Working Drawings consisting of the permanent 
ground anchor grout mix design and the procedures for placing the grout to the Engineer 
for approval.

Soldier Pile and Soldier Pile Tieback Walls 

6-16

The Contractor shall submit Type 2E Working Drawings consisting of forming plans for 
the concrete fascia panels, as specified in Sections

 6-02.3(16)

 and 

6-02.3(17)

.

1.  Where the lateral pressure from concrete placement, as specified in 

Section 

6-02.3(17)J

, is less than or equal to the design earth pressure, the Contractor may tie 

forms directly to the soldier piles.

2.  Where the lateral pressure from concrete placement, as specified in 

Section 

6-02.3(17)J

, is greater than the design earth pressure, the Contractor shall follow 

one of the following procedures:
a.  Tie the forms to strongbacks behind the lagging, or use some other system that 

confines the pressure from concrete placement between the lagging and the 
form panels, in addition to the ties to the soldier piles.

b.  Reduce the rate of placing concrete to reduce the pressure from concrete 

placement to less than or equal to the design earth pressure in addition to the 
ties to the soldier piles.

c.  Follow a procedure with a combination of a. and b.

3.  The Contractor shall design the forms for an appropriate rate of placing concrete so 

that no cold joints occur, considering the wall thickness and height, and volume of 
concrete to be placed.

The Contractor shall submit Type 2 Working Drawings consisting of a shaft installation 
plan. In preparing the submittal, the Contractor shall reference the available subsurface 
data provided in the Contract test hole boring logs and the geotechnical report(s) 
prepared for this project. This plan shall provide at least the following information:
1.  An overall construction operation sequence and the sequence of shaft construction.
2.  List, description, and capacities of proposed equipment including but not limited to 

cranes, drills, augers, bailing buckets, final cleaning equipment, and drilling units. The 
narrative shall describe why the equipment was selected, and describe equipment 
suitability to the anticipated site and subsurface conditions. The narrative shall 
include a project history of the drilling equipment demonstrating the successful use 
of the equipment on shafts of equal or greater size in similar soil/rock conditions.

3.  Details of shaft excavation methods including proposed drilling methods, methods 

for cleanout of the shafts, disposal plan for excavated material and drilling slurry 
(if applicable), and a review of method suitability to the anticipated site and 
subsurface conditions.

4.  Details of the method(s) to be used to ensure shaft stability (i.e., prevention of 

caving, bottom heave, etc. using temporary casing, slurry, or other means) during 
excavation and concrete placement. This shall include a review of method suitability 
to the anticipated site and subsurface conditions. If temporary casings are proposed, 
casing dimensions and detailed procedures for casing installation and removal shall 
be provided. If slurry is proposed, detailed procedures for mixing, using, maintaining, 
and disposing of the slurry shall be provided. A detailed mix design, and a discussion 
of its suitability to the anticipated subsurface conditions shall also be provided for 
the proposed slurry.

Page 6-308 

Soldier Pile and Soldier Pile Tieback Walls

5.  Details of soldier pile placement including internal support bracing and centralization 

methods.

6.  Details of concrete placement including proposed operational procedures for 

pumping and/or tremie methods.

7.  Details of the device used to prevent unauthorized entry into a shaft excavation.
8.  The method to be used to form the horizontal construction joint at the top elevation 

specified for concrete Class 4000P in the shaft.

6-16.3(3)  Shaft Excavation

Shafts shall be excavated to the required depth as shown in the Plans. The minimum 
diameter of the shaft shall be as shown in the Plans. The excavation shall be completed 
in a continuous operation using equipment capable of excavating through the type of 
material expected to be encountered.

The Contractor may use temporary telescoping casing to construct the shafts.

If the shaft excavation is stopped the shaft shall be secured by installation of a safety 
cover. It shall be the Contractor’s responsibility to ensure the safety of the shaft and 
surrounding soil and the stability of the sidewalls. A temporary casing, slurry, or other 
methods specified in the shaft installation plan shall be used if necessary to ensure such 
safety and stability.

Where caving in conditions are encountered, no further excavation will be allowed until 
the Contractor has implemented the method to prevent ground caving as submitted in 
accordance with item 4 of the Shaft Installation Plan.

No more than 2 inches of loose or disturbed material, for soldier piles with permanent 
ground anchors, nor more than 12 inches of loose or disturbed material, for soldier piles 
without permanent ground anchors, shall be present at the bottom of the shaft just prior 
to beginning concrete placement.

