|
|
Note: Although financial information can be included in the MoC this procedure does not cover any financial controls and normal
budgetary processes and controls will apply.
CVP Stages
appraise
select
define
execute
operate
MoC Process
EQ or other
Close
Process
Initiate
Verify
Review
Approve
Authorise
Out
Annual MoC review for each division across the SPU
MoC compliance will be checked across all of the MoC process and system Performance
indicators will be made available for all by the MoC team
review report will be issued to division vice president and any agreed
corrective actions will be entered in Traction ( the action tracking data
base)
4.1
Management of Change Stages
All change goes through six main stages and is coordinated through the process after verify
1.
Initiate - the creation of the MoC this is the responsibility of the initiator who will:
a. Create the eMOC choosing the affected Site and Facility and choose the correct template for the MoC
type process to be followed (the use of a template is a mandatory requirement).
b. Identify the scope of work (identifies the change and describes all work necessary to produce the
change). The scope establishes the tone for the remainder of the planning efforts and therefore
should be sufficiently detailed. (Keep in mind however that being too detailed can be as bothersome
as not providing enough detail).
Note: for DC&I deviations the DWOP reference number shall be included
c. Provide a justification for the work (this section details why the change is required)
d. Provide details of other options considered.
e. Reference any other business process, Engineering Query, Engineering Technical Practice, Drilling
SEQ or DWOP incident report etc, where this is required. (using the TQ/ EQ box in the eMoC
application box)
f.
Identify the Key Change Verifier as per the specific guidance for the MoC type.
g.
Identify other reviewers and approvers, authorizers as defined as a minimum requirement under
each MoC type
h. Suggest a priority as per the definition in this procedure
i.
Attach all relevant documentation as applicable to MoC for information at REV A (more advance
revisions may be issued if available)
2.
Verify - that the change can proceed. This is the responsibility of Key Verifier (as defined in each MoC type) to
ensure that:
a. The change is described clearly and adequately to avoid any possible confusion
b. The justification for the change is clear and adequate
c. That all options have been considered and documented in the MoC (as appropriate)
d. That the budget is approved and a cost center is identified (as appropriate)
e. Any post start up reviews that may be required to assess the success of the change (as appropriate)
have been identified.
f.
All persons who are required to execute various stages of the MoC have been identified
g.
The priority level as per the IFP matrix
h.
The person who is responsible for the detailed design has been identified and ensure that a full
design work pack has been assembled and attached, with all documents marked up REV A, dated
and signed (more advance revisions may be used if available)
i.
The full scope of work is agreed and appropriate documentation has been identified.
AzSPU-GEN-PRC-001-A2
Page 9 of 102
j.
Any hazards and risks associated with, the change as per the OMS requirements and confirm or
change the risk level (this includes deviations from company or industry standards or practices and
any compliance issues.
k. If the change is to be rejected then the key verifier will cancel the MoC giving a reason
3. Review - confirm that the detail is complete, correct and suitable, it is the responsibility of the reviewers to:
a. Review the change for major hazard, safety or operability issues, and check that key design
documents have been provided appropriate for the risk level and MoC type.
4. Approve - the change for implementation on the site, the approver will
a. Ensure the appropriate process has been followed and will approve the work for implementation
b. Approve the budget for any procurