Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 69

 

  Главная      Manuals     Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     67      68      69      70     ..

 

 

 

Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 69

 

 

Page 6-188 

6-05.3(11)H  Pile Driving From or Near Adjacent Structures

The Contractor shall not drive piling from an existing Structure unless all of the following 
conditions are met:
1.  The existing Structure will be demolished within the Contract;
2.  The existing Structure is permanently closed to traffic; and
3.  Type 2E Working Drawings are submitted in accordance with 

Sections 1-05.3

 and 

6-02.3(16)

, showing the structural adequacy of the existing Structure to safely 

support all of the construction loads.

Freshly placed concrete in the vicinity of the pile driving operation shall be protected 
against vibration in accordance with 

Section 6-02.3(6)D

.

6-05.3(12)  Determination of Bearing Values

The following formula shall be used to determine ultimate bearing resistances:

P = F × E × Ln(10N)

Where:

=  ultimate bearing resistance, in tons

=  1.8 for air/steam hammers

 

=  1.2 for open ended diesel hammers and precast concrete or timber piles

 

=  1.6 for open ended diesel hammers and steel piles

 

=  1.2 for closed ended diesel hammers

 

=  1.9 for hydraulic hammers

 

=  0.9 for drop hammers

=  developed energy, equal to W times H

1

, in ft-kips

=  weight of ram, in kips

=  vertical drop of hammer or stroke of ram, in feet

N 

=  average penetration resistance in blows per inch for the last 4 inches of driving

Ln 

=  the natural logarithm, in base “e”

1

For closed-end diesel hammers (double-acting), the developed hammer energy (E) is to be determined 

from the bounce chamber reading. Hammer manufacturer calibration data may be used to correlate bounce 

chamber pressure to developed hammer energy. For double acting hammer hydraulic and air/steam 

hammers, the developed hammer energy shall be calculated from ram impact velocity measurements or 

other means acceptable to the Engineer. For open ended diesel hammers (single-acting) use the blows per 

minute to determine the developed energy (E).

The above formula applies only when:
1.  The hammer is in good condition and operating in a satisfactory manner.
2.  A follower is not used.
3.  The pile top is not damaged.
4.  The pile head is free from broomed or crushed wood fiber.
5.  The penetration occurs at a reasonably quick, uniform rate; and the pile has been 

driven at least 2 feet after any interruption in driving greater than 1 hour in length.

Piling 6-05

6.  There is no perceptible bounce after the blow. If a significant bounce cannot be 

avoided, twice the height of the bounce shall be deducted from “H” to determine its 
true value in the formula.

7.  For timber piles, bearing resistances calculated by the formula above shall be 

considered effective only when it is less than the crushing strength of the piles.

8.  If “N” is greater than or equal to 1.0 blow/inch.

If “N” required to achieve the required ultimate bearing resistance using the above 
formula is less than 1.0 blow/inch, the pile shall be driven until the penetration resistance 
is a minimum of 1.0 blow/inch for the last 2 feet of driving.

The Engineer may require the Contractor to install a pressure gauge on the inboard end of 
the hose to check pressure at the hammer.

If water jets are used in driving, bearing resistances shall be determined either: (1) 
by calculating it with the driving data and the formula above after the jets have been 
withdrawn and the pile is driven at least 2 feet, or (2) by applying a test load.

6-05.3(13)  Treatment of Timber Pile Heads

After cutting timber piles to correct elevation, the Contractor shall thoroughly coat the 
heads of all untreated piles with two coats of an approved preservative that meets the 
requirements of 

Section 9-09

 (except concrete-encased piles).

After cutting treated timber piles to correct elevation, the Contractor shall brush three 
coats of a preservative that meets the requirements of 

Section 9-09

 on all pile heads 

(except those to be covered with concrete footings or concrete caps). The pile heads shall 
then be capped with alternate layers of an approved roofing asphalt and a waterproofing 
fabric that conforms to 

Section 9-11.2

. The cap shall be made of four layers of an 

approved roofing asphalt and three layers of fabric. The fabric shall be cut large enough 
to cover the pile top and fold down at least 6 inches along all sides of the pile. After 
the fabric cover is bent down over the pile, its edges shall be fastened with large-head 
galvanized nails or with three turns of galvanized wire. The edges of the cover shall be 
neatly trimmed.

On any treated timber pile encased in concrete, the cut end shall receive two coats of 
an approved preservative that meets the requirements of 

Section 9-09

 and then a heavy 

coat of an approved roofing asphalt.

