Page 6-172
6-05 Piling
6-05.1 Description
This Work consists of furnishing and driving piles (timber, precast concrete, cast-in-place
concrete, and steel) of the sizes and types the Contract or the Engineer require. This
Work also includes cutting off or building up piles when required. In furnishing and driving
piles, the Contractor shall comply with the requirements of this Section, the Contract, and
the Engineer.
6-05.2 Materials
Materials shall meet the requirements of the following sections:
Reinforcing Steel
9-07
Prestressing Steel
9-07.10
Timber Piling
9-10.1
Concrete Piling
9-10.2
Cast-In-Place Concrete Piling
9-10.3
Steel Pile Tips and Shoes
9-10.4
Steel Piling
9-10.5
Mortar
9-20.4
6-05.3
Construction Requirements
6-05.3(1) Piling Terms
Concrete Piles – Concrete piling may be precast or precast-prestressed concrete, or steel
casings driven to the ultimate bearing resistance called for in the Contract which are filled
with concrete (cast-in-place) after driving.
Steel Piles – Steel piles may be open-ended or closed-ended pipe piles, or H-piles.
Overdriving – Over-driving of piles occurs when the ultimate bearing resistance
calculated from the equation in
Section 6-05.3(12)
, or the wave equation driving criteria
if applicable, exceeds the ultimate bearing resistance required in the Contract in order to
reach the minimum tip elevation specified in the Contract, or as required by the Engineer.
Maximum Driving Resistance – The maximum driving resistance is either the pile ultimate
bearing resistance, or ultimate bearing resistance plus overdriving to reach minimum tip
elevation as specified in the Contract, whichever is greater.
Wave Equation Analysis – Wave equation analysis is an analysis performed using the
wave equation analysis program (WEAP) with a version dated 1987 or later. The wave
equation may be used as specified herein to verify the Contractor’s proposed pile driving
system. The pile driving system includes, but is not necessarily limited to, the pile, the
hammer, the helmet, and any cushion. The wave equation may also be used by the
Engineer to determine pile driving criteria as may be required in the Contract.