Chapter –9   Safety & Environment  

 

Version No: 1.0-d0 

Date Issued: dd/mm/yyyy 

Document Title: MANUAL MAINTENANCE FOR  DIESEL LOCOMOTIVES 
 

Revised 2013 

Printed: 2015/03/08 

Page 208 of 303

 

 

briefed through organized training courses so as to know what are the special 
precautions that he has to take.  

 

9.7.12 

The supervisor and some of his men should be trained in firefighting & first aid. 
Periodic refresher courses should be used to keep them in readiness.   

 

9.7.13 

Sufficient nos. of safety precautions/posters shall be displayed prominently in shed. 
Some sample safety precautions in different areas of working in shed are at 
Annexures-9.3.1 to 9.3.14.

 

 These are only illustrative and not exhaustive ones. 

9.7.14 

Unsafe working conditions should be completely eliminated. Tools, machinery and 
plants which help in reducing staff fatigue can be used to improve safety. These can 
be pneumatic, hydraulic and electrical tools for torquing, slackening, etc.  

 

9.7.15 

Material handling equipment like forklifts, battery operated platform trucks, 
hydraulic trolleys etc. should be maintained by following laid down maintenance 
schedules. 

 

9.7.16 

Points and crossings in shed area should be attended/renewed as per laid down 
periodicity. Electrically operated points in place of manually operated points should 
be provided. 

 

9.7.17 

Staff involved in safety related activities like: Welding, EOT crane operators, M&P 
maintainers, etc.,  should have competency certificate, issued by Authorized 
Agency. 

 

9.7.18 

Indian Electricity Rules 1956: Compliance to Indian Electricity Rules 1956 need 
to be ensured. Some of the vital requirements are:- 
 

9.7.18.1  Certification of electrical installations in shed every five years. 

 

9.7.18.2  Staff working on electrical installation to have Competency certificate 

 

9.7.18.3  Measurement of IR of HV and LV circuits of electric installations.  

 

9.7.18.4  Proper earthing of all electrical devices. 

 

9.7.18.5  Checking of earthing devices of shed once in two years. 

 

9.7.19 

A safety review committee shall be formed consisting of: Officers, Supervisors, 
trade union representatives and interested staff. This review committee shall 
conduct a thorough inspection of shed floor once in a month and take corrective & 
preventive action for deficiencies noticed. 

 

9.7.20 

A multi-disciplinary team of JS/SS of Civil, Mechanical and Electrical departments 
should carry out checks and identify the actions to be taken for improving safety. 
The periodicity of such checks should be once in a year. 

 

9.8  Prevention of Fire: With fire preventing units disbanded from most of the sheds, proper 

planning needs to be done for prevention of fire. 

 

Home 

Ch-9 

Draft

Document No: 

Chapter –9   Safety & Environment  

 

Version No: 1.0-d0 

Date Issued: dd/mm/yyyy 

Document Title: MANUAL MAINTENANCE FOR  DIESEL LOCOMOTIVES 
 

Revised 2013 

Printed: 2015/03/08 

Page 209 of 303

 

 

9.8.1 

The SSE/General of Diesel Shed will be responsible for the provision, maintenance 
and operation of the fire prevention and firefighting equipment and organization in 
the Diesel sheds. 

 

9.8.2 

Proper network of approach roads, static tanks and hydrants at suitable  locations 
shall be available. If not included in the original plan, these measures should be 
designed and completed as early as possible. 

 

9.8.3 

Sufficient water supply arrangements in Static Tanks & Hydrants shall be ensured. 

 

9.8.4 

Hoses for use in fire hydrants shall be provided near the hydrants. These hoses shall 
be housed in a box with glass front.   

 

9.8.5 

Fire extinguishers shall be conspicuously available at strategic points. Periodic 
maintenance, testing and refilling of Fire Extinguishers shall be ensured. The date 
of last inspection done and next due date shall be painted on inspected/ maintained 
fire extinguishers.  

 

9.8.6 

Adequate number of Fire Alarm boxes shall be provided at various locations of the 
shed. 

 

9.8.7 

A layout plan of the shed indicating availability of fire fighting facilities: fire 
extinguishers, sand buckets, Hydrants, Static tanks, fire alarm boxes, etc., shall be 
displayed at three prominent locations in the shed.  

 

9.8.8 

Proper record keeping of operational history, inspection and maintenance of fire 
extinguishers, working of water supply and pumping out arrangement in Static 
Tanks and of Hydrants provided in different places of shed shall be maintained. 

 

9.8.9 

Apart from the regular fire fighting staff of SSE/General, supervisors and a nucleus 
staff in every section  should be trained to handle ‘ABC’ class fires. Regular 
refresher courses for such staff should also be arranged. 

 

9.8.10 

The SSE/General shall make periodic inspection of the premises to check correct 
working practices, particularly stocking of combustible materials and accordingly 
take corrective action, if required.  

 

9.8.11 

Fire extinguishers suitable for ‘BC’ Class equipment have to be provided on locos. 
Timely and correct maintenance of these fire extinguishers should be ensured by 
SSE/General. 

 

9.8.12 

The large stocks of  combustibles such as HSD, oils, lubricants, solvents, etc., in a 
typical maintenance depot are specific responsibilities of the SSE/General. He 
should be fully associated in the construction stage and follow up through regular 
works progress to upgrade the stocking and handling facilities, as and when 
required.  

