Military reference books and manuals (2009-2023, Volume 5) - page 32

 

  Index      Manuals     Military reference books and manuals (2009-2023, Volume 5)

 

Search            copyright infringement  

 

   

 

   

 

Content      ..     30      31      32      33     ..

 

 

 

Military reference books and manuals (2009-2023, Volume 5) - page 32

 

 

Procedure for Energy Isolation - Electrical
Page 32 of 32
Revision/Review Log
Revision Date
Authority
Custodian
Revision Details
24 Aug 2004
Central
EI (electrical)
Initial issue as controlled document
Engineering
Technical
Senior Authority
Authority
18 June 2007
Steve Grittner
Yvonne Hepburn
Table of Contents changed as follows:
(Central
EI (electrical)
Sub-sections included into the Table of Contents.
Engineering
Technical
General:
Senior
Authority
Throughout the procedure the document
Authority)
numbering for referred procedures has been
changed.
Section 1. Introduction:
1.1 is now Scope. 1.2 is now General
Requirements. 1.3 is now Stopping Unsafe Work.
1.4 is now Deviations. 1.5 is now Document
Review. 1.6 is now BP Golden Rules of Safety.
1.7 is now SSOW Specific Cross References. 1.8
is now Language Facilitation. 1.9 is now
Procedure Summary. 1.10 is now Document
review.
Section 2. Roles and Responsibilities:
2.6 Responsible Electrical Person: Added on to
end of paragraph, “and assessed by site Electrical
Technical Authority or delegate”. 2.11Competent
Isolator: Added into the paragraph after REP is
“with the agreement of the ETA”.
Section 6. Isolation & Planning:
6.4 Isolation Methods: New sub-section added
titled “(d) Prove Dead, Disconnect, Label”. 6.5
Isolation Standards: Note 4 added to the standard
stating “Competent Isolator perform isolations for
the specific equipment and voltage that they have
been authorized for”.
Section 7. Isolation Implementation and
Control:
7.5 Operational Locks; Added into
the second paragraph after maintenance is “or for
transformer offload tap chargers”.
Appendices.
2 additional appendices included to the document
as follows:
 Procedure Summary
 Procedure Feedback & Improvement
Suggestions
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Process
Page 1 of 40
Procedure for Energy Isolation - Process
AZSPU-HSSE-DOC-00049-2
This number supersedes UNIF-HSE-PRO-107-C2
Authority:
AzSPU CHSSE
Custodian:
Central Engineering Senior Authority
Manager
:
AzSPU
Document
Administrator:
Document Asset Technician
Issue Date:
09 Sept 2004
Issuing Dept:
CHSSE
Revision Date:
14 September 2007
Control Tier:
2
Next Review
14 September 2008
Date:
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 2 of 40
TABLE OF CONTENTS
1
INTRODUCTION
4
1.1
PURPOSE
4
1.2
SCOPE
4
1.3
LEGISLATION & STANDARDS
4
1.4
COMPANY REQUIREMENTS
4
1.5
STOPPING UNSAFE WORK
5
1.6
DEVIATIONS
5
1.7
DOCUMENT REVIEW
5
1.8
SSOW SPECIFIC CROSS REFERENCES
5
1.9
ENERGY ISOLATION GOLDEN RULES OF SAFETY
5
1.10
LANGUAGE FACILITATION
6
1.11
PROCEDURE SUMMARY
6
2
DEFINITIONS
6
2.1
DEFINITIONS
6
2.2
ABBREVIATIONS
8
3
ROLES AND RESPONSIBILITIES
8
3.1
PERFORMANCE UNIT LEADER
8
3.2
ASSET MANAGER
8
3.3
OFFSHORE INSTALLATION MANAGER (OIM)/SITE CONTROLLER (SC)/SITE MANAGER (SM)9
3.4
AREA AUTHORITY (AA)
9
3.5
ISOLATING AUTHORITY (IA)
9
3.6
PERFORMING AUTHORITY (PA)
10
3.7
MAINTENANCE PERSONNEL
10
3.8
THE ONSHORE SUPPORT ENGINEER
10
3.9
CUSTODIAN
10
4
MONITORING AND AUDITING OF ISOLATIONS
10
4.1
MONITORING
10
4.2
SELF-REGULATION AND AUDIT
10
5
COMPETENCY, TRAINING AND AWARENESS
11
5.1
GENERAL
11
5.2
LEVELS OF TRAINING
11
6
THE ISOLATION CONFIRMATION CERTIFICATION (ICC) PROCESS
11
6.1
GENERAL
11
7
ISOLATION REVIEW AND LEVEL 2 RISK ASSESSMENT PROCESS
12
7.1
REVIEW AND RISK ASSESSMENT PROCESS
12
7.2
REJECTION OF ISOLATION DESIGN
12
7.3
RISK ASSESSMENT OF NON-COMPLIANT ISOLATIONS
13
7.4
RISK ASSESSMENT RECORDS
13
7.5
HAZARDOUS WORK
13
8
TYPES OF ISOLATIONS
13
8.1
BOUNDARY ISOLATIONS
13
8.2
LONG-TERM ISOLATIONS
14
8.3
PERSONAL ISOLATIONS
14
8.4
ADDITIONAL ISOLATIONS
15
8.5
ISOLATION FOR CONFINED SPACE ENTRY
15
8.6
PROVISION FOR ISOLATIONS DURING MODIFICATION OF DESIGN AND NEW FACILITIES.. 15
8.7
ISOLATION OF HIGH PRESSURE SMALL BORE PIPING
15
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 3 of 40
9
REGISTERS
16
10 RECORDS
16
APPENDIX A: ISOLATION STANDARDS
17
APPENDIX B: GUIDANCE NOTES
19
APPENDIX C: TYPICAL VALVE ISOLATIONS INTEGRITY TESTS
30
APPENDIX D: ENERGY ISOLATIONS FLOWCHART
33
APPENDIX E: PROCEDURE SUMMARY………………………………………………35
APPENDIX F: FEEDBACK & IMPROVEMENT SUGGESTIONS……………………38
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 4 of 40
1
INTRODUCTION
1.1
PURPOSE
The purpose of this document is to ensure there is clarity to the detailed requirements that
applies to the preparation for isolation and reinstatement of process, utility and drilling
systems.
1.2
SCOPE
The contents of this procedure are applicable to all BP owned and managed sites /
installations in Azerbaijan and Georgia. Contractors working on BP owned or managed sites
/ installations are also responsible for alignment with this procedure.
This document does not replace the procedures prepared and adopted by specialist
contractors. Neither does it supersede any national and local regulatory requirements.
This procedure contributes to compliance with the “HSE expectations” contained in “getting
HSE right”, the „Golden Rules of Safety‟ and the Control of Work (CoW) standard that the
Hazards associated with BP activities are identified and that the Risks are assessed and
managed.
All guidelines contained shall be regarded as the minimum requirements for BP owned or
managed sites / installations in Azerbaijan and Georgia.
The scope covers defined activities of BP and Contractors at all BP AzSPU sites and
installations.
1.3
LEGISLATION & STANDARDS
The aim of this Safe System of Work is to achieve ”no accidents”, “no harm to people” and
“no damage to the environment”. To achieve this aim, this SSOW complies with National
Legislation, the terms of the Production Sharing Agreement (PSA) and mandatory BP
Standards.
The best International Oil Industry practice and relevant goal setting legislation have been
adopted to reduce the level of risk to as low as reasonably practicable and therefore well
below that mandated by applicable statutory laws and regulations.
In the absence of local regulations, BP Group Standards will apply. In addition, appropriate
UK and US regulations and industry best practice have been considered in setting suitable
goals and targets.
1.4
COMPANY REQUIREMENTS
It is a company requirement that all tasks are subjected to an assessment of risk to
demonstrate that risks have been reduced to as low a level as reasonably practicable
(ALARP). This can be achieved by complying with the Company‟s existing standards. Where
compliance with Company standards cannot reasonably be achieved, a formal level 2 Risk
Assessment will be undertaken to identify any additional controls and demonstrate that risks
remain as low as reasonably practicable. Whether by compliance with Company Standards
or through level 2 Risk Assessment, the Company‟s Golden Rules of Safety must be
complied with. Golden Rules are non-negotiable.
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 5 of 40
1.5
STOPPING UNSAFE WORK
To stop the continuation of potentially unsafe work at the earliest possible stage the Control
of Work (CoW) Policy and this procedure for Energy Isolation - Process make it very clear
that all personnel are obliged and have the authority to “STOP” the work that they consider
to be unsafe.
1.6
DEVIATIONS
This procedure is written in sufficient detail that it should be able to be applied consistently
at all sites / installations. There may still be the requirement for some local rules covering
site
/ installation specific logistical/administrative arrangements and local variations in
responsibilities to reflect differences in organisational arrangements. These local rules
should not deviate from the core processes within this document. Any form of deviation from
this procedure, including but not limited to local rules, shall be requested and authorised in
accordance with SSOW, Deviations from Regulations and Procedures procedure (Doc. No:
AZSPU-HSSE-DOC-00011-2).
1.7
DOCUMENT REVIEW
This document will be reviewed on an annual basis when users from the sites / installations
will have an opportunity to propose changes to the existing processes and procedures. The
document Technical Authority will be responsible for coordinating this review.
1.8
SSOW SPECIFIC CROSS REFERENCES
This SSOW procedure shall, where appropriate, be used in conjunction with this suite of BP
AzSPU SSOW Procedures referenced below.
Document Number
Title of Procedure
AZSPU-HSSE-DOC-00011-2
Deviations from Regulations and Procedures
AZSPU-HSSE-DOC-00054-2
Incident Investigation and Reporting
AZSPU-HSSE-DOC-00060-2
Permit To Work
AZSPU-HSSE-DOC-00012-2
Authorization
AZSPU-HSSE-DOC-00063-2
Task Risk Assessment
AZSPU-HSSE-DOC-00048-2
Energy Isolations-Electrical
AZSPU-HSSE-DOC-00013-2
Confined Space Entry
AZSPU-HSSE-DOC-00055-2
Leak Testing
AZSPU-HSSE-DOC-00002-2
BP Control of Work Standards
1.9
ENERGY ISOLATION GOLDEN RULES OF SAFETY
Energy Isolation is one of BP‟s Golden Rules. It states that:
Any isolation of energy systems, e.g. mechanical, electrical, process, hydraulic, pneumatic,
gravitational, chemical, radioactive, thermal, or other energy source that could cause injury,
cannot proceed unless:
 The method of isolation and discharge of stored energy are agreed and executed by a
competent person(s)
 Any Stored energy is discharged
 A system of locks and tags is utilized at isolation points
 A test is conducted to ensure the isolation is effective
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 6 of 40
 Isolation effectiveness is periodically monitored
1.10 LANGUAGE FACILITATION
Due to the various languages spoken at sites / installations, there is a necessity to assist all
with “an ease of understanding”. Therefore, the development and use of information tools
are available.
1.11 PROCEDURE SUMMARY
A Procedure Summary has been developed in a form of a leaflet, which can be carried by
the Line Supervisors while conducting their day-to-day work tasks. The Leaflet summarizes
the contents of this procedure for Energy Isolation - Process. The Procedure Summary can
also be used as a guideline for Line Supervisors to deliver their daily toolbox talk. (See
Appendix E)
2
DEFINITIONS
2.1
DEFINITIONS
Auto Ignition
The temperature at which a flammable substance would auto ignite without an
external ignition source
Competent
A person who, by reason of his or her training, knowledge, experience and
Person
judgment is considered by management to be capable of planning and
supervising the safe isolation of plant.
Confined Space
A “confined space” is any enclosed space or partially enclosed space which is
large enough that an employee can bodily enter it and perform assigned work,
has limited or restricted means of entry or exit, unfavourable natural ventilation
and is not designed for continuous occupancy.
The general definition of “confined space” shows that many types of spaces
may be considered confined and therefore hazardous - large pipelines, tanks,
vessels, separators, ducts, sewers, mud, pits, flues, manholes and voids
between modules and in legs on offshore installations.
The definition also includes any space in which dangerous levels of
contaminants can accumulate and ventilation is restricted, e.g. excavations
(normally deeper than 1.2m), the space above floating roofs on floating roof
tanks, open topped tanks, closed or unventilated rooms, sumps and culverts
and any other poorly ventilated areas.
Hazardous
Corrosive, toxic or irritant chemical fluid, e.g., nitrogen, steam or hot water,
Utility
drilling mud, diesel oil, Aviation Turbine Kerosene, and other fluids that could
have an environmental impact.
Isolation
A method of preventing the passage of fluids through connecting pipe work
and the disconnection of all forms of motive power in order to allow safe
access to allow intrusive equipment maintenance.
Isolation
This combines in one document a record of all isolations required for a task to
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 7 of 40
Confirmation
be carried out safely.
Certificate
Long Term
An isolation that remains in place after permit to work cancellation, and
Isolation
recorded as “Long Term”. A register is maintained of all Long Term Isolations
Mothballed
Equipment that has been taken out of service, and will not be used in the near
future. The equipment is disconnected from all energy sources. No isolation is
required.
Non-hazardous
Cold water, air, etc.
Utility
Performing
These terms shall have the meanings assigned to them in AZSPU-HSSE-
Authority, Area
DOC-00012-2, Authorisation.
Authority and
Isolating
Authority
Positive
Isolation by means of a fixed barrier, such as a blank flange (following spool
Isolation
removal), blind plate or spectacle plate, bolted or clamped in place and
conforming to the pipe work specification, which provides an equivalent
standard of containment to the pipe work in which it is installed.
Process Fluid
Well fluids, produced water, live crude, stabilised crude, gas, NGL or any other
produced fluid containing hydrocarbon gas or liquid. H2S, Naturally Occurring
Radio-active Material or hydrates may also be present.
Reasonably
This term implies that an evaluation of costs versus benefits must be made.
Practicable
Where the cost or difficulty of a precaution is grossly out of proportion to the
reduction in risk likely to be achieved by implementing the precaution, the
precaution can be considered not reasonably practicable.
Any additional risks that may arise while installing or removing the precaution
must also be taken into consideration in determining what is reasonably
practicable.
Secondary
A method of isolation normally used only to support process isolation involving
means of
valves, with the objective being process isolation, e.g., isolation of an actuator
isolation
before isolating the appropriate valve, or isolation of an emergency shutdown
panel, providing a closed signal to a valve, disconnecting the actuator air
supply and then isolating the appropriate valve.
Spade
A physical obstruction to flow whose design characteristics are the same as
the plant, equipment and / or systems into which the obstruction is inserted,
e.g., a spade, spectacle blind or line blind.
Toxic Material
Material, which can cause harm by means of inhalation, ingestion or
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 8 of 40
absorption.
2.2
ABBREVIATIONS
AA
Area Authority
AzSPU
Azerbaijan Strategic Performance Unit
Carbon Dioxide
CO2
CARA
Chemical Agents Risk Assessment
COSHH
Control of Substances Hazardous to Health
COW
Control of Work
CoW
Control of Work
DBB
Double Block and Bleed
ESD
Emergency Shutdown
H2S
Hydrogen Sulphide
IA
Isolating Authority
ICC
Isolation Confirmation Certificate
L2RA
Level 2 Risk Assessment
LC
Locked Closed
LO
Locked Open
LSA
Low Specific Activity
MSDS
Material Safety Data Sheets
Nitrogen
N2
NORM
Naturally Occurring Radioactive Material
OIM
Offshore Installation Manager
OSM
Operations Safety Manual
PA
Performing Authority
PSA
Production Sharing Agreement
PTW
Permit to Work
SC
Site Controller
SM
Site Manager
SSOW
Safe System of Work
STT
Sanction to Test
SVI
Single Valve Isolation
3
ROLES AND RESPONSIBILITIES
3.1
PERFORMANCE UNIT LEADER
The Performance Unit Leader is responsible for operating in accordance with this document
and for the self-regulation of compliance.
3.2
ASSET MANAGER
The Asset Managers are responsible for:
 Ensuring that the Processes applied at their sites are authorised by them prior to
implementation
 Periodic internal review
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 9 of 40
3.3
OFFSHORE INSTALLATION MANAGER (OIM)/SITE CONTROLLER (SC)/SITE MANAGER (SM)
The OIM/Site Controller/Site Manager is responsible for ensuring that those performing the
roles of Area Authority, Isolating Authority and Performing Authority are competent to do so
and have overall responsibility for the implementation of the Permit to Work and isolation
procedures at their site. They are responsible for:
Ensuring the operation and assurance of the isolation procedure at their site, acting
upon all recommendations and proposing system improvements
Authorising the Area Authority and Isolating Authority (in writing) as competent to
carry out their responsibilities within the Permit To Work and isolations procedures
Maintaining a control log of all authorised personnel. Details of this control log are
included in AZSPU-HSSE-DOC-00012-2 Authorization
Communicating the responsibilities of key participants within the isolations procedures
to those personnel under their direction
Approving all Level 2 Risk Assessments undertaken for non-compliant isolations
Ensuring the required competent personnel are available at the installation to carry
out isolation activities
Ensuring that plant and equipment isolations are subjected to the appropriate level of
self-regulation and audit
3.4
AREA AUTHORITY (AA)
The Area Authority is responsible for approving the isolation design, providing assurance
that the design achieves the highest quality of isolation reasonably practicable. He/She can
delegate the detailed isolation design to an Isolating Authority. The Area Authority is then
responsible for authorising the work to proceed under the appropriate controls. They are
responsible for:
 Ensuring only authorized personnel perform isolations
 Advising the OIM
/ Site Controller
/ Site Manager on Isolating Authority
(IA)
competence
 Ensuring isolation specification, application, removal, certification and security are
accomplished in accordance with this procedure
 Facilitating the Risk Assessment process in accordance with AZSPU-HSSE-DOC-
00063-2 Task Risk Assessment
 Approving all Energy Isolations
 The weekly review and quarterly audit of long-term isolations
 The control of all lock-off devices and tags involved with isolations
3.5
ISOLATING AUTHORITY (IA)
The Isolating Authority is responsible for:
 The specification, application, removal and recording of Energy Isolations in support
of a Permit to Work
 The design of process isolation when requested by the Area Authority. When
designing the isolation the Isolating Authority must agree the scope and content of
isolation with appropriate personnel e.g. the Performing Authority.
 Isolating specific sections of plant or items of equipment to the highest quality and
security of isolation, which is reasonably practicable.
 Demonstrating to the Performing Authority the integrity of the Energy Isolations
 Monitoring of isolations in-place
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 10 of 40
3.6
PERFORMING AUTHORITY (PA)
The Performing Authority is the person charged with the responsibility of carrying out the
work and has the right to request demonstration of the integrity of any isolation. They are
responsible for checking that Energy Isolations `have been implemented in accordance with
the isolation specification before starting work.
3.7
MAINTENANCE PERSONNEL
Maintenance personnel work under the direction of the Isolating Authority and are
responsible for installing the means of isolation (e.g., spades) and removing equipment /
pipe work (e.g., spool pieces) taking into consideration the equipment rating and service.
3.8
THE ONSHORE SUPPORT ENGINEER
The Onshore Support Engineer is responsible for providing engineering advice and
guidance to the Area Authority.
3.9
CUSTODIAN
The custodian of this document is the Technical Authority for Energy Isolations Process.
The TA is responsible for ensuring that an annual review of this document is carried out.
4
MONITORING AND AUDITING OF ISOLATIONS
4.1
MONITORING
The integrity of each isolation point shall be monitored at suitable intervals to detect any
actual leakage or deterioration in condition caused, for example, by vibration or disturbance
(or changing pressure upstream). This monitoring may involve partial testing of valve
isolations. The minimum recommended frequency of monitoring is once per shift and
immediately prior to breaking containment. The results of any monitoring of isolation integrity
shall be recorded and will form part of the shift handover.
4.2
SELF-REGULATION AND AUDIT
Each Site / Installation shall:
 Undertake internal audits of the operation of Energy Isolations at each site.
 Maintain an Audit Register.
 Have in place a system for tracking recommendations through to closeout.
 Periodically review isolation-related activities including review of individual isolations
and the overall isolation process. Such reviews may also include:
o General compliance with this document and any local procedures
o The Level 2 Risk Assessment of non-compliant isolations and the extent of any
approved deviations
o A register of competent Isolating Authorities
The use of a standard audit checklist is recommended, to allow comparison with externals
audit results. Audits, which are independent of the location, shall be carried out and will form
part of the Site Safety Adviser‟s audit programme and the HSE compliance assurance
