Military reference books and manuals (2009-2023, Volume 5) - page 31

 

  Index      Manuals     Military reference books and manuals (2009-2023, Volume 5)

 

Search            copyright infringement  

 

   

 

   

 

Content      ..     29      30      31      32     ..

 

 

 

Military reference books and manuals (2009-2023, Volume 5) - page 31

 

 

Control Of Over Control Of Over-rides, Inhibits
Page 10 of 18
And Alarm Disables
9
Alarm Disabling
The key tool available for the management of alarms in real time is the ability to
disable (and subsequently re-Enable) individual alarms to meet short-term needs
(for example the alarm is ‘bouncing’ due to unusual operating conditions).
Application of Alarm Disables
Application of alarm disables will be the responsibility of the PA.The PA will also be
responsible for updating of the Disables register, and shall make reference to
reasons why the Alarm disable has been applied. The RP shall review the register
and sign the review log at every shift handover.
Removal of Alarm Disables
Alarm Disables should be removed from the systems as quickly as possible, when
the reason for application has been resolved
Audit of Alarm Disables
Audit of alarm disables, shall be carried out on a weekly basis. A suitably qualified
and competent person, designated by the OIM/Site Controller, shall conduct this
audit. In addition to this there will be an Annual review of the performance of the
Alarm System, and identification of agreed improvements to be worked.
Control Tier:
<<2>>
Revision Date: <<28 December 2004>>
Document Number: << AZSPU-HSSE-DOC-00015-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Control Of Over Control Of Over-rides, Inhibits
Page 11 of 18
And Alarm Disables
10
Registers and Review Log
A register of over-rides and Inhibits and a Register of Alarm Disables must be held in
the Control room, at each site location. The Registers are mandatory and shall be
used at all times.
The Over-rides and Inhibits Register will contain the following details for each Over-
ride or Inhibit applied.
ƒ Tag Number
ƒ Over-ride Category (A, B or C as per procedure).
ƒ Reason For Override
ƒ Date Applied
ƒ Time Applied
ƒ Applied By (PA)
ƒ Approved By (RP)
ƒ Risk Assessment Ref
ƒ Isolation Confirmation Certificate no If applicable
ƒ Permit NO
ƒ Date Removed
ƒ Time Removed
ƒ Removed By
ƒ Action Required, for any reference to Maximo Job or MOC etc where remedial
action is being worked towards removal of long term overrides.
The Alarm Disables Register will contain the following details for each Alarm Disabled
ƒ Tag Number
ƒ Reason For Disablement
ƒ Date Applied
ƒ Time Applied
ƒ Applied By (PA)
ƒ Date Removed
ƒ Time Removed
ƒ Removed By
ƒ Action Required, for any reference to Maximo Job or MOC etc where remedial
action is being worked towards removal of long term Alarm Disables
Over-rides Inhibits and Alarms Disables Review Log
A review log with the following fields shall be held with the above registers:
¾ Date
¾ Shift
¾ Time
¾ RP signature
Comments/Remarks
Control Tier:
<<2>>
Revision Date: <<28 December 2004>>
Document Number: << AZSPU-HSSE-DOC-00015-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Control Of Over Control Of Over-rides, Inhibits
Page 12 of 18
And Alarm Disables
Appendix A - Abbreviations and Definitions
ESD
Emergency Shutdown
ICC
Isolation Control Certificate
SSOW
Safe System Of Work
PA
Performing Authority
RP
Responsible Person
TA
Technical Authority
PTW
Permit to Work
OIM
Offshore Installation Manager
Control Tier:
<<2>>
Revision Date: <<28 December 2004>>
Document Number: << AZSPU-HSSE-DOC-00015-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Control Of Over Control Of Over-rides, Inhibits
Page 13 of 18
And Alarm Disables
Appendix B - Applicable to
This document applies to the following job functions:
OIM / Site Manager / Site Controller
Operations Engineer
Control Room Technicians
Area Authority
Maintenance Supervisors
Instrument Technicians
Electrical Technicians
Performing Authority
Responsible Person
Business Unit Leader
Document Controller
Technical Authority
Control Tier:
<<2>>
Revision Date: <<28 December 2004>>
Document Number: << AZSPU-HSSE-DOC-00015-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Control Of Over Control Of Over-rides, Inhibits
Page 14 of 18
And Alarm Disables
Appendix C - Over-Rides and Inhibits Register
OVER-RIDES AND INHIBITS REGISTER.
FACILITY _____________
SHEET NO__________
Tag No
Cat
Reason
RA
ICC no
Approved
Applied (PA)
Removed (PA)
MOC /
(A,B,C)
Ref
(RP)
Date
Time
By
Date
Time
By
Maximo
Ref
Control Tier:
<<2>>
Revision Date: <<28 December 2004>>
Document Number: << AZSPU-HSSE-DOC-00015-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Control Of Over Control Of Over-rides, Inhibits
Page 15 of 18
And Alarm Disables
Appendix D - Alarm Disables Register
ALARM DISABLES REGISTER. FACILITY _____________
SHEET NO__________
Tag No
Reason
Applied
Removed
MOC /
Date
Time
By
Date
Time
By
Maximo
Ref
Control Tier:
<<2>>
Revision Date: <<28 December 2004>>
Document Number: << AZSPU-HSSE-DOC-00015-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Control Of Over Control Of Over-rides, Inhibits
Page 16 of 18
And Alarm Disables
Appendix E - Over-Rides and Inhibits and Alarm Disables Review Log
OVER-RIDES INHIBITS AND ALARM DISABLES REVIEW LOG. FACILITY _____________
SHEET NO__________
Date
Shift
Time
RP sign
Comments / Remarks
Control Tier:
<<2>>
Revision Date: <<28 December 2004>>
Document Number: << AZSPU-HSSE-DOC-00015-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Control Of Over Control Of Over-rides, Inhibits
Page 17 of 18
And Alarm Disables
Appendix F - Audit Checklist
OVER-RIDES, INHIBITS, AND ALARM DISABLES AUDIT
CHECKLIST
FACILITY
DATE
Audit Purpose
To review the Management and control of safety systems over-rides, inhibits, and
alarm disables in compliance with Procedure UNIF-HSE-PRO-155.
COMMENTS
1 Verify that the record of Over-rides
,inhibits, and alarm disables is up to date
with the over-rides and inhibits applied,
and in compliance with requirements of
Procedure
2. Verify that appropriate risk
assessments have been carried out and are
available in compliance with procedure
section 4
3. Verify that for any long-term over-
rides, demonstrable measures are in place
either by means of Repairs or MOC, and
being managed to resolve the reason for
disablement.
4 Verify that appropriate Risk
assessments are up to date and mitigation
measures in place where appropriate for
any long term over-rides as identified in
step 3
5.Review reasons for use of over-rides ,
inhibits, and alarm disables, identify any
repetitive applications where further
investigations for improvements may be
required.
6. Verify that registers are reviewed and
review logs are updated accordingly.
COMMENTS / ACTIONS
AUDIT COMPLETED BY
NAME
SIGNATURE
Revision/Review Log
Control Tier:
<<2>>
Revision Date: <<28 December 2004>>
Document Number: << AZSPU-HSSE-DOC-00015-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Control Of Over Control Of Over-rides, Inhibits
Page 18 of 18
And Alarm Disables
Revision Date
Authority
Custodian
Revision Details
<<28 December
<< Alan McNulty
<< Esmira
<< Initial Issue>>
04>>
>>
Akhundova >>
Control Tier:
<<2>>
Revision Date: <<28 December 2004>>
Document Number: << AZSPU-HSSE-DOC-00015-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 1 of 15
Procedure for Asbestos Risk Management
AZSPU-HSSE-DOC-00016-2
This number supersedes UNIF-HSE-PRO-
207-C1
Authority:
<<AzSPU Safety Manager
Custodian:
<< AzSPU Safety Team Leader >>
>>
Scope:
<<AzSPU >>
Document
Administrator:
<< Document Asset Technician Name >>
Issue Date:
<< 30 Sept 2005>>
Issuing Dept:
<< CHSSE >>
Revision Date:
<<30 Sept 2005>>
Control Tier:
<<2>>
Next Review
<<20 Sept 2006 >>
Date:
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 2 of 15
TABLE OF CONTENTS
1
INTRODUCTION
3
1.1 Document Purpose
3
1.2 Document Scope
3
1.3 References and Related Procedures
3
2
ROLES AND RESPONSIBILITIES
4
2.1 Site Manager / Offshore Installation Manager
4
2.2 Area Authority
4
2.3 HSE Adviser
4
2.4 Occupation Health
4
2.5 All Personnel
5
2.6 Consultants / Specialist Contractors
5
3
ASBESTOS HYGIENE STANDARDS AND AIR MONITORING
5
3.1 Occupational Exposure Limits
5
3.2 Clearance Standard
5
3.3 Air Monitoring
6
4
MANAGING ASBESTOS
6
4.1 Locating and Monitoring Existing Asbestos
6
4.2 Asbestos Register
6
4.3 Assessing the Condition of Asbestos
7
4.4 Identifying Asbestos and Asbestos Types
7
5
WORKING WITH ASBESTOS
7
5.1 Risk Assessment and Permit to Work
7
5.2 Asbestos Hazardous Area
8
6
STORAGE AND DISPOSAL OF ASBESTOS WASTE
9
7
HEALTH SURVEILLANCE
9
8
RECORD KEEPING
10
APPENDIX A - DEFINITIONS
11
APPENDIX B - AIR MONITORING METHODS
12
APPENDIX D - ASBESTOS RELATED DISEASES
14
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 3 of 15
1
Introduction
Document Purpose
Note: It is BP policy in Azerbaijan and Georgia that all work with asbestos,
including air monitoring, asbestos identification, asbestos removal and
asbestos disposal, shall only be undertaken by specialist contractors or
consultants.
This Safe System of Work provides the necessary information for ensuring that
asbestos is dealt with correctly and consistently across all sites and that personnel and
the environment are adequately protected from asbestos related hazards.
The contents of this safe System of Work provide information on what to do when
asbestos is discovered and the subsequent safety requirements of the contractors and
specialists called in to deal with it.
The contents of this document are not intended to provide detailed procedures for
working with asbestos. Such procedures will be prepared and owned by the specialist
contractors and consultants employed for the task.
Document Scope
The contents of this Safe system of Work are applicable to all BP owned and managed
sites in Azerbaijan and Georgia. This document does not replace the procedures
prepared and adopted by specialist contractors. Neither does it supercede any national
and local regulatory requirements.
References and Related Procedures
References
Further information is available in:
Occupational Hygiene Network Best Practice Document, ASBESTOS: Health and
Protection in its Use, Handling and Removal (Available from Occupational Health).
H&SE Booklet, Managing Asbestos in Workplace Buildings
(Available from
Occupational Health).
Related Procedures
This Safe System of Work should be used in conjunction with:
UNIF-HSE-PRO-103 Permit to Work
UNIF-HSE-PRO-105 Task Risk Assessment
UNIF-HSE-PRO-156 Personal Protective Equipment
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 4 of 15
2
Roles and Responsibilities
Site Manager / Offshore Installation Manager
The Site Manager / Offshore Installation Manager is responsible for:
ensuring compliance with this Safe System of Work throughout the site
/
installation
ensuring that only suitable and experienced contractors or specialists are
employed for all asbestos related activity
where necessary, establishing and maintaining an Asbestos Register for
recording the use and presence of all known asbestos-containing materials on
site
establishing and maintaining records of:
o asbestos monitoring and survey results
o inspection and maintenance of respiratory protection equipment
o the review of asbestos related Risk Assessments and precautions taken
o training records for all personnel working with or who may be expected
to work with or in the proximity of asbestos related work
ensuring that all personnel required to work with asbestos:
o are made aware of the hazards involved and the methods used to
mitigate those hazards
o are equipped with the necessary personal protective equipment.
Area Authority
Area Authorities are responsible within their area of authority for:
 ensuring compliance with this Safe System of Work
 facilitating Risk Assessments involving asbestos hazards
 maintaining an awareness of all known asbestos-containing materials and their
use and location
 ensuring that only suitably trained and briefed personnel are engaged in
activities involving asbestos.
Note: All personnel working with or near asbestos must be fully briefed on
the health hazards involved and the precautions necessary to
minimise or remove those hazards.
2.3
HSE Adviser
The HSE Adviser is responsible for providing advice and assistance on asbestos
related matters and where necessary liaising with the Occupational Health Department
and the contractor.
2.4
Occupation Health
The Occupational Health Department is responsible for:
 providing advice and assistance on health matters related to working with
asbestos
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 5 of 15
 facilitating formal health monitoring and screening of all personnel involved with
asbestos related activities
 providing advice and assistance in the setting-up of Asbestos Hazardous Areas,
and the atmospheric monitoring of those areas.
2.5
All Personnel
All personnel are responsible for:
 reporting any suspected asbestos or asbestos-containing material to their
immediate supervisor.
 the correct, conscientious and responsible use of all personal protective
equipment with which they are supplied, including respiratory equipment
 halting and reporting to their supervisor any work they consider to be unsafe.
2.6
Consultants / Specialist Contractors
The handling and removal of asbestos will usually be carried out by an independent
contracting company with the necessary specialist knowledge and experience.
Companies contracted by BP to work on asbestos related activities are responsible for
carrying out their work on BP sites and installations in accordance with the
requirements of local legislation.
In addition, contracting companies and their personnel shall be required to provide
evidence of their relevant expertise and knowledge, and their ability to work safely with
asbestos, whenever required by BP.
3
Asbestos Hygiene Standards and Air Monitoring
3.1