6-05.3(14)  Extensions and Buildups of Precast Concrete Piles

The Contractor shall add extensions, or buildups (if necessary) on precast concrete 
piles after they are driven to the required ultimate bearing resistance and minimum tip 
elevation.

Before adding extensions or buildups to precast-prestressed piles, the Contractor shall 
remove any spalled concrete, leaving the pile fresh-headed and with a top surface 
perpendicular to the axis of the pile. The concrete in the buildup shall be Class 5000.

Page 6-190 

Before adding to non-prestressed precast concrete piles, the Contractor shall cut the 
pile head away to a depth 40 times the diameter of the vertical reinforcing bar. The final 
cut shall be perpendicular to the axis of the pile. Reinforcement of the same density and 
configuration as used in the pile shall be used in the buildup and shall be fastened firmly 
to the projecting steel. Forms shall be placed to prevent concrete from leaking along the 
pile. The concrete in the buildup shall be Class 4000.

Just before placing the concrete for extensions or buildups to precast or precast-
prestressed concrete piles, the Contractor shall thoroughly wet the top of the pile. Forms 
shall remain in place at least 3 days.

6-05.3(15)  Completion of Cast-In-Place Concrete Piles

After acceptance by the Engineer, driven casings shall be cut off horizontally at the 
required elevation. They shall be clean and free of water when concrete and reinforcing 
steel are placed.

These piles shall consist of steel casings driven into the ground, reinforced as specified, 
and filled with Class 4000P concrete.

6-05.3(15)A Reinforcement

All bars shall be fastened rigidly into a single unit, then lowered into the casing before the 
concrete is placed. Loose bars shall not be used.

Spiral hooping reinforcement shall be deformed steel bar, plain steel bar, cold-drawn wire, 
or deformed wire.

6-05.3(15)B 

Placing Concrete

Before placing concrete, the Contractor shall remove all debris and water from the casing. 
If the water cannot be removed, the casing shall be removed (or cut off 2 feet below the 
ground and filled with sand) and a new one driven.

The Contractor shall place concrete continuously through a 5-foot rigid conduit directing 
the concrete down the center of the pile casing, ensuring that every part of the pile is 
filled and the concrete is worked around the reinforcement. The top 5 feet of concrete 
shall be placed with the tip of the conduit below the top of fresh concrete. The Contractor 
shall vibrate, as a minimum, the top 10 feet of concrete. In all cases, the concrete shall be 
vibrated to a point at least 5 feet below the original ground line.

6-05.4 Measurement

Measurement for driving (type) pile will be the number of piles driven in place.

In these categories, measurement will be the longer of either the number of linear feet 
driven below cutoff or as shown in the Engineer’s order list:
1.  Furnishing timber piling (untreated or name of treatment).
2.  Precast concrete and precast-prestressed concrete piling.

Piling 6-05

In these categories, measurement will be the number of linear feet driven below cutoff, 
but no Engineer’s order list will be provided:
1.  Cast-in-place concrete piling.
2.  Furnishing steel piling.

Measurement for furnishing and driving test piles will be the number actually furnished 
and driven as the Contract requires.

Measurement for steel pile tips or shoes will be by the number of tips or shoes actually 
installed and driven in place on steel casings or steel piles.

6-05.5 Payment

Payment will be made for each of the following Bid items that are included in the 
Proposal:

“Furnishing and Driving (type) Test Pile”, per each.
The unit Contract price per each for “Furnishing and Driving (type) Test Pile” shall 
be full pay for furnishing and driving test piles to the ultimate bearing resistance or 
penetration required by the Engineer, furnishing and installing a pile tip when pile 
tips are specified for the permanent piles, preboring when preboring is specified 
for the permanent piles, for pulling the piles or cutting them off as required, and for 
removing them from the site or for delivery to the Contracting Agency for salvage 
when ordered by the Engineer. For cast-in-place concrete test piles, this price shall 
include furnishing, fabricating, and installing the steel reinforcing bar cage, and 
furnishing, casting, and curing the concrete. This price shall also include all costs in 
connection with moving all pile driving equipment or other necessary equipment 
to the site of the Work and for removing all such equipment from the site after the 
piles have been driven. If, after the test piles have been driven, it is found necessary 
to eliminate the piling from all or any part of the Structure, no additional pay will be 
allowed for moving the pile driving equipment to and from the site of the Work.
“Driving Timber Pile (untreated or name treatment)”, per each.
The unit Contract price per each for “Driving Timber (type) Pile” shall include any 
metal shoes which the Contractor has determined to be beneficial to the pile driving.
“Driving Conc. Pile (size)”, per each.
“Driving St. Pile”, per each.
The unit Contract price per each for “Driving (type) Pile (____)” shall be full pay for 
driving the pile to the ultimate bearing and/or penetration specified.
“Furnishing Timber Piling (untreated or name treatment)”, per linear foot.
“Furnishing Conc. Piling (size)”, per linear foot.
“Furnishing St. Piling”, per linear foot.
The unit Contract price per linear foot for “Furnishing (type) Piling (____)” shall be full 
pay for furnishing the piling specified, including furnishing, fabricating, and installing 