The excavated shaft shall be inspected and receive acceptance by the Engineer prior to 
proceeding with construction.

When obstructions are encountered, the Contractor shall notify the Engineer promptly. 
An obstruction is defined as a specific object (including, but not limited to, boulders, 
logs, and man made objects) encountered during the shaft excavation operation that 
prevents or hinders the advance of the shaft excavation. When efforts to advance past 
the obstruction to the design shaft tip elevation result in the rate of advance of the 
shaft drilling equipment being significantly reduced relative to the rate of advance for 
the rest of the shaft excavation, then the Contractor shall remove the obstruction under 
the provisions of 

Section 6-16.5

The method of removal of such obstructions, and the 

continuation of excavation shall be as proposed by the Contractor and approved by 
the Engineer.

Soldier Pile and Soldier Pile Tieback Walls 

6-16

Excavation of shafts shall not commence until a minimum of 12 hours after the shaft 
backfill for the adjacent shafts has been placed.

The temporary casings for the shafts shall be removed. A minimum 5-foot head of 
concrete shall be maintained to balance the soil and water pressure at the bottom of the 
casing. The casing shall be smooth.

6-16.3(4)  Installing Soldier Piles

Soldier piles, if spliced, shall conform to all requirements of 

Section 6-05.3(6)

.

The prefabricated steel soldier piles shall be lowered into the drilled shafts and secured in 
position. Concrete cover over the soldier pile shall be 3 inches minimum, except that the 
cover over the soldier pile flange plate reinforcing at permanent ground anchor locations 
shall be 1½ inches minimum.

The steel soldier piles and attachments shall be shop painted after fabrication to the limits 
shown in the Plans with one coat of inorganic zinc primer. Application of the one coat of 
primer shall be in accordance with 

Section 6-07

. The welded shear studs may be attached 

before or after painting. Paint damaged by welding shear studs in place does not require 
repair.

6-16.3(5)  Backfilling Shaft

The excavated shaft shall be backfilled with either controlled density fill (CDF), or 
pumpable lean concrete, as shown in the Plans and subject to the following requirements:
1.  Dry shaft excavations shall be backfilled with CDF.
2.  Wet shaft excavations shall be backfilled with pumpable lean concrete.
3.  Pumpable lean concrete shall be a Contractor designed mix providing a minimum 

28-day compressive strength of 100 psi. Acceptance of pumpable lean concrete will 
conform to the acceptance requirements specified in 

Section 2-09.3(1)

 for CDF.

4.  A wet shaft is defined as a shaft where water is entering the excavation and remains 

present to a depth of 6 inches or more.

5.  When the Plans or test hole boring logs identify the presence of a water table at 

or above the elevation of the bottom of soldier pile shaft, the excavation shall be 
considered as wet, except as otherwise noted. Such a shaft may be considered a dry 
shaft provided the Contractor furnishes and installs casing that is sufficiently sealed 
into competent soils such that water cannot enter the excavation.

Placement of the shaft backfill shall commence immediately after completing the shaft 
excavation and receiving the Engineer’s approval of the excavation. CDF or pumpable lean 
concrete shall be placed in one continuous operation to the top of the shaft. Vibration of 
shaft backfill is not required.

If water is not present, the shaft backfill shall be deposited by a method that prevents 
segregation of aggregates. The shaft backfill shall be placed such that the free-fall is 
vertical down the shaft without hitting the sides of the soldier pile or the excavated 

Page 6-310 

Soldier Pile and Soldier Pile Tieback Walls

shaft. The Contractor’s method for depositing the shaft backfill shall have approval of the 
Engineer prior to the placement of the shaft backfill.

If water is present, the shaft backfill shall be deposited in accordance with 

Section  

6-02.3(6)B

.

6-16.3(6)  Designing and Installing Lagging and Installing Permanent Ground Anchors

Lagging for soldier pile walls shall conform to one of the following two categories:
1.  Temporary lagging is defined as lagging that is in service as a structural member for 

a maximum of 36 months before a permanent load-carrying fascia is in place, except 
for the following exception: Lagging for soldier pile walls in site soils conforming 
to an excluded soil type as defined under 

Section 6-16.3(6)A

 will be classified as 

permanent lagging conforming t

Section 6-16.3(6)C

, in which case this requirement 

will be specified in the Plans along with design details for such lagging.