Occupational Exposure Limits
The occupational exposure limits included her shall be applied to all types of asbestos
in all locations where asbestos exposure is not otherwise subject to legislative control.
The following exposure limits apply to air samples taken from the breathing zone by
suitably qualified personnel.
Exposure Limit = 0.2 fibres/ml, 8-hour time weighted average
Action Level = 0.1 fibres/ml, 8-hour time weighted average
These limits do not represent ‘safe’ and ‘dangerous’ conditions as they cannot be
guaranteed to avoid all risks to health. Therefore, exposure should be reduced to at
least these limits and preferably as far below them as reasonably practicable.
In particular it should be noted that the interpretation of any atmospheric monitoring
results should only be undertaken by suitably qualified, trained, and experienced
personnel. The use of specialist contractors for this task is strongly recommended.
3.2
Clearance Standard
Where asbestos work has been carried out in an Asbestos Hazardous Area (see
Paragraph 5 Asbestos Hazardous Areas) the area shall not be returned to unrestricted
or normal use until the ambient fibre concentration no longer exceeds the Clearance
Standard:
Clearance Standard = 0.1 fibres/ml.
Note: The Clearance Standard should only be regarded as a transient indication of
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 6 of 15
cleanliness following completion of asbestos related activity.
3.3
Air Monitoring
Note: The collection and analysis of air samples shall only be carried out by
personnel who are properly trained and knowledgeable in air monitoring
techniques. The use of specialist contractors or consultants for these tasks
is strongly recommended.
Airborne fibre monitoring (see Appendix B) shall be carried out:
 during all work involving the removal of asbestos
 damaged or friable asbestos is present.
Air monitoring (personal sampling - see Appendix B) shall be carried out wherever
and whenever it is known or suspected that asbestos dust is likely to be generated.
The purpose of air monitoring is to:
 ensure compliance with asbestos hygiene standards
 check the effectiveness of control measures
 confirm the appropriate level of personnel protective equipment is in use.
4
Managing asbestos
In order to manage asbestos safely it is necessary to be aware of the:
 location of the asbestos
 form of the asbestos (lagging, ceiling tiles, partition board, etc)
 condition of the asbestos
 type of asbestos (blue, brown, or white).
Locating and Monitoring Existing Asbestos
If asbestos or asbestos-containing material is in good condition and unlikely to be
damaged, the safest and most pragmatic option is often to leave it in place. For
example, asbestos-containing building materials (floor tiles, felts, mastics, insulating
board, etc) may be present in buildings used but not owned by BP.
Asbestos-containing material that is left in place shall be recorded and regularly
monitored for any sign of deterioration.
Arrangements shall be made to alert personnel to the presence of asbestos, either by
clearly labelling the material or by briefing and informing all personnel who might work
on the material or in its vicinity.
Note: Even when all known asbestos has been removed or recorded, other hidden
asbestos may still be present.
4.2
Asbestos Register
Where asbestos is known to exist on-site, an Asbestos register should be established
and maintained in order to record the location and type of asbestos and to ensure that
the asbestos is regularly monitored for condition. The register should include instances
where materials that have been thought to asbestos containing materials but have
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 7 of 15
since been proved otherwise in order to prevent confusion. See also Appendix C
Asbestos Register Form.
4.3
Assessing the Condition of Asbestos
The condition of the asbestos or asbestos-containing material shall be assessed by a
suitably qualified and experienced person knowledgeable in the subject. In general a
risk of asbestos being released into the air shall be expected if:
 the material is being disturbed or if it is prone to accidental damage
 the surface of the material is damaged, frayed or scratched
 surface sealants are peeling or breaking off
 the material is becoming detached from its base
 protective coverings for the asbestos are missing or damaged
 there is asbestos dust or debris in the immediate surrounding area.
Asbestos or asbestos-containing materials, suspected or otherwise, displaying any of
the above conditions will require the area to be sealed off to form an Asbestos
Hazardous Area and an air-monitoring programme introduced.
4.4
Identifying Asbestos and Asbestos Types
Asbestos Types
There are three types of asbestos:
 crocidolite (‘blue’ asbestos)
 amosite (‘brown’ asbestos)
 chrysotile (‘white’ asbestos).
Although blue and brown asbestos are considered to be the most hazardous of the
three, all asbestos is dangerous and should be handled with care.
Sampling and Laboratory Analysis
Asbestos cannot be recognised by its visual appearance alone. Nor can the asbestos
types be identified solely by colour. A full laboratory analysis is required to identify any
substance as being asbestos and to distinguish its type.
Wherever asbestos or asbestos containing material is suspected, arrangements shall
be made for samples to taken and sent for laboratory analysis.
Sampling shall only be carried out by suitably trained, qualified and experienced
contract personnel or consultants who specialise in dealing with asbestos.
Warning: Do not break or damage material that may contain asbestos, even when
attempting to identify it.
5
Working with asbestos
5.1
Risk Assessment and Permit to Work
All work involving asbestos shall be carried out under the Permit to Work system and
must be supported by a formal Risk Assessment
A formal Risk Assessment, completed by a suitably competent person, shall be carried
out before any work involving asbestos or asbestos-containing material may take place.
The Risk Assessment must identify and address:
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 8 of 15
 the type(s) and locations of asbestos
 the nature and the extent of the proposed work
 the expected exposure levels for personnel involved in the work, including:
o whether exposure will be intermittent, exposure frequency and duration
o potential exposure level of personnel not involved in the work
o any existing air-monitoring results which may be relevant.
 measures required to prevent or control the release of asbestos into the
workplace or general environment
 any other hazards, not necessarily asbestos related
 emergency and contingency plans
 asbestos removal procedures, including:
o route selected for transferring asbestos waste through the site
o temporary storage of waste on site
o ultimate disposal of waste.
Note: In the case of small-scale maintenance, a documented Risk Assessment may
not be necessary.
5.2
Asbestos Hazardous Area
Whenever it is reasonably foreseeable that an operation may give rise to airborne
concentrations of asbestos in excess of the Action level, the area involved shall be
designated an Asbestos Hazardous Area.
Enclosure
The asbestos work area shall be enclosed completely to contain any airborne asbestos
fibre. To minimise contamination and to reduce interference with process plant, the
enclosure area will be kept as small as possible. If work is to carried out over a large
area, the area should be divided into smaller enclosures that are more easily
manageable.
Access to and from the area should be designed to prevent the escape of asbestos
dust as personnel pass through. Ideally, an ‘airlock’ system should be used.
Negative Air Pressure
Air extraction equipment should be incorporated within the enclosure to maintain a
slightly negative air pressure so that any leakage will be of clean air inwards.
Decontamination Facilities
Adequate vacuum cleaning, changing and showering facilities should be provided to
enable personnel to decontaminate themselves before leaving the work area.
Control of Access
The area shall be isolated and access denied to all unnecessary and unauthorised
personnel and also any personnel not wearing the required respiratory and personal
protective equipment. Warning signs should be strategically placed informing personnel
of the hazardous area conditions and entry restrictions.
Dust Levels
Airborne dust levels shall be maintained as low as reasonably practicable through
regular and frequent cleaning using vacuum cleaners and wet-wiping only. Cleaning
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 9 of 15
procedures should also be established for cleaning the asbestos workers’
decontamination, toilet facilities and eating / drinking areas.
Note: Dry sweeping or any other method that may raise dust shall be prohibited.
Waste Disposal and Transfer
All asbestos waste, including vacuum cleaner contents, should be placed in suitable
and clearly labelled containers inside the asbestos hazardous area. Labelling should
clearly indicate ‘Asbestos Waste’ and, where material is of a dusty nature, ‘Do Not
Inhale Dust’.
Where ‘double-bagging’ is used, the waste should be placed within a red bag and
sealed. The outside of the bag should be vacuum cleaned or water sprayed before
being placed within a second, clear bag, preferably inside the asbestos hazardous area
airlock.
Bags should not be overfilled. Where the waste includes large, heavy or sharp objects,
different types of container should be used that are puncture and tear-proof.
Decommissioning
Following completion of asbestos work, the hazardous area shall be thoroughly
cleaned so that all visible traces of asbestos are removed. When cleaning is complete,
air monitoring shall be conducted to confirm that the atmosphere within the area does
not exceed the Clearance Standard (see Paragraph 3.2).
6
Storage and Disposal of Asbestos Waste
If asbestos waste is to be stored on site, it shall be placed in a clearly demarcated and
secure area, to which only authorised personnel shall have access. The waste shall be
transferred off-site inside a closed, secure skip or vehicle to an approved hazardous
waste disposal site, in accordance with company requirements and nation / local
legislation.
Note: The final disposal of asbestos shall be undertaken by a specialist contractor.
7 Health Surveillance
BP employees working within or near asbestos hazardous areas should be kept under
routine health surveillance in order to:
 ensure that they have adequate respiratory function and are fit to wear
respiratory protective equipment when working under adverse conditions
 allow early detection of lung fibrosis and removal from further exposure may
limit the progression of asbestos in some individuals.
Medical records, particularly when correlated with asbestos exposure data, may
provide important evidence in case of litigation. Review of these records may, in the
longer term, assist the evaluation of the adequacy of occupational exposure limits and
control measures.
Note: Health surveillance of asbestos workers should include pre-employment
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 10 of 15
examinations with periodic review during employment in asbestos work.
8 Record Keeping
In addition to that recorded in the Asbestos Register (see Paragraph 4.2), the following
information should be recorded:
 Identities of all workers involved in the handling or use of asbestos.
 Results of personal monitoring of occupational exposure to asbestos.
 Medical records for all workers subject to health surveillance.
This information should be retained-ideally until at least 5 years after each individual
concerned has died, in case it is needed in connection with claims for compensation
arising from the delayed onset of occupational disease. In practice, this means that
medical records should be archived for at least 30 (preferably 50) years after the
employee has left the Company, or until 75 years after their date of birth.
The following information should be retained for at least 5 years:
 Summaries of the results of area/fixed position monitoring.
 Records of examination and testing of local extract ventilation systems.
 Records of inspection/maintenance of respiratory protective equipment.
 Records of assessments of risks and precautions.
 Records of training given to asbestos workers.
Records and documentation relating to asbestos waste disposals should be retained
indefinitely.
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 11 of 15
APPENDIX A - DEFINITIONS
Amosite
Commonly referred to as brown asbestos, similar to crocidolite but with
slightly curly fibres when viewed under a microscope.
Asbestos
A group of naturally occurring crystalline silicate minerals with
characteristic long thin fibres capable of being split longitudinally to
create progressively thinner fibres. It is these fibres that, in airborne
form, can cause asbestos related diseases when inhaled.
Asbestos
Any material that has asbestos as a component. For example, some
Containing
cement products, floor tiles, insulation material and lagging, clutch and
Material
brake linings, etc.
Asbestos
An enclosed area set up to contain the spread of asbestos dust from an
Hazardous Area
area where asbestos related activity is being carried out.
Asbestos
A record of all occurrences of asbestos that has been left in place on-
Register
site. The register should record the asbestos type, its condition and
inspection record.
Asbestos Related
Any disease attributable to the inhalation of asbestos dust. These
Diseases
diseases might not occur until 20 - 30 years after inhalation.
Chrysotile
Sometimes called white asbestos. Although this type of asbestos is
considered to be less hazardous than crocidolite and amosite, it still
connected with asbestos related diseases.
Clearance
The maximum level to which asbestos contamination of the atmosphere