Page 6-192 

the steel reinforcing bar cage, and furnishing casting, and curing the concrete, as 
required for concrete piling. Such price shall also be full pay, for furnishing timber, 
precast concrete, or precast-prestressed concrete piling length ordered from an 
Engineer’s order sheet but not driven.
“Precast Concrete Pile Buildup”, by force account.
Payment for buildups of precast or precast-prestressed concrete piles will be made 
on the basis of force account Work as covered in 

Section 1-09.6

. No payment will 

be made for buildups or additional lengths of buildup made necessary because of 
damage to the piling during driving. The length of splice for precast concrete piles 
includes the length cut off to expose reinforcing steel for the splice. The length of 
splice for precast-prestressed piles includes the length in which holes are drilled and 
reinforcing bars are grouted.
For the purpose of providing a common Proposal for all Bidders, the Contracting 
Agency entered an amount for “Precast Concrete Pile Buildup” in the Proposal to 
become part of the total Bid by the Contractor.
“Furnishing Steel Pile Tip or Shoe (size)”, per each.

6-06 

Bridge Railings

6-06.1 Description

This Work consists of providing and building bridge railings that meet the requirements 
of the Plans, these Specifications, and the Engineer.

6-06.2 Materials

Materials shall meet the requirements of the following sections:
 

Timber Railing 

9-09

 

Metal Railing 

9-06.18

6-06.3 

Construction Requirements

6-06.3(1)  Timber Railings

Wheel guards and railings shall be true to line and grade and framed accurately. 
The Contractor shall follow 

Section 6-04

 whenever this Subsection does not specify 

a construction method.

Unless the Plans show otherwise, wheel guards shall be:
1.  Beveled and surfaced on the Roadway side and surfaced on the top edge. 

They may be surfaced on four sides (S4S).

2.  Laid in sections at least 12 feet long.
3.  Bolted through the floor plank and outside stringer (or nailing piece) with ¾ inch 

diameter bolts spaced no more than 4 feet apart.

All rails and rail post material shall be S4S and painted as required in 

Section 6-07

. Railing 

members shall be fastened securely together, with the bolts tightened once at installation 
and again just before the Contracting Agency’s final acceptance of the Contract.

6-06.3(2)  Metal Railings

Metal railing includes posts, web members, and horizontal members of the sidewalk 
and Roadway railing. Unless the Plans or Special Provisions show otherwise, these shall 
be made of aluminum alloy or steel.

Before fabricating the railing, the Contractor shall submit Type 2 Working Drawings of the 
shop plans. The Contractor may substitute other rail connection details for those shown 
in the Plans if details of these changes show in the shop plans and if the Engineer accepts 
them in the Working Drawing response comments. In reviewing the shop plans, the 
Engineer indicates only that they are adequate and complete enough. The review does 
not indicate a check on dimensions.

Page 6-194 

Bridge Railings

Anchor bolts shall be positioned with a template to ensure that bolts match the hole 
spacing of the bottom channels or anchorage plates.

Where specified, cover plates shall fit the bottom channel tightly after being snapped 
into position.

Metal railings shall be installed true to line and grade (or camber). After first setting 
the railing, the Contractor shall readjust all or part of it, if necessary, to create an overall 
line and grade pleasing to the eye.

6-06.4 Measurement

Timber railing will be measured by the thousand board feet (MBM) as shown in 

Section 6-04

.

Metal railing will be measured by the linear foot along the line and slope at the base 
of the completed railing.