2.  Permanent lagging is defined as all lagging not conforming to the definition of 

temporary lagging as specified in category 1, above.

6-16.3(6)A 

Soil Classification

For the purposes of designing lagging for soldier pile walls, soils shall be categorized in the 
classifications defined below.

Soil Type 1

The following shall be considered Type 1 soils:
1.  Cohesive fine-grained soils either CL or CH of medium consistency with  

γH/Su < 5.

2.  Cohesive fine-grained soils either CL or CH that are stiff to very stiff and 

nonfissured.

3.  Fine-grained soils either ML or SM-ML that are above the water table.
4.  Coarse-grained soils either GW, GP, GM, GC, SW, SP, or SM that are medium 

dense to dense.

Soil Type 2

The following shall be considered Type 2 soils:
1.  Cohesive fine-grained soils either CL or CH that are heavily overconsolidated 

and fissured.

2.  Fine-grained ML soils or coarse-grained SM-ML soils that are below the water 

table.

3.  Coarse-grained SC soil that is medium dense to dense and is below the water 

table.

4.  Coarse-grained soils either SW, SP, or SM that are loose.

Soldier Pile and Soldier Pile Tieback Walls 

6-16

Soil Type 3

The following shall be considered Type 3 soils:

1.  Cohesive fine-grained soils either CL or CH that are soft with γH/Su > 5.

2.  Fine-grained slightly plastic ML soil that is below the water table.
3.  Coarse-grained SC soil that is loose and below the water table.

Exclusions

Regardless of whether site soils conform to one of the soil types defined above, site soils 
under the following conditions are excluded from the Type 1, Type 2, and Type 3 soil 
classifications:
1.  Disturbed soils such as those in landslides or known unstable areas.
2.  Layered soils dipping into the excavation steeper than 4H:1V.

Lagging for soldier pile walls located in site soils excluded from the Type 1, Type 2, and 
Type 3 soil classifications shall be designed in accordance with the latest AASHTO LRFD 
Bridge Design Specifications
 with current interim specifications. Use of the table in

 Section 

6-16.3(6)B

 for timber lagging in these situations will not be allowed.

6-16.3(6)B 

Temporary Lagging

The Contractor shall design temporary lagging for all soldier pile walls. The temporary 
lagging design shall be based on the following:
1.  The AASHTO LRFD Bridge Design Specifications, latest edition with current interim 

specifications, except that timber members used for temporary lagging may be 
selected based on the table below.

2.  The soil type as specified in the Plans or as determined from the geotechnical report 

prepared for the project.

3.  The soil pressure diagram, either as shown in the Plans or as included in the 

geotechnical report prepared for the project, including the surcharge for temporary 
construction load when shown in the Plans.

The Contractor shall submit Type 2E Working Drawings consisting of the soldier pile wall 
lagging design details and supporting design calculations. The submittal shall include, at a 
minimum, the following:
1.  Description of the material used for the lagging, including identification of applicable 

material specifications.

2.  Installation method and sequence.
3.  If the lagging material is to be removed during or after installation of the permanent 

fascia, a description of how the lagging is removed without disturbing or damaging 
the fascia, soldier piles, and retained soil, and a description of how, and with what 
material, the void left by the removal of lagging is to be filled.

Page 6-312 

Soldier Pile and Soldier Pile Tieback Walls

4.  For all cases, except with timber for temporary lagging, a description with 

appropriate details of how subsurface drainage is to be accommodated, either 
in accordance with 

Section 6-16.3(7)

 for timber lagging, 

Section 6-15.3(7)

 for 

shotcrete facing, or other means appropriate for the geotechnical site conditions and 
acceptable to the Engineer for other lagging materials. Lagging materials and lagging 
installation methods that cause the buildup of, and prevent the relief of, pore water 
pressure will not be allowed. Free-draining materials are defined as those materials 
that exhibit a greater permeability than the material being retained.

Temporary lagging may be untreated timber conforming to the 

Section 9-09.2

 

requirements specified under Structures for timber lagging or another material selected 
by the Contractor.

Timber for temporary lagging shall conform to the minimum actual thickness specified in 
the table below for the soil type, exposed wall height, and lagging clear span as shown in 
the Plans.