Standard
must be reduced before an asbestos hazardous area may be returned
to normal use.
Competent
A person recognised as being suitably trained and experienced to carry
Person
out specific tasks in a safe and efficient manner.
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 12 of 15
Crocidolite
Commonly referred to as blue asbestos. Under a microscope its fibres
are short and straight.
Exposure Limit
Maximum allowable personal exposure to all types of asbestos,
presently set at 0.2 fibres/ml 8-hour time weighted average
Specialist
A contractor, or consultant, specialising in working with asbestos. The company
Contractor
must be satisfied that the contractor is suitably equipped, trained, experienced
and knowledgeable for the asbestos related activities (air-monitoring, asbestos
removal and disposal, etc) for which they are contracted
APPENDIX B - AIR MONITORING METHODS
Air Sampling Methods
Personal Sampling
For determining occupational exposure to airborne asbestos fibres and compliance with
occupational exposure limits, only personal sampling provides valid results.
For personal sampling, a potentially exposed individual wears a lightweight sampling
pump with the sampling head located in their breathing zone.
Note: Although 'fixed position' sampling may be useful to determine the
effectiveness of process control and workplace measures, it is not suitable
for monitoring personal exposures
Airborne Fibre Monitoring
Airborne fibre monitoring techniques involve drawing a measured volume of air through
a membrane filter at a constant flow rate.
Following sampling, the filter is mounted on a glass slide so that the fibres collected
may be counted by using phase contrast optical microscopy.
Note: It is important not to produce a density of particles on the filter which is too
great to allow individual fibres to be counted. Except in the USA, a 'fibre' is
defined as a particle having a length to breadth ratio greater than 3:1, a
diameter of less than 3µ and a length greater than 5µ.
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 13 of 15
APPENDIX C - ASBESTOS REGISTER FORMAT
Asbestos Register Form
Site:_________________________ Register Ref. No:_________________________
Material Location:______________________________________________________
_________________________Date of Inspection:____________________________
Function of Material:____________________________________________________
Approximate Quantity:__________________________________________________
Condition:____________________________________________________________
Samples Taken:
YES/NO
Sample
Fibre Type(s)
Approximate Quantity
No.
(% Composition)
Action Required
Designated Responsibilities
Date
and Target Date
Completed
1. Removal and disposal
2. Seal (encapsulate)
3. Store in sealed containers
4. No action unless maintenance
or demolition work is undertaken
Inspection-while asbestos remains, its condition should be inspected, at a frequency
depending upon the likelihood of damage occurring but once/year is usually
appropriate.
Inspection Frequency:___________________________________________________
Additional Information & Comments:
INSPECTION CONDUCTED
DATE
Comments/Action Required/
Name/signature
Designated Responsibility
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 14 of 15
APPENDIX D - ASBESTOS RELATED DISEASES
Asbestos Related Diseases
Asbestos only poses a risk to health if asbestos fibres are released into the air where
they form a very fine dust which is often invisible to the naked eye. When inhaled, this
dust is capable of being deposited in the deepest regions of the lungs where they may
cause any of what are collectively known as asbestos related diseases for which there
is no known cure. These diseases include:
 Asbestosis
 Pleural Thickening
 Pleural Effusions
 Lung Cancer
 Mesothelioma.
Any of these diseases may be caused by either exposure to high levels of asbestos
dust, or repeated exposure to low levels.
Asbestosis
Prolonged exposure to airborne asbestos may lead to asbestosis, a collagenous
fibrosis of the lungs. Fibrosis leads to a progressive reduction in lung elasticity and
impairment of the gas exchange mechanism.
Early symptoms of asbestosis include breathlessness and coughing.
The disease may progress to cause severe disability and heart failure.
Pleural Thickening
Exposure to airborne asbestos fibres may cause thickening of the pleura, and glass-like
plaques in the membranes surrounding the chest cavity. Although these changes do
not usually cause any ill effects, widespread pleural thickening may restrict lung
expansion and cause breathlessness.
Lung Cancer
Exposure to airborne asbestos fibres is associated with an increased risk of lung
cancer. In particular, asbestos exposure and cigarette smoking act synergistically to
produce a much greater risk of lung cancer than would be expected from the sum of
independent risks from smoking and asbestos exposure.
Pleural Effusions
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Asbestos Risk Management
Page 15 of 15
Asbestos fibres can cause irritation of the pleura leading to rapid outpouring of fluid into
the pleural cavity, squashing the lung on that side. Although rarely life-threatening, the
sudden shortness of breath is frightening and urgent medical attention is required.
Mesothelioma
Exposure to airborne asbestos fibres, particularly crocidolite and amosite, may lead to
the development of mesothelioma, a cancer of the pleura and more rarely, the
peritoneum (the membrane lining the abdominal cavity). Mesothelioma may develop 20
or years after exposure to asbestos. It is also associated with other fibrous materials,
such as erionite (a naturally occurring mineral), and may occur in persons with no
known occupational exposure to asbestos or other fibrous materials.
Mesothelioma is always fatal.
Control Tier:
<<2>>
Revision Date: <<30 Sept 2005>>
Document Number: << AZSPU-HSSE-DOC-00016-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 1 of 15
Procedure for:
Diving & Subsea Operations
AZSPU-HSSE-DOC-00017-2
This number supersedes UNIF-HSE-PRO-272-C1
Authority:
<< AzSPU H&S Manager >>
Custodian:
<< AzSPU Safety TL >>
Scope:
<< AzSPU >>
Document
Administrator:
<< Document Asset Technician Name >>
Issue Date:
<< 11 October 2004>>
Issuing Dept:
<< CHSSE >>
Revision Date:
<< 11 October 2004 >>
Control Tier:
<< 2 >>
Next Review
<< 11 October 2005 >>
Date:
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 2 of 15
Table of Contents
1
INTRODUCTION
3
1.1 Safety Goals
3
1.2 Expectations
3
1.3 Scope 3
1.4 References
3
2
ROLES AND RESPONSIBILITIES
4
2.1 Diving Technical Authorities
4
2.2 Dive Contractors
4
2.3 Management of the Diving and Subsea Operations SsoW
4
2.4 Dive Responsible Personnel and Company Authorized Representatives
4
3
SAFETY MANAGEMENT PROCESS
5
3.1 Compliance and Standards
5
3.2 Planning
6
3.3 Performing
7
3.4 Measuring and Improving
8
3.5 Additional AzBU Safe Systems of Work
9
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 3 of 15
1
Introduction
The purpose of this document is to define the Azerbaijan Business Unit standards and
expectations regarding diving and subsea operations within the AzBU. This document
specifies the minimum mandatory BP and/or contractor safety management system
requirements for diving and subsea operations. Compliance with this Safe System of
Work (SSoW) will ensure that the standards of safety on diving and subsea projects are
in accordance with BP getting HSE right and the AzBU safety management processes.
Safety Goals
The goal of this SSoW is to achieve no accidents, no harm to people and no damage to
the environment. To achieve this goal the SSoW complies with the following:
ƒ Internationally accepted good engineering practice, as required by the operating
Production Sharing Agreement (PSA) across the Business Unit
ƒ Diving and subsea industry standards and guidance
ƒ BP policies and expectations - What We Stand For
ƒ BP HSE management system - getting HSE right
ƒ Azerbaijan Business Unit Safe Systems of Work
Expectations
The expectations of the SSoW are to:
ƒ Comply fully with all legal requirements.
ƒ Provide a secure and safe working environment.
ƒ Ensure that all employees, contractors and others are well informed, well
trained, engaged in and committed to the HSE improvement process.
ƒ Provide assurance that the safety processes in place are working effectively.
ƒ Maintain confidence in the integrity of BP operations.
ƒ Confirm that the management systems of contractors fully support BP’s
commitment to HSE performance.
Scope
This SSoW applies to all inshore or offshore diving and subsea operations that take
place on behalf of the BP AzBU. All contractors directly contracted by any AzBU
Project or Operations Performance Unit, and those directly contracted by UTG Subsea
Team working in the Business Unit must comply with this Safe System of Work.
Whereas the boundary of BP control and accountability is defined by work that takes
place on behalf of BP, it is the intent that through BP influence that all diving and
subsea contractors operating within the Caspian and Black Sea regions shall likewise
comply with these expectations.
References
The reference documents with which compliance is the minimum standard in
conjunction with this SSoW are:
ƒ International Marine Contractors Association
(IMCA) International Code of
Practice for Offshore Diving
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 4 of 15
ƒ United Kingdom Offshore Operators Association (UKOOA) Diving Guidance
ƒ Diving Medical Advisory Committee
(DMAC) Guidance and Best Industry
Practice
2
Roles and Responsibilities
Operations and Project Groups operating within the AzBU are responsible for the safe
management of diving and subsea projects. They control the diving or subsea
requirement, the worksite and the management control systems. These responsibilities
are met through full compliance with this document and those referenced. Those
responsible for diving in the AzBU must verify that third parties operating within BP’s
sphere of influence accord with the safety management system requirements. Any
deviations from this SSoW or the Dive Safety Management System must be justified
through a risk management process.
Diving Technical Authorities
Within the AzBU, two diving technical authorities are recognized
- one for the
Operations Performance Unit, and another for Azeri Projects Performance Unit. Prior
to commencement of any new diving operation the respective technical authority must
be consulted.
In addition, the AzBU seeks further advice and guidance from recognized technical
authorities within the Upstream Technology Group (UTG Dyce, Aberdeen). Besides
technical competence on subsea operations, UTG also provide independent audit of
compliance with the Diving and Subsea Operations Practice. If required, UTG will
provide preparation, planning and support for diving and subsea emergency response
and investigation of diving related accidents.
Dive Contractors
Dive contractors are responsible to fully understand and comply with the requirements
for development of the safety management system. Other third parties not directly
contracted by the AzBU but working within the BP sphere of influence must also
comply with the SMS requirements.
Management of the Diving and Subsea Operations SsoW
This custodian for this Safe System of Work is the Business Unit central HSE
Department. Regular review, maintenance and management of document changes are
the responsibility of HSE through reliance on technical input from the technical
authorities.
Dive Responsible Personnel and Company Authorized Representatives
Responsibilities for these individuals shall be thoroughly defined in the work scope
specific Dive Safety Management System. A BP authorized representative shall be on
board all dive support vessels. The Diving Representative is accountable to ensure
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 5 of 15
that all diving operations comply with the safety management system. In addition, they
must be competent in their ability to provide overall HSE assurance in accordance with
other AzBU standards.
3
Safety Management Process
The intent of this SSoW is to describe the applicable processes for the management of
diving and subsea operations within the AzBU. Prior to the commencement of any dive
operation the BP Technical Authority shall develop, or shall ensure that the dive
contractor develops a Dive and Subsea Operations Safety Management System
(SMS). The components of the SMS are depicted in the following figure, and shall
include as a minimum the various elements described in this section.
COMPLIANCE
PLANNING
PERFORMING
MEASURING & IMPROVING
Communicating
Expectations
Roles &
Responsibilities
Site Rules
Competency
Assessment
Process
Risk
HSE Overview
NATIONAL
Assessment
REGULATIONS
Audit Plan
Operational
CLOSE OUT
Safety Briefings
Issues
REPORT &
BP DIVING &
MEETING
BP POLICIES &
SUBSEA
Information
BRIDGING
OPERATIONS
EXPECTATIONS
OPERATIONS
Validation
DOCUMENT
COMPLETED
SHARE
PRACTICE
LESSONS
Permit to Work
Technical Issues
LEARNT
Process
Workscope
DIVING
& Procedures
INDUSTRY
STANDARDS
Progress
Commercial
Reporting
Risk
Assessment
Accident
Investigation &
Emergency
Reporting
Response Plan
Management
of Change
3.1
Compliance and Standards
To assure AzBU and project groups that any work undertaken by a contractor
supplying diving or subsea services, direct or through third parties meets BP
expectations, the diving standards must be stated. The minimum compliance
standards are of International Marine Contractors Association (IMCA) and the rules of
the International Code of Practice for Offshore Diving Operations, D014.
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 6 of 15
The diving and subsea contractor must maintain a full membership of IMCA. IMCA
codes of practices shall be applied including Former Dynamic Positioning Vessel