6-06.5 Payment

Payment will be made for each of the following Bid items that are included in the 
Proposal:

“Timber and Lumber (untreated or name treatment)”, per MBM.
“Bridge Railing Type ____”, per linear foot.
In case no item is included in the Contract for “Bridge Railing Type ____” and 
payment is not otherwise provided, all metal railings shall be included in the lump 
sum Contract price for “Structural Carbon St”. as specified in 

Section 6-03

.

Page 6-294 

Geosynthetic Retaining Walls

All costs in connection with constructing the concrete fascia panels as specified shall 
be included in the unit Contract price per square foot for “Concrete Fascia Panel 
For Geosynthetic Wall”, including all steel reinforcing bars, premolded joint filler, 
polyethylene bond breaker strip, joint sealant, PVC pipe for weep holes, exterior 
surface finish, and pigmented sealer (when specified), constructing and placing the 
concrete footing, edge beam, anchor beam, anchor rod assembly, and backfill.
Shotcrete facing will be paid for in accordance with 

Section 6-18.5

.

“Geosynthetic Wall Single Slope Traffic Barrier”, per linear foot.
“Geosynthetic Wall F-Shape Traffic Barrier”, per linear foot.
“Geosynthetic Retaining Wall Pedestrian Barrier”, per linear foot.
The unit Contract price per linear foot for “Geosynthetic Wall Single Slope Traffic 
Barrier”, “Geosynthetic Wall F-Shape Traffic Barrier”, and “Geosynthetic Retaining 
Wall Pedestrian Barrier” shall be full pay for constructing the barrier on top of the 
geosynthetic retaining wall.

Soil Nail Walls 

6-15

6-15 

Soil Nail Walls

6-15.1 Description

This Work consists of constructing soil nail walls.

6-15.2 Materials

Materials shall meet the requirements of the following sections:
 Grout 

9-20.3(4)

 

Prefabricated Drainage Mat 

9-33.2(3)

Other materials required, including materials for soil nails, shall be as specified in the 
Special Provisions.

6-15.3 

Construction Requirements

6-15.3(1)  General Description

Soil nailing shall consist of excavating to the layer limits shown in the Plans, drilling holes 
at the specified angle into the native material, placing and grouting epoxy coated or 
encapsulated steel reinforcing bars (soil nails) in the drilled holes, placing prefabricated 
drainage material and steel reinforcement, and applying a shotcrete facing over the steel 
reinforcement. After completing the wall to full height, the Contractor shall construct the 
concrete fascia panels as shown in the Plans.

All proprietary items used in the soil nailed Structure shall be installed in accordance 
with the manufacturer’s recommendations. In the event of a conflict between the 
manufacturer’s recommendations and these Specifications, these Specifications 
shall prevail.

6-15.3(2)  Contractor’s Experience Requirements

The Contractor or Subcontractor performing this Work shall have completed at least five 
projects, within the last 5 years, involving construction of retaining walls using soil nails or 
ground anchors or shall have completed the construction of two or more projects totaling 
at least 15,000 square feet of retaining wall with a minimum total of 500 soil nails or 
ground anchors.

The Contractor shall assign an engineer with at least 3 years of experience in the design 
and construction of permanently anchored or nailed Structures to supervise the Work. 
The Contractor shall not use consultants or manufacturer’s representatives in order to 
meet the requirements of this Section. Drill operators and on-site supervisors shall have a 
minimum of 1 year experience installing permanent soil nails or ground anchors.

Contractors or Subcontractors that are specifically prequalified in Class 36 Work will be 
considered to have met the above experience requirements.

Page 6-296 

Soil Nail Walls

6-15.3(3) Submittals

The Contractor shall submit Type 2 Working Drawings of the following information.
1.  A brief description of each project satisfying the Contractors Experience 

Requirements with the Owner’s name and current phone number (this item is not 
required if the Contractor or Subcontractor is prequalified in Class 36).

2.  A list identifying the following personnel assigned to this project and their 

experience with permanently anchored or nailed Structures:
a.  Supervising Engineer.
b.  Drill Operators.
c.  On-site Supervisors who will be assigned to the project. 

3.  The proposed detailed construction procedure that includes:

a.  Proposed method(s) of excavation of the soil and/or rock.
b.  A plan for the removal and control of groundwater encountered during 

excavation, drilling, and other earth moving activities. Include a list of the 
equipment used to remove and control groundwater.

Proposed drilling methods and equipment. 

d.  Proposed hole diameter(s).
e.  Proposed method of soil nail installation.
f. 