programme. The recommended frequency of audit is as follows:
Installation /Site personnel
1 permit and isolation confirmation (ICC) certificate per day
Site Safety Adviser
1 permit and isolation confirmation (ICC) certificate per week
SM / SC / OIM
1 permit and isolation confirmation (ICC) certificate per month
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 11 of 40
Note: Audits should be a cross section of activities ongoing i.e. hot work, cold work, and
spark potential. Installation
/ Site personnel should carry out audits of individual tasks
covering both the PTW and the Isolation Confirmation Certificate (ICC) on a regular basis.
The SM / SC / OIM shall carry out regular internal reviews of the findings of Energy Isolation
Certificates, to ensure that any critical failings in the system, or its manner of
implementation, have been identified and appropriate actions have been or will be taken.
The Site / Installation HSE Department as part of their audit schedule shall carry out Energy
Isolation audits. Such audits shall examine a cross section of at least
20 Energised
Isolations together with compliance to this procedure and any deviations in place.
The results of the audit shall be discussed with Management and issued for information and
action as appropriate.
5
COMPETENCY, TRAINING AND AWARENESS
5.1
GENERAL
All personnel involved in Energy Isolations-Process shall be trained and deemed competent.
The competency of all relevant personnel shall be determined during the planning process
for any particular risk assessment. The Area Authority and/or Line Supervisor shall ensure
that the personnel involved in the activity have the correct competencies by examining
records, or requesting individuals to produce relevant certification.
5.2
LEVELS OF TRAINING
A training programme providing initial and refresher training and trainee assessment on the
contents of this document shall be carried out involving all personnel responsible for the
specification, approval, application and recording of process isolations.
The competency requirements for Energy Isolation - Process for Site Managers / Site
Controllers / Offshore Installation Managers / Area Authorities / Department Heads shall be
in accordance with AzSPU Training Policy (AZSPU-HSSE-DOC-00088-2).
In special circumstances individuals can be assessed as competent isolators for specific
items of equipment providing that they have completed the formal training and have been
assessed as competent on the specific tasks. Site management is responsible for ensuring
that this is recorded so that it is clear which tasks these individuals are competent to
undertake.
6
THE ISOLATION CONFIRMATION CERTIFICATION (ICC) PROCESS
6.1
GENERAL
Where isolations are required an Isolation Confirmation Certificate (ICC) must be completed
as detailed in the Permit to Work (PTW) procedure.
The Isolation Confirmation Certificate supports the Permit to Work by providing the means
of:
 Recording the isolations which are required before the task detailed on the associated
Permit to Work can proceed
 Confirming that the isolations have been made for the task to proceed (subject to
authorisation of other certificates e.g., Confined Space Entry)
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 12 of 40
 Authorisation and recording of de-isolations and isolations which may be required to
test equipment under a Sanction to Test (STT)
 Authorisation and recording of de-isolation on completion of the task detailed on the
associated Permit to Work
Note: The Isolation Confirmation Certificate (ICC) must be completed before the
relevant Permit to Work can be issued
The Area Authority, Isolating Authority and Authorised Electrical Persons involved must be
fully informed of the plant, equipment or system to be worked upon and the scope of work to
be carried out under each permit where isolations are required. Marked-up Process &
Instrument Diagrams and site checks must be utilised to ensure that the plant, equipment or
system is clearly identified for isolation.
When each isolation is complete, the Isolating Authority/Authorised Electrical Person enters
the isolation details onto the Isolation Confirmation Certificate. The certificate must be cross-
referenced to the initial permit and any subsequent permits that utilise the same isolations.
Note: The Isolation Confirmation Certificate is raised before the permit is issued, and
remains in force (as a minimum) until the permit is cancelled.
The Isolation Certificate shall only be cancelled when “WORK is COMPLETE”. The
Area Authority can then sign the “CANCELLATION” section.
A single individual may not define and approve the design of energy isolations. The
Isolating Authorities are responsible for designing the isolation but must liaise with
the Area Authority, Support Engineer (where applicable) and Performing Authority on
the scope, content and application method of proposed isolations.
7
ISOLATION REVIEW AND LEVEL 2 RISK ASSESSMENT PROCESS
7.1
REVIEW AND RISK ASSESSMENT PROCESS
Where an isolation cannot achieve the standard detailed in Energy Isolations Process the
Area Authority or Support Engineer is responsible for commencing the Isolation Review and
Risk Assessment:
As a minimum, the Area Authority or Support Engineer together with the Isolating Authority,
and the Performing Authority complete a Risk Assessment. There must be three members,
minimum for a Level 2 Risk Assessment.
The completed Risk Assessment shall be submitted to the OIM / SC / SM who will, if
necessary, discuss and clarify the isolation design with the team. If accepted, the OIM / SC /
SM shall approve the Risk Assessment.
When a satisfactory method of achieving isolation is agreed, isolations are planned, carried
out and documented in accordance with the methodology described in the Permit to Work
procedure, Energy Isolations Process procedure and the Task Risk Assessment procedure.
7.2
REJECTION OF ISOLATION DESIGN
Under no circumstances where the Isolation Review procedure is used, shall any proposed
isolation design be carried out without the agreement of the team involved in the Risk
Assessment.
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 13 of 40
Where the proposed isolation design is reviewed by the OIM / SC / SM and rejected, new
proposals in accordance with the Process Isolation Selection Chart shall be proposed, or a
new Risk Assessment Record sheet submitted.
Note: No amendments or additions to the Risk Assessment Record sheet shall be made.
7.3
RISK ASSESSMENT OF NON-COMPLIANT ISOLATIONS
In the event that the minimum recommended isolation standard cannot be achieved, a Level
2 Risk Assessment shall be carried out according to the following guidelines:
The assessment team shall specify appropriate safeguards, which may replace or be
in addition to those listed in Table 1 (Appendix A). The team shall be satisfied that
these safeguards shall reduce the risks to an acceptable level before the Level 2 Risk
Assessment is submitted to the OIM / SC / SM for the task requiring isolation is
permitted to proceed
When risk assessing non-compliant isolations, consideration shall be given to the
risks associated with swinging large spades compared with the risk associated with
the lower level of isolation
Consideration shall be given to: extended monitoring periods, prior to breaking
containment, reducing the duration of the tasks, provision of a permanent standby
man and development of a contingency plan for isolation failure
Full consideration shall be given to the alternatives including partial or full production
shutdown or deferral of the work
The recommendations from the Level 2 Risk Assessment shall be approved by the
OIM / SC / SM who may also recommend further review by technical specialists or
management before taking the decision on whether to proceed with the work
7.4
RISK ASSESSMENT RECORDS
The Risk Assessment shall be attached to the appropriate Permit(s).
7.5
HAZARDOUS WORK
Where hazardous or potentially hazardous work such as spading, removing a section of
pipeline, or electrical disconnection is required, a permit must be raised to carry out the
isolation.
8
TYPES OF ISOLATIONS
There are varying types of isolations, which are described within this section. These include:
 Boundary Isolations
 Long Term Isolation
 Personal Isolations
 Additional Isolations
 Isolation for Confined Space Entry
8.1
BOUNDARY ISOLATIONS
Where an area of plant is isolated such that several activities can safely take place within
this common set of strategically placed isolation points then this can be termed as a
'Boundary Isolation'. It must be clearly identified that the isolation is appropriate for all the
individual tasks to be carried out against the Boundary Isolation. An Isolation Certificate is
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 14 of 40
raised and identified, as Boundary Isolation and all individual PTW are cross-referenced to
this Boundary Isolation.
If any of the proposed tasks requires a level of isolation or implementation of control
measures greater than that covered by the Boundary then a separate Isolation Certificate
should be raised for this task.
Once work is in progress and subsequent PTW is applied for within the recognised
framework of the Boundary Isolation, they can be added providing it is clearly established
that the existing isolation is appropriate for the task. However, this should be avoided if
possible and it is preferable to identify all activities when the Boundary Isolation is being
planned.
Entry to a confined space within a boundary requires separate Isolation and a Confined
Space Entry Certificate to be raised.
No isolations within Boundary isolation shall be removed until all applicable PTW having
been cancelled.
If for any reason work on a particular piece of plant within the Boundary needs to be
suspended (e.g. whilst awaiting spares) then a separate isolation shall be implemented and
an ICC raised before the Boundary Isolation can be cancelled.
Where the de-isolation of boundary isolations is proposed, an isolation review team that
includes an Area Authority shall ensure that all associated PTW have been cancelled. They
should also ensure that equipment within the boundary is in a safe condition.
8.2
LONG-TERM ISOLATIONS
Long-term isolations are defined as those that no longer have work performed against them.
Each site should maintain a detailed register of long-term isolations.
Long-term isolations shall be subject to two levels of review:
 A weekly review of the register to check the status of the isolations in place and
whether they should be removed or replaced by a plant modification
 A quarterly audit to physically check all the isolation points to confirm their security
and integrity
 Before any work is recommenced against a long-term isolation, a full integrity check
of the valved isolation shall be carried out.
8.3
PERSONAL ISOLATIONS
Personal isolations are intended for short duration tasks of relatively low risk; for example
replacing pressure gauges, filters or small valves, or other such tasks where the completion
of an ICC is considered to add no significant value in terms of risk reduction. The rules for
approval of a personal isolation are as follows:
 The task and isolation are performed by one person within one shift; the person may
receive assistance from others but he shall be present at all times when work is in
progress
 Before approval, the Area Authority must be satisfied with the competence of the
Performing Authority to both carry out the isolation and execute the work. Personal
isolations shall only be carried out by those deemed to be a competent Isolating
Authority. Where an isolation involves competency in more than one discipline eg
electrical, mechanical, instrument or process, personal isolation is only permissible if
the Performing Authority has all the appropriate isolating competencies
 The same isolation standards apply to personal isolations other than the completion
of the ICC
 The isolation points shall be labelled with a personal isolation label and locked
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 15 of 40
 If the worksite is left unattended, the plant shall be left safe, including capping or
plugging of any open ends
An ICC shall be raised whenever these conditions are not adhered to.
8.4
ADDITIONAL ISOLATIONS
An individual Isolation Confirmation Certificate must be completed for each Permit to Work
requiring isolations; unless isolations are controlled by a Boundary Isolation Certificate.
Where working within a defined boundary, further isolations may not be required. However,
where additional isolations are identified, an Isolation Confirmation Certificate will be
required.
8.5
ISOLATION FOR CONFINED SPACE ENTRY
Positive isolation shall be effected on all live lines for any task requiring entry to a vessel or
confined space. Spool removal is to be preferred, although spade isolation may be used
where it is not reasonably practicable to remove pipework sections. It should be noted that
in some cases it may not be reasonably practicable to comply with this requirement in
making entry to mud tanks, pump pits, ballast tanks, or other utility systems. Here, a Level 2
Risk Assessment shall be undertaken and approval obtained from the OIM or Site Controller
before entry can be permitted under work control.
Vessel nozzles should normally be left open to assist with free ventilation. Air movers or
ducted fans may also be used to create a flow of clean air through the vessel. If there is any
likelihood of fumes, water or other contaminant entering the vessel from sources other than
the isolated pipework while persons are inside, the need to blank off any affected nozzles
shall be considered. Blanks used for this purpose do not need to be pressure-rated.
However non-pressure rated blanks shall be clearly identified by either a tag, painted
circumference or other marking. In the case of tanks with „swan necks‟, mechanical plugs
may be an option, to prevent ingress of fumes, etc.
The manway doors on a vessel being prepared for entry shall be removed last and
reinstalled first to reduce the risk of unauthorised entry.
Further details on Confined Space Entry are given in AZSPU-HSSE-DOC-00013-2.
8.6
PROVISION FOR ISOLATIONS DURING MODIFICATION OF DESIGN AND NEW FACILITIES
In relation to existing Installations and Sites:
 The design of all modifications and new facilities shall include a review of the
provision of means of isolation for maintenance to ensure compliance with this
document
 Such reviews shall address both isolations within the modified/new facilities and any
opportunities to upgrade existing isolation facilities where these are inadequate
 New valves supplied as part of a modification or as a replacement shall be provided
with a facility to lock off in the open or closed position
8.7
ISOLATION OF HIGH PRESSURE SMALL BORE PIPING
When isolating small bore piping consideration shall be given to the pipe connection to the
isolating valve to ensure that there is no possibility of the security of the fitting being
dislodged during disconnection or reconnection of any pipe work used for invasive
maintenance. In addition to the isolation type consideration needs to be given to the integrity
of the system fittings/connections (i.e. Swagelocks).
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 16 of 40
9
REGISTERS
All Isolation Confirmation Certificates
(ICCs) shall be registered on the Isolation
Confirmation Certificate Register, which is maintained by the Area Authority(s). Where a site
has more than one Area Authority, the nominated responsible Site Isolating Authority (IA)
Co-ordinator shall assume overall control of the Register.
10
RECORDS
When all the isolations have been implemented, the Area Authority signs and dates the
Isolation Confirmation Certificate. He then records the Isolation Confirmation Certificate
number on the permit. The Control Room Operator and/or the Permit Coordinator may also
perform this where they are appointed.
Isolation Confirmation Certificates shall be accessible to each Area Authority and are held in
the vicinity of the Control Room for ease of monitoring each area.
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 17 of 40
APPENDIX A: ISOLATION STANDARDS
GENERAL
Experience has shown that for most types of fluid hazard, isolation by valves alone can be
adequate if used in conjunction with certain additional mandatory safeguards, appropriate to
the level of risk, to ensure effectiveness and security.
Minimum recommended isolation standards have been developed and should be referred to
when designing process isolation where it is not reasonably practicable to achieve positive
isolation (refer to Table 1). The minimum standard also identifies mandatory safeguards,
which the Area Authority is responsible for putting in place to reduce the risk level to as low
as reasonably practicable.
For short-term operational tasks such as corrosion coupon retrieval or filter replacements,
where no positive isolation is practicable or where the job duration is shorter than the time to
install positive isolation, then the „V‟ value from Table 1 can be considered as the minimum
recommended isolation standard. These tasks shall be conducted using a Permit and a local
operating procedure.
Note 1:
Any proposed isolation, which deviates from those shown in Table 1 must be
subject to an Isolation Review and a Level 2 Risk Assessment.
Note 2:
Isolation against a tested single valve is permissible while swinging a
spectacle blind, inserting a spade or fitting a blank flange to achieve a positive
isolation.
Positive isolation is regarded as the most secure method and shall be considered when
planning maintenance work. It is mandatory for entry into confined spaces.
Positive Isolation is also recommended in the following situations, in view of the additional
security it offers:
 Long duration isolations, eg more than one week
 Where equipment is to be removed from service, and all energy sources
disconnected
 Where naked flame hot work is to be undertaken
 For process fluids at or above auto-ignition temperature
 When breaking containment in systems likely to contain toxic material
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 18 of 40
Table 1 Minimum Recommended Isolation Standards for Predetermined Risk Levels
Fluid Type
Operating Pressure
<10barg
>10barg <55barg
>55barg
Process fluids and hazardous utilities
V = SVI
V = SVI+B
V = DBB+A
I = SVI+A
I = DBB+B
I = DBB+B
Non-hazardous utilities
V = SVI
V = SVI+A
V = SVI+B
I = SVI
I = SVI+B
I = DBB+B
V
Valve configuration required to permit the installation of blank flanges and spades (positive isolation)
I
Valve configuration required to permit carrying out intrusive maintenance without positive isolation
A
Use mandatory safeguards as on List A
B
Use mandatory safeguards as on List B
SVI
Single Valve Isolation
DBB
Double Block and Bleed
Mandatory Safeguards
Category A
Category B
(Low Risk)
(High Risk)
Continuous gas monitoring (for hydrocarbon systems only)
y
y
Pressure build-up to test valve integrity
y
y
Regular monitoring of isolation integrity
y
y
Control and prevent nearby work
y
y
Operations Technician in attendance
y
y
Radio link to control room when breaking containment
y
Develop contingency plan against leakage
y
Identify backup isolation valves, shutdown systems etc
y
Minimise task time
y
Portable fire-fighting equipment available (for hydrocarbon systems only)
y
Minimise possibility of plant disturbance
y
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 19 of 40
APPENDIX B: GUIDANCE NOTES
B1 ISOLATION PLANNING
B1.1 ISOLATION PLANNING
Isolation of any piece of equipment shall be planned such that the risk of removing it from
service and then reinstating it on completion of the work is minimised. The Flowchart
(Appendix D) should be referred to when planning any isolation. All isolations shall be
designed according to the standards set out in Appendix A (including Table 1).
The following key points should also be considered:
 Plant and equipment isolation requirements should be identified early in the work
planning cycle for the Installation or site so that adequate time can be made available
for formal risk assessment, should it become necessary. Where necessary, reference
shall be made to the Installation or site Operations Safety Manual (OSM) and the
identification of high-risk areas
 A boundary isolation may be put in place to cover several planned activities in an area
of plant. The Isolation Certificate shall describe the scope of work planned and the
Permits for these jobs shall be cross-referred to the same Isolation Certificate
 The need for good access and egress to allow isolations to be effected
 Isolations should be as close to the vessel or worksite as possible, to assist in
security and ease of monitoring
 Preparation for isolation involving draining, flushing, purging and venting of process
pipe-work shall be conducted under the AzSPU Safe System of Work (SSOW)
according to the appropriate procedures for the task and including the appropriate
isolation
 Amendments shall not normally be made to isolations in place other than to allow