Notwithstanding the requirements of 

Section 1-06.1

, steel materials used by the 

Contractor as temporary lagging may be salvaged steel provided that the use of such 
salvaged steel materials shall be subject to visual inspection and acceptance by the 
Engineer. For salvaged steel materials where the grade of steel cannot be positively 
identified, the design stresses for the steel shall conform to the 

Section 6-02.3(17)B

 

requirements for salvaged steel, regardless of whether rivets are present or not.

Minimum Actual Thickness of Timber Used as Temporary Lagging

Soil Type

1

1

1

2

2

3

3

3

Exposed Wall 

Height (feet)

25 and 

under

Over 25 

to 60

25 and 

under

Over 25 

to 60

15 and 

under

Over 15 

to 25

Over 25

Clear Span of 

Lagging (feet)

Minimum Actual Thickness of Rough Cut Timber Lagging (inches)

3

5

2

3

3

3

3

3

4

6

3

3

3

3

3

4

5

7

3

3

3

4

4

5

6

8

3

4

4

4

5

6

See 

Note

2

9

4

4

4

5

See 

Note

2

See 

Note

2

See 

Note

2

10

4

5

5

5

See 

Note

2

See 

Note

2

See 

Note

2

1

Soil Type as defined in 

Section 6-16.3(6)A

2

For exposed wall heights exceeding the limits in the table above, or where minimum rough cut lagging 

thickness is not provided, the Contractor shall design the lagging in accordance with the latest AASHTO LRFD 
Bridge Design Specifications
 with current interim specifications.

3

Table modified from FHWA document “Lateral Support Systems and Underpinning” (Report No. FHWA-

RD-75-130).

Soldier Pile and Soldier Pile Tieback Walls 

6-16

6-16.3(6)C 

Permanent Lagging

Permanent lagging, including timber, shall be as shown in the Plans. The use of the table 
in 

Section 6-16.3(6)B

 for the design of timber lagging for permanent lagging will not 

be allowed.

6-16.3(6)D 

Installing Lagging and Permanent Ground Anchors

The excavation and removal of CDF and pumpable lean concrete for the lagging 
installation shall proceed in advance of the lagging and shall not begin until the CDF 
and pumpable lean concrete are of sufficient strength that the material remains in 
place during excavation and lagging installation. If the CDF or pumpable lean concrete 
separates from the soldier pile, or caves or spalls from around the soldier pile, the 
Contractor shall discontinue excavation and lagging installation operations until the CDF 
and pumpable lean concrete is completely set. The bottom of the excavation in front of 
the wall shall be level. Excavation shall conform t

Section 2-03

.

For walls without permanent ground anchors, the bottom of excavation shall not be more 
than 3 feet below the bottom level of the lagging already installed, but in no case shall 
the depth of excavation beneath the bottom level of installed lagging be such to cause 
instability of the excavated face. For walls with permanent ground anchors, the bottom 
of excavation shall be not more than 3 feet below the permanent ground anchor level 
until all permanent ground anchors at that level are installed and stressed, but in no case 
shall the depth of excavation beneath the permanent ground anchor level be such to 
cause instability of the excavated face. Any caving that occurs during excavation shall be 
backfilled with free-draining material.

Installing, stressing, and testing the permanent ground anchors shall be in accordance 
with 

Section 6-17

 and the construction sequence specified in the Plans.

The lagging shall be installed from the top of the soldier pile proceeding downward. The 
lagging shall make direct contact with the soil. When and where lagging is not in full 
contact with the soil being retained, either the lagging shall be wedged back to create 
contact or the void shall be filled with a free-draining material.

When utilizing lagging in fill situations, the backfill layers shall be placed in accordance 
with 

Section 2-03.3(14)

 except that all layers shall be compacted to 90 percent of 

maximum density.

6-16.3(7)  Prefabricated Drainage Mat

For walls with concrete fascia panels, a 4-foot-wide strip of prefabricated drainage mat 
shall be installed full height of the concrete fascia panel, centered between soldier pile 
flanges, unless otherwise shown in the Plans.

The prefabricated drainage mat shall be attached to the lagging in accordance with 
the manufacturer’s recommendations. The fabric side shall face the lagging. Splicing 
of the prefabricated drainage mat shall be in accordance with the manufacturer’s 
recommendations.

Page 6-314 

Soldier Pile and Soldier Pile Tieback Walls

The Contractor shall ensure the hydraulic connection of the prefabricated drainage mat to 
the previously installed material so that the vertical flow of water is not impeded.

The Contractor shall tape all joints in the prefabricated drainage mat to prevent concrete 
intrusion during concrete fascia panel construction.