Mix design and procedures for placing the grout.

g.  Shotcrete mix design with compressive strength test results.
h.  Procedures for placing the shotcrete (include placement in conditions when 

ground water is encountered).

i. 

Encapsulation system for additional corrosion protection selected for the soil 
nails and anchorages requiring encapsulation.

4.  Detailed Working Drawings of the method proposed for the soil nail testing that 

includes:
a.  All necessary drawings and details to clearly describe the proposed system of 

jacking support, framing, and bracing to be used during testing. 

b.  Calibration data for each load cell, test jack, pressure gauge, stroke counter on 

the grout pump, and master gauge to be used. The calibration tests shall have 
been performed by an independent testing Laboratory, and tests shall have 
been performed within 60 calendar days of the date submitted. Testing or Work 
shall not commence until the Engineer has approved the load cell, jack, pressure 
gage, and master pressure gauge calibrations.

5.  Certified mill test results and typical stress-strain curves along with samples from 

each heat, properly marked, for the soil nail steel. The typical stress-strain curve shall 
be obtained by approved standard practices. The guaranteed ultimate strength, yield 
strength, elongation, and composition shall be specified.

Soil Nail Walls 

6-15

6-15.3(4)  Preconstruction Conference

A soil nail preconstruction conference shall be held at least 5 working days prior to the 
Contractor beginning any permanent soil nail Work at the site to discuss construction 
procedures, personnel and equipment to be used. The list of materials specified on the 
Record of Materials Form (ROM) for this item of Work will also be discussed. Those 
attending shall include:
1.  (representing the Contractor) The superintendent, on site supervisors, and all 

foremen in charge of excavating the soil face, drilling the soil nail hole, placing the 
soil nail and grout, placing the shotcrete facing, and tensioning and testing the 
soil nail.

2.  (representing the Contracting Agency) The Engineer, key inspection personnel, and 

representatives from the WSDOT Construction Office and Materials Laboratory 
Geotechnical Services Branch.

If the Contractor’s key personnel change, or if the Contractor proposes a significant 
revision of the approved permanent soil nail installation plan, an additional conference 
shall be held before any additional permanent soil nail operations are performed.

6-15.3(5) Earthwork

The ground contour above the wall shall be established to its final configuration and slope 
as shown in the Plans prior to beginning excavation of the soil for the first row of soil 
nails. All excavation shall conform t

Section 2-03

.

The excavation shall proceed from the top down in a horizontal lift sequence with the 
ground level excavated no more than 3 feet below the elevation of the row of nails to 
be installed in that lift. The excavated vertical wall face shall not be left unshored more 
than 24 hours for any reason. A lift shall not be excavated until the nail installation and 
reinforced shotcrete placement for the preceding lift has been completed and accepted. 
After a lift is excavated, the cut surface shall be cleaned of all loose materials, mud, 
rebound, and other foreign matter that could prevent or reduce shotcrete bond.

The accuracy of the ground cut shall be such that the required thickness of shotcrete can 
be placed within a tolerance of plus or minus 2 inches from the defined face of the wall, 
and over excavation does not damage overlying shotcrete sections by undermining or 
other causes.

The Contractor should review the geotechnical recommendations report prepared for this 
project for further information on the soil conditions at the location of each wall. Copies 
of the geotechnical recommendations report are available for review by prospective 
Bidders at the location identified in the Special Provisions.

Page 6-298 

Soil Nail Walls

6-15.3(6)  Soil Nailing

The Contractor shall not handle and transport the encapsulated soil nails until the 
encapsulation grout has reached sufficient strength to resist damage during handling. 
The Contractor shall handle the encapsulated soil nails in such a manner to prevent large 
deflections or distortions during handling. When handling or transporting encapsulated 
soil nails, the Contractor shall provide slings or other equipment necessary to prevent 
damage to the soil nails and the corrosion protection. The Engineer may reject any 
encapsulated nail which is damaged during transportation or handling. Damaged 
or defective encapsulation shall be repaired in accordance with the manufacturer’s 
recommendations.

Soil nails shall be handled and sorted in such a manner as to avoid damage or corrosion. 
Prior to inserting a soil nail in the drilled hole, the Contractor and the Engineer will 
examine the soil nail for damage. If, in the opinion of the Engineer, the epoxy coating or 
bar has been damaged, the nail shall be repaired. If, in the opinion of the Engineer, the 
damage is beyond repair, the soil nail shall be rejected.