testing of equipment prior to return to service. Amendments may be made to improve
the integrity of the isolation with the approval of the Area Authority. The reason for the
amendment shall be recorded and the Performing Authority advised of the change
 Pressure relief valves shall only be isolated following the provision of an alternative
means of pressure relief
B1.2 ISOLATION METHODS
The highest quality of isolation which is reasonably practicable shall be applied to every
individual isolation point. The methods of isolation normally available are detailed below,
listed in decreasing order of security and effectiveness.
B1.2.1 Positive Isolation
Positive isolation may be affected by either of the following:
 Spool removal - removal of pipework section and bolting/clamping blank flanges
rated for full line design pressure onto live ends
 Spade isolation - witnessed insertion between bolted or clamped flanges of a blind
plate; swinging of a spectacle plate. Any such insertion must be rated to the pipe
design specification. The insertion of spades shall be witnessed by the competent
Isolating Authority
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 20 of 40
B1.2.2 DOUBLE BLOCK AND BLEED
Double Block and Bleed (DBB) consists of the closure of two block valves in series with an
intermediate bleed valve. The integrity of both valves shall be tested separately and the
bleed valve will then be left in the closed position, with periodic integrity checks. The Area
Authority shall specify how frequently this bleed valve is opened to check for pressure
buildup. As a minimum this shall include:
 Prior to the issue and/or revision of a PTW
 At the start of every work period (this includes after any form of work break between
normal periods of work).
 Continuous monitoring during any breaking of containment activity (including but not
limited to, the removal of spools, pumps, valves; the insertion of spades)
Emergency Shutdown (ESD) valves may be used as part of a DBB isolation, providing they
can be reliably immobilised.
Single valves of a type which provide a double seal in a single body and with a bleed
between the seals are also acceptable. Examples of such valves are suitably specified
double wedge gate, parallel expanding gate, double seating ball valves, etc, but not double
piston seal ball valves where the cavity pressure provides the downstream positive seal.
Where double-seal single valves are used, additional identification of the isolation on the
valve shall be included, as full loss of isolation will occur on inadvertant valve operation.
Additional means of identification for this type of valve shall be two (2) appropriate locking
devices. Each shall be individually labelled and identified appropriately as
“Upstream
Isolation” and
“Downstream Isolation”. Both shall be recorded on the ICC and be
sequentially numbered.
It should be noted that „standard‟ ball valves “do not’ provide a double seal. In such cases it
is important to note that the integrity of the isolation is critically dependent upon the security
of a single valve operating stem. Also, it is not normally possible to perform a full integrity
test as the two seals cannot be applied independently.
B1.2.3 Single Valve Isolation
Single Valve Isolation (SVI) consists of the closure of a single block valve. A measure of
additional security can be achieved by closing several valves in series but the absence of a
bleed or vent in the intervening volume means that this method must be classified as SVI.
The hazard of trapped pressure due to thermal expansion may be created in this case.
Any valve used for SVI must provide a reliable seal. Non-return valves, flow control valves
and other valves which may not provide tight shut-off must not be used.
B1.2.4 Other Isolation Devices
Devices such as mechanically expanded plugs, stopple bags or frozen plugs shall not be
used as primary forms of isolation, except where the application has been properly
engineered, risk assessed and approved by the appropriate Technical Authority.
Conventional mechanical plugs or stopple bags may be used as a vapour or liquid seal to
contain and direct to vent any small amounts of vapour. Flammable vapour monitors shall be
used where the presence of vapour could create a hazard.
In all cases, contingency measures against injury or damage caused by sudden ejection of
the isolation device shall be put in place.
B1.3 PRECAUTIONS WHEN BREAKING CONTAINMENT
The key safeguards for both low-risk and high-risk isolations (refer to Appendix A, Table1
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 21 of 40
Categories A and B respectively) are the pressure buildup tests on the integrity of each valve
immediately prior to breaking containment, together with the appropriate level of regular
monitoring of the isolation integrity. The Area Authority shall control and prevent nearby work
and ensure continuous gas monitoring at the worksite. An Operations Technician shall be
present during breaking containment and any other critical phases of the task.
Isolations with Category B safeguards require additional control and contingency measures.
The key additional safeguards are to minimise the task duration, ensure plant stability and to
develop a contingency plan against leakage.
The contingency plan shall consider the following:
 How to respond to a leakage
 Identifying additional isolation valves and the expected action if the isolation fails
 Knowing the position of the local ESD facilities
Firefighting equipment shall be readily available and the work party shall be in radio contact
with the control room.
Other precautions that should be considered when breaking containment are as follows:
 Consideration should be given to hot bolting flanges prior to the operation and all
materials for the job shall be available at the job site
 Bolts are to be slackened off in the correct sequence. No bolts shall be removed until
they have all been slackened and the joint cracked, and until it has been confirmed
that the line contents will not be released in an uncontrolled manner and any
appropriate gas testing has been carried out
 Particular care shall be taken with clamp lock type fittings. With nuts slackened, the
fitting should be physically dislodged to confirm there is no residual pressure, before
final disassembly
 The person who opens the flange shall do so in such a way as to minimise the
possibility of contact with the contained fluids and of sudden escape of large
quantities. Suitable Personal Protection Equipment (PPE) shall be worn
 Where there is a danger of H
2S being present, full H2S procedures covered in the BP
Hydrogen Sulphide Procedures shall be followed
 The Area Classification procedure used for the selection of electrical equipment in
hazardous areas does not consider abnormal operations when breaking containment.
Consideration shall be given to restricting the use of electrical (and other) equipment
during breaking containment due to the risk of releasing flammable gas
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Energy Isolation - Process
Page 22 of 40
B2 ISOLATION IMPLEMENTATION AND CONTROL
B2.1 Security
Any isolation must achieve and maintain effective containment of the relevant fluid for as
long as required. Valves shall be locked or otherwise immobilised to prevent unauthorised
operation. It may be necessary to apply additional immobilising devices under certain
circumstances.
Where valves are required to be locked (open or closed) as part of an isolation, only the
following methods are acceptable:
 The use of wire locking loops to immobilise the valve which would require
considerable effort to force the valve from the lock position
 Padlock and chains which likewise would take considerable effort to force the valve
from the locked position. Where this method is used, padlock keys shall be held by
the Area Authority
 The use of specifically designed tamper-proof valve interlocks. The activation of the
interlock shall be controlled by the Area Authority utilising the master key held at
the site
When isolating any valve that cannot be locked and may inadvertently be opened by
accidental contact, the valve handle shall be removed where practicable.
Electrically operated valves shall have the power supply positively isolated and any handjack
shall be manually locked. If the valve cannot be physically immobilised it should not normally
be used for isolation purposes.
Pneumatically and hydraulically operated valves which fail closed shall have their control
lines isolated and physically disconnected.
Pneumatically and hydraulically operated valves which fail open should not normally be used
for isolation purposes. If no other alternative is reasonably practicable, the valve shall be
prevented from moving. Under this situation the isolation shall be considered as non-
compliant with Energy Isolations-Process and a Level 2 Isolation Risk Assessment carried
out.
It is not necessary to lock bleed valves in a DBB arrangement as they are required to be
opened periodically to check the integrity of the isolation.
Personal isolations (refer to section 8.3) shall be secured to the same standard to prevent
unauthorised operation of the valves.
B2.2 Identification Methods
All valves, spades and blank flanges used for isolation purposes shall be identified by means
of tag-labels. The following information shall be identified on the tags:
 The Isolation Confirmation Certificate (ICC) Number
 The Equipment Tag No
 The IA‟s Name (clearly printed) and their Signature
 The date of Isolation
Bleed points shall also be labelled with the same format.
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Energy Isolation - Process
Page 23 of 40
Where padlocks are used, the individual key number shall be listed on the ICC and a means
of referencing the correct key to the isolation point included. Keys should be held centrally in
a secure fashion and controlled by the Area Authority either by using a master key cabinet or
individual key safes.
Where there are overlapping isolations where some of the isolation points are common to
more than one isolation then these points shall have a separate locking device and tag from
each isolation. Each isolation shall be registered and controlled by its own individual ICC.
B2.2.1 FLANGE TAGGING FOR BREAKING CONTAINMENT
Flanges used in breaking containment should be identified as an aid to ensuring that they
are reinstated and their integrity is confirmed once all work is complete. A tag-label shall be
used as the method of identification. Both halves of the label are completed by the person
carrying out the work and the details recorded on a Breaking of Containment Register. When
the flange or connection has been re-made, the lower half of the tag is removed and
recorded on the register. The upper half is left to allow the integrity of the reinstated joint to
be monitored during leak testing and startup. The tag is removed when the plant is back up
to its normal operating conditions and kept in place for a minimum of 2 days after startup.
Consideration should be given to tagging critical neighbouring joints which have not been
broken but which could be affected by the reinstatement activity.
B2.3 CONTROL OF ISOLATIONS
The ICC, cross-referenced to all relevant Permits, shall be the principal means of control
once isolations are in place. The ICC performs the following functions:
 Identifies the plant concerned and the reasons for isolation
 Authorises isolation by disciplines
 Records the complete list of isolations and valve tag numbers used for a
particular task
 Records bleed points for checking valve integrity. The operation of the bleed valves to
check integrity need not be recorded as an amendment on the ICC
 Confirms that the isolations have been effected
 Authorises any temporary de-isolations and isolations necessary for testing
 Authorises and records de-isolation on completion of the task
The ICC shall show a complete list of isolations and valve tag numbers. A marked-up
P&ID/EFD or other suitable drawing must be attached to the ICC, together with a record of
the Isolation Level 2 Risk Assessment where this is needed.
B2.3.1 CONTROL OF ISOLATIONS FOR WELL OPERATIONS ACTIVITIES
During well operations the isolation of the xmas tree from the process plant shall be
controlled via an ICC. This isolation should be used in conjunction with a Well Handover
Certificate to manage the handover to well operations. The recommended practice is to
include the appropriate flowline isolation valves, the wing valve and the hydraulic supplies to
the UMV and DHSV, on the ICC, thus documenting the isolation from the process. The Well
Handover Certificate details the status of all tree valves at handover and confirms valve
integrity and depressurisation details thus documenting the isolation from the reservoir.
During the wireline operations, the swab valve, upper and lower master valves and DHSV
are under the control of the Wireline Supervisor and the appropriate detailed operating
procedure which will cover removal and reinstatement of the swab cap. On completion of the
wireline work the Wireline Supervisor will use the Well Handover Certificate to document the
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT: http://baku.bpweb.bp.com/dep/hse/safe/
Procedure for Energy Isolation - Process
Page 24 of 40
tree status for handover to Operations. During production logging operations where it is
necessary to flow the well a specific PERMIT will be raised for the wireline work that requires
the well to be online and this will be cross-referenced to the ICC described above and run
under sanction to test.
B2.3.2 LOCKED OPEN/LOCKED CLOSED VALVES
For integrity reasons, certain process and drain valves will be in the normally locked open or
locked closed position. It is vital that the position and security of these valves is carefully
controlled. A register shall be maintained of all these valves to record any changes from their
normal position and a regular audit shall be carried out to confirm the security and position of
these valves. It is important that these valves are in their correct position, particularly after
de-isolation where they have been part of an isolation. If these valves are moved from their
normal position for operational reasons or as part of an isolation then this movement and
subsequent return to their normal position shall be recorded in the register.
B2.4 Testing Isolation Integrity
All isolations shall be tested and shown to be effective before containment is broken.
Integrity tests shall be conducted for a minimum of 10 minutes.
Typical valve isolation integrity tests for DBB and single valve isolations are described in
Appendix C. It is important that all bleeds (vents/drains) are checked free from obstruction
prior to testing. It is also important to realise that a bleed which is hard-piped to a closed
drain or flare line will provide single valve isolation only from the drain/flare line.
On completion of checking valve integrity, a bleed valve shall be left in the closed position,
unlocked to allow regular monitoring. A pressure gauge may be fitted to the bleed valve to
monitor for pressure buildup.
An isolation can only be considered to be of DBB standard if the integrity of both valves has
been proven.
If zero pressure buildup is not achievable when checking integrity of a valved isolation,
consideration should be given to either including additional isolation valves, installing
positive isolation or carrying out an assessment of risk to determine whether it is acceptable
to proceed.
Alternative methods of valve integrity testing may be considered where there are practical
difficulties in using the conventional method, providing that they have been endorsed by the
relevant Technical Authority.
Once the Area Authority is satisfied with the integrity of the valved isolation and that the
system is depressurised and drained, containment may be carefully broken either to effect
positive isolation or to perform the required task
(taking into account all precautions
regarding H2 S, pyrophoric scale, Low Specific Activity (LSA) scale, Naturally Occurring
Radioactive Material (NORM) or hydrates).
The extra security of untested but witnessed positive isolation, in addition to the valved
isolation used to effect it, is normally acceptable for most confined space entry tasks.
However, for longer term positive isolations (eg a week or more), or where the valved
isolation used to effect the positive isolation needs to be removed for operational reasons,
then integrity testing of the positive isolation is required. This shall be done by service leak
testing or formal leak testing of the joint, depending on the level of risk.
Where a single flare or vent valve forms part of an isolation it may not be possible to fully
test integrity. In this situation the valve cannot be considered as a reliable barrier and
therefore an isolation risk assessment shall be carried out to determine whether the task
should proceed.
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT: http://baku.bpweb.bp.com/dep/hse/safe/
Procedure for Energy Isolation - Process
Page 25 of 40
B2.5 Plant Preparation - for Breaking Containment
All plant preparation work covering the draining and flushing of vessels or pipework shall be
carried out under a Permit within the AzSPU Safe Systems of Work (SSOW). For more
complex operations a marked-up P&ID and a specific procedure should be used to support
the activity.
B2.5.1 POTENTIAL HAZARDS
Some of the potential hazards that should be considered when planning these activities are
as follows:
 Chemical reactions between cleaning materials and a tank or its fittings (eg acidic
cleaning fluid attacking a blanking spade installed for isolation)
 Leakage or collapse of a tank or its supports caused by reaction with cleaning
materials, excessive weight of wash solutions, or by creating vacuum conditions
 Accidental spillage during draining/flushing (environmental impact)
 Possibility of radiological contamination from LSA / NORM
 Pyrophoric scale which can be formed in systems that may contain H
2S. If these
systems are subsequently opened up and the scale is exposed to currents of air,
there is a danger that the scale could ignite. The pyrophoric scale shall be rendered
harmless by constant thorough wetting until the scale is either removed or the system
is again closed up
 Gaskets containing asbestos which shall be handled and disposed of in accordance
with the guidance identified in Working with Asbestos Procedures
 Explosions and fires caused by the sudden mixing of water with hot oil, either during
steam cleaning or on the admission of hot oil into systems which have just been
steamed or flushed with water and which have not been thoroughly drained and dried
 Static electricity as an ignition source or electric shock during steam cleaning or
high-pressure water jetting if equipment is not earth bonded
 Possible asphyxiation through personnel exposure to nitrogen
 Accidental spillage and freezing effects of nitrogen
B2.5.2 Depressurising and Draining Containment Systems
For this purpose containment systems may be divided into:
 Pressurised vessels and pipelines/pipework
 Atmospheric tanks and vessels
B2.5.2.1 Pressurised Vessels and Pipelines/Pipework
The precautions for depressurisation and draining of pressurised hydrocarbon and chemical
containment systems include the following:
1) The system shall be adequately isolated from fluid pressure and inventory for the
purpose of emptying.
2) The appropriate Material Safety Data Sheet (MSDS) and Control of Substances
Hazardous to Health (COSHH) or Chemical Agent Risk Assessments
(CARA) shall
be studied.
3) The pressure within the system shall be relieved in a safe manner and the system
drained. The residual pressure within the system shall be substantially atmospheric
before containment is broken.
4) Systems containing gas shall be depressurised to a closed system or a vent/flare
header designed to accept such gas. If possible, venting to flare is preferred.
5) Gas systems shall only be depressurised to the atmosphere under strictly controlled
conditions. Persons working downwind of any drainage/venting operation shall be
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT: http://baku.bpweb.bp.com/dep/hse/safe/
Procedure for Energy Isolation - Process
Page 26 of 40
warned by the Area Authority or his nominee and, if instructed, shall vacate the area.
All hot work shall cease within the affected area.
6) Where suitable facilities exist, liquid residues shall be drained to a closed system.
Where this is not possible, an estimate should be made of the quantity of liquid
remaining in the system. Catchment facilities should then be provided sufficient for at
least this quantity. Liquid can then be drained by carefully opening a flange at a low
point in the system. Precautions should also be taken to prevent the spread of any
accidental spillage.
7) The existence of possible „dead-legs‟ in the system must be borne in mind. Such traps
may have to be flushed with water to remove residual liquids if there are no flanges or