6-16.3(8)  Concrete Fascia Panel

The Contractor shall construct the concrete fascia panels as shown in the Plans, and in 
accordance with the forming plan. The concrete fascia panels shall be cured in accordance 
with the 

Section 6-02.3(11)

 requirements specified for retaining walls.

The Contractor shall provide the specified surface finish as noted, and to the limits 
shown, in the Plans to the exterior concrete surface. When noted in the Plans, the 
Contractor shall apply pigmented sealer to the limits shown in the Plans.

Asphalt or cement concrete gutter shall be constructed as shown in the Plans.

6-16.4 Measurement

Soldier pile shaft construction will be measured by the linear foot of shaft excavated 
below the top of ground line for the shaft, defined as the highest existing ground point 
within the shaft diameter.

Furnishing soldier pile will be measured by the linear foot of pile assembly specified 
in the Proposal, including adjustments to the Plan quantity made in accordance with 

Section 1-04.4

.

Lagging will be measured by the square foot area of lagging installed. The quantity will 
be computed based on the vertical dimension from the highest lagging elevation to 
the lowest lagging elevation between each pair of adjacent soldier piles as the height 
dimension and the center-to-center spacing of the soldier piles as the length dimension.

Prefabricated drainage mat will be measured by the square yard of material furnished 
and installed.

Concrete fascia panel will be measured by the square foot surface area of the completed 
fascia panel, measured to the neat lines of the panel as shown in the Plans.

6-16.5 Payment

Payment will be made for each of the following Bid items when they are included in the 
Proposal:

“Shaft - ___ Diameter”, per linear foot.
All costs in connection with constructing soldier pile shafts shall be included in 
the unit Contract price per linear foot for “Shaft - ___ Diameter”, including shaft 
excavation, temporary casing if used, CDF, lean concrete, concrete Class 4000P, and 
installing the soldier pile assembly.
“Furnishing Soldier Pile - ___”, per linear foot.

Soldier Pile and Soldier Pile Tieback Walls 

6-16

All costs in connection with furnishing soldier pile assemblies shall be included in 
the unit Contract price per linear foot for “Furnishing Soldier Pile - ___”, including 
fabricating and painting the pile assemblies, and field splicing and field trimming the 
soldier piles. Payment will be made based on the quantity specified in the Proposal 
unless changes are made to this quantity in accordance with 

Section 1-04.4

in which 

case the quantity specified in the Proposal will be adjusted by the amount of the 
change and will be paid for in accordance with 

Section 1-04.4

.

“Lagging”, per square foot.
All costs in connection with furnishing and installing lagging shall be included in 
the unit contract price per square foot for “Lagging”, including design of temporary 
lagging and filling voids behind the lagging with a free-draining material as approved 
by the Engineer.
“Prefabricated Drainage Mat”, per square yard.
“Concrete Fascia Panel”, per square foot.
All costs in connection with constructing the concrete fascia panels as specified shall 
be included in the unit Contract price per square foot for “Concrete Fascia Panel”, 
including all steel reinforcing bars, premolded joint filler, polyethylene bond breaker 
strip, joint sealant, PVC pipe for weep holes, exterior surface finish, and pigmented 
sealer (when specified).
Unless otherwise specified, all costs in connection with non-shaft excavation, 
including all excavation required for placement of timber lagging, shall be included 
in the unit Contract price per cubic yard for “Roadway Excavation” or “Roadway 
Excavation Incl. Haul” as specified in 

Section 2-03.5

.

“Removing Soldier Pile Shaft Obstructions”, estimated.
Payment for removing obstructions, as defined in 

Section 6-16.3(3)

, will be made 

for the changes in shaft construction methods necessary to remove the obstruction. 
The Contractor and the Engineer shall evaluate the effort made and reach agreement 
on the equipment and employees utilized, and the number of hours involved 
for each. Once these cost items and their duration have been agreed upon, the 
payment amount will be determined using the rate and markup methods specified in 

Section 1-09.6

. For the purpose of providing a common proposal for all bidders, the 

Contracting Agency has entered an amount for the item “Removing Soldier Pile Shaft 
Obstructions” in the bid proposal to become a part of the total bid by the Contractor.
If the shaft construction equipment is idled as a result of the obstruction removal 
work and cannot be reasonably reassigned within the project, then standby payment 
for the idled equipment will be added to the payment calculations. If labor is idled as 
a result of the obstruction removal work and cannot be reasonably reassigned within 
the project, then all labor costs resulting from Contractor labor agreements and 
established Contractor policies will be added to the payment calculations.