If, in the opinion of the Engineer, the epoxy coating can be repaired, the Contractor shall 
patch the coating with an Engineer approved patching material.

Nail holes shall be drilled at the locations shown in the Plans or as staked by the Engineer. 
The nails shall be positioned plus or minus 6 inches from the theoretical location shown in 
the Plans. The Contractor shall select the drilling method and the grouting pressure used 
for the installation of the soil nail. The drill hole shall be located so that the longitudinal 
axis of the drill hole and the longitudinal axis of the nail are parallel. At the point of entry 
the soil nail shall be installed within plus or minus 3 degrees of the inclination from 
horizontal shown in the Plans, and the nail shall be within plus or minus 3 degrees of a 
line drawn perpendicular to the face of the wall unless otherwise shown in the Plans.

Water or other liquids shall not be used to flush cuttings during drilling, but air may be 
used. The nail shall be inserted into the drilled hole with centralizers to the desired depth 
in such a manner as to prevent damage to the drilled hole, sheathing or epoxy during 
installation. The centralizers shall provide a minimum of 0.5 inches of grout cover over 
the soil nail and shall be spaced no further than 8 feet apart. When the soil nail cannot be 
completely inserted into the drilled hole without difficulty, the Contractor shall remove 
the nail from the drilled hole and clean or redrill the hole to permit insertion. Partially 
inserted soil nails shall not be driven or forced into the hole. Subsidence, or any other 
detrimental impact from drilling shall be cause for immediate cessation of drilling and 
repair of all damages in a manner approved by the Engineer at no additional cost to the 
Contracting Agency.

If caving conditions are encountered, no further drilling will be allowed until the 
Contractor selects a method to prevent ground movement. The Contractor may use 
temporary casing. The Contractor’s method to prevent ground movement shall be 
approved by the Engineer. The casings for the nail holes, if used, shall be removed as the 
grout is being placed.

Soil Nail Walls 

6-15

Where necessary for stability of the excavation face, a sealing layer of shotcrete may be 
placed before drilling is started, or the Contractor shall have the option of drilling and 
grouting of nails through a stabilizing berm of native soil at the face of the excavation. 
The stabilizing berm shall extend horizontally from the soil face and from the face of 
the shotcrete a minimum distance of 1 foot, and shall be cut down from that point at 
a safe slope, no steeper than 1H:1V unless approved by the Engineer. The berm shall 
be excavated to final grade after installation and full length grouting of the nails. Nails 
damaged during berm excavation shall be repaired or replaced by the Contractor, to the 
satisfaction of the Engineer, at no added cost to the Contracting Agency.

If sections of the wall are constructed at different times than the adjacent soil nail 
sections, the Contractor shall use stabilizing berms, temporary slopes, or other 
measures acceptable to the Engineer, to prevent sloughing or failure of the adjacent soil 
nail sections.

If cobbles and boulders are encountered at the soil face during excavation, the Contractor 
shall remove all cobbles and boulders that protrude from the soil face into the design wall 
section and fill the void with shotcrete. All shotcrete used to fill voids created by removal 
of cobbles and boulders shall be incidental to shotcrete facing.

The grout equipment shall produce a grout free of lumps and undispersed cement. 
A positive displacement grout pump shall be used. The pump shall be equipped with 
a pressure gauge near the discharge end to monitor grout pressures. The pressure 
gauge shall be capable of measuring pressures of at least 150 psi or twice the actual 
grout pressures used by the Contractor, whichever is greater. The grouting equipment 
shall be sized to enable the grout to be pumped in one continuous operation. The mixer 
shall be capable of continuously agitating the grout.

The grout shall be injected from the lowest point of the drilled hole. The quantity of the 
grout and the grout pressures shall be recorded. The grout pressures and grout takes 
shall be controlled to prevent excessive ground heave.

The Contractor shall make and cure grout cubes once per day in accordance with WSDOT 

T 813

. These samples shall be retained by the Contractor until all associated verification 

and proof testing of the soil nails has been successfully completed. If the Contractor 
elects to test the grout cubes for compressive strength, testing shall be conducted by 
an independent laboratory and shall be in accordance with the FOP for AASHTO T106.