connections.
8) Oil contaminated/soaked lagging material shall be removed from hot equipment as it
is prone to spontaneous ignition.
B2.5.2.2 Atmospheric Tanks and Vessels
When emptying atmospheric tanks and vessels in preparation for either changing their
contents, carrying out inspections, repairs or modifications, or prior to dismantling, the
following guidelines shall be observed:
1) Prior to emptying any tank/vessel, reference shall be made to the as-built engineering
drawings. These drawings show in detail the internals of the tank/vessel which will aid
in the methods to be adopted for draining and isolation, eg a bottom offtake of a
vessel from the outside may lead to the assumption that the offtake is flush whereas
the drawing may show that the offtake is raised internally.
2) Storage tanks and vessels shall be emptied initially by means of the normal off-take
lines, until suction is lost. The contents should be transferred to another suitable tank
or, onshore, to a mobile tank, if appropriate.
3) When emptying and draining, care shall be taken to avoid pulling a vacuum. This may
occur if the atmospheric or vacuum vents are blocked, or by excessive lowering rates
through large diameter lines.
4) Once suction is lost through the normal offtake it may be necessary to remove
residual liquid contents by means of either a portable pump operating through
an open manhole
(by the use of the tank water drain valve) or possibly by
water-flotation, taking appropriate precautions against spillage.
5) The hazards of using portable pumps in an area likely to be contaminated with
flammable vapour must be taken into account. Appropriately sited, air-powered pumps
should be used where possible.
6) Residual liquids and sludge must be disposed of in accordance with the requirements
of pollution-control legislation.
1.
B2.6 Cleaning and Gas-freeing Methods
After depressurisation and draining, residual hydrocarbon liquids, vapours and gases must
be removed before further work can proceed.
Caution: If a Confined Space Entry is required, please also make reference to procedure
AZSPU-HSSE-DOC-00013-2 Confined Space Entry
Various media can be used for this purpose but the choice is liable to be governed by what
is available at the work location.
B2.6.1 WATER FLOODING
Cold water is usually the most readily available cleaning medium. It is reasonably effective at
displacing hydrocarbons, although it does not easily remove sludges or oils trapped in
complex pipework or vessel internals.
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT: http://baku.bpweb.bp.com/dep/hse/safe/
Procedure for Energy Isolation - Process
Page 27 of 40
Before a tank or vessel is flooded with water, it shall be confirmed that its supporting
structure is capable of sustaining the weight. In addition, adequate run-down and draining
facilities shall be provided, due to large volumes of water usually necessary for these
operations.
To avoid a buildup of a static charge when this method is used, water shall be added from
the base of the tank or vessel. If a hosepipe is used, the velocity shall be kept low until the
end is submerged, and the nozzle shall be electrically earthed. Flooding with water shall not
be relied upon to remove all petroleum vapour, liquid or solid residues.
It is possible to carry out hot work on the external surface of a water-flooded tank or vessel
without further removal of internal hydrocarbon residue providing the work is below the water
level and an appropriate level of risk assessment has been conducted.
Water used for displacing and removing liquid hydrocarbons will be heavily contaminated
after use. It must be disposed of in an environmentally-responsible manner.
B2.6.2 INERT GAS
Nitrogen (N2), Carbon Dioxide (CO2) or combustion gas (N2/CO2 mixture) may be used to
displace hydrocarbon gas and vapour. This method may be useful if it is impracticable to
introduce water into a system in case of damage. Care should be taken to ensure when
injecting such mixtures not to induce localised freezing of valves, gauges etc due to
excessive injection rates.
Particular care should be taken with systems which may contain pyrophoric scale from high-
sulphur bearing hydrocarbons. If such scale is subsequently exposed to the air, it may
rapidly burst into flame. Water sprays may be used to prevent this by keeping the scale
constantly wetted.
A quantity of inert gas at least double the volume of the vessel being purged is likely to be
necessary to ensure adequate dispersal of hydrocarbon gases. Introduction of gas at
reasonably high velocity is also helpful in ensuring good mixing. Purge with inert gas until
concentration of flammable vapour is less than 4% in emerging mixture of flammable/inert
gas.
Normal flammable vapour monitoring devices will not work accurately in atmospheres which
are deficient in oxygen, therefore it is necessary to use specialised equipment to determine
the effectiveness of an inert gas purge.
Following the displacement of hydrocarbon vapour with inert gas, the vessel or tank should
then normally be purged again with air to displace the inert gas. This shall always be done in
cases where man-entry is planned, regardless of any intended use of PPE.
B2.6.3 Steam
At onshore sites, steam may be available in sufficient quantities to use for purging and
cleaning vessels, tanks and pipework. Steam is the most effective of the common media for
this purpose. It should be used at low pressure, not exceeding 1bar maximum.
Two methods of steaming may be employed; open or closed steaming:
 Open steaming is used where the tank, vessel and its associated system is fully open
to the atmosphere
 Closed steaming is used for closed vessels and their associated equipment. During
this operation, the temperature is raised allowing volatile liquids to vaporise and
disperse together with the bulk of the steam via a condensing system. The heavy
constituents can flow freely and be drained off with the condensed steam from the
base of the system
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT: http://baku.bpweb.bp.com/dep/hse/safe/
Procedure for Energy Isolation - Process
Page 28 of 40
For all but the largest vessels and tanks, sufficient steam should be available to raise the
external surface temperature to at least 95°C. Steaming should be continued until the
condensate flowing from the vessel is substantially free of hydrocarbon.
Steam may be used in the case of process vessels, small storage tanks and medium sized
insulated tanks. It is essential that following a period of closed steaming, adequate provision
is made to prevent damage due to a vacuum being drawn by condensation of steam. In
large tanks, the rate of condensation of steam is such that adequate purging is not possible.
After steaming, it is normal practice to cool down the equipment with copious quantities of
water, this gives an additional wash to help remove residual hydrocarbons.
Where residual material is left on the tank or vessel surface after prolonged steaming, such
residual material may still evolve vapour on application of heat, eg burning or welding. In
such cases, cold cutting may be employed or the internal surface kept thoroughly wet during
the heating operation.
All temporary steam hoses used shall be electrically bonded and earthed.
B2.6.4 Air
Where it is not possible or practicable to use any of the foregoing methods, it may be
necessary to use air directly to ventilate equipment and remove hydrocarbon vapour.
When a decision is made to use this technique, every effort shall be made to pump out as
much oil and sludge as possible before opening the tank or vessel. Where practicable,
forced ventilation shall be used so that flammable vapour is cleared in the shortest possible
time. During this purging operation, the flammable range will be passed through, presenting
an explosion hazard if an ignition source is nearby. All electrical equipment used shall
therefore be suitable for use in a Zone 1 Hazardous Area. Other equipment within the
hazard range of flammable vapour shall be effectively isolated.
Air movers shall be fitted at the roof or top manhole so as to pull air in at low level.
Temporary trunking may be needed to achieve high-level disposal. In order to minimise the
emission of gas/vapour when the lower manhole door is opened, the air movers shall be
started up first to obtain a slightly negative pressure before the lower manhole is opened.
Vapour issuing from shell manholes may give rise to a dangerous concentration in a bunded
or confined area and, under such conditions, no kind of ignition source is allowed. Removal
of vapour by air movers attached to the roof manhole is the recommended safe practice.
Care shall be taken when using natural draught ventilation during periods of calm weather at
onshore sites, since vapour released from tanks can travel considerable distances without
being dispersed. Due regard shall be taken of wind direction and the risk to adjacent
premises or to the public.
Owing to the possible presence of pyrophoric scale within tanks or vessels which have
contained sour crude or products, provision shall be made for continuous wetting of the
internal surfaces by means of water from one or more water fog nozzles inserted into the
roof opening. The nozzles shall be turned on first and the air movers opened immediately
afterwards. A shell manhole shall be opened after approximately 5 minutes operation, when
the internals are thoroughly wet. With the air movers still in operation, the fog nozzles should
then be removed and loose scale dislodged with high-pressure water streams.
CAUTION: WHEN THIS METHOD IS EMPLOYED, THE WATER NOZZLES SHALL BE
EARTHED
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT: http://baku.bpweb.bp.com/dep/hse/safe/
Procedure for Energy Isolation - Process
Page 29 of 40
B3 PLANT REINSTATEMENT
B3.1 General
The reinstatement of plant and equipment requires equal attention to planning and detail as
the initial isolation. Historical data shows that many incidents involving failure of an
isolation occur during reinstatement. Reinstatement of process plant is not complete until
the section where containment was broken has been leak tested.
The reinstatement leak test is different from strength tests as required by Code, which are
pressure/strength tests to prove the structural integrity of the system.
The purpose of reinstatement leak testing is to render the production equipment and piping
systems safe for the introduction of hydrocarbon gases and liquids, and to create an
auditable record to demonstrate the integrity of all hydrocarbon production systems.
For an an overview of the leak testing process refer to the SSOW for Leak Testing
(Document No. AZSPU-HSSE-DOC-00055-2).
B3.2 De-isolation of Plant
B3.2.1 Integrity Checks
Prior to reinstatement, the integrity of any isolations associated with the removal of spades
or other isolations devices should be reassessed to confirm that it is safe to proceed with the
reinstatement work.
B3.2.2 Sequence of De-isolation
In some cases the sequence of de-isolating plant is critical and requires planning to ensure
safe reinstatement.
B3.2.3 De-isolation of Non-manual Valves
Removal of a valved isolation does not necessarily involve any opening or closing of the
valves, just the removal of locking devices and/or other immobilising equipment. Particular
care should be taken with regard to electrically, pneumatically or hydraulically operated
valves, which may open or close on reinstatement of the operating source/medium.
B3.2.4 De-isolation of Safety Critical Valves
Care must be taken to ensure that safety critical valves are returned to their correct position
during de-isolation. These valves are registered as Locked Open (LO) or Locked Closed
(LC) and each site holds a register which records the current position of all LO/LC valves.
During de-isolation, these valves should be returned to their correct position for plant
operation and the register updated accordingly.
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT: http://baku.bpweb.bp.com/dep/hse/safe/
Procedure for Energy Isolation - Process
Page 30 of 40
APPENDIX C: TYPICAL VALVE ISOLATIONS INTEGRITY TESTS
Double Block and Bleed Isolation Integrity Test (Two Valves)
Diagram
Key
V1 - First (upstream) isolation valve from live system.
M1 - Live side-monitoring point (pressure gauge or vent/drain).
V2 - Second (downstream) isolation valve from live system.
M2 - Monitoring point between valves and break point (pressure gauge or vent/drain).
B - Bleed point between the isolation valves.
Procedure
1. If possible, ensure tapings at M1, M2 and B are not blocked and pressure gauges, where
installed, are operating.
2. Close downstream valve V2 and secure in closed position.
3. Record pressure at monitoring points M1 and M2.
4. Vent/drain section of line to be broken and monitor at M2 until the pressure is near zero.
5. Close vent/drain at break point and monitor at M2 for a minimum of 10 minutes. No
pressure build-up at M2 indicates the integrity of the downstream valve V2.
6. Close upstream valve V1 and secure in closed position.
7. Record pressure at M1 and B.
8. Vent/drain between V1 and V2 (B) and monitor at B until pressure is near zero.
9. Close vent/drain (B) and monitor at M1 and B for a minimum of 10 minutes. (No pressure
build-up at B indicates integrity of upstream valve V1).
10. Leave vent/drain (B) in closed position to allow further monitoring.
Isolation
Both block valves are now closed and secured. The bleed valve is closed but not locked. It is
Summary
possible for pressure to build up between the two block valves therefore regular monitoring of
the isolation is essential; a suitable calibrated pressure gauge may be fitted to the vent to
monitor for any pressure.
For further information refer to Section B1.2.2 Double Block and Bleed
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT: http://baku.bpweb.bp.com/dep/hse/safe/
Procedure for Energy Isolation - Process
Page 31 of 40
Isolation Integrity Test (BP-Approved Double Sealed, Single Valve)
Diagram
Key
M1 - Live (upstream) side monitoring point.
M2 - Monitoring point between valve and break point (downstream).
C - Cavity drain (between seals).
Procedure
1. If possible, ensure tapings at M1, M2 and C are not blocked and pressure gauges, where
installed, are operating.
2. Close isolation valve and secure in closed position.
3. Record pressure at M1, C (in cavity) and M2.
4. Vent/drain downstream section of line to be broken and monitor pressure at M2 until
pressure is near zero.
5. Close vent/drain at break point and monitor at M2 and C for a minimum of 10 minutes. (No
pressure build-up at M2 and no pressure fall-off at C indicates integrity of downstream
seal.)
6. Record pressure at M1 and C.
7. Vent/drain off fluid in cavity (between seals) and monitor at C until the pressure is near
zero.
8. Close cavity vent/drain (C) and monitor at M1 and C for a minimum of 10 minutes. (No
pressure build-up at C indicates integrity of upstream seal).
9. Leave vent/drain C in closed position to allow further monitoring.
Isolation
The double sealed, single block valve is now closed and secured. The bleed valve is closed
Summary
but not locked. Any fluid passing through the upstream seal will be detected at the cavity drain
C. Regular monitoring of the isolation is therefore essential and a suitable calibrated pressure
gauge may be fitted to the vent to monitor the pressure.
2.
For further information refer to Section B1.2.2 Double Block and Bleed
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT: http://baku.bpweb.bp.com/dep/hse/safe/
Procedure for Energy Isolation - Process
Page 32 of 40
Single Valve Isolation Integrity Test
Diagram
Key
M1 - Live (upstream) side monitoring point.
M2 - Monitoring point between valve and break point (downstream).
Procedure
1. Ensure tapings at M1 and M2 are not blocked and pressure gauges, where installed,
are operating.
2. Close isolation valve and secure in closed position.
3. Record pressure at M1 and M2.
4. Vent/drain downstream section of line to be broken into and monitor at M2 until
pressure is near zero.
5. Close downstream vent/drain and monitor at M2 for a minimum of 10 minutes. (No
pressure build-up at M2 indicates integrity of single valve.)
6. Leave downstream vent/drain at break point in closed position to allow further
monitoring.
Isolation
The single isolation valve is now closed and secured, and the downstream vent/drain is
Summary
closed. Any fluid passing through the single valve seal would be monitored by means of the
mandatory additional safeguards listed in Appendix A, Table 1.
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT: http://baku.bpweb.bp.com/dep/hse/safe/
Procedure for Energy Isolation - Process
Page 33 of 40
APPENDIX D: ENERGY ISOLATIONS FLOWCHART
Requirement
for
Isolation
No
Is this
Yes
a CSE?
Is this
Positive
No
Yes
Assess breaking
Yes
No
breaking
isolation
Containment risks/hazards
co
tainment?
available?
Define cleaning / flushing /
purging method
Select
Is this a
Can minimum
No
Yes
ICC
Isolation
Special isolation
Isolation standard
method
technique
be ac
ieved
Yes
No
L2RA
Install initial isolation
ICC
Complete draining / flushing /
Purging of eqpt where necessary
Isolation
Yes
Install final
Yes
No
Isolation
P
r
rogress work, monitor
successfully
isolation integrity
isolation
roved?
roved?
STOP
No
Reassess and consider
Job complete
Yes
production shutdown,
lleak test req‟d?
deferral of work and
further risk assessment
Is leak test
No
No
Prepare specific
covered by existing
Leak test procedure
rocedure
Yes
Carry out appropriate
Carry out leak test
Service test for
Service test for
Level of risk assessment
And record results
Non-haz utilities
Process hydrocarbons.
Mandatory L2RA
Fully de-isolate and
return to service
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Energy Isolation - Process
Page 34 of 40
APPENDIX E: Procedure Summary
Ensuring the required competent personnel are
Performing Authority:
available at the installation to carry out isolation
The Performing Authority is the person charged with the
ENERGY ISOLATION (Process)
activities
responsibility of carrying out the work and has the right to
Ensuring that plant and equipment isolations are
request demonstration of the integrity of any isolation. They
subjected to the appropriate level of self-regulation
are responsible for checking that Energy Isolations `have
Golden Rules of Safety
and audit
been implemented in accordance with the isolation
Energy Isolation is one of BP‟s Golden Rules. It states that,
specification before starting work.
any isolation of energy systems, e.g. mechanical, electrical,
Area Authority:
process, hydraulic, pneumatic, gravitational, chemical,
The Area Authority is responsible for approving the isolation
Maintenance Personnel:
radioactive, thermal, or other energy source that could cause
design, providing assurance that the design achieves the
Maintenance personnel work under the direction of the
injury, cannot proceed unless:
highest quality of isolation reasonably practicable. He/She
Isolating Authority and are responsible for installing the
The method of isolation and discharge of stored
can delegate the detailed isolation design to an Isolating
means of isolation (e.g., spades) and removing equipment /
energy are agreed and executed by a competent
Authority. The Area Authority is then responsible for
pipe work (e.g., spool pieces) taking into consideration the
person(s)
authorising the work to proceed under the appropriate
equipment rating and service.
Any Stored energy is discharged
controls. They are responsible for:
A system of locks and tags is utilised at isolation
Monitoring
Ensuring only authorized personnel perform
points
isolations
The integrity of each isolation point shall be monitored at
A test is conducted to ensure the isolation is
suitable intervals to detect any actual leakage or deterioration
Advising the OIM / Site Controller / Site Manager on
effective
in condition caused, for example, by vibration or disturbance
Isolating Authority (IA) competence
Isolation effectiveness is periodically monitored
(or changing pressure upstream). The results of any
Ensuring isolation specification, application, removal,
monitoring of isolation integrity shall be recorded and will form
certification and security are accomplished in
Roles & Responsibilities
part of the shift handover.
accordance with this procedure
Facilitating the Risk Assessment process in
Site Manager
/ Site Controller
/ Offshore Installation
Self-Regulation & Audit
accordance with AZSPU-HSSE-DOC-00063-2; Task
Manager:
Each Site / Installation shall:
Risk Assessment
The OIM/SC/SM is responsible for ensuring that those
Undertake internal audits of the operation of Energy
Approving all Energy Isolations
performing the roles of Area Authority, Isolating Authority and
Isolations at each site.
The weekly review and quarterly audit of long-term
Performing Authority are competent to do so and have overall
Maintain an Audit Register.
isolations
responsibility for the implementation of the Permit to Work
Have in place a system for tracking
