Permanent Ground Anchors
6-17
3. Unbonded length corrosion protection system, including the permanent rubber seal
between the trumpet and the tendon unbonded length corrosion protection and
the transition between the tendon bond length and the unbonded tendon length
corrosion protection.
4. Bond length corrosion protection system
5. Anchorage and trumpet
6. Anchorage corrosion protection system
7. Anchors using non-restressable anchorage devices
The Contractor shall submit Type 2 Working Drawings consisting of shop plans as
specified in
Section 6-03.3(7)
for all structural steel, including the permanent ground
anchors.
The Contractor shall submit Type 1 Working Drawings consisting of the mix design for
the grout conforming to
Section 9-20.3(4)
and the procedures for placing the grout. The
Contractor shall also submit the methods and materials used in filling the annulus over
the unbonded length of the anchor.
The Contractor shall submit Type 2 Working Drawings consisting of the method proposed
to be followed for the permanent ground anchor testing. This shall include all necessary
drawings and details to clearly describe the method proposed.
The Contractor shall submit Type 2 Working Drawings consisting of calibration data
for each load cell, test jack, pressure gauge and master pressure gauge to be used. The
calibration tests shall have been performed by an independent testing Laboratory and
tests shall have been performed within 60 calendar days of the date submitted.
6-17.3(4) Preconstruction Conference
A permanent ground anchor preconstruction conference shall be held at least 5 working
days prior to the Contractor beginning any permanent ground anchor Work at the site
to discuss construction procedures, personnel, and equipment to be used. The list of
materials specified on the Record of Materials Form (ROM) for this item of Work will also
be discussed. Those attending shall include:
1. (representing the Contractor) The superintendent, on site supervisors, and all
foremen in charge of drilling the ground anchor hole, placing the permanent ground
anchor and grout, and tensioning and testing the permanent ground anchor.
2. (representing the Contracting Agency) The Engineer, key inspection personnel, and
representatives from the WSDOT Construction Office and Materials Laboratory
Geotechnical Services Branch.
If the Contractor’s key personnel change, or if the Contractor proposes a significant
revision of the approved permanent ground anchor installation plan, an additional
conference shall be held before any additional permanent ground anchor operations
are performed.