6-15.3(7)  Shotcrete Facing

Prior to placing any shotcrete on an excavated layer, the Contractor shall vertically 
center prefabricated drainage mat between the columns of nails as shown in the Plans. 
The prefabricated drainage mat shall be installed in accordance with the manufacturer’s 
recommendations. The permeable drain side shall be placed against the exposed soil 
face. The prefabricated drainage mat shall be installed after each excavation lift and shall 
be hydraulically connected with the prefabricated drainage mat previously placed, such 
that the vertical flow of water is not impeded. The Contractor shall tape all joints in the 
prefabricated drainage mat to prevent shotcrete intrusion during shotcrete application.

Page 6-300 

Soil Nail Walls

The Contractor shall place steel reinforcing bars and welded wire fabric, and apply the 
shotcrete facing in accordance with 

Section 6-18

 and the details shown in the Plans.

The shotcrete shall be constructed to the minimum thickness as shown in the Plans. Costs 
associated with additional thickness of shotcrete due to over excavation or irregularities 
in the cut face shall be borne by the Contractor.

Each soil nail shall be secured at the shotcrete facing with a steel plate as shown in the 
Plans. The plate shall be seated on a wet grout pad of a pasty consistency similar to that 
of mortar for brick-laying. The nut shall then be sufficiently tightened to achieve full 
bearing surface behind the plate. After the shotcrete and grout have had time to gain the 
specified strength, the nut shall be tightened with at least 100 foot-pounds of torque. 
After final tightening of the nut, the threads of the soil nail shall at a minimum be flush 
with the end of the nut.

6-15.3(8)  Soil Nail Testing and Acceptance

Both verification and proof testing of the nails is required. The Contractor shall supply all 
materials, equipment, and labor to perform the tests. The Contractor shall submit Type 
1 Working Drawings of all test data. Soil nails used for verification tests and proof tests 
shall not be production soil nails, but instead shall be separate sacrificial soil nails not 
otherwise incorporated into the Work.

The testing equipment shall include a dial gauge or vernier scale capable of measuring to 
0.001 inch of the ground anchor movement. A hydraulic jack and pump shall be used to 
apply the test load. The movement-measuring device shall have a minimum travel equal 
to the theoretical elastic elongation of the total nail length plus 1 inch. The dial gauge or 
vernier scale shall be aligned so that its axis is within 5 degrees from the axis of the nail 
and shall be monitored with a reference system that is independent of the jacking system 
and excavation face.

The jack and pressure gauge shall be calibrated by an independent testing Laboratory 
as a unit. Each load cell, test jack and pressure gauge, grout pump stroke counter, and 
master gauge, shall be calibrated as specified in 

Section 6-15.3(3)

, item 4b. Additionally, 

the Contractor shall not use load cells, test jacks and pressure gauges, grout pump stroke 
counters, and master gauges, greater than 60 calendar days past their most recent 
calibration date, until such items are re-calibrated by an independent testing Laboratory.

The pressure gauge shall be graduated in increments of either 100 psi or 2 percent of 
the maximum test load, whichever is less. The pressure gauge shall be selected to place 

the maximum test load within the middle ⅔ of the range of the gauge. The ram travel of 

the jack shall not be less than the theoretical elastic elongation of the total length at the 
maximum test load plus 1 inch. The jack shall be independently supported and centered 
over the nail so that the nail does not carry the weight of the jack. The Contractor shall 
have a second calibrated jack pressure gauge at the site. Calibration data shall provide a 
specific reference to the jack and the pressure gauge.

Soil Nail Walls 

6-15

The loads on the nails during the verification and proof tests shall be monitored to 
verify consistency of load – defined as maintaining the test load within 5 percent of the 
specified value. Verification and proof test loads less than 20,000 pounds or sustained for 
5 minutes or less shall be monitored by the jack pressure gauge alone. Verification and 
proof test loads equal to or greater than 20,000 pounds and sustained for longer than 
5 minutes shall be monitored with the assistance of an electric or hydraulic load cell. The 
Contractor shall provide the load cell, the readout device, and a calibration curve from 
the most recent calibration as specified in 

Section 6-15.3(3)

, item 4b. The load cell shall 

be selected to place the maximum test load within the middle ⅔ of the range of the load 

cell. The load cell shall be mounted between the jack and the anchor plate. The stressing 
equipment shall be placed over the nail in such a manner that the jack bearing plates, load 
cell and stressing anchorage are in alignment.