The control of all lock-off devices and tags involved
and isolation procedures at their site. They are responsible
recommendations through to closeout.
with isolations
for:
Periodically review isolation-related activities
Ensuring the operation and assurance of the
including review of individual isolations and the
Isolating Authority:
isolation procedure at their site, acting upon all
overall isolation process. Such reviews may also
The Isolating Authority is responsible for:
recommendations
and
proposing
system
include:
The specification, application, removal and recording
improvements
o General compliance with this document and
of Energy Isolations in support of a Permit to Work
Authorising the Area Authority and Isolating
any local procedures
The design of process isolation when requested by
Authority (in writing) as competent to carry out their
o The Level 2 Risk Assessment of non-compliant
the Area Authority. When designing the isolation the
responsibilities within the Permit To Work and
isolation and the extent of any approved
Isolating Authority must agree the scope and content
isolations procedures
deviations
of isolation with appropriate personnel e.g. the
Maintaining a control log of all authorised personnel.
o A register of competent Isolating Authorities
Performing Authority.
Details of this control log are included in AZSPU-
Isolating specific sections of plant or items of
HSSE-DOC-00012-2; Authorization
The recommended frequency of audit is as follows:
equipment to the highest quality and security of
Communicating the responsibilities of key
¾ Installation /Site personnel - 1 permit and isolation
isolation, which is reasonably practicable.
participants within the isolations procedures to those
confirmation (ICC) certificate per day
Demonstrating to the Performing Authority the
personnel under their direction
¾ Site Safety Adviser
- 1 permit and isolation
integrity of the Energy Isolations
Approving all Level 2 Risk Assessments undertaken
confirmation (ICC) certificate per week
Monitoring of isolations in-place
for non-compliant isolations
¾ SM / SC / OIM - 1 permit and isolation confirmation
(ICC) certificate per month
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT:
Procedure for Energy Isolation - Process
Page 35 of 40
ENERGY ISOLATION (Process) cont
Note: The Isolation Confirmation Certificate is raised
The recommendations from the Level
2 Risk
before the permit is issued, and remains in force
(as a
Assessment shall be approved by the OIM / SC / SM
minimum) until the permit is cancelled.
who may also recommend further review by
Note: Audits should be a cross section of activities ongoing
technical specialists or management before taking
i.e. hot work, cold work, and spark potential. Installation / Site
The Isolation Certificate shall only be cancelled when
the decision on whether to proceed with the work
personnel should carry out audits of individual tasks covering
“WORK is COMPLETE”. The Area Authority can then sign
The Risk Assessment shall be attached to the
both the PTW and the Isolation Confirmation Certificate (ICC)
the “CANCELLATION” section.
appropriate Permit(s)
on a regular basis.
Competency, Training & Awareness
Isolation Review & Level 2 Risk Assessment
Types of Isolations
All personnel involved in Energy Isolations-Process shall be
Where an isolation cannot achieve the standard detailed in
There are varying types of isolations, which are described
trained and deemed competent. The competency of all
Energy Isolations Process the Area Authority or Support
within this section. These include:
relevant personnel shall be determined during the planning
Engineer is responsible for commencing the Isolation Review
Boundary Isolations
process for any particular risk assessment. The Area
and Risk Assessment.
Long Term Isolation
Authority and/or Line Supervisor shall ensure that the
Personal Isolations
personnel involved in the activity have the correct
As a minimum, the Area Authority or Support Engineer
Additional Isolations
competencies by examining records, or requesting individuals
together with the Isolating Authority, and the Performing
Isolation for Confined Space Entry
to produce relevant certification.
Authority complete a Risk Assessment. There must be three
members as a minimum for a Level 2 Risk Assessment.
Boundary Isolations:
Levels of Training - A training programme providing initial
Where an area of plant is isolated such that several activities
and refresher training and trainee assessment on the
The completed Risk Assessment shall be submitted to the
can safely take place within this common set of strategically
contents of this document shall be carried out involving all
OIM / SC / SM who will, if necessary, discuss and clarify the
placed isolation points then this can be termed as a
personnel responsible for the specification, approval,
isolation design with the team. If accepted, the OIM / SC / SM
'Boundary Isolation'. It must be clearly identified that the
application and recording of process isolations.
shall approve the Risk Assessment.
isolation is appropriate for all the individual tasks to be carried
out against the Boundary Isolation. An Isolation Certificate is
The competency requirements for Energy Isolation - Process
Risk Assessment Process
raised and identified, as Boundary Isolation and all individual
for Site Managers / Site Controllers / Offshore Installation
In the event that the minimum recommended isolation
PTW are cross-referenced to this Boundary Isolation.
Managers / Area Authorities / Department Heads shall be in
standard cannot be achieved, a Level 2 Risk Assessment
accordance with AzSPU Training Policy;
(AZSPU-HSSE-
shall be carried out according to the following guidelines:
Long-Term Isolations:
DOC-00088-2).
The assessment team shall specify appropriate
Long-term isolations are defined as those that no longer have
safeguards, which may replace or be in addition to
work performed against them. Each site should maintain a
The Isolation Confirmation Certificate (ICC) Process
those listed in Table 1 (Appendix B). The team shall
detailed register of long-term isolations.
Where isolations are required an Isolation Confirmation
be satisfied that these safeguards shall reduce the
Long-term isolations shall be subject to two levels of review:
Certificate (ICC) must be completed as detailed in the Permit
risks to an acceptable level before the Level 2 Risk
A weekly review of the register to check the status of
to Work
(PTW) procedure. The Isolation Confirmation
Assessment is submitted to the OIM / SC / SM for
the isolations in place and whether they should be
Certificate supports the Permit to Work by providing the
the task requiring isolation is permitted to proceed
removed or replaced by a plant modification
means of:
When risk assessing non-compliant isolations,
A quarterly audit to physically check all the isolation
Recording the isolations which are required before
consideration shall be given to the risks associated
points to confirm their security and integrity
the task detailed on the associated Permit to Work
with swinging large spades compared with the risk
Before any work is recommenced against a long-
can proceed
associated with the lower level of isolation
term isolation, a full integrity check of the valved
Confirming that the isolations have been made for
Consideration shall be given to: extended monitoring
isolation shall be carried out.
the task to proceed (subject to authorisation of other
periods, prior to breaking containment, reducing the
certificates e.g., Confined Space Entry)
duration of the tasks, provision of a permanent
Personal Isolations:
Authorisation and recording of de-isolations and
standby man and development of a contingency plan
Personal isolations are intended for short duration tasks of
isolations which may be required to test equipment
for isolation failure
relatively low risk; for example replacing pressure gauges,
under a Sanction to Test (STT)
Full consideration shall be given to the alternatives
filters or small valves, or other such tasks where the
Authorisation and recording of de-isolation on
including partial or full production shutdown or
completion of an ICC is considered to add no significant value
completion of the task detailed on the associated
deferral of the work
Permit to Work
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT:
Procedure for Energy Isolation - Process
Page 36 of 40
ENERGY ISOLATION (Process) cont
undertaken and approval obtained from the SM / SC / OIM
TABLE 1: Minimum Recommended Isolation Standards for
before entry can be permitted under work control.
Predetermined Risk Levels:
in terms of risk reduction. The rules for approval of a personal
isolation are as follows:
The manway doors on a vessel being prepared for entry shall
be removed last and reinstalled first to reduce the risk of
Fluid Type
Operating Pressure
The task and isolation are performed by one person
unauthorised entry.
within one shift; the person may receive assistance
<10barg
>10barg
>55barg
from others but he shall be present at all times when
work is in progress
Further details on Confined Space Entry are given in:
<55barg
AZSPU-HSSE-DOC-00013-2.
Before approval, the Area Authority must be satisfied
Process fluids
V = SVI
V = SVI+B
V = DBB+A
with the competence of the Performing Authority to
Registers
and hazardous
I = SVI+A
I = DBB+B
I = DBB+B
both carry out the isolation and execute the work.
All Isolation Confirmation Certificates
(ICC‟s) shall be
utilities
Personal isolations shall only be carried out by those
registered on the Isolation Confirmation Certificate Register,
deemed to be a competent Isolating Authority.
Non-hazardous
V = SVI
V = SVI+A
V = SVI+B
which is maintained by the Area Authority(s). Where a site
Where an isolation involves competency in more
utilities
I = SVI
I = SVI+B
I = DBB+B
has more than one Area Authority, the nominated responsible
than one discipline eg electrical, mechanical,
V Valve configuration required to permit the installation
Site Isolating Authority (IA) Co-ordinator shall assume overall
instrument or process, personal isolation is only
of blank flanges and spades (positive isolation)
control of the Register.
permissible if the Performing Authority has all the
I
Valve configuration required to permit carrying out
appropriate isolating competencies
intrusive maintenance without positive isolation
Records
The same isolation standards apply to personal
A Use mandatory safeguards as on List A
When all the isolations have been implemented, the Area
isolations other than the completion of the ICC
B Use mandatory safeguards as on List B
Authority signs and dates the Isolation Confirmation
The isolation points shall be labelled with a personal
SVI Single Valve Isolation
Certificate. He then records the Isolation Confirmation
isolation label and locked
DBB Double Block and Bleed
Certificate number on the permit. The Control Room Operator
If the worksite is left unattended, the plant shall be
and/or the Permit Coordinator may also perform this where
left safe, including capping or plugging of any open
Mandatory Safeguards
Category A
Category B
they are appointed.
ends
(Low Risk)
(High Risk)
Isolation Confirmation Certificates shall be accessible to each
An ICC shall be raised whenever these conditions are not
Continuous gas monitoring
y
y
Area Authority and are held in the vicinity of the Control
adhered to.
(for hydrocarbon systems
Room for ease of monitoring each area.
only)
Additional Isolations:
Isolation Standards
Pressure build-up to test
y
y
An individual Isolation Confirmation Certificate must be
Minimum recommended isolation standards have been
valve integrity
completed for each Permit to Work requiring isolations;
developed and should be referred to when designing process
unless isolations are controlled by a Boundary Isolation
Regular monitoring of
y
y
isolation where it is not reasonably practicable to achieve
Certificate. Where working within a defined boundary, further
isolation integrity
positive isolation (refer to Table 1). The minimum standard
isolations may not be required. However, where additional
also identifies mandatory safeguards, which the Area
Control and prevent nearby
y
y
isolations are identified, an Isolation Confirmation Certificate
Authority is responsible for putting in place to reduce the risk
work
will be required.
level to as low as reasonably practicable.
Operations Technician in
y
y
Isolation for Confined Space Entry:
attendance
Positive isolation shall be effected on all live lines for any task
Note 1: Any proposed isolation, which deviates from those
requiring entry to a vessel or confined space. Spool removal
shown in Table 1 (Appendix B), must be subject to an
Radio link to control room
y
is to be preferred, although spade isolation may be used
Isolation Review and a Level 2 Risk Assessment.
when breaking
where it is not reasonably practicable to remove pipework
containment
sections. It should be noted that in some cases it may not be
Note 2: Isolation against a tested single valve is permissible
Develop contingency plan
y
reasonably practicable to comply with this requirement in
while swinging a spectacle blind, inserting a spade or fitting a
against leakage
making entry to mud tanks, pump pits, ballast tanks, or other
blank flange to achieve a positive isolation.
utility systems. Here, a Level 2 Risk Assessment shall be
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT:
Procedure for Energy Isolation - Process
Page 37 of 40
for the amendment shall be recorded and the
It is not necessary to lock bleed valves in a DBB arrangement
Identify backup isolation
y
Performing Authority advised of the change
as they are required to be opened periodically to check the
valves, shutdown systems
etc
Pressure relief valves shall only be isolated following
integrity of the isolation.
the provision of an alternative means of pressure
Minimise task time
y
relief
Personal isolations (refer to section 8.3) shall be secured to
the same standard to prevent unauthorised operation of the
Portable fire-fighting
y
Isolation Implementation & Control
valves.
equipment available (for
hydrocarbon systems only)
Any isolation must achieve and maintain effective
containment of the relevant fluid for as long as required.
Plant Reinstatement
Minimise possibility of plant
y
The reinstatement of plant and equipment requires equal
disturbance
attention to planning and detail as the initial isolation.
Valves shall be locked or otherwise immobilised to prevent
Isolation Planning
unauthorised operation. It may be necessary to apply
Isolation of any piece of equipment shall be planned such that
additional immobilising devices under certain circumstances.
Historical data shows that many incidents involving
the risk of removing it from service and then reinstating it on
failure of an isolation occur during reinstatement.
completion of the work is minimised. The Flowchart
Where valves are required to be locked (open or closed) as
(Appendix D) should be referred to when planning any
part of an isolation, only the following methods are
Reinstatement of process plant is not complete until the
isolation. All isolations shall be designed according to the
acceptable:
section where containment was broken has been leak tested.
standards set out in Appendix A (including Table 1).
The use of wire locking loops to immobilise the valve
which would require considerable effort to force the
The reinstatement leak test is different from strength tests as
The following key points should also be considered:
valve from the lock position
required by Code, which are pressure/strength tests to prove
Plant and equipment isolation requirements should
Padlock and chains which likewise would take
the structural integrity of the system.
be identified early in the work planning cycle for the
considerable effort to force the valve from the locked
Installation or site so that adequate time can be
position. Where this method is used, padlock keys
The purpose of reinstatement leak testing is to render the
made available for formal risk assessment, should it
shall be held by the Area Authority
production equipment and piping systems safe for the
become necessary. Where necessary, reference
The use of specifically designed tamper-proof valve
introduction of hydrocarbon gases and liquids, and to create
shall be made to the Installation or site Operations
an auditable record to demonstrate the integrity of all
interlocks. The activation of the interlock shall be
Safety Manual
(OSM) and the identification of
controlled by the Area Authority utilising the master
hydrocarbon production systems.
high-risk areas
key held at the site
A boundary isolation may be put in place to cover
For an an overview of the leak testing process refer to the
several planned activities in an area of plant. The
When isolating any valve that cannot be locked and may
SSOW for Leak Testing (Document No. AZSPU-HSSE-DOC-
Isolation Certificate shall describe the scope of work
inadvertently be opened by accidental contact, the valve
00055-2).
planned and the Permits for these jobs shall be
handle shall be removed where practicable.
cross-referred to the same Isolation Certificate
The need for good access and egress to allow
Electrically operated valves shall have the power supply
isolations to be effected
positively isolated and any handjack shall be manually locked.
Isolations should be as close to the vessel or
If the valve cannot be physically immobilised it should not
worksite as possible, to assist in security and ease
normally be used for isolation purposes.
of monitoring
Preparation for isolation involving draining, flushing,
Pneumatically and hydraulically operated valves which fail
purging and venting of process pipe-work shall be
closed shall have their control lines isolated and physically
conducted under the AzSPU Safe System of Work
disconnected.
(SSOW) according to the appropriate procedures for
the task and including the appropriate isolation
Pneumatically and hydraulically operated valves which fail
Amendments shall not normally be made to
open should not normally be used for isolation purposes. If no
isolations in place other than to allow testing of
other alternative is reasonably practicable, the valve shall be
equipment prior to return to service. Amendments
prevented from moving. Under this situation the isolation shall
may be made to improve the integrity of the isolation
be considered as non-compliant with Energy Isolations-
with the approval of the Area Authority. The reason
Process and a Level 2 Isolation Risk Assessment carried out.
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT:
Procedure for Energy Isolation - Process
Page 38 of 40
APPENDIX F: FEEDBACK & IMPROVEMENT SUGGESTIONS
Procedure Feedback & Improvement Suggestions
Project Name: ______________________________
Date: ______________________________________
Name:_____________________________________
Badge Number: _____________________________
Procedure Reference: ________________________
Procedure Title: _____________________________
Improvement Suggestions (Write below your improvement suggestions)
Forward your Improvement Suggestion to the HSSE
Manager at the Central HSSE Office, Hyatt Tower 2,
Signature: _____________
6th Floor
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: <<AZSPU-HSSE-DOC-00049-2
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT: http://baku.bpweb.bp.com/dep/hse/safe/
Procedure for Energy Isolation - Process
Page 39 of 40
Revision/Review Log
Revision Date
Authority
Custodian
Revision Details
09 Sept 2004
Central
EI (process) Technical
Initial issue as controlled document
Engineering Senior
Authority
Authority
07 Sept 2007
Alan McNulty
Steve Grittner
Table of Contents changed as follows:
CHSSE Manager
Central Engineering
Additional sub-sections added to Section 1:
Senior Authority
Introduction
General:
Throughout the procedure the document
numbering for referred SSOW‟s has been
changed from UNIF-HSE-PRO to AZSPU-
HSSE-DOC.
Section 1. Introduction:
1.2 is now Scope. 1.3 is now Legislation &
Standards. 1.4 is now Company
Requirements. 1.5 is now Stopping Unsafe
Work. 1.6 is now Deviations. 1.7 is now
Document Review. 1.8 is now SSOW
Specific Cross Reference. 1.9 is now
Golden Rules of Safety. 1.10 is now
Language Facilitation. 1.11 is now
Procedure Summary
Section 2. Definitions:
Definitions moved from Appendix „A‟ to this
section.
Section 3. Roles & Responsibilities:
3.3 OIM/SC/SM: 3rd bullet point; updated
document number for Authorization.
3.4 Area Authority: 2nd bullet point; added
Site Manager. 4th bullet point; updated
document number for Task Risk
Assessment.
Section 4. Monitoring & Auditing of
Isolations:
4.2 Self-Regulation and Audit: Changed;
Each Business Asset shall: to Each Site /
Installation shall:…
Section 5. Competency, Training &
Awareness:
5.2 Levels of Training: Added competency
requirements shall be in accordance with
AzSPU Training Policy (AZSPU-HSSE-
DOC-00088-2). Training Matrix removed
from this section
Section 8. Types of Isolations:
Last bullet point; updated document number
for Confined Space Entry.
Appendix A. Is now Isolation Standards