Operators Association, Association of Offshore Diving Contractors, and Diving Medical
Advisory Committee Guidance Notes.
3.2
Planning
3.2.1 Communicating Expectations
At the start of and throughout a diving or subsea project, it is essential that BP
expectations on policies, practices and procedures be communicated to all key
personnel. The Dive SMS must describe how this will be accomplished.
3.2.2 Roles and Responsibilities
The roles and responsibilities of all organizations and key personnel involved in the
emergency response, management and control of a diving or subsea project must be
clearly defined.
3.2.3 Competency Assessment Process
A process for ensuring the competence of onshore and offshore personnel shall be
adopted and applied to key personnel involved in the emergency response,
management and control of a diving or subsea project.
3.2.4Audit Plan
An audit plan for the diving or subsea operation shall be developed. As a minimum the
contractors’ management systems, vessels, plant and equipment shall be audited to
BP and IMCA International standards prior to work commencing. The audit plan should
discuss how ongoing assurance would be maintained throughout the scope of
operations.
3.2.5 Information Validation
A system shall be in place to ensure that all information on the worksite is current and
valid. Key documents with the latest revisions should be listed in the bridging
document. Though non-mandatory, an Asset Information Dossier can be useful in
providing relevant information for the site including the following topics:
 Field description
 Work control systems
 Communications
 Simultaneous operations
 Hazid
 Generic risk assessment
 Documentation references
3.2.6 Work Scopes and Procedures
Work scopes and procedures must be clearly defined and reviewed by the BP technical
authority before work can commence. They shall be written with due regard to BP
expectations, policies and practices.
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 7 of 15
3.2.7 Emergency Response Plan
Response systems and callout procedures must be in place for BP, the diving and
subsea contractor, other offshore operators and other key parties.
3.2.8 Risk Assessment
All activities including work scopes, generic and specific procedures must be subject to
a formal risk assessment process during the planning phase. The process will identify
any requirement to change the work scope and procedures and/or any mitigating
measures to be applied. The process should employ the diving or subsea contractor's
SMS with active involvement from all parties whose acts or omissions could adversely
affect the health and safety of persons engaged in the project or could affect plant,
equipment or the environment.
3.2.9 Management of Change
The diving and Subsea contractor must have a documented system to manage
change. The management of change procedure will define how change is
implemented, who is authorized to approve levels of change and how any appropriate
risk-reducing measures are applied.
3.2.10 Bridging Document
No diving or subsea operation can commence until an authorized bridging document
has been issued. The bridging document is the interface between BP and other parties
SMS’s. It provides scope overview, operational detail for an emergency response and
outlines how the SMS requirements have been met. A separate bridging document will
be required for each phase of a diving or subsea project or major element of work. Key
personnel and the AzBU Crisis Management Department and Incident Management
Team must receive controlled copies.
The contents of a bridging document should include but are not limited to:
 Project title and revision status.
 Circulation list and authorisation signatures.
 Project overview including dates and contract arrangements.
 Identification of the relevant work scopes and procedures.
 Identification and allocation of key personnel roles and responsibilities.
 Communication contact numbers for key personnel and worksites.
 Accident and incident reporting mechanisms.
 Management of change process.
 Emergency and contingency procedures including clarification of primacy.
 List of referenced documentation including revision status.
 Work control system.
 Audit status of key items of equipment.
3.3
Performing
3.3.1 Site Rules
Site rules that define the specific arrangements to manage and control diving and
Subsea projects safely shall be in place for all sites. These will include HAZID, work
control system, simultaneous operations, emergency response, and communications.
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 8 of 15
3.3.2 Risk Assessment
Formal onsite risk assessments, the review of generic risk assessments, job safety
analysis and personal risk assessments must be conducted for all elements of the
project including routine maintenance activities. The process should employ the diving
and subsea contractor's SMS with active involvement from all parties whose acts or
omissions could adversely affect the project.
3.3.3 Safety Briefings
Briefings on BP expectations, policies and practices are to be given to all personnel
involved in the project, including marine crew and third parties. A system of general
safety briefings, safety meetings and toolbox talks must be carried out and recorded.
Appropriate site orientation, induction and project specific training that includes site
rules and emergency procedures shall be undertaken to clarify roles, responsibilities
and actions. All personnel should attend the briefings and training, and a register
should be maintained.
3.3.4 Permit to Work Process
In addition to the diving and subsea contractor or vessel permit to work system, when
working inside the sphere of influence of the BP AzBU, the BP Permit to Work (PTW)
system is to be employed. A nominated competent person will act as the Performing
Authority and will remain onsite throughout operations.
3.3.5 Progress Reporting
A process of regular communications between the key parties shall be in place to
report project progress including safety operational and technical issues.
3.3.6 Incident Investigation and Reporting
An agreed system of accident, incident and near miss reporting must be implemented
to ensure BP reporting requirements are met. All health, safety, technical integrity and
environmental incidents including near misses shall be openly reported, investigated
and documented in order to analyse and learn from the incident. A multi-functional
team with independent participation and leadership from BP management will
investigate major incidents.
3.3.7 Operations Completed
On completion or suspension of operations the diving and subsea contractor is to
inform BP of the status of the project in accordance with the requirements detailed in
the relevant contract or third party agreement. Only on the acceptance by BP of the
as-builds and close out documentation produced by the diving and subsea contractor
can final acceptance of the works be achieved.
3.4
Measuring and Improving
In order to assess the performance of the project or a phase of work it is essential that
a measurement and improvement process is in place and the project details are
recorded in a closeout report. This will allow lessons learned to be carried forward to
other projects or phases of work. The items detailed below should form the structure of
the closeout report.
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 9 of 15
3.4.1 HSE Overview
HSE data including a summary of accident, incident and near miss reports from the
diving and subsea contractors shall be collated. The conduct and culture of contractors
and other parties should be reviewed and issues raised in order to improve standards
and compliance with requirements. The information gathered from all levels of reporting
is to be analysed to identify and monitor trends and develop prevention programmes
and actions.
3.4.2 Operational Issues
Information on all activities including, but not limited to, the following list should be
reviewed, recommendations raised and actions recorded in order to improve standards
and compliance:
Chronology of the project
Positive and negative performance of contractors, personnel and plant
Procedures and work processes
Logistics and communications
Project documentation
3.4.3 Technical Issues
As-built and closeout documentation must be used to revise BP documentation.
Relevant documentation must be updated immediately if the changes affect diving and
subsea safety.
3.4.4 Commercial
An itemized outline breakdown of costs and expenditure should be recorded for
reference and audit purposes.
3.4.5 Closeout Reporting and Meeting
The closeout report and meeting are central to the measuring and improving stage.
The objectives of the closeout meeting will be to:
 Review the final closeout report and corrective action requirements
 Review the project and its final status
 Highlight any lessons learned
3.4.6 Sharing Lessons Learned
Lessons learned from the project or phase of work must be shared and where
appropriate distributed to the wider diving and subsea industry.
3.5
Additional AzBU Safe Systems of Work
In addition to the applicable processes, other AzBU Safe Systems of Work must also
be taken into consideration, as well as the Golden Rules of Safety.
The AzBU authorization to dive procedures must also be completed to allow diving and
subsea operations to commence.
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 10 of 15
TECHNICAL DOCUMENTATION FRONT SHEET
Total pages: 2 including cover
Azerbaijan Business Unit
Standing Instruction
In addendum to Safe System of Work for
Diving and Subsea Operations
Approved Helmets
Rev
Date
Reason for
Prepared
Technical Authority
Technical
Checked
Engineering
Director HSE
Issue
Authority
Manager
1
24 July 03
Equipment
M.Sinquefield
H.Kuhlmann
R.McKay
K.Kennelley
G Campbell
approvals
Document Number:
Disk Ref.
Addendum to UNIF-HSE-PRO-272
Category
Code
Description
Area Code
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 11 of 15
Document Type
Controlled
Standing Instruction to Technical
Authorities
System Number
UNIF-HSE-SI-272
Life Cycle
As changes are identified
This document is copyright and
shall not be reproduced without
permission of BP
1 Introduction
The purpose of this standing instruction is to define the Azerbaijan Business Unit
expectations regarding diving helmets within the AzBU.
2 Standing instruction
All diving helmets must be identified in pre dive equipment audits. If Kirby Morgan
models S/L 17 A/B or Mark 21 helmets are to be used then the following standing
instruction applies.
1. Any S/L 17 models A/B or Mark 21 that are to be used, must comply with all
KMB’s recommended modifications and safety checks (see attached No.1).
2. Any S/L 17s models A/B or Mark 21s that are to be used, must be installed with
Divex recommended modifications, which have been approved and
recommended by UTG (see attached No. 2).
3 Responsibilities
All dive programs shall be reviewed and approved by the AzBU Technical Authority for
Dive Operations. It is the Dive TA responsibility for ensuring the implementation of this
Standing Instruction. Compliance with this standing instruction should be verified
during pre-dive audits, and throughout the dive operations.
4 Attachments
Attachment 1. KMB modifications and safety recommendations
Attachment2. Divex modifications/ approved by UTG
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 12 of 15
Safety Notice #1 of 1999:
SuperLite 17 A/B & MK 21 Neck Clamp
11 May, 1999
Subject: Weld Strength
Products Affected: SuperLite 17 A/B & MK 21
Neck Clamp Assemblies Manufactured from
10/97 to 12/98
The purpose of this Safety Notice is to alert all
end users and owners of Diving Systems
International SuperLite 17 & MK 21 helmet neck
clamps, DSI Part #505-055, to a potential
problem with the welded stud on the neck clamp
assembly.
Inspect your neck clamp immediately.
This weld should have 1/8" of material (1/8" fillet weld) all around the stud as shown in figure
A. If your clamp has a weld like the one shown in figure B, (no extra material), please return
it to your nearest Authorized DSI Dealer immediately for inspection and replacement, if
necessary.
NOTE: The potential of possible failure of the weld shown in figure B increases when the
user's neck clamp is not properly adjusted.
If you use any neck seal other than the standard DSI neck dams,
YOU MUST RE-ADJUST YOUR NECK CLAMP ASSEMBLY FOR PROPER OPERATION!
Before every dive, your equipment must be completely checked for any damage or wear.
Even normal wear and aging will eventually result in the need to replace parts. Any abnormal
condition of any component requires the removal and replacement of the component. If any
part doesn't look right, don't use it. All metal parts should be inspected for cracks or
corrosion and replaced immediately if this type of damage is found. While some surface rust
or corrosion is to be expected, severe corrosion can lead to the eventual failure of the part.
Important Caution Note
This reference guide is to eliminate confusion as to which neck clamps qualify for Warranty
Replacement. Please check that neck clamps fit these specifications before sending
them to DSI. Any type of marking on the hinge block area does not warrant replacement.
Any type of
NO Marking
letter or number
Neck Clamp with No gusset - No
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 13 of 15
gusset
Warranty
(current product) These are at
least ten years
old
This is the exact dimension of the stud that will help identify warranty replacement.
Anything other than this will not qualify under the safety notice.
Safety Notice #1 of 2000:
SuperLite 17 A/B & MK 21 Neck Clamp
27 January, 2000
This Notice is an addendum to the Safety Notice #1, 11 May 1999
Subject: Weld Strength
Product Affected:\SuperLite 17 A/B & MK 21 Neck Clamp Assemblies
The purpose of this Safety Notice is to alert all end users and owners of Diving
Systems International SuperLite 17 A/B & MK 21 helmet neck clamps, DSI part # 505-