 

9.8.13 

Shed floors should be kept clean – free of oil/muck. Habit of spillage free handling 
of oil/grease on floor should be inculcated in the staff. This will not only improve 
work environment, but also curtail the chances of fire accidents. 

 

Home 

Ch-9 

Draft

Document No: 

Chapter –9   Safety & Environment  

 

Version No: 1.0-d0 

Date Issued: dd/mm/yyyy 

Document Title: MANUAL MAINTENANCE FOR  DIESEL LOCOMOTIVES 
 

Revised 2013 

Printed: 2015/03/08 

Page 210 of 303

 

 

9.8.14 

All electrical fittings/Circuit breakers, etc., shall be checked as per schedule for 
avoiding any short circuits. The “electrical earthing” of shed should be checked as 
per schedule. No hanging or loose wires shall be allowed in the shed. 

 

9.9  Safety Management System: Diesel sheds shall have integrated safety management 

system in line with provisions of OHSAS so that an assured safety management system is 
in place in the shed.  

 

9.9.1 

Identification and Control of Hazard:  Diesel Sheds shall establish and maintain 
a system for ongoing identification of hazards, the assessment of risk and 
implementation of necessary control measures of various activities in Diesel Sheds 
to facilitate setting up of occupational health and safety targets.  
 

9.9.1.1  While identifying the hazards not only the routine and non-routine activities shall 

be taken into consideration, but also identification of the hazardous activities of 
all personnel having access to the workplace shall be taken into account. 

 

9.9.1.2  A cross functional team shall be used for identification of hazards. The team shall 

consider process flow diagram, select activity and use work activity 
information, its effect on safety and health of employees, requirements of 
relevant acts and reactive monitoring data to identify hazards. 

 

9.9.1.3  The hazards are reviewed and the risk of each of these hazards is determined by 

estimating the likelihood and potential severity of harm. While estimating the 
likelihood of harm, the existing adequacy of control measures already 
implemented is considered.  

 

9.9.1.4  Risks are identified and classified according to their estimated likelihood and 

potential severity of harm, as mentioned below: 

 

a)  Severity of risk will be assessed as follows: 

 

Severity 

Remarks 

Slightly harmful  Injury of very minor nature where there is no incapacitation from 

work place.  

Harmful 

The cases of injury in which loss of man days takes place and/or 
permanent disability  

Extremely 
harmful 

The cases of fatal injury  

 

 

b)  Probability of occurrence is assessed as follows: 

 

Probability 

Remarks 

Highly unlikely 

There is no occurrence in the past and no such possibility in the 
future as well. 

Unlikely 

There are very few cases reported in the past 

Likely 

There are cases which have occurred in the past & there is 
likelihood of occurrence in the future also 

 

Home 

Ch-9 

Draft

Document No: 

Chapter –9   Safety & Environment  

 

Version No: 1.0-d0 

Date Issued: dd/mm/yyyy 

Document Title: MANUAL MAINTENANCE FOR  DIESEL LOCOMOTIVES 
 

Revised 2013 

Printed: 2015/03/08 

Page 211 of 303

 

 

c)  The various risk levels are shown in the following table. These risk levels in form the 

basis for deciding whether improved controls are required and timetable for action. 
The outcome of risk assessment is treated as inventory of actions, in priority order, to 
devise, maintain or improve controls. 

 

Risk Level 

 

Remarks 

Trivial 

No action is required and documentary records need to be kept for 
data analysis. 

Acceptable  

No additional controls are required. Monitoring is required to 
ensure that the controls are maintained.  

Moderate 

Efforts may be made to reduce the risk, but the cost of prevention 
should be measured and limited. Risk reduction measures should 
be implemented within a definite time period. 

Substantial 

Work should not be started until the risk has been reduced. 
Considerable resources may have to be allocated to reduce risk. 
Where the risk involves work in progress, urgent action should be 
taken. 

Unacceptable 
Risk 

Work should not be started or continued until the risk has been 
reduced. The work has to remain prohibited until the risk is 
reduced. There is no consideration for limitation of resources.  

 

9.9.1.5  Operational Control Procedures shall be implemented to control the significant 

risks. Management programme  are drawn up to introduce time bound action 
plans to reduce risks and also to monitor the action plans. 

 

9.9.1.6  Risk assessment provides input to facility requirements and identification of 

training needs. 

 

9.9.1.7  Control of Hazard:  For moderate risk levels, management  programme  are 

planned to reduce risk level in a definite time period. The result of this 
assessment is considered while setting up objectives. In case any new activity is 
added or the existing one is changed, it shall be taken into account and the risk 
assessment again done  for this risk. The hazards associated with the same are 
identified and risks assessed. The process of risk assessment is carried out once 
in a year to assess the effectiveness of control measures and to see if the hazards 
and risks have been significantly controlled over the period. 

 

9.9.2 

Monitoring and Measurement of OHSAS performance:  Diesel Shed shall 
establish and maintain a system for monitoring and measurement of OHSAS 
performance on a regular basis and following plan be followed:- 
 

9.9.2.1  Procedure has been established which identifies the measures of performance to 

be measured and monitored. 

 

9.9.2.2  Both quantitative and qualitative measures have been considered, where 

appropriate 

 

9.9.2.3  Proactive measures of performance that monitor compliance  of  OHSAS 

arrangements through surveillance and inspection have been identified 

 