Appendix B. Is now Guidance Notes.
Appendix C. Is now Typical Valve
Isolations Integrity Tests
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS
Procedure for Energy Isolation - Process
Page 40 of 40
Appendix D. Is now Energy Isolation
Flowchart
Appendix E. Is an addition - Procedure
Summary
Appendix F. Is an addition - Feedback &
Improvement Suggestions
Control Tier: <<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00049-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS
Procedure for Excavations
Page 1 of 32
Procedure for Excavations and Trenches
AZSPU-HSSE-DOC-00050-2
This number supersedes UNIF-HSE-PRO-112-C
Authority:
AzSPU CHSSE Manager
Custodian:
AzSPU CHSSE Team Leader
Scope:
AzSPU
Document
Administrator:
Document Asset Technician Name
Issue Date:
22 October 2004
Issuing Dept:
CHSSE
Revision Date:
14 September 2007
Control Tier:
2
Next Review
14 September 2008
Date:
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 2 of 32
TABLE OF CONTENTS
1
INTRODUCTION
4
1.1 Purpose
4
1.2 Scope
4
1.3 Legislation & Standards
4
1.4 Ground Disturbance Golden Rules of Safety
5
1.5 Company Requirements
5
1.6 Stopping Unsafe Work
5
1.7 Deviations
5
1.8 Document Review
6
1.9 SSOW Specific Cross References
6
1.10 Language Facilitation
6
1.11 Procedure Summary
6
2
DEFINITIONS & ABBREVIATIONS
6
3
ROLES & RESPONSIBILITIES
7
3.1 Site Manager (SM) / Site Controller (SC)
7
3.2 Area Authority (AA)
7
3.3 Performing Authority
8
3.4 Machinery Operator
8
3.5 Banksmen
8
3.6 All Personnel
8
3.7 Environmental Adviser
8
4
EXCAVATIONS AND TRENCHES DEEPER THAN 1.2M
9
5
ACCESS ROUTES
9
6
ROUTE IDENTIFICATION AND PREPARATION
9
6.1 Locating and Marking Existing Pipelines
9
6.2 Pipeline Crossing Points
10
7
SITE SAFETY
10
7.1 Access and Security
10
7.2 Vehicle Traffic
11
7.3 Personnel
11
7.4 Equipment
11
7.5 The Use of Mechanical Equipment near Overhead Power Lines
12
7.6 Working Hours
13
7.7 Fires
13
8
PRE-EXCAVATION REQUIREMENTS AND PROCEDURE
14
8.1 BP Consent
14
8.2 Landowners
14
8.3 Third Party Services
14
8.4 Excavation Boundaries
14
8.5 Drainage Patterns
14
8.6 Excavation design requirements
14
8.7 Risk Assessment, Permit to Work and Supplementary Certificates
17
8.8 Environmental Impact Assessment
17
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 3 of 32
9
EXCAVATION PROCEDURES
18
9.1 Excavation Inspections
18
9.2 Toolbox Talks
19
9.3 Non-Mechanical Excavation
19
9.4 Mechanical Excavation
20
9.5 Excavated Materials
22
10 BACKFILLING PROCEDURE
23
10.1 Preparation
23
11 SITE REINSTATEMENT
24
11.1 Drainage
24
11.2 Topography
24
12 DOCUMENTATION
24
APPENDIX A: EMERGENCY PROCEDURE IN THE EVENT OF PIPELINE DAMAGE
25
APPENDIX B: EXCAVATION INSPECTION CHECKLIST
26
APPENDIX C: PROCEDURE SUMMARY
27
APPENDIX D: FEEDBACK & IMPROVEMENT SUGGESTIONS
30
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 4 of 32
1
INTRODUCTION
Purpose
This document sets out the precautions and conditions considered necessary for the
safety of all excavation works carried out on BP owned or managed sites in Azerbaijan
and Georgia. It has been produced so that all involved parties can make a uniform
approach to excavations.
Scope
The contents of this procedure are applicable to all BP owned and managed sites /
installations in Azerbaijan and Georgia. Contractors working on BP owned or managed
sites / installations are also responsible for alignment with this procedure.
This document does not replace the procedures prepared and adopted by specialist
contractors. Neither does it supersede any national and local regulatory requirements.
This procedure contributes to compliance with the “HSE expectations” contained in
“getting HSE right”, the „Golden Rules of Safety‟ and the Control of Work (CoW)
standard that the Hazards associated with BP activities are identified and that the risks
are assessed and managed.
All guidelines contained shall be regarded as the minimum requirements for BP owned
or managed sites / installations in Azerbaijan and Georgia.
The scope covers defined activities of BP and Contractors at all BP AzSPU sites and
installations.
This document refers to:
 Method of excavation
 Excavation and protection of all pipelines and services
 Excavation of oil contaminated soils
 Backfilling guidelines
Legislation & Standards
The aim of this Safe System of Work is to achieve ”no accidents”, “no harm to people”
and “no damage to the environment”. To achieve this aim, this SSOW complies with
National Legislation, the terms of the Production Sharing Agreement
(PSA) and
mandatory BP Standards.
The best International Oil Industry practice and relevant goal setting legislation have
been adopted to reduce the level of risk to as low as reasonably practicable and
therefore well below that mandated by applicable statutory laws and regulations.
In the absence of local regulations, BP Group Standards will apply. In addition,
appropriate UK and US regulations and industry best practice have been considered in
setting suitable goals and targets.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 5 of 32
Ground Disturbance Golden Rules of Safety
Ground Disturbance is one of BP‟s Golden Rules of Safety and states:
Work that involves a manmade cut, cavity, trench or depression formed by earth
removal, or driving of piles into the earth‟s surface cannot proceed unless:
 All underground hazards, i.e., pipelines, electric cables, etc., have been
identified, located and if necessary, isolated
 A permit has been issued
 Ground movement has been controlled and collapse prevented by
systematically shoring, sloping, benching, etc., as appropriate
 Ground and environmental conditions are monitored for change
 Unauthorized access is prevented
Where persons are to enter an excavation:
 A confined space entry permit must be issued if the entry meets the confined
space definition
Company Requirements
It is a company requirement that all tasks are subjected to an assessment of risk to
demonstrate that risks have been reduced to as low a level as reasonably practicable
(ALARP). This can be achieved by complying with the Company‟s existing standards.
Where compliance with Company standards cannot reasonably be achieved, a formal
level 2 Risk Assessment will be undertaken to identify any additional controls and
demonstrate that risks remain as low as reasonably practicable. Whether by
compliance with Company Standards or through level
2 Risk Assessment, the
Company‟s Golden Rules of Safety must be complied with. Golden Rules are non-
negotiable.
Stopping Unsafe Work
To stop the continuation of potentially unsafe work at the earliest possible stage, the
Control of Work (CoW) Policy and this procedure for Excavations make it very clear
that all personnel are obliged and have the authority to “STOP” the work that they
consider to be unsafe.
Deviations
This procedure is written in sufficient detail that it should be able to be applied
consistently at all sites / installations. There may still be the requirement for some local
rules covering site / installation specific logistical/administrative arrangements and local
variations in responsibilities to reflect differences in organisational arrangements.
These local rules should not deviate from the core processes within this document. Any
form of deviation from this procedure, including but not limited to local rules, shall be
requested and authorised in accordance with SSOW, Deviations from Regulations and
Procedures (Doc. No: AZSPU-HSSE-DOC-00011-2).
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 6 of 32
Document Review
This document will be reviewed on an annual basis when users from the sites /
installations will have an opportunity to propose changes to the existing processes and
procedures. The document Technical Authority will be responsible for coordinating this
review.
SSOW Specific Cross References
This procedure shall, where appropriate, be used in conjunction with this suite of
AzSPU Procedures referenced below.
Document Number
Title of Procedure
AZSPU-HSSE-DOC-00011-2
Deviations from Regulations and Procedures
AZSPU-HSSE-DOC-00060-2
Permit To Work
AZSPU-HSSE-DOC-00063-2
Task Risk Assessment
AZSPU-HSSE-DOC-00048-2
Energy Isolations-Electrical
AZSPU-HSSE-DOC-00049-2
Energy Isolations-Process
AZSPU-HSSE-DOC-00013-2
Confined Space Entry
AZSPU-HSSE-DOC-00066-2
Hydrogen Sulphide
AZSPU-HSSE-DOC-00002-2
BP Control of Work Standards
Language Facilitation
Due to the various languages spoken at sites / installations, there is a necessity to
assist all with “an ease of understanding”. Therefore, the development and use of
information tools are available.
Procedure Summary
A Procedure Summary has been developed in a form of a leaflet, which can be carried
by the Line Supervisors while conducting their day-to-day work tasks. The Leaflet
summarizes the contents of this procedure for Excavations. The Procedure Summary
can also be used as a guideline for Line Supervisors to deliver their daily toolbox talk.
(See Appendix C)
2
DEFINITIONS & ABBREVIATIONS
ROW
Right of Way
GIS
Geotechnical Information System
GPS
Global Positioning System
SM
Site Manager
SC
Site Controller
OIM
Offshore Installation Manager
AA
Area Authority
PA
Performing Authority
ALARP
As Low as Reasonably Practicable
COW
Control of Work
CSE
Confined Space Entry
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 7 of 32
ICC
Isolation Control Certificate
L2RA
Level 2 Risk Assessment
PTW
Permit to Work
RTC
Risk It, Talk It, Check It Pre-Task Risk Assessment
SSOW
Safe System of Work
TRA
Task Risk Assessment
TA
Technical Authority
TBT
Toolbox Talk
ROPS
Roll Over Protective Structure
Competent
A person trained in soil analysis (as far as is reasonably practicable),
Person
the use of protective systems and hazardous atmospheric conditions
who has the authorization to take prompt corrective measures to
eliminate hazards
Excavation
Any man-made cut, cavity, trench or depression in an earth surface
formed by earth removal. Examples include ditches, trenches, bell
holes, etc
Way Leave
The strip of land through which BP has acquired the right to lay,
Strip
construct and maintain a pipeline
3
ROLES & RESPONSIBILITIES
Site Manager (SM) / Site Controller (SC)
The Site Manager / Site Controller shall be responsible and accountable for the
application of this procedure in his area of responsibility, He shall ensure:
 That this procedure is strictly adhered to for all work activities that involve open
excavations in the earth‟s surface
 That only certified and experienced operators operate excavating equipment
 That all work activities that involve open excavations in the earth‟s surface are
subject to risk assessment and the Project Permit to Work System
 That all work activities that involve open excavations in the earth‟s surface are
closely monitored to ensure compliance with this procedure
 That suitably qualified and experienced personnel are appointed to control and
perform all work activities that involve open excavations in the earth‟s surface
Area Authority (AA)
Area Authorities are responsible for:
 Compliance with this Safe System of Work within their area of authority
 The safety of personnel and the safe execution of activities within their area
 Ensuring daily equipment checks are completed on equipment within their area
by the Machinery Operator and that equipment is maintained in good working
order
 Ensuring that all excavations are conducted in accordance with this procedure
and BP Golden Rules of Safety (ground disturbance)
 Provision of instruction to personnel as required
 Monitoring work activities to ensure compliance with the requirements of safe
systems of work
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 8 of 32
Performing Authority (PA)
Performing Authorities are responsible for:
 Complying with the requirements of this procedure during the performance of
all the excavation work or preparing and submitting to the Area Authority, for
review and approval, their own Excavation procedure to cover the work
 Ensuring that only suitably trained persons are assigned to excavating and
trenching activities in their area of operation
 Ensure that all workers under their control understand the specific excavation
safeguards and comply with this procedure and any other BP standard, local
regulation ands applicable safety rules, standards, and procedures during
excavation and trenching operations
Machinery Operator
Machinery operators are responsible for:
 The safe and responsible operation of machinery under their control
 Immediately reporting to their supervisor if they believe the equipment they are
using is in a dangerous or unsafe condition
 Ensuring that the machinery or equipment they use has all the safety devices
and guards in place and that all guards are properly fitted.
 Ensuring daily equipment checks are completed on equipment within their area
and that equipment is maintained in good working order
Banksmen
Banksmen are responsible for:
 Preventing access to working areas under their control by unauthorised
personnel
 Providing safe guidance and assisting in the safe operation of machinery under
their direction
 Remain in communication with the rigger/slinger and crane operator at all times.
 Be known and clearly identifiable to all concerned by wearing high visibility
identification
All Personnel
All personnel are responsible for:
 Carrying out their duties in a safe and responsible manner
 For halting any work where they feel that conditions are unsafe and for bringing
this to the attention of their immediate supervisor
Environmental Adviser
Environmental Advisers are responsible for:
 Providing advice and assistance to the Site Supervisor on environmental
matters as and when required
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 9 of 32
 Providing Geotechnical Information System information and Global Positioning
Survey coordinates regarding natural, archaeological and other important
features within and adjacent to the excavation site.
Note: Photographs of important features should also be provided if required.
4
EXCAVATIONS AND TRENCHES DEEPER THAN 1.2m
All excavations and trenches deeper than 1.2 metres in “hazardous areas” as defined
by the site / installation are classified as confined spaces.
In “non hazardous areas” where there are no significant hazards identified prior to entry,
the following criteria must be established before determining the requirement for a
“Confined Space Entry permit”:
 No risk of atmospeheric hazards either from surrounding area or from the task
being performed.
 The excavation does not require any form of isolation prior to entry.
 No risk of engulfment from Ingress of solids or liquids.
 No risk from excessive heat.
 Unrestricted safe means of access and egress for work party
 Unrestricted safe means of aceess and egress for rescue purposes
 Excavations benched or shored to reduce risk of collapse
 Continuous monitoring of O2, LEL and other toxic gasses are carried out inside
the excavation
The excavation / trench may be classified as “not a confined space” if all the above
criteria can be established and a Level 2 Risk Assessment is conducted.
Note: A Permit to Work and Level 2 Risk Assessment are mandatory for “all work” in
excavations and trenches deeper than 1.2m.
5
ACCESS ROUTES
Access routes to proposed sites shall be properly surveyed and. In particular, for all
access routes:
 Risk assessments shall be made, and actions documented, for all crossing
points and other points of difficulty recognised on the route
 Method statements shall be produced for negotiating all crossing points and
other points of difficulty
 The route shall be clearly marked
6
ROUTE IDENTIFICATION AND PREPARATION
Locating and Marking Existing Pipelines
Note: At locations where there is hydrocarbon or a suspected leak a gas survey
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 10 of 32
must be carried out before pipeline location activities begin.
Prior to the commencement of any excavation a site survey shall be carried out in order
to:
 Locate, identify and mark any existing pipelines and foreign services and
utilities and any cathodic protection system components, using pipe locating
equipment and hand excavated trial holes
 Peg out the pipeline routing
 Define and log the point of excavation
Pipeline Crossing Points
Requirements
Construction traffic and other plant shall cross the pipeline only by:
 Public roads
 Previously agreed and clearly marked crossing lanes or bridges
Construction
All crossing lanes shall be fenced on both sides over a width to be specified and
agreed by the Pipeline Patrolman as far as is reasonably practicable as dictated by
local conditions and acts of vandalism. These fences shall be returned along the edge
of the way-leave strip for a distance of 6 m away from the crossing.
Where it is necessary at crossing points to install a temporary bridge to protect the
pipeline, the bridge will be of engineered design and approved by the Site Manager or
Site Controller. The design and construction of such bridges and crossings shall be by
a competent person or approved civil engineering subcontractor where it is deemed
necessary.
Markings
Any temporary crossing or bridge must be clearly marked by appropriate notices and
flags, and additionally with lights at dusk, at night or in foggy conditions.
7
SITE SAFETY
Access and Security
Guards and Barricades
Open excavations near public areas must be:
 Attended by a watchman
 Protected by a barricade and marked with a warning sign
All other open excavations should be attended by a watchman, marked or barricaded. If
there is a recognised chance of people or cattle falling into the excavation, a decision
may be taken regarding the use of a night watchman.
Note: If a night watchman is used, he shall be equipped with appropriate
communications and shelter for use in case of prowling animals, sickness or
other emergency. Vehicle for night watchman to be provided as far as is
reasonably practicable.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 11 of 32
Fencing, Gates and Safety Notices
Erection of stock fencing, gates and bunting safety notices, etc., shall be undertaken
over access ways and worksites.
When the pipeline is exposed outside normal working hours a security presence will be
required over and above that of the normal construction personnel. This service shall
be supplied by a BP approved Contractor.
Vehicle Traffic
Vehicular traffic should not operate within 1.5 m of a trench or excavation. Vibration
created by traffic may cause cave-ins.
Personnel
Warning: Workers should not stand on the edge of an excavation or between a
pipeline ditch and strung pipe resting on skids. The bank might slough, or
temperature changes in the pipe could cause skids to fail and allow the
pipe to fall.
Protective Equipment (PPE)
With temperatures experienced in Azerbaijan and Georgia the use of Inherently Fire
Resistant or Flame Retardant Coveralls during summer where personnel are working
all day outside could be unbearable. An alternative to IFR/FR coveralls for the low flash
risk applications is 100% cotton. Personnel involved in specific work activities near live
hydrocarbon lines should wear Flame Retardant coveralls.
During all activities on site all personnel shall wear minimum PPE (helmet, safety
boots/shoes, fire coveralls, and eye protection).
Personnel involved in specific work activities shall wear additional PPE to suit the
requirements of the work as agreed/detailed at the pre-work toolbox talk.
Equipment
Type and Location
All equipment shall be checked and registered on the appropriate checklists and
registered in accordance with the site operating procedures. All operatives‟ certificates
shall be checked and logged prior to works commencing.
Warning: Machinery vibration may cause cave-in. No running plant shall be located
within 1.5 m of an excavation.
Equipment Inspection
Equipment shall be inspected daily and maintained as necessary to ensure that it is in
good working order. This includes the inspection of brakes, pivot pins, hydraulic
cylinders, hoses, snap rings, main attaching bolts, etc.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 12 of 32
Adjustments and Repairs
Do not lubricate or make mechanical adjustments to the unit while the unit is in motion
or the engine is running.
Do not repair or tighten hydraulic hoses or fittings when the:
 System in under pressure
 Engine is running
 Equipment hydraulic cylinders are under a load
Refuelling
A method statement covering spill containment and management of personnel injury
risks shall be prepared for all refuelling operations. In all cases, equipment shall be
shut down prior to being refuelled.
Lighting
All lighting shall be either explosion proof or located outside Zone 2.
The Use of Mechanical Equipment near Overhead Power Lines
Introduction
All personnel working near overhead power lines with a machine or mechanical
equipment shall be made aware of:
 The dangers associated with power lines
 The precautions they should follow to deal with those dangers
 What to do if they make contact with a power line
Warning: Physical contact with high-voltage overhead power lines is likely to be fatal
or cause severe and irreversible maiming.