055 to a potential problem with the welded stud on the neck clamp assembly. The
welded stud on some clamps may not have sufficient weld and could pose a Safety
Threat.
Prior to April of 1999, the neck clamp assemblies were not marked in any way. These
assemblies were manufactured to an engineering drawing calling for a minimum
standard of 1/16" inch (.0625) (1.588mm) fillet weld on the stud
(fig A below).
Beginning in April of 1999, neck clamp assemblies are
manufactured with a date of production and identification number
engraved directly onto the part. Every neck clamp is N.D.T.
(nondestructive testing) tested to A.W.S. standard D1.1. These
clamps are welded to a minimum standard of 1/8" inch (.1250)
(3.175mm) fillet weld on the stud (fig A below).
All owners and end users of the SuperLite 17 A/B and US
Navy MK 21 helmets should inspect the welded stud as
follows:
Determine if the clamp has a manufacture date stamp as
illustrated.
If it does, you should check to ensure the stud contains a minimum of 1/8" inch (.1250)
(3.175mm) fillet weld as shown in illustration A. The weld leg length must be no less
than 1/8-inch (.1250) (3.175mm).
If there is no date stamp, you should check to ensure the stud contains a minimum of
1/16" inch (.0625) (1.588mm) fillet weld as shown in illustration A. The weld leg length
must be no less than 1/16" inch (.0625) (1.588mm)
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 14 of 15
In either case, the clamp must also conform to criteria below.
1. Weld must show no visual signs of cracking.
2. Crater pits are acceptable provided the area contains no cracks and the minimum
1/16" inch (.0625) (1.588mm) weld thickness is met.
3. Porosity. Disregard any pores 1/32" inch (.03125) (.794mm) or less in diameter.
Pores the sum of whose diameter exceeds 1/8" inch (.1250) (3.175mm) are
unacceptable.
4. Undercut. Maximum depth of undercut of the stud base metal measured from the un-
ground adjacent base metal shall not exceed 1/64" inch (.015625) (.397mm).
5. Weld shall be free of linear indications greater than 1/16" inch (.0625) (1.588mm) in
length.
6. Non-Linear /round indications less than 1/32" inch (.03125) (.794mm) in diameter
shall be disregarded.
Inspect your neck clamp immediately.
B
A
If your clamp has a weld like the one
If your clamp has a date stamp, this
shown (no extra material) please return
weld should have a minimum 1/8"
it to your nearest Authorized DSI dealer
(.1250) (3.175mm) of material (1/8"
immediately for inspection and
(.1250) (3.175mm) fillet weld) all
replacement if necessary.
around the stud as shown.
If there is no date stamp, this weld
should have a minimum 1/16" inch
(.0625) (1.588mm) of material 1/16"
inch (.0625) (1.588mm) fillet weld) all
around the stud as shown
NOTE: The potential of possible failure of the weld shown in figure B
increases when the users neck clamp is not properly adjusted. This is
especially true with use of any drysuit dams.
If you use any neck seal other than the standard DSI neck dams,
YOU MUST RE-ADJUST YOUR NECK CLAMP ASSEMBLY FOR
PROPER OPERATION!
Before every dive, your equipment must be completely checked for any
damage or wear. Even normal wear & aging will eventually result in the
need to replace parts. Any abnormal condition of any component requires
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Diving & Subsea Operations
Page 15 of 15
the removal and replacement of the component.
If any part doesn't look right, don't use it.
All metal parts should be inspected for cracks or corrosion and replaced
immediately if this type of damage is found. While some surface rust or
corrosion is to be expected, severe corrosion can lead to the eventual
failure of the part.
Revision/Review Log
Revision Date
Authority
Custodian
Revision Details
<<11 October
<< Alan McNulty
<< Esmira
<< Initial Issue>>
2004>>
>>
Akhundova >>
Control Tier:
<<2>>
Revision Date: <<11 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00017-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 1 of 32
Procedure for Energy Isolation - Electrical
AZSPU-HSSE-DOC-00048-2
This number supersedes UNIF-HSE-PRO-106-C2
Authority:
Central Engineering Senior
Custodian:
Electrical Technical Authority
Authority
Scope:
AzSPU.
Document
Administrator:
Document Asset Technician
Issue Date:
24 Aug 2004
Issuing Dept:
CHSSE
Revision Date:
18 June 2007
Control Tier:
2
Next Review
18 June 2008
Date:
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 2 of 32
TABLE OF CONTENTS
1.
INTRODUCTION
1.1
Purpose
1.2
Scope
1.3
Legislation & Standards
1.4
Stopping Unsafe Work
1.5
Deviations
1.6
Document Review
1.7
Energy Isolation Golden Rules of Safety
1.8
SSOW Specific Cross References
1.9
Language Facilitation
1.10
Procedure Summary
2.
DEFINITIONS
3.
ROLES AND RESPONSIBILITIES
Electrical Functional Work Group
Site Manager / Site Controller / Offshore Installation Manager
Area Authority
Isolating Authority
Performing Authority
Responsible Electrical Person
Electrical Technical Authority
Senior Authorized Electrical Personnel
Authorized Electrical personnel
Authorized Instrument Personnel
Competent Isolator
Competent Person
4.
SELF-REGULATION & AUDIT
5.
ISOLATING AUTHORITY - TRAINING, COMPETENCY & AUTHORIZATION
6.
MODIFICATION & NEW FACILITIES
7.
ISOLATION & PLANNING
7.1
Isolation
7.2
Isolation Planning
7.3
Switching Programmes
7.4
Isolation Methods
7.5
Isolation Standards
7.6
Risk Assessment of Non-compliant Isolations
7.7
Live Working
7.8
Isolations for Work Near Live Conductor
8.
ISOLATION IMPLEMENTATION & CONTROL
8.1
Security
8.2
Isolation Labelling
8.3
Positive Identification of Equipment
8.4
Control of Isolations
8.5
Operational Locks
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 3 of 32
8.6
Boundary Isolations
8.7
Long-Term Isolations
8.8
Personal Isolations
8.9
Testing Isolation Integrity - Proving dead
8.10
Monitoring Isolation Integrity
9.
DE-ISOLATION OF PLANT
Appendix A: Applicability
Appendix B: Adjacent Working Assessment
Appendix C: Switching Programme
Appendix D: Operational Locking System
Appendix E: Control of Electrical Work
Appendix F: Labels
Appendix G: Procedure Summary
Appendix H: Feedback & Improvement Suggestions
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 4 of 32
1
Introduction
1.1
Purpose
The purpose of this document is to define the Azerbaijan Performance Unit (AzSPU)
functional standard for the safe isolation of electrical plant or equipment from sources
of electrical energy.
1.2
Scope
The contents of this Safe System of Work are applicable to all BP owned and
managed sites/installations in Azerbaijan and Georgia. Contractors working on BP
owned or managed sites/installations are also responsible for alignment with this
SSOW.
This document does not replace the procedures prepared and adopted by specialist
contractors. Neither does it supersede any national and local regulatory
requirements.
This SSOW contributes to compliance with the “HSE expectations” contained in
“getting HSE right”, the ‘Golden Rules of Safety’ and the Control of Work (CoW)
standard that the Hazards associated with BP activities are identified and that the
Risks are assessed and managed.
All guidelines contained shall be regarded as the minimum requirements for BP
owned or managed sites in Azerbaijan and Georgia.
This document applies to the electrical isolation of equipment for work. It shall be
followed at all AzSPU operated sites / installations and is applicable to both onshore
and offshore.
1.3
Legislation & Standards
The aim of this Safe System of Work is to achieve no accidents, no harm to people
and no damage to the environment. To achieve this aim, this SSOW complies with
National Legislation, the terms of the Production Sharing Agreement (PSA) and
mandatory BP Standards.
The best International Oil Industry practice and relevant goal setting legislation have
been adopted to reduce the level of risk to as low as reasonably practicable and
therefore well below that mandated by applicable statutory laws and regulations.
In the absence of local regulations, BP Group Standards will apply. In addition,
appropriate UK and US regulations and industry best practice have been considered
in setting suitable goals and targets.
1.4
Stopping Unsafe Work
To stop the continuation of potentially unsafe work at the earliest possible stage the
Control of Work (CoW) Policy and this Energy Isolation - Electrical procedure make it
very clear that all personnel are obliged and have the authority to “STOP” the work
that they consider to be unsafe.
1.5
Deviations
This procedure is written in sufficient detail that it should be able to be applied
consistently at all sites / installations. There may still be the requirement for some
local rules covering site / installation specific logistical / administrative arrangements
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 5 of 32
and local variations in responsibilities to reflect differences in organisational
arrangements. These local rules should not deviate from the core processes within
this document. Any form of deviation from this procedure, including but not limited to
local rules, shall be requested and authorised in accordance with the SSOW
Deviations from Regulations and Procedures (Doc. No: AZSPU-HSSE-DOC-00011-
2)
1.6
Document Review
This document will be reviewed on an annual basis when users from the site will
have an opportunity to propose changes to the existing processes and procedures.
The document Technical Authority will be responsible for coordinating this review.
1.7
Energy Isolation Golden Rules of Safety
Energy Isolation is one of BP‟s Golden Rules of Safety and states:
Any isolation of energy systems, e.g. mechanical, electrical, process, hydraulic,
pneumatic, gravitational, chemical, radioactive, thermal, or other energy source that
could cause injury, cannot proceed unless:
 The method of isolation and discharge of stored energy are agreed and
executed by a responsible person
 Any stored energy is safely discharged
 A system of locks and tags is utilized at isolation points
 A test is conducted to ensure the isolation is effective
 Isolation effectiveness is periodically monitored
1.8
SSOW Specific Cross References
Document No
Title of Procedure
AZSPU-HSSE-DOC-00012-2
Procedure for: Authorization
AZSPU-HSSE-DOC-00012-A2
Guideline for: Electrical Safety
AZSPU-HSSE-DOC-00063-2
Task Risk Assessment
AZSPU-HSSE-DOC-00049-2
Energy Isolation
AZSPU-HSSE-DOC-00060-2
BU PTW Process
AZSPU-HSSE-DOC- 0002-2
Control of Work
1.9
Language Facilitation
Due to the various languages spoken at sites / installations, there is a necessity to
assist all with “an ease of understanding”. Therefore, the development and use of
information tools are available.
1.10 Procedure Summary
A Procedure Summary has been developed in a form of a leaflet, which can be
carried by the Line Supervisors while conducting their day-to-day work tasks. The
Leaflet summarizes the contents of this Procedure for Energy Isolation - Electrical.
The Procedure Summary can also be used as a guideline for Line Supervisors to
deliver their daily toolbox talk. (See Appendix G)
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 6 of 32
2
Definitions
AA
Area Authority
AEP
Authorized Electrical Person
AIP
Authorized Instrument Person
SC
Site Controller
SM
Site Manager
BUL
Business Unit Leader
CI
Competent isolator
CMAS
Competence Management Assurance
System
D
Main conductor disconnected
E
Earth the isolated conductor
IA
Isolating Authority
ICC
Isolation Control Certificate
Is
Isolate
IP
Ingress protection
SSOW
Safe System Of Work
LL
Lock and Label
LTI
Long-term isolations
P
Prove dead with proprietary voltage
tester
PA
Performing Authority
REP
Responsible Electrical Person
SAEP
Senior Authorized Electrical Person
SP
Authorized Switching Programme
TA
Technical Authority
PTW
Permit to Work
OIM
Offshore Installation Manager
HV
“High Voltage” voltages that exceed
1000Vac or
1500Vdc between
conductors or
600Vac or
900Vdc
between conductors and earth
LV
“Low Voltage” is a voltage normally
exceeding extra low voltage by not
exceeding
1000V ac or
1500 Vdc
between conductors or
600Vac or
900Vdc between conductors and earth
ELV
“extra low voltage” Voltage which does
not exceed
50V ac rms between
conductors or between any conductor
and earth, in a circuit isolated from the
supply be means such as a safety
isolating transformer or converter with
separate windings.
A voltage which does not exceed 50V dc
between conductors or any conductor
and earth in a circuit isolated from
Higher voltage circuits
3
Roles and Responsibilities
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 7 of 32
3.1
Electrical Functional Work Group
The Electrical Functional Work Group (EFWG) has produced this document to
support the safe system of work. The Document Technical Authority will issue any
new revisions of the document for approval.
3.2
Site Manager (SM) / Site Controller (SC) / Offshore Installation Manager
(OIM)
The SM / SC / OIM are responsible for ensuring that those performing the roles of
Area Authority, Responsible Electrical Person, Isolation Authority and Performing
Authority are competent to do so. The SM / SC / OIM are responsible for authorizing
any deviations from the isolation standard through the risk assessment process. In
doing so, he/she may choose to defer or not to carry out the activity and seek further
technical guidance if the residual risk is perceived to be excessive.
The SM / SC / OIM are also responsible for ensuring that plant and equipment
isolations are subject to the appropriate level of self-regulation and audit.
3.3
Area Authority (AA)
The Area Authority is responsible for approving the isolation design, providing
assurance that the design achieves the highest quality of isolation reasonably
practicable. He/she can delegate the detailed isolation design to an appropriately
competent or authorized person. The Area Authority is then responsible for