Nails to be tested shall be initially grouted no closer to the excavation face than the 
dimension shown in the Plans. After placing the grout, the nail shall remain undisturbed 
until the grout has reached strength sufficient to provide resistance during testing. Test 
nails shall be left in the ground after testing, with the exposed portion of the test nail cut 
and removed to 2 feet behind the excavated face or inside face of shotcrete. The drill 
holes for test nails shall be completely backfilled with grout or nonstructural filler after 
testing on those test nails has been completed.

Load testing shall be performed against a temporary reaction frame with bearing pads 
that bear directly against the existing soil or the shotcrete facing. Bearing pads shall be 
kept a minimum of 12 inches from the edges of the drilled hole and the load shall be 
distributed to prevent failure of the soil face or fracture of the shotcrete. The Contractor 
shall submit Type 2E Working Drawings of the reaction frame.

The soil nail load monitoring procedure for verification and proof test load greater than 
20,000 pounds and sustained for longer than 5 minutes shall be as follows:
1.  For each increment of load, attainment of the load shall be initially established and 

confirmed by the reading taken from the jack gauge.

2.  Once the soil nail anchor load has been stabilized, based on the jack gauge reading, 

the load cell readout device shall immediately be read and recorded to establish the 
load cell reading to be used at this load. The load cell reading is intended only as a 
confirmation of a stable soil nail load, and shall not be taken as the actual load on the 
soil nail.

3.  During the time period that the load on the soil nail is held at this load increment, 

the Contractor shall monitor the load cell reading. The Contractor shall adjust the 
jack pressure as necessary to maintain the initial load cell reading. Jack pressure 
adjustment for any other reason will not be allowed.

4.  Soil nail elongation measurements shall be taken at each load increment as specified 

in Sections

 6-15.3(8)A

 and 

6-15.3(8)B

.

5.  Steps 1 through 4 shall be repeated at each increment of load, in accordance with 

the load sequence specified in Sections

 6-15.3(8)A

 and 

6-15.3(8)B

.

Page 6-302 

Soil Nail Walls

6-15.3(8)A 

Verification Testing

Verification testing shall be performed on nails installed within the pattern of production 
nails to verify the Contractor’s procedures, hole diameter, and design assumptions. No 
drilling or installation of production nails will be permitted in any ground/rock unit unless 
successful verification testing of anchors in that unit has been completed and approved 
by the Engineer, using the same equipment, methods, nail inclination, nail length, and 
hole diameter as planned for the production nails. Changes in the drilling or installation 
method may require additional verification testing as determined by the Engineer and 
shall be done at no additional expense to the Contracting Agency. Verification tests may 
be performed prior to excavation for the soil nail wall.

Successful verification tests are required within the limits as specified in the Special 
Provisions. Test nail locations within these limits shall be at locations selected by 
the Engineer.

The Contractor shall submit Type 2E Working Drawings consisting of design details of 
the verification testing, including the system for distributing test load pressures to the 
excavation surface and appropriate nail bar size and reaction plate. The intent is to stress 
the bond between the grout and the surrounding soil/rock to at least twice the design 
load transfer. Prior to beginning verification testing, the Contractor shall measure and 
record the length of the nonbonded zone for each verification test soil nail.

The bar shall be proportioned such that the maximum stress at 200 percent of the test 
load does not exceed 80 percent of the yield strength of the steel. The jack shall be 
positioned at the beginning of the test such that unloading and repositioning of the jack 
during the test will not be required. The verification tests shall be made by incrementally 
loading the nails in accordance with the following schedule of hold time:
 

AL 

1 minute 

0.25TL 

10 minutes 

0.50TL 

10 minutes 

0.75TL 

10 minutes 

1.00TL 

10 minutes 

1.25TL 

10 minutes 

1.50TL 

60 minutes 

1.75TL 

10 minutes 

2.00TL 

10 minutes 

AL = Nail Alignment Load  
TL = Nail Test Load

The test load shall be determined by the following equation = Test Load (TL) = Bond 
Length (BL) × Design Load Transfer (DLT).

The load shall be applied in increments of 25 percent of the test load. Each load 
increment shall be held for at least 10 minutes. Measurement of nail movement shall be 
obtained at each load increment. The load-hold period shall start as soon as the load is 
applied and the nail movement with respect to a fixed reference shall be measured and 
recorded at 1 minute, 2, 3, 4, 5, 6, 10, 20, 30, 40, 50, and 60 minutes.

 

 

 

 

 

 

 

Content      ..     67      68      69      70     ..