It is impossible to say whether an overhead cable is a power line or a
telephone line from observation alone. The only sure method is to make
contact with the line owner.
Note: Further guidance on safe working in the vicinity of over head power lines can be
gained from HSE note GS 6; Avoidance of Danger from Overhead Electric
Power Lines.
Safe Vertical Working Clearance
The minimum safe working distance between mechanical excavation equipment and
live overhead power lines will vary according to:
 Type of power line (for example, insulated or un-insulated)
 Voltage carried by the power line
 Ground and weather conditions
To establish and maintain safe vertical working distances between mechanical
equipment and overhead power lines the following practice shall always apply:
1. Establish and record the maximum vertical reach of all machines on site.
2. Identify the routes of all overhead lines on or near the land to be excavated and
clearly mark these routes on site plans.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 13 of 32
3. For each overhead power line, identify the line owner.
4. From the line owner find out:
a. If the line can be conveniently made DEAD
b. The line type (for example, insulated or un-insulated)
c. The voltage carried
d. The minimum safe working clearance for mechanical machinery operating
near the power line
5. If the line cannot conveniently be made DEAD then the established minimum
safe operating clearance shall be adhered to at all times.
Reducing the Risk from Overhead Power Lines
Risks associated with working close to overhead power lines can be reduced by:
 Taking care not to damage poles and stays
 Fitting shorter radio aerials or repositioning existing ones on high machines so
they cannot cause danger
 Carrying long items (for example, pipes or ladders) horizontally and not storing
pipes or other materials and equipment near or under power lines and their
supports
 Designating safe areas for high-risk activities; for example, tipping trailers
 Using barriers and goalposts: by erecting goalposts and barriers, machines
which have to pass beneath lines can be limited to a safe height - an option
especially suited to gateways and tracks
If Contact is made With an Overhead Power Line:
 Never touch an overhead line - even if it has been brought down by machinery,
or has fallen through other means.
 Never assume that lines are dead.
 When a machine is in contact with an overhead line, electrocution is possible if
anyone touches both the machine and the ground. Stay in the machine and
lower any raised parts that are in contact or drive the machines out of the lines if
you can.
 If you need to get out to summon help or because of fire, jump out as far as you
can without touching any wires or the machine - keep upright and away from
the machine.
 Get the line owners to disconnect the power supply. Even if the line appears
dead, do not touch it - automatic switching may reconnect the power
Working Hours
Excavation work shall only be carried out during daylight hours where practicable. If the
task overruns dayshift then the area will be barriered off and illuminated using
approved out side site lighting. Preferably this should be a mobile tower, diesel driven
arc light if available. These are additional requirements in addition to the site being
fenced off.
Fires
Storage of material for lighting of fires within the pipeline way-leave or in the vicinity of
above ground installations associated with it is not permitted.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 14 of 32
8
PRE-EXCAVATION REQUIREMENTS AND PROCEDURE
Note: Excavation activity should preferably be undertaken in the summer as far as is
reasonably practicable, in order to minimise both ground disturbance and soil
compaction.
BP Consent
Excavations may only take place on BP managed or owned property with formal
consent from BP, with 72 hours notice as far as is reasonably practicable. Where
excavation is to take place, a Permit to Work and an Excavation Certificate shall be
obtained before work begins.
Landowners
Ensure that access has been granted by the landowner, that a pre-entry survey with
photographs has been done and that compensation, access route and area protection
have also been agreed.
Landowners and neighbours in close proximity to the proposed excavation must be
informed that work is about to begin and that the inspection is of a routine nature.
Note: This requirement may be negated under an emergency situation.
Third Party Services
Owners of third party services shall be contacted before the excavation of their services
begins. A No Objection Certificate shall be obtained when applicable.
Excavation Boundaries
The extent of required excavation shall be clearly marked out prior to commencement
of the work.
All PTW for excavations shall include a drawing of sufficient scale to clearly define the
excavation boundaries.
Drainage Patterns
Prior to excavation, existing drainage patterns should be noted, so that subsequent
drainage schemes can mimic the original pattern (see 11.1 Drainage).
Excavation design requirements
Access
Whenever personnel will be in an excavation, ramps, stairways or ladders should be
kept within 7.6m of workers for all excavations over 1.2m deep.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 15 of 32
A ladder, stairway or ramp shall be installed on both sides of the pipeline to provide
ingress and egress for workers.
Windsocks
In hazardous areas, windsocks or flags must be positioned on both sides of the
excavation in order to determine wind direction.
Portable Gas Detectors
Portable gas detectors are to be used in hazardous areas and they are to be sited up-
wind of the excavation. Care is to be taken as to ensure the work party are in audible
range of the detector. The detectors are to be checked and monitored regularly. It may
also be necessary to supply the work party inside the excavation an additional gas
detector.
Slope Requirements and Ground Type
Except in stable rock, all excavations must be shored, shielded (i.e., trench box),
benched or sloped if:
 The excavation is 1.2m or more in depth
 A worker‟s head is below the level of the excavation when bending or stooping
to perform the work task - as far as is reasonably practicable and/or required by
Risk Assessment.
Excavations deeper then 1m shall have the sides benched or battered back, as per
Figure 1 Minimum Acceptable Excavation Design Profiles for battered profile or figure 2
for benched profile. Shoring shall be used when required and site specific drawings, for
approval by BP, shall be prepared.
STEEPER SLOPES
REQUIRES SOIL
CLASSIFICATION TEST
“C”
“B”
“A”
SEE OSHA STANDARD
FOR EXCAVATIONS
DEEPER THAN 20 FEET
Note: 20 feet = 6.1m
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 16 of 32
Figure 1 Minimum Acceptable Excavation Design Profiles
TYPE A
TYPE B
SOIL
SOIL
53
45
Figure 2 Benched Excavation
The following table describes the soil types and minimum acceptable slope
requirements for excavations.
Note: Soil type must be determined by visual and manual tests; otherwise, assume
Type C soil with 1 ½ to 1 slopes.
Soil Type
Description
Maximum Slope
(Horizontal to
Vertical)
Solid rock
N/A
Vertical (90º)
A
Strong soils, compressive strength greater
¾ to 1 (53º)
than 144kPa, clay or clay soils, hardpan,
caliche.
B
Medium soils, strength > 48kPa, but
1 to 1 (45º)
<144kPa angular gravels, silty soils, Type A
soil that has been disturbed, subjected to
vibration or is fissured.
C
Weak soils, strength < or = 48kPa gravel,
1 ½ to 1 (34º)
sand, wet (seeping or submerged) soil.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 17 of 32
Planning for Water Accumulation
Works shall be suspended / re-scheduled during periods of severe/inclement weather.
A portable diesel driven dewatering pump with a suitable length of hose shall be in
attendance to drain the excavation if required.
When someone will be working in an excavation where water may accumulate,
consideration should be given to:
 Special support or shield systems
 Water removal equipment, and
 Emergency rescue procedures
Risk Assessment, Permit to Work and Supplementary Certificates
All Excavation Work
All works shall be:
 Preceded by a Risk Assessment
 Carried out under a Permit to Work, supported where necessary by:
o Isolation Confirmation Certificate, if applicable
o Clearance for Excavation Certificate
o An application to perform lifting operations/Clearance to Move Heavy
Equipment Certificate, if applicable
o Confined Space Entry Certificate, if excavation defined as confined space
 Implemented by competent and suitably qualified personnel under control of a
Site Supervisor or his appointed nominee
Permit Requirements
Prior to permit issue, the following must be ascertained:
 All Isolation Confirmation Certificates
(ICC's) for the pipeline have been
checked and validated, if applicable.
 The landowner has granted right of access.
 The Task Risk Assessment has been carried out (in particular, all power, pilot or
tracer cables that are within the excavation zone, overhead and below ground,
must be located and identified).
 The Task Work-pack, if applicable, are approved and onsite
In addition, the procedures listed in 1.9 SSOW Specific Cross References should be
consulted wherever there is a potential for:
 Possible energy release
 The presence of hydrogen sulphide or hydrocarbon gas
 An oxygen deficient environment
 The presence of carbon monoxide or other chemical substances
Environmental Impact Assessment
For new excavations in areas not previously excavated or areas containing refurbished
sections of the old GIOC pipeline, before any excavation
(mechanical or non-
mechanical) may begin, an Environmental Impact Assessment must be conducted to
establish whether or not the area of excavation is of ecological or archaeological
importance. An Environmental Impact Assessment Report / Letter (based on the
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 18 of 32
findings of the assessment) shall be sent to the State Committee of Ecology (SCE) for
approval. Only when this report / letter has been approved can excavation commence,
and even then, only in accordance with any requirements specified by the SCE.
Note: Protection of Historical and Cultural Monuments shall be implemented in
accordance with the EMS Manual and Procedure No. EP - 003
Site Supervisor - Assessment Responsibilities
The Site Manager / Site Controller shall review archaeological maps, ensure that the
Environmental Adviser is notified of any scheduled ground disturbance (inside and
outside the right-of-way) and shall ensure all relevant personnel are made aware of the
resulting Environmental Assessment.
Environmental Adviser - Assessment Responsibilities
Upon notification of the intended excavation, the Environmental Adviser shall:
 Provide the Site Supervisor with GIS information regarding natural and
archaeological features on the site
 Provide the Site Supervisor with GPS coordinates and photographs of any
important features
 Conduct a presentation identifying relevant natural and archaeological features
on the site. Attendees for the presentation shall include the Area Authority /
Performing Authority / Supervisor and machinery / excavator operators
9
EXCAVATION PROCEDURES
Note: No excavation shall be performed:
Without a BP representative being on site as far as is reasonably practicable
Until adequate communications with management and/or the emergency
response team are assured (the communications protocol to be adopted shall
be included in the Emergency Response Bridging Document) and/or in the
relevant operations procedures).
Note: No mechanical excavation shall take place closer than1m to any existing live
pipelines, cables, services and services. Use of mechanical excavation to within
1m is subject to said pipelines, cables or services being identified, located and
suitably protected.
Excavation Inspections
Where personnel are required to work in excavations of 1.2m or deeper a safety
inspection by a competent person must be carried out on each shift as follows:
 Before work is started
 After severe weather conditions or seismic activity
 After other occurrences which may increase the hazard of cave-ins
All high-risk excavations as defined by the Risk Assessment must be attended by a
geo-technical engineer/person trained in soil analysis.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 19 of 32
Toolbox Talks
A toolbox talk shall be carried out prior to works commencing with all parties involved in
the works. Talks shall be carried out during the works when the initial shift handover
takes place and when new works come on site.
Note: Toolbox talks shall be recorded.
Non-Mechanical Excavation
Once the position of the pipeline has been found, mechanical excavation may proceed
down to 500mm from the top of the pipe, leaving the remainder to be removed by hand.
This also applies to each side of the pipe except that the last 1000mm is to be removed
by hand. Machine excavation down to a depth of 500mm to top of pipe is only allowed if
combined with hand excavation as follows:
 Hand excavate a slit trench across the intended excavation up to a depth of
300mm
 Probe the hand excavated area to confirm the pipeline is at 500mm or greater
depth
 Machine excavate the remaining area to a depth not exceeding the depth of the
hand excavation
 Hand excavate a slit trench as above, probe and the if pipe cover below depth
of hand excavation is greater than
500mm again machine excavate the
remaining area to a depth not exceeding the depth of the hand excavation
 Repeat the above until a cover of 500mm over the pipeline remains. This shall
then be removed by hand excavation only
Note: An entry certificate will be required for work in an excavation that is deeper
than 1.2m. (See section 4 Trenches and Excavations)
Note: Excavator buckets shall not be fitted with teeth during excavations in the
vicinity of pipelines or any other service.
Soil below the pipeline shall be removed by hand to the side of the excavations where it
can be mechanically removed.
If the pipeline at any time is exposed by excavation, it shall be properly supported and
protected against damage to the satisfaction of the Area Authority or BP representative.
On completion, permanent support shall, if necessary, be constructed to avoid future
settlement.
Temporary supports shall be installed under exposed services, where required and the
Contractor shall submit a sketch of proposed support for approval prior to excavating.
To avoid damage during work, any exposed part of the pipeline shall be protected by
cladding (for example, timber) as directed by the Area Authority/BP representative and
any damage to the protective wrap/coating of the pipeline, whether existing or caused
by excavation work, etc., shall be brought to his notice.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 20 of 32
Mechanical Excavation
Before machine excavation begins:
Pipelines, should be depressurised as far as is reasonably practicable, and hand
digging should be completed around pipelines, utilities, and cathodic protection system
components
Note: Use caution when excavating around live lines and / or lines that may be
severely corroded.
Note: Excavator buckets shall not be fitted with teeth during excavations in the
vicinity of pipelines or any other service.
Operating restrictions
The following are operating restrictions for excavating equipment:
 Tracked vehicles should be used in preference to wheeled equipment on the
side of the excavation to minimise soil compaction.
 Equipment must be operated within its rated capacity.
 Personnel must stay clear of excavating equipment while in operation.
 Examples of unsafe areas include: under or beside the bucket of a backhoe,
near hydraulic rams of a bulldozer, etc.
 Roll Over Protective Structure (ROPS) is required by PUWER 98 to be fitted on
any mobile equipment as far as is reasonably practicable.
Decision whether or not ROPS is required, is based on pre-job Risk Assessment and
exemptions from this rule are as follows:
 The ROPS would increase the overall risk to safety
 It is not reasonably practicable to operate the mobile work equipment with such
a device fitted
 If mobile equipment was purchased for use in the business before 5 December
1998
 A seat belt must be installed on equipment manufactured with a ROPS.
 Do not use equipment if the ROPS has been removed
Note: “Pure” ditching machines (those without blades or backhoe attachments) are
excluded from ROPS requirements.
Operators
Equipment operators must:
 Be trained in the use of the equipment
 Be properly seated when operating equipment controls
 Wear seat belts if the equipment is in operation and furnished from the
manufacturer with a Roll Over Protective Structure (ROPS)
Note: Seat belts should not be worn if the equipment is not fitted with a ROPS.
 Use care at all times to maintain equipment stability
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 21 of 32
 Always drive at safe speeds for the conditions encountered (for example, on
rough ground, slopes, crossing ditches, turning, etc)
 Always use steps and handles provided when mounting or dismounting
equipment
Equipment operators must not:
 Start the engine unless seated in the driver‟s seat
 Allow other personnel to ride on the equipment unless it is designated for more
than one occupant
 Get off the equipment while it is in motion, except in an emergency
Parking and Moving Equipment
The table below describes the operator requirements for specific excavating equipment.
Activity
Precautions
Parking excavating
 Park the unit on level ground if possible and lower the boom to
equipment
a relaxed position
Parking a backhoe on
 Lower the bucket so that the cutting blade contacts the
an incline
ground, then apply the parking brake and securely chock the
wheels.
Loading equipment
 Use crawl gear.
on a trailer
Storing or
 Use trainer ramps
transporting a ditcher
 Lower the boom
on a trailer
 Place the transmission in gear and fasten the ditcher securely
to the trailer
Using Backhoes
The following precautions apply whenever a backhoe is used during excavation:
 Personnel must not be in an excavation within the full reach of the backhoe
while it is excavating
 The boom must be raised and centred before engaging or disengaging the
transport.
 Avoid using the full reach or swinging a loaded bucket to the downhill side
Note: This will prevent upsets when operating on a slope.
 Attach towlines at a point below the rear axle
Note: Attaching above this level increases the risk of rollover.
Waste Management
Waste management on the excavation site shall be implemented according to the EMS
Manual and Procedure No. EP 80
Power Lines
Before operating equipment, all utility lines and overhead power lines must be located
and identified.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 22 of 32
Note: See 4.5 The Use of Mechanical Equipment Near Overhead Power Lines.
Hydrocarbon Pipelines
Mechanized excavation in close proximity to hydrocarbon lines poses an increased risk
of fire/explosion in the event of hydrocarbon release.
Note: Mechanical excavation shall not occur within 15.2m of an open flame, such as
a flare, an equipment burner without a flame arrester, cutting torch, etc.
Excavated Materials
Excavated material shall be placed at least 1m away from the edge of the excavation
and shall be stockpiled within the Right of Way area.
Topsoil
The stripped topsoil shall be stored for re-use away from the side of the excavation and
separate from the sub-soil.
The height of stored soils should be limited to 2m in order to reduce erosion problems
and prevent the development of anaerobic conditions within the stockpile. Weed growth
may need to be controlled by spraying with approved herbicides.
Warning: Do not pile topsoil under overhead power lines.
Subsoil
The stripped sub-soil shall be stored for re-use away from the side of the excavation
and separate from the topsoil.
Warning: Do not pile subsoil under overhead power lines.
Contaminated Soil
Note: Any excavation where contaminated ground is encountered shall have a
Hazard Risk Assessment completed. This Risk Assessment shall take into
consideration the duration that the excavation is expected to be open.
All excavations in contaminated ground conditions will be bounded to prevent the
ingress of surface water and shall be monitored on a regular basis for any change in
the level of the ground water or liquid level (particularly in the event of heavy rainfall).
Monitoring shall be on a 24hour basis in high-risk areas as determined by the Hazard
Risk Assessment.
Excavated contaminated soil shall be placed into a bunded area lined with heavy - duty
plastic sheeting to avoid seepage and shall be segregated from uncontaminated soil.
All excavated soil grossly contaminated with hydrocarbons and not re-used shall be
transported to a designated treatment facility approved by BP.
Where work in an area of contaminated ground cannot proceed in accordance with the
schedule, consideration will be given to back-filling the excavation
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 23 of 32
10
BACKFILLING PROCEDURE