Page 6-316 

Soldier Pile and Soldier Pile Tieback Walls

The Contractor shall perform the amount of obstruction work estimated by the 
Contracting Agency within the original time of the contract. The Engineer will 
consider a time adjustment and additional compensation for costs related to the 
extended duration of the shaft construction operations, provided:
1.  The dollar amount estimated by the Contracting Agency has been exceeded, 

and;

2.  The Contractor shows that the obstruction removal work represents a delay to 

the completion of the project based on the current progress schedule provided 
in accordance with 

Section 1-08.3

Permanent Ground Anchors 

6-17

6-17 

Permanent Ground Anchors

6-17.1 Description

This Work consists of constructing permanent ground anchors.

6-17.2 Materials

Materials required, including materials for permanent ground anchors, shall be as 
specified in the Special Provisions.

6-17.3 

Construction Requirements

The Contractor shall select the ground anchor type and the installation method, and 
determine the bond length and anchor diameter. The Contractor shall install ground 
anchors that will develop the load indicated in the Plans and verified by tests specified in 
Sections

 6-17.3(8)A

6-17.3(8)B

, and 

6-17.3(8)C.

6-17.3(1) Definitions

Anchor Devices: The anchor head wedges or nuts that grip the prestressing steel.

Bearing Plate: The steel plate that evenly distributes the ground anchor force to the 
Structure.

Bond Length: The length of the ground anchor that is bonded to the ground and transmits 
the tensile force to the soil or rock.

Ground Anchor: A system, referred to as a tieback or as an anchor, used to transfer tensile 
loads to soil or rock. A ground anchor includes all prestressing steel, anchorage devices, 
grout, coatings, sheathings, and couplers if used.

Maintaining Consistency of Load: Maintaining the test load within 5 percent of the 
specified value.

Minimum Guaranteed Ultimate Tensile Strength (MUTS): The minimum guaranteed 
breaking load of the prestressing steel as defined by the specified standard.

Tendon Bond Length: The length of the tendon that is bonded to the anchor grout.

Tendon Unbonded Length: The length of the tendon that is not bonded to the anchor 
grout.

Total Anchor Length: The unbonded length plus the tendon bond length.

Page 6-318 

Permanent Ground Anchors

6-17.3(2)  Contractor Experience Requirements

The Contractor or Subcontractor performing this Work shall have installed permanent 
ground anchors for a minimum of 3 years. Prior to the beginning of construction, the 
Contractor shall submit a list containing at least five projects on which the Contractor has 
installed permanent ground anchors. A brief description of each project and a reference 
shall be included for each project listed. As a minimum, the reference shall include an 
individual’s name and current phone number.

The Contractor shall assign an engineer to supervise the Work with at least 3 years of 
experience in the design and construction of permanently anchored Structures. The 
Contractor shall not use consultants or manufacturer’s representatives in order to meet 
the requirements of this Section. Drill operators and on-site supervisors shall have a 
minimum of 1 year experience installing permanent ground anchors.

Contractors or Subcontractors that are specifically prequalified in Class 36 Work will be 
considered to have met the above experience requirements.

The Contractor shall allow up to 15 calendar days for the Engineer’s review of the 
qualifications and staff as noted above. Work shall not be started on any anchored wall 
system nor materials ordered until approval of the Contractor’s qualifications are given.

6-17.3(3) Submittals

The Contractor shall submit Type 2E Working Drawings consisting of details and 
structural design calculations for the ground anchor system or systems intended for use.

The Contractor shall submit a Type 1 Working Drawing consisting of a detailed 
description of the construction procedure proposed for use.

The Contractor shall submit a Type 2 Working Drawing consisting of ground anchor 
schedule giving:
1.  Ground anchor number
2.  Ground anchor factored design load
3.  Type and size of tendon
4.  Minimum total bond length
5.  Minimum anchor length
6.  Minimum tendon bond length
7.  Minimum unbonded length

The Contractor shall submit a Type 2 Working Drawing detailing the ground anchor 
tendon and the corrosion protection system. Include details of the following:
1.  Spacers and their location
2.  Centralizers and their location

 

 

 

 

 

 

 

Content      ..     68      69      70      71     ..