authorizing the work to proceed under appropriate controls. This includes approval
of any preparatory work and, on completion of the task, the work required to
complete reinstatement.
3.4
Isolating Authority (IA)
The Isolating Authority is responsible for design of an electrical isolation when
requested by the Area Authority. He/she is then responsible for safely isolating a
specific section of plant or items of equipment to the highest quality and security of
isolation, which is reasonably practicable. The Isolating Authority is also responsible
for demonstrating the integrity of the isolation to the Performing Authority. The
Isolating Authority will be authorized to the maximum voltage level required for the
isolation.
3.5
Performing Authority (PA)
The Performing Authority is the person charged with the responsibility of carrying out
the work and has the right to request demonstration of the integrity of any isolation.
The Performing Authority will ensure that they have witnessed, at the point of work,
that the conductors are dead. The Performing Authority may complete this task
themselves if suitably authorized.
3.6
Responsible Electrical Person (REP)
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 8 of 32
This is a role under the „safe system of work‟ or „permit to work system‟ to clearly
identify which authorized person has the responsibility for the electrical system, the
REP is nominated by the SM / SC / OIM from those persons having the highest level
of authorization required for that site / installation and assessed by site Electrical
Technical Authority or delegate.
The REP will:
 Approve any switching programs
 Countersign permits with electrical content where the Area Authority isn‟t
electrically competent, ensuring that the isolation has been correctly designed
and the Isolating Authority has the appropriate authorization level for the work
 Assess and recommend site personnel for authorization to AEP, AIP, CI
At any one time there can be only one REP on site. The REP may also be the
isolating authority.
3.7
Electrical Technical Authority (ETA)
The Electrical Technical Authority is an Electrical Engineer who is recognized by
management as the site technical authority. The technical authority or their delegate
assesses and recommends site personnel for authorization to SAEP and will assess
and recommend personnel for the role of REP.
3.8
Senior Authorized Electrical Personnel (SAEP)
Electrical personnel who have been formally assessed by the site Electrical
Technical Authority or delegate and authorized by the SM / SC / OIM to switch,
isolate and test electrical equipment with voltage levels up to, and greater than
1000V, can act as an isolating authority under the safe systems of work for electrical
systems with voltage levels up to and greater than 1000V.
3.9
Authorized Electrical Personnel (AEP)
Electrical personnel who have been formally assessed by the site REP and
authorized by the SM / SC / OIM to switch, isolate and test electrical equipment with
voltage levels less than 1000V, can act as an isolating authority under the safe
systems of work for electrical systems with voltage levels less than 1000V.
3.10 Authorized Instrument Personnel (AIP)
Instrument personnel who have been formally assessed by the site REP and
authorized by the SM / SC / OIM to switch, isolate and test control, instrument and
telecom equipment with voltage levels less than 50V, can act as an isolating authority
under the safe systems of work for control, instrument and telecom systems with
voltage levels less than 50V phase to earth.
3.11 Competent Isolator (CI)
In special circumstances individuals can be assessed as competent isolators by the
site REP with agreement of the ETA and authorized by the SM / SC / OIM specific
items of equipment providing that they have completed the formal training and have
been assessed as competent.
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 9 of 32
3.12 Competent Person (CP)
An essential requirement for persons undertaking electrical work is that they are
competent, established by virtue of training and or experience. A competent person
is capable of recognising danger and knows when to seek guidance when the work
falls outside their area of competence.
The employing company will certify competency of the employee and will supply BP
with copies of their competence assessment as required. The AzSPU certifies the
competence of its own employees using CMAS.
4
Self-regulation and Audit
Business Units shall periodically review isolation related activities, including review of
individual isolations and review of overall isolation processes. Such reviews may
also include:
 General compliance with this document and any local procedures
 The assessment of non-compliant isolations and the extent of any approved
deviations
 Registers of competent and authorized persons
5
Isolating Authority - Training, Competency and Authorisation
The Isolating Authority will be authorized by SM / SC / OIM based on the following
criteria.
The Isolating Authority will be:
 Familiar with the site / installation
 Have Electrical First Aid Training
 Will be EX certified, when working on Hydrocarbon Plants
 Where appropriate, will have HV operational training
 Will have been formally and practically assessed for electrical isolations and
recognised as authorized at a specific voltage level for the work site
 The Authorisation levels on site will be as follows:
o Authorised Instrument Person (AIP) authorised to isolate instrument circuits
up to 50V
o Authorised Electrical Person (AEP) authorised to isolate electrical circuits
up to 1000V
o Senior Authorised Electrical Person (SAEP) authorised to isolate electrical
systems above 1000v and prepare and carry out switching operations
In special circumstances individuals can be assessed as Competent Isolators (CI) for
specific items of equipment providing that they have completed the formal training
and have been assessed as competent on the specific tasks. Site management is
responsible for ensuring that this is recorded so that it is clear which tasks these
individuals are competent to undertake.
6
Modification and New Facilities
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 10 of 32
In relation to existing Installations and sites:
 The design of all modification and new facilities shall include a review of the
provision of means of isolation for maintenance to ensure compliance with this
document
 Such reviews shall address both isolations within the modified/new facilities
and any opportunities to upgrade existing isolation facilities where these are
inadequate
 New isolators supplied as part of a modification or as a replacement shall be
provided with a facility to be locked off.
7
Isolation and Planning
7.1
Isolation
The highest quality and security of isolations, which is reasonably practicable in the
prevailing circumstances, shall always be used. This document sets out the
minimum recommended isolation standard to be used in the Azerbaijan Strategic
performance Unit.
Any isolation, which does not meet the Minimum Recommended Isolation Standard
as defined in section 7.5, including the application of the Mandatory Safeguards,
must be assessed using the Level 2 Risk Assessment Process before the isolation is
approved. Should any non-compliant isolation have to be repeatedly justified by risk
assessment, consideration shall be given to a permanently engineered solution.
All key participants in the implementation of the BP Isolations Policy shall be trained
and assessed as competent to the appropriate level in the Electrical Isolation
Standard.
An audit programme shall be established by the SM / SC / OIM at each site to ensure
that regular checks are made on isolations to provide assurance that the isolations
policy and standards are being applied and that lessons learned are communicated
effectively.
7.2
Isolation Planning
Isolation of any piece of equipment shall be planned to minimize risk to personnel,
property and production. To achieve this, the following information will be required:
 A clear description of the work, ensuring that if the activity includes electrical
work that this is clearly identified
 A clear description of the equipment which needs to be isolated, this will
include the Plant Tag Number and the Plant Tag Description
 A drawing identifying the isolation, earth and disconnection points where this is
not obvious
 Tag references of all the switching and isolation points
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 11 of 32
 Locks and Labels for securing the isolation points
 Test equipment for proving effectiveness of the isolation
 Switching program detailing the sequence of switching required to achieve the
isolation where the equipment is fed from more than one source or at the
REP‟s discretion.
7.3
Switching Programmes
Where main distribution equipment is to be switched it is essential that the equipment
be switched in the correct sequence. To achieve this, a switching programme will be
required, detailing the switching sequence. This will be accompanied by a marked
up single line drawing. An HV switching programme will be prepared by an SAEP
and checked by the REP. Where the REP is alone on site, the site electrical
technical authority will check the switching program. Technical advice will be sought
as required. See Appendix C for a blank Switching Programme. The Switching
Programme does not replace an ICC.
7.4
Isolation Methods
The highest quality of isolation, which is reasonably practicable, shall be applied to
every individual isolation point. The methods of isolation normally available are
detailed below; listed in descending order of security and effectiveness. The key to
all of these isolations is the positive identification of the equipment to be isolated, to
this end all equipment and isolation points on a site will be uniquely identified and
clearly labelled, a secondary check could be to use the cable numbers which connect
the isolator to the equipment. If there is any doubt about the correct identification of
the equipment to be isolated and the isolation point then the work should be
suspended and clarification sought.
(a)
Isolate Circuit, Prove Dead, Disconnect, Lock, Label and Earth
This is a positive isolation of the main phase conductors with an isolator and
disconnection of the main phase and neutral conductors by removal of fuses, links or
withdrawal of a circuit breaker or some other means of disconnection. The circuit is
proven dead to ensure that the circuit is discharged and is earthed to prevent
recharging. Locks and labels are applied to all points of isolation and earthing
Note: When the isolation requires switching of main distribution equipment, a
Switching Program is also required.
(b)
Isolate Circuit, Prove Dead, Disconnect, Lock and Label
This is a positive isolation of the main phase conductors with an isolator and
disconnection of the main phase and neutral conductors by removal of fuses, links or
withdrawal of a circuit breaker or some other means of disconnection. The circuit is
proven dead to ensure that the circuit is discharged. Locks and labels are applied to
all points of isolation.
Note: Where the isolation switch meets the minimum standard for disconnection, as
defined in IEC
60947, and it includes all phases and neutral then no further
disconnection is necessary if the risk of physical disconnection outweighs the
advantage. However, this is a minimum standard and it is expected that if fuses or
links are part of the circuit that they will be removed.
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 12 of 32
(c)
Isolate, Lock and Label (not suitable for electrical work)
This is a positive isolation of the main phase conductors with an isolator; the isolator
type will be of such construction that it breaks the main phase conductors when
open. Locks and labels are applied to all points of isolation.
Note: Isolation by auxiliary control circuits only is not acceptable for isolation
purposes.
(d)
Prove Dead, Disconnect, Label
This is a positive isolation typically used for isolating instruments where there is no
lockable isolator. It is required that the circuit cable cores are disconnected from the
terminal rail and terminated into a temporary terminal block with isolation labelling at
the disconnected cores.
General Note:
When completing the isolation confirmation certificate for reasons of clarity the check
block should be completed with YES when:
Isolated
When the isolation point has been isolated to the
approved standard as defined in this document
Fuse Removed
When at the isolation point Fuses or Links have
been removed
Disconnected
When at the isolation point a cable is removed ( the
isolation point tag reference will be the termination
point of the cable and the cable number)
Earths
When any earth is applied
( the isolation point tag
reference will be the earth application point)
Proved Dead
When a point in the circuit has been positively
proven dead as defined in this document ( the
isolation point tag reference will be the prove dead
test point)
Label
When a label has been applied to the isolation
point
Locked
When a lock has been applied to the isolation point
7.5
Isolation Standards
Operating Voltages
Isolation requirements for:
<50V
>50V < 1000V
>1000V
Non-electrical work only
N/A
Is+LL
Is+LL
Electrical work on single
circuit
Is+P+D+Label
Is+P+D+LL
Is+P+D+LL+E
Electrical work on distribution
SP+Is+P+D+L
SP+Is+P+D+LL
system
N/A
L
+E
Note 1:If any work requires Proving Dead in a Hazardous Area, a gas monitor will
be required with a Hot Work 2 (Spark Potential) Permit.
Note 2:If any work is done adjacent to live conductors then this must be considered
when providing the isolation.
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 13 of 32
Is - Isolation of the main phase conductors with an isolator
LL - Lock and labelled
D - Main phase and neutral disconnected