Preparation
Notice, Approval and Supervision
Adequate notice shall be given to BP of the intention to backfill within the wayleave of
the pipeline.
In addition, backfilling of the trench shall not commence without the approval of the Site
Team Leader or the Area Authority/BP representative and shall only proceed in the
presence of the Area Authority/BP representative. The Area Authority/BP
representative shall advise on the specification of the backfill and the method of
consolidation around the pipeline.
Backfill Materials
No perishable materials such as vegetable growth, timber bush, etc are to be filled into
the trench.
Special care must be taken to prevent any stones, cinders, slag, debris of made up
ground or other harmful matter such as will be likely to set up corrosion from coming
into contact with the pipe.
Stony or gravely trenches are frequently a problem at river crossings and old riverbeds.
If rock, stones or gravel are present in the bottom of the trench then fine material is first
placed below the pipeline to ensure that only fine material surrounds the pipe.
Backfilling Guidelines
Backfilling operations in well-compacted layers should be carried out in such a manner
as to prevent heavy loads passing over the pipeline. Allowance should be made for
sufficient overfilling or mounding of the filled trench to compensate for subsequent
settlement. The following guidelines apply to backfilling operations:
Note: If a compactor is used, area gas monitoring shall be conducted throughout
the compacting activity
1. All water shall be removed from the trench before backfilling commences.
2. The bottom of the trench shall be padded as far as is reasonably practicable
with a minimum of 150mm of suitable granular material, i.e., building sand, to be
approved by the Area Authority/BP representative, free from hard objects which
might damage the pipe coating. This padding shall be compacted in layers of
150mm.
Note: The removal of any fine materials from riverbanks and / or riverbeds is strictly
prohibited.
3. Before backfilling, it must be checked that the pipe is evenly bedded on the
trench padding throughout its length.
4. Imported granular or selected excavated materials, i.e., building sand, shall then
be rammed at sides (150mm) and around the pipe until 300mm of cover over
the top of the pipe has been hand rammed.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 24 of 32
5. The original topsoil is to be replaced in the top of the trench with the same
depth as that on the working width.
6. All surplus excavated materials, rock, welding rods, waste and all unwanted
material shall be removed from the site of the works and the site left in a tidy
condition.
7. The backfill can be compacted if deemed necessary using a diesel driven plate
compacter. Care must be taken not to damage pipelines
8. On completion of backfilling all fields, verges, tracks, paths, garage drives and
access roads should be permanently reinstated to a condition equivalent to that
before the commencement of the work.
9. Any damage to field drains etc must be repaired and local farmer/land owner be
invited to inspect the repair(s) prior to backfill.
11
SITE REINSTATEMENT
Reinstatement of the site shall be implemented in accordance with the EMS Manual
and Procedure No. EP-100.
Drainage
Any field drains that have been damaged should be repaired or replaced. Drainage
patterns should be returned to their original state by using the same permeable
materials that were excavated.
Topsoil reinstatement should take place in dry conditions to prevent permeability and
drainage characteristics from being altered through compaction.
Topography
In addition, excavated soils should be redistributed across the entire right-of-way to
restore the natural topography. Any areas outside the trench area that have been
compacted by moving vehicles should be loosened using deep-tine cultivators.
The responsible department in order to ensure that restoration is satisfactory or to
ensure that monitoring should continue should carry out a final inspection.
12
DOCUMENTATION
The following documentation and information must be maintained and readily available:
 Risk Assessments
 Permits and Supplementary Certificates
 Equipment inspection reports
 Operator certificates
 Notices to 3rd parties
 Notices received
 Excavation Report
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 25 of 32
Appendix A: Emergency Procedure in the Event of Pipeline Damage
SAFETY PROCEDURE IN CASE OF DAMAGE TO A PIPELINE
Should the pipeline be damaged, the following steps shall be taken:
a)
Shutdown all running plant and ensure that all other sources of ignition
are removed.
b)
Remove all personnel from immediate vicinity.
c)
Prevent the approach of traffic or any unauthorized persons.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 26 of 32
Appendix B: Excavation Inspection Checklist
If the answer to any of the questions below is „NO‟ then permission must be granted by
the Site Manager / Site Controller.
Checklist
YES
NO
Supervisor is aware of the Golden Rule for Ground
Disturbance and definition of Confined Space
Risk Assessment conducted
PTW or Excavation Certificates are in place
Toolbox meeting has been conducted
Workgroup is aware of the hazards associated with the task
Excavation has been shored, sloped or benched
Machinery has been inspected
Banks man is on site and easily identifiable
Correct PPE is being worn by all workers
There is no evidence of diesel or oil spills
Underground services have been identified
Overhead power lines have been identified
Spoil heaps are kept back from the sides of the excavation by
at least 1m
Drip trays are in place under stationary machinery
Excavation approved by the Site Manager / Site Controller:
Signed……………………….
Date……………………….
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 27 of 32
Appendix C: Procedure Summary
¾ No risk of engulfment from Ingress of solids or liquids
¾ That all work activities that involve open excavations in the
¾ No risk from excessive heat
earth‟s surface are subject to risk assessment and the
¾ Safe means of access and egress.
Project Permit to Work System
EXCAVATIONS
¾ Excavations benched or shored to reduce risk of collapse (See
¾ That all work activities that involve open excavations in the
- AZSPU-HSSE-DOC-00055-2 - Procedure for Excavation.)
earth‟s surface are closely monitored to ensure compliance
BP Golden Rule
¾ Continuous monitoring of O2, LEL and other toxic gasses are
with this procedure
Work that involves a man-made cut, cavity, trench or depression
carried out inside the excavation
¾ That suitably qualified and experienced personnel are
in the earth‟s surface formed by earth removal cannot proceed
appointed to control and perform all work activities that
unless:
The mandatory Level 2 risk assessment for the above mentioned
involve open excavations in the earth‟s surface
¾ A hazard assessment of the work-site is completed by a
criteria, must ensure a practical application of mitigations based on
competent person(s)
the hazards that are ‟„actually” present, then, providing that the
Area Authorities are responsible for:
¾ All underground hazards e.g. pipelines, electric cables, etc,
above criteria is satisfied, the excavation may be classified as “not a
¾ Compliance with this Procedure for Excavations
have been identified, located and if necessary isolated
confined space”.
¾ The safety of personnel and the safe execution of
Where people are to enter an excavation:
excavation activities within their area
¾ A confined space entry certificate must be issued if the
Definition of Confined Space
¾ Ensuring daily equipment checks are completed on
space meets the confined space definition
A “Confined space” is an enclosed or partially enclosed space
equipment within their assigned area and that equipment is
¾ Ground movement must be controlled and collapse
which:
maintained in good working order
prevented by systematically shoring, sloping, benching, etc.
¾ Is large enough for any person to bodily enter it and perform
¾ Provision of instruction to personnel as required
as appropriate
assigned work
¾ Monitoring work activities to ensure compliance with the
¾ Ground and environmental conditions must be continuously
¾ Has limited or restricted means of entry or exit
requirements of safe systems of work
monitored for change
¾ Has unfavourable natural ventilation
¾ Is not designed for continuous occupancy
Banks Men
Trenches and Excavations
For all excavations involving heavy plant and machinery a
All excavations and trenches deeper than
1.2 metres in
All Excavation Work
trained and qualified Banks man will be on site at all times.
“hazardous areas” should be considered as confined spaces.
All excavation works shall be:
¾ Preceded by a Risk Assessment. This could be based on a
Banks men are responsible for:
In contrast, “non hazardous areas” where there are open areas of
generic RA, but shall be reviewed or updated if conditions are
¾ Preventing access to excavation areas under their control
low ground, tank bunds, and other areas where natural ventilation
changed by the responsible person prior to work commencing
by unauthorised personnel. This may include the setting up
will prevent slow accumulation of heavy gases, are not included in
¾ Carried out under a PTW, supported where necessary by;
of barriers.
this definition.
o Isolation Confirmation Certificate
¾ Providing safe guidance and assisting in the safe operation
o Clearance for Excavation Certificate
of machinery under their direction
Note: In both “hazardous” and “non hazardous” areas, any work
o An application to perform lifting operations / Clearance to
task performed will require a Permit to Work and a Level 2 Risk
Move Heavy Equipment Certificate, if applicable
Machine Operators
Assessment conducted.
o Confined Space Entry Certificate, if excavation defined as
Only experienced and competent operators are to operate any
confined space
plant or machinery.
In “non hazardous” areas where excavations and trenches are
o Implemented by competent and suitably qualified personnel
deeper than 1.2 metres where there are no significant hazards
under the control of the Site Supervisor
Machinery operators are responsible for:
identified prior to entry, cases such as these must follow the
¾ Ensuring that daily inspections are performed on their
following criteria before determining the requirement for a
Responsibilities
machinery or equipment prior to the commencement of
“Confined Space Entry permit”:
Site Manager‟s
/ Site Controller‟s shall be responsible and
excavation works
¾ No risk of atmospeheric hazards either from surrounding
accountable for the application of this procedure in his area of
¾ The safe and responsible operation of machinery and
area or from the task being performed
responsibility, He shall ensure:
equipment under their control when conducting excavation
¾ Excavation is outwith areas identified as being hazardous
¾ That this procedure is strictly adhered to for all work activities
work
¾ The excavation does not require any form of isolation prior to
that involve open excavations in the earth‟s surface
entry
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 28 of 32
Refuelling
Personnel Access
EXCAVATIONS (cont)
A method statement covering spill containment and management of
Whenever personnel will be in an excavation, ramps, stairways
personnel injury risks shall be prepared for all refuelling operations.
or ladders should be kept within
7.6m of workers for all
In all cases, equipment shall be shut down prior to being refuelled.
excavations over 1.2m deep.
¾ Immediate reporting to their supervisor if they believe the
machinery or equipment they are using is in a dangerous or
Underground Services
Shoring and Benching
unsafe condition
No mechanical excavation shall take place closer than 1m to any
Except in stable rock, all excavations must be shored, shielded
¾ Ensuring that the machinery or equipment they use has all
existing live pipelines, cables, services that belong to other parties.
(e.g. Trench box), benched or sloped if:
the safety devices and guards in place and that all guards
¾ The excavation is 1.2m or more in depth
are properly fitted
Use of mechanical excavation to within
1m is subject to said
¾ A worker‟s head is below the level of the excavation when
¾ Ensuring daily equipment checks are completed on
pipelines, cables or services being identified, located and suitably
bending or stooping to perform the work task, as far as is
equipment within their area and that equipment is maintained
protected.
reasonably practicable and/or required by the Risk
in good working order
Assessment
Pipeline Crossing Points
Toolbox Talks
Construction traffic and other plant shall cross the pipeline only by:
Risk Assessment, PTW & Supplementary Certificates
A toolbox talk shall be carried out prior to works commencing with
¾ Public roads
All Excavation Work
all parties involved in the works. Additional talks must be held if
¾ Previously agreed and clearly marked crossing lanes or bridges
All works shall be:
ground conditions change.
¾ Preceded by a Risk Assessment - could be based on
All crossing lanes shall be fenced on both sides over a width to be
generic RA but should be reviewed or updated if conditions
Guards and Barricades
specified and agreed by the Pipeline Patrolman as far as is
changed by responsible persons prior to work commencing.
Open excavations deeper than 1.2m must be attended by a
reasonably practicable as dictated by local conditions and acts of
¾ Carried out under a Permit to Work, supported where
watchman or protected by a rigid barricade and marked with a
vandalism. These fences shall be returned along the edge of the
necessary by:
warning sign.
wayleave strip for a distance of 6 m away from the crossing.
o Isolation Confirmation Certificate, if applicable
o Clearance for Excavation Certificate
NOTE: In areas close to overhead power lines goal post must be
Where it is necessary at crossing points to install a temporary bridge
o An application to perform lifting operations/Clearance to
erected.
to protect the pipeline, the bridge will consist of the laying of steel
Move Heavy Equipment Certificate, if applicable
plates of adequate thickness with hard core laid in, or an approved
o Confined Space Entry Certificate, if excavation defined
Overhead Power Lines
sleeper raft, or a combination of these methods.
as confined space
All personnel working near power lines with a machine or
o Permit to Work Certificate
mechanical equipment shall be made aware of:
Any temporary crossing or bridge must be clearly marked by
¾ Implemented by competent and suitably qualified
¾ The dangers associated with power lines
appropriate notices and flags, and additionally with lights at dusk, at
personnel under control of a Site Supervisor or his
¾ The precautions they should take to deal with those dangers
night or in foggy conditions.
appointed nominee
¾ What to do if they make contact with a power line
Access and Security
Permit Requirements
Machinery & Equipment
Open excavations near public areas must be:
Prior to permit issue, the following must be ascertained:
Adjustments and Repairs:
¾ Attended by a watchman
¾ All Isolation Confirmation Certificates
(ICC's) for the
¾ Do not lubricate or make mechanical adjustments to the unit
¾ Protected by a barricade and marked with a warning sign
pipeline have been checked and validated, if applicable.
while the unit is in motion or the engine is running
¾ The landowner has granted right of access.
¾ Do not repair or tighten hydraulic hoses or fittings when the:
Erection of stock fencing, gates and bunting safety notices, etc.,
¾ The Task Risk Assessment has been carried out
(in
o system is under pressure
shall be undertaken over access ways and worksites.
particular, all power, pilot or tracer cables that are within
o engine is running
the excavation zone, overhead and below ground, must be
o equipment hydraulic cylinders are under a load
When the pipeline is exposed outside normal working hours a
located and identified).
security presence will be required over and above that of the normal
¾ The Task Work-pack, if applicable, are approved and
construction personnel.
onsite
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Excavations
Page 29 of 32
EXCAVATIONS (cont)
Machinery Workers could get caught in rotating parts during
Excavation An unprotected excavation possesses a fall hazard
unscheduled maintenance. Machinery must be turned off and
to workers and third parties.
isolated during all maintenance. Movement of machinery during
In addition, the procedures listed in 1.9 SSOW Specific Cross
excavation could result in injury due to being struck by the bucket or
NOTE: Excavations are to be barriered off prior
to
References should be consulted wherever there is a potential for:
counterweight.
commencement of work and removed upon completion.
¾ Possible energy release
¾ The presence of hydrogen sulphide or hydrocarbon gas
NOTE: Banks men are to direct the operator and keep personnel
¾ An oxygen deficient environment
clear of operating machinery.
¾ The presence of carbon dioxide or other chemical
Excavation Inspection Checklist
substances
Overhead Power Lines Potential for electrocution if excavator or
tipping trailer comes into contact with overhead lines.
Checklist
YES
NO
Environmental Impact Assessment
Supervisor is aware of the Golden Rule for
For new excavations in areas not previously excavated or areas
NOTE: Goalposts must be erected at either side of the power lines
Ground Disturbance and definition of Confined
containing refurbished sections of the old GIOC pipeline, before
that warn operators of height restrictions. No machinery is to operate
Space
any excavation (mechanical or non-mechanical) may begin, an
directly under live power lines.
Risk Assessment conducted
Environmental Impact Assessment must be conducted to
establish whether or not the area of excavation is of ecological or
PTW or Excavation Certificates are in place
NOTE: Goalposts must be erected at either side of the power lines
archaeological importance. An Environmental Impact Assessment
Toolbox meeting has been conducted
that warn operators of height restrictions. No machinery is to operate
Report / Letter (based on the findings of the assessment) shall be
Workgroup is aware of the hazards associated
directly under live power lines.
sent to the State Committee of Ecology (SCE) for approval. Only
with the task
when this report
/ letter has been approved can excavation
Excavation has been shored, sloped or
Underground Services Potential for fire, explosion or
commence, and even then, only in accordance with any
benched
environmental damage if underground pipelines are ruptured.
requirements specified by the SCE.
Machinery has been inspected
Potential electrocution if contact is made with underground cables.
Banks man is on site and easily identifiable
Note: Protection of Historical and Culteral Monuments shall be
Correct PPE is being worn by all workers
NOTE: Underground services plot plan to be referenced prior to
implemented in accordance with the EMS Manual and Procedure
There is no evidence of diesel or oil spills
excavation. Excavation certificate is to be in place prior to
No: EP-03.
Underground services have been identified
commencement of excavation. Hand digging only within 1m of any
underground service unless a banks man is present to guide the
Overhead power lines have been identified
Personal Protective Equipment (PPE)
operator.
Spoil heaps are kept back from the sides of the
During all activities on site all personnel shall wear minimum PPE
excavation by at least 1m
(helmet, safety boots/shoes, flame retardant coveralls, and eye
Wet Weather Can potentially degrade the integrity of the sides of
Drip trays are in place under stationary
protection).
excavations. Increasing the potential for cave-in‟s or collapse.
machinery
Excavation approved by the SM / SC:
Personnel involved in specific work activities shall wear additional
NOTE: Sides of excavations to be shored, sloped or benched.
PPE to suit the requirements of the work as agreed/detailed at the
Inspections are to be conducted to assure integrity of excavations
Name: …………………...
pre-work toolbox talk.
after periods of rain and prior to each shift.
Sign: ……………………..
Date: ………………….
Hazards Associated with Ground Disturbance
Diesel Has the potential for ignition occurring during refuelling
Vibration from machinery, equipment or vehicles could cause
operations and the potential for environmental damage if diesel is
cave-in or collapse of the excavation. Workers could be engulfed
spilt during refuelling.
in the excavation.
NOTE: Equipment and machinery must be turned off during
NOTE: No plant, vehicles or equipment should be set-up any
refuelling. Refueller must be trained and follow refuelling method
closer than 1m from the edge of an excavation.
statement. Spill
/ drip trays are to be in place under stationary
machinery.
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00050-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT

 

 

 

 

 

 

 

Content      ..     30      31      32      33     ..