P - Prove dead with an approved voltage tester which is proved before and after
testing
E - Earth the isolated conductors
SP - Authorized Switching Programme
Precautions
<50V
>50V < 1000V
>1000V
SAEP or AEP
under
direct
Authorisation level required to
AIP,
AEP,
supervision of
perform the isolation
SAEP
AEP, SAEP
SAEP
Accompanied for proving
AEP, SAEP
dead, distribution switching,
based on Risk
testing, fault finding
No
assessment
SAEP
Communications link
Yes
Yes
Yes
Nomex gloves or leather
gauntlets
No
Yes
Yes
Note 3:If work is to be accompanied there must be a clear understanding between
the Isolating Authority and the accompanying person identifying what the
accompanying person will do in the event of an emergency.
Note 4:Competent Isolator perform isolations for the specific equipment and voltage
that they have been authorised for
Table 1: Minimum Recommended Isolations Standard
7.6
Risk Assessment of Non-compliant Isolations
In the event that the Minimum Recommended Isolation Standard cannot be
achieved, a Risk Assessment shall be carried out in accordance with SSOW
guidelines
The assessment team, including the REP shall specify appropriate safeguards, which
may replace or be in addition to those listed in Table 1. The team shall be satisfied
that these safeguards shall reduce the risks to an acceptable level before the task
requiring isolation is permitted to proceed.
The SM / SC / OIM must authorize all level 2 risk assessments prior to any work
proceeding.
7.7
Live Working
Live working is defined as work on or in close proximity to live conductors; this
includes testing.
All conductors will be assumed live unless proven dead. (See section 8.9)
Live work will not be a normal activity and will not be carried out unless there is no
other reasonably practicable method available. Where it is not possible to avoid live
work, an appropriate level of risk assessment shall be carried out before work
commences.
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 14 of 32
Is the live working justified? Consider:
 If the work could be done when equipment is isolated (an example of work
which must be done live would be work on battery systems)
 If isolating the equipment introduces other greater safety risks
 When identifying the risks consider:
 Voltage level
 Fault level of the equipment and the arc energy if a fault develops while
working
 Working environment (wet, dusty, noisy, vibration, at height etc)
 What exposed voltage levels will be adjacent to the worksite
 What could go wrong
Can adequate precautions be taken to reduce risk to an acceptable level? Some
precautions, which should be considered:
 Competent people with training and experience
 Insulated tools and test equipment
 Accompanied work - Accompanying person to be First Aid Trained and it
should be clear what is expected of the accompanying person to ensure that
they are competent to accomplish this expectation
 Insulated barriers, mats, grab hooks
 Work site control (e.g. cordoning off area, limiting access)
 Additional and / or specialist personal protective equipment
 Reference to any specific safety rules or guidance
See Appendix F for a flowchart covering the Control of Electrical Work.
Isolations for Work Near Live Conductor
Frequently, work inside of complex control equipment means that although the circuit
to be worked on is isolated, there may be other circuits that are still energised. It is a
requirement that the risk from these adjacent conductors is assessed and
appropriate precautions taken to reduce the risk.
See Appendix B for an adjacent working assessment form.
8
Isolation Implementation and Control
8.1
Security
Any isolation must effectively disconnect the worksite from all sources of energy.
Locks must be used to prevent unauthorized de-isolation; to this end unique locking
devices must be used. Keys to any locks used for isolation purposes must be
effectively controlled via the Area Authority and the Permit to Work
- Isolation
Confirmation Certificate (ICC). Only when the ICC allows should the Area Authority
make the key available to remove a lock.
The locks should be a high security type, which are tamper proof. See appendix D.
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 15 of 32
8.2
Isolation Labelling
All isolation points shall be clearly identified, tagged and recorded on the ICC.
Where not obvious, a drawing should be attached to the ICC showing the location of
each isolation and earth point (where applied).
At the isolation point there should be a Yellow Isolation Label with the following
clearly identified:
 ICC number
 The Tag number of the isolation point
 Reason for isolation
 Isolation Authority name and signature
 Date
At the Earth point there should be a Green Earth Label with the following clearly
identified:
 ICC number
 The Tag number of the isolation point
 Reason for isolation
 Isolation Authority name and signature
 Date
Adjacent live circuits will be identified with a Red Danger notice, e.g. live bus bar
shutters when work is to be carried on the circuit.
See Appendix G for labels
8.3
Positive Identification of Equipment
To allow effective isolation, equipment must be clearly labelled with unique tag
numbers. If equipment is not tagged then another method of positive identification of
equipment must be used, e.g. use of the cable number and cable schedule and
interconnection drawings. These provide a unique number, which should be located
at each end of the cable. If there is any doubt about the correct identification of the
equipment to be isolated and the isolation point, then the work should be suspended
and clarification sought.
8.4
Control of Isolations
The ICC, cross-referenced to all relevant work permits, shall be the principal means
of control once isolations are in place. The ICC performs the following functions:
 Identifies the plant concerned and the reasons for isolations
 Authorises isolation by disciplines
 Records the complete list of isolation points
 Records „prove dead‟ operations
 Records the position of any earths applied
 Records locking points and lock numbers
 Records where isolation labels have been applied
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 16 of 32
 Confirms that the isolation has been effected
 Authorises any temporary de-isolations and isolations necessary for testing
(sanction for test)
 Authorises and records de-isolations on completion of the task
 The Area Authority must effectively control all keys for locks used for isolation.
8.5
Operational Locks
Operational Locks will be used as required on switchgear to ensure that normal
operating standards are maintained. These locks will be kept in the switch rooms in
lock cabinets where only appropriately authorised competent personnel will have
access.
An example of this would be manual close buttons on switchgear, which will normally
be locked for operational purposes and unlocked for maintenance or for transformer
offload tap changers.
Appendix: D shows an example of an operational locking system, which could be
used for the control of locks.
8.6
Boundary Isolations
Where an area of plant is isolated such that several activities (typically construction
work) can safely take place within this common set of strategically placed isolation
points then this can be termed as a „Boundary Isolation‟. It must be clearly identified
that the isolation is appropriate for all the individual tasks to be carried out within the
Boundary Isolation and all individual Work Permits are cross-referenced to this
Boundary Isolation.
If any of the proposed tasks require a level of isolation or implementation of control
measures greater than that covered by the Boundary then a separate Isolation
Confirmation Certificate should be raised for this task.
Thorough planning and preparation is essential when planning Boundary Isolation. A
team including the Area Authority and Isolating Authority and any additional technical
support required should be set up away from the work place to properly review and
agree the scope of the Boundary Isolation and the tasks to be carried out.
Once work is in progress and subsequent Work Permits are applied for within the
recognised framework of the Boundary Isolation, they can be added providing it is
clearly established that the existing isolation is appropriate to the task. However, this
should be avoided if possible and it is preferable to identify all activities when the
Boundary isolation is being planned.
Boundary Isolations shall not be removed until all applicable Work Permits have been
cancelled.
If, for any reason, work on a particular piece of plant within the Boundary needs to be
suspended
(e.g. whilst awaiting spares) then a separate isolation shall be
implemented and an ICC raised before the Boundary Isolation can be cancelled and
confirmation that the installation can be energised safely.
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 17 of 32
Where the de-isolation of the Boundary Isolation is proposed, the Area Authority shall
ensure that all associated Work Permits have been cancelled. He/she should also
ensure that equipment within the boundary is in safe condition.
8.7
Long-Term Isolations
Long-term Isolations (LTI) are defined as those that no longer have work performed
against them. Each site should maintain a detailed register of long-term isolations
with a reason why they are in place.
Long-term isolations shall be subject to two levels of review:
 A weekly review of the register to check the status of the isolations in place
 A quarterly review to physically check all the isolation points to confirm their
security and integrity and that the keys to all locks are being adequately
controlled
 If the LTI is in place for more than 1 year, review the requirement for LTI.
Consider if something else could be done (i.e. decommission circuit)
Before any work is performed against a long-term isolation a full integrity check of all
isolation points is required and the point of work must be proven dead.
Before an electrical LTI is removed a physical check of the equipment to be
energized will be made to ensure that the equipment is safe to energize.
8.8
Personal Isolations
Personal isolations are intended for short-duration tasks of relatively low risk. For
example, when work is required on a single motor feeder circuit or other such tasks
where the completion of an ICC is considered to add no significant value in terms of
risk reduction. The use of personnel isolation may only be authorized by the Area
Authority on the permit to work. The rules for approval of a personal isolation are as
follows:
 One person within one shift performs the task and isolation; the person may
receive assistance from others but he/she shall be present at all times when
work is in progress
 Before approval, the Area Authority must be satisfied with the competence of
the Performing Authority and check that they have sufficient authorisation to
both carry out the isolation and execute the work. Personal isolations shall
only be carried out by those deemed to be a competent Isolating Authority
 The same isolating standards apply to personal isolations other than the
completion of the ICC
 The isolation points shall be labelled with an isolation label (which includes the
date, the name of the person isolating and the task information) and locked
(the Performing Authority must keep effective control of keys to isolation locks)
 If the worksite is left unattended, the plant shall be left safe, with all covers or
barriers in place
 The personal isolation is authorised on the work permit
An ICC shall be raised if any of these conditions cannot be met or conditions change
during the work activity.
Personal isolations are not allowed on the following:
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 18 of 32
 High Voltage
 Safety systems e.g. Fire and Gas or Emergency Shutdown (ESD) panels or
sections thereof
 Equipment fed from more than one source
8.9
Testing Isolation Integrity - Proving Dead
All electrical conductors shall be considered to be live until positively proven dead
using an approved live line tester suitable for the voltage to be tested; this tester will
be proved both before and after use. The conductor will be proven dead between
circuit and earth. Where there is a neutral or the system is unearthed the conductors
will also be proven dead between all of the circuit conductors. It is a requirement
under the BP Golden Rule of Energy Isolation that energy has been discharged and
that testing has proved the isolation.
The Performing Authority will be required to witness this test or prove dead
themselves before commencing work on any conductor.
It is essential that after testing with an applied voltage, a conductor be adequately
discharged to earth using approved discharging equipment. Once discharged, the
conductor is again proven dead.
Proving Dead is considered to be live working and therefore each location must
assess the risks of this activity based on sited conditions and produce a standalone
risk assessment, which covers this activity. The understanding of these precautions
will form part of the authorisation process for the site.
8.10 Monitoring Isolation Integrity
Locks and effective control of their keys maintain the integrity of electrical isolation.
An isolation lock may not be removed unless written permission is given on its ICC. A
lock may not be removed by any other means than the key. If for any reason the key
is not available, the Area Authority, Responsible Electrical Person, Isolation Authority
and Performing Authority must apply in writing to the OIM / Site Manager / Site
Controller for permission to remove the lock.
Where possible, a multi-hasp device will be used to allow for more that one padlock
at each isolation point.
If the integrity of the isolation requires the use of barriers or shields then their
condition will be checked before the start of any work activity.
9
De-isolation of Plant
Before plant is de-isolated the Area Authority shall ensure that all work is complete,
all permits are cancelled, all covers and safety barriers have been replaced, the plant
has been tested and inspected and any relevant certification is completed. When the
Area Authority is satisfied and has checked that there are no other permits cross
referenced to the isolation, he will instruct the Isolation Authority to de-isolate the
plant.
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 19 of 32
In a Hazardous Areas before de-isolation, the plant must be inspected to ensure that
the equipment meets the requirements to prevent danger in the hazardous area,
commonly know as an EX inspection.
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 20 of 32
Flow Sheet Electrical Isolations
AA REQUESTS
ISOLATION
ELECTRICAL/ INSTRUMENT
NON-ELECTRICAL WORK
WORK
WHAT TYPE
OF ISOLATION?
POSITEVELY IDENTIFY
EQUIPMENT, PREPARE
>1000V
<50V
WHAT VOLTAGE
ICC, ISOLATE CIRCUIT
LEVEL?
NO
LOW ENERGY?
>50 & <1000
LOCK AND LABEL
COMPLETE ICC,
NO
SINGLE
YES
RECORD ISOLATION IN
CIRCUIT
SWITCHROOM LOGBOOK
ISOLATION?
POSITEVELY IDENTIFY
EQUIPMENT, PREPARE
PREPARE
ICC, ISOLATE CIRCUIT
AND
YES
NO
SINGLE
APPROVE
CIRCUIT
ISOLATION?
SWITCHING
PROGRAMME
PROVE DEAD
PREPARE
AND
APPROVE
SWITCHING
POSITEVELY IDENTIFY
PROGRAMME
EQUIPMENT, PREPARE
LOCK OR DISCONNECTOR
CONTUCTORS AND TERMINATE IN
ICC, ISOLATE CIRCUIT
TO CHOC BLOC AND LABEL
POSITEVELY IDENTIFY
PROVE DEAD WITH
COMPLETE ICC
EQUIPMENT, PREPARE
APPROVED TEST UNIT
ICC, ISOLATE CIRCUIT
PROVE DEAD AT
DISCONNECT BY
POINT OF WORK
REMOVING FUSES AND
LINKS (INCL. NEUTRAL)
Motor contactor
NO
or auto circuit
earth
LOCK AND LABEL
PROVE DEAD WITH
YES
APPROVED TEST UNIT
COMPLETE ICC,
RECORD ISOLATION IN
SWITCHROOM LOGBOOK
EARTH CIRCUIT
LOCK AND LABEL
PROVE DEAD AT
ALL ISOLAION POINTS
POINT OF WORK
COMPLETE ICC,
RECORD ISOLATION IN
SWITCHROOM LOGBOOK
PROVE DEAD AT
POINT OF WORK
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 21 of 32
Appendix A: Applicable to
This document applies to the following job functions:
Area Authority
Authorized Electrical Personnel
Authorized Instrument Personnel
Azerbaijan Strategic Performance Unit Leader
Document Controller
Electrical Technical Authority
Isolating Authority
Site Manager / Site Controller / Offshore Installation Manager
Operations Engineer
Performing Authority
Responsible Electrical Person
Senior Authorized Electrical Personnel
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 22 of 32
Appendix B: Adjacent Working Assessment
ADJACENT WORKING ASSESSMENT
(working adjacent to live conductors)
Sketch of Working Area
Is working position marked on sketch?
YES
NO
Is the working area clear and free of debris?
YES
NO
Are live adjacent voltages marked on sketch?
YES
NO
Is shrouding IP rating marked on sketch?
YES
NO
Size of smallest loose conductive component to be worked with?
mm
Is the IP rating below the working area adequate to prevent any loose
YES
NO
components being worked with falling on to live components?
Is the min IP protection IP2X or more?
YES
NO
Position:
Date:
Name:
Signature:
 If any of the above are answered with “NO”, then please review work with REP
IP Classification list overleaf
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 23 of 32
ADJACENT WORKING ASSESSMENT
(working adjacent to live conductors)
IP - INGRESS PROTECTION
The IP classification system designates, by means of a number, the degree of
protection provided by an enclosure against impact or dust and water ingress.
Please note that the IP classification should not be construed as indicating corrosion
resistance.
Degrees of Protection to IEC 529
IP Classification list
IP0X
Non-protected.
IP1X
Protected against a solid object greater than 50mm, such as a hand.
IP2X
Protected against a solid object greater than 12mm, such as a finger.
IP3X
Protected against a solid object greater than 2.5mm, such as a tool or wire.
IP4X
Protected against a solid object greater than 1.0mm, such as wire or
thin strips.
IP5X
Dust-protected. Prevents ingress of dust sufficient to cause harm.
IP6X
Dust tight. No dust ingress.
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 24 of 32
Appendix C: Switching Programme
Site:
ICC number
WCC number
Reason for switching:
Ref Drw no:
Electrical Key Single Line Diagram
Date of switching:
Item
Voltage
Switchboard
Cub/ Cir
Action
Comments
By
Ref.
Prepared by
Date:
Checked by
Date:
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 25 of 32
Appendix D: Operational Locking System
Locking system for electrical equipment after energization covering operations
and isolation control
Operational locks
Each switchboard will have a locking suite of unique locks for each locking point on
the switchgear these will be housed in a lock cabinet within the switch room. Access
to the locking suite will be controlled to suitably authorized persons.
The locks should be a high security type, which are tamper proof. (an example of such a
lock is the ABLOY high security padlocks). There should only be one key that fits a lock
in the isolation system (any spares or masters are to be removed and controlled by the
site manager who should only issue these keys after the REP has made a formal request
in writing)
AUTHORIZED ACCESS
ACCESS
AIP
AEP
SAEP
HV switchboard locking suite
NO
NO
YES
SINGLE CIRCUITS
LV switchboard locking suite
NO
YES
YES
SINGLE CIRCUITS
Control locks
YES
YES
YES
Operational Locking
Operational locks will normally be applied to:
Local remote switches
Manual close switches on circuit breakers
Earth switches
Racking mechanisms
The keys to these locks will be kept with the locking suite for the switchboard.
Isolation Locking
When the Area Authority requires an isolation to be locked off, a lock and key will be
taken from the switchboard-locking suite that the isolation is required for. Where
possible a multi-hasp will be used and the lock and label will be applied.
Once the locks are in place the keys will be returned with the ICC to the Area
Authority who will control the keys until a de-isolation or a sanction to test has been
approved.
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 26 of 32
Appendix E: Control of Electrical Work
START
ROUTINE
MODIFICATION
FAULT REPORT
MAINTENANCE
REFER TO PMP
SHEETS
IDENTIFY AND DOCUMENT THE EQUIPMENT, SCOPE OF WORK AND
CIRCUITS TO BE WORKED ON
ARE THE
IS
ENVIRONMENTAL
THERE A
OR CLIMATIC CONDITIONS
POTENTIAL FOR
NO
CONSIDERED APPROPRIATE TO
COMMING INTO CONTACT
ALLOW THE WORK TO BE
WITH VOLTAGES
CARRIED OUT SAFELY.
ABOVE THOSE
I.e. WET CONDITIONS
IN BOX
OR LOCAL TO ANY
A
GAS RELEASE.
YES
YES
NO
BOX A
IS THE
CIRCUIT BEING
CAN
WORKED ON, PART OF A
IDENTIFY AND ASSESS
DECIDE
NORMAL
CONTROL OR TELECOMMUNICATION
REFER TO
RISKS AND METHODS
WHETHER IT
POLICY OF
NO
PLANT OPERATING AT LOW
LIVE WORKING
FOR CONTROLLING THEM
IS REASONABLE
DEAD WORKING
VOLTAGES (<50v
PROCEDURE
CONSIDER ISOLATING
TO WORK
BE CARRIED
BETWEEN ELECTRICAL
NO
ADJACENT CIRCUITS
LIVE
OUT
CONDUCTORS AND
EARTH)
YES
NO
WORKING DEAD
DEAD WORKING
NO
NECESSARY
DEFINE CIRCUIT
ISOLATION POINTS
DECIDE
WHETHER SUITABLE
PRECAUTIONS CAN BE
YES
LIVE WORKING
TAKEN TO PREVENT INJURY
PERMITTED
(SHOCK, BURNS OR
IGNITION SOURCES)
SPECIFY SYSTEMS OF WORK
CUT OFF SUPPLY AND
REFER BP
ISOLATE SECURE ISOLATION
PROCEDURES
SECURE KEYS AS PER
SPECIFY LEVEL OF SUPERVISION
SSOW SYSTEMS
AND WHETHER ACCOMPANIMENT
NECESSARY
REFER HS (G) 85
POST WARNING SIGNS
NOTE 1
AS REQUIRED
NO LIVE WORKING TO TAKE PLACE ON
SYSTEMS OVER 750 VOLTS
EXCEPT FOR DIAGNOSTIC TESTING AND PROVING DEAD
SELECT ACCESSAND INSTRUCT
COMPETENT PERSONS
ENSURE CIRCUIT OR EQUIPMENT
DEAD. IN APPROVED MANNER
Procedure for Energy Isolation - Electrical
Page 27 of 32
Appendix F: Labels
ISOLATION
NOTICE
REASON FOR ISOLATION:
ISOLATION
NAME
POINT
TAG No
SIGNED
DATE
ICCNo
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 28 of 32
EARTH
NOTICE
CIRCUIT MAIN
ADDITIONAL
REASON FOR EARTH:
ISOLATION
NAME
POINT
TAG NO
SIGNED
ICC No
DATE
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 29 of 32
DANGER
NOTICE
LIVE EQUIPMENT
DO NOT INTERFERE WITH THIS EQUIPMENT
REASON FOR DANGER NOTICE:
NAME
SIGNED
DATE
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 30 of 32
Appendix G: Procedure Summary
¾ The same isolating standards apply to personal
Isolation Standard Summary
isolations other than the completion of the ICC
Operating Voltages
¾ The isolation points shall be labelled with an isolation
Isolation
>50V <
ENERGY ISOLATION (electrical)
requirements for:
label (which includes the date, the name of the person
<50V
1000V
>1000V
isolating and the task information) and locked
(the
Non-electrical
General Requirements
Performing Authority must keep effective control of keys
work only
N/A
Is+LL
Is+LL
This Safe System of work defines the Azerbaijan Business
to isolation locks)
Is+P+
Unit functional standard for the safe isolation of electrical plant
¾ If the worksite is left unattended, the plant shall be left
Electrical work on
D+Lab
Is+P+D+
Is+P+D+LL+
or equipment from sources of electrical energy.
safe, with all covers or barriers in place
single circuit
el
LL
E
¾ The personal isolation is authorised on the work permit
BP Golden Rule
Electrical work on
SP+Is+P
SP+Is+P+D+
Energy Isolation is one of BP‟s Golden Rules of Safety and
An ICC shall be raised if any of these conditions cannot be
distribution system
N/A
+D+LL
LL+E
states:
met or conditions change during the work activity.
Note 1: If any work requires Proving Dead in a Hazardous Area,
a gas monitor will be required with a Hot Work 2 (Spark Potential)
Any isolation of energy systems, e.g. mechanical, electrical,
Personal isolations are not allowed on the following:
Permit.
process, hydraulic, pneumatic, gravitational, chemical,
Note 2: If any work is done adjacent to live conductors then this
radioactive, thermal, or other energy source that could cause
¾ High Voltage
must be considered when providing the isolation.
injury, cannot proceed unless:
¾ Safety systems e.g. Fire and Gas or Emergency
Shutdown (ESD) panels or sections thereof
Is - Isolation of the main phase conductors with an isolator
¾ The method of isolation and discharge of stored energy
¾ Equipment fed from more than one source
LL - Lock and labelled
are agreed and executed by a responsible person
D - Main phase and neutral disconnected
¾ Any stored energy is safely discharged
ICC
P - Prove dead with an approved voltage tester which is
¾ A system of locks and tags is utilized at isolation points
General Note: When completing the isolation confirmation
proved before and after testing
¾ A test is conducted to ensure the isolation is effective
certificate for reasons of clarity the check block should be
E - Earth the isolated conductors
¾ Isolation effectiveness is periodically monitored
completed with YES when:
SP - Authorized Switching Programme
Isolated
When the isolation point has been
>50V <
Isolation Standard
isolated to the approved standard as
Precautions
<50V
1000V
>1000V
The highest quality of isolation, which is reasonably
defined in this document
Authorisation level
AIP,
SAEP or
practicable, shall be applied to every individual isolation point.
Fuse Removed When at the isolation point Fuses or
required to
AEP,
AEP under
Links have been removed
perform the
SAE
supervision
Personal Isolations
isolation
P
AEP, SAEP
of SAEP
Disconnected
When at the isolation point a cable is
Personal isolations are intended for short-duration tasks of
removed
( the isolation point tag
Accompanied for
relatively low risk. The use of personnel isolation may only be
reference will be the termination point
proving dead,
AEP, SAEP
authorized by the Area Authority on the permit to work. The
distribution
based on
of the cable and the cable number)
rules for approval of a personal isolation are as follows:
switching, testing,
Risk
Earths
When any earth is applied
( the
isolation point tag reference will be the
fault finding
No
assessment
SAEP
¾ One person within one shift performs the task and
earth application point)
Communications
isolation; the person may receive assistance from
Proved Dead
When a point in the circuit has been
link
Yes
Yes
Yes
others but he/she shall be present at all times when
positively proven dead as defined in
Nomex gloves or
work is in progress
this document ( the isolation point tag
leather gauntlets
No
Yes
Yes
¾ Before approval, the Area Authority must be satisfied
reference will be the prove dead test
Note 3: If work is to be accompanied there must be a clear
with the competence of the Performing Authority and
point)
understanding between the Isolating Authority and the
check that they have sufficient authorisation to both
Label
When a label has been applied to the
accompanying person identifying what the accompanying person
carry out the isolation and execute the work. Personal
will do in the event of an emergency.
isolation point
isolations shall only be carried out by those deemed to
Note 4: Competent Isolator performs isolations for the specific
Locked
When a lock has been applied to the
be a competent Isolating Authority
equipment and voltage that they have been authorised for.
isolation point
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Energy Isolation - Electrical
Page 31 of 32
APPENDIX H - Feedback & Improvement Suggestions
Procedure Feedback & Improvement Suggestions
Project Name: ______________________________
Date: ______________________________________
Name:_____________________________________
Badge Number: _____________________________
Procedure Reference: ________________________
Procedure Title: _____________________________
Improvement Suggestions (Write below your improvement suggestions)
Forward your Improvement Suggestion to the HSSE Manager
Signature: _____________
at the Central HSSE Office, Hyatt Tower 2, 6th Floor
Control Tier:
<<2>>
Revision Date: <<18 June 2007>>
Document Number: << AZSPU-HSSE-DOC-00048-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT

 

 

 

 

 

 

 

Content      ..     29      30      31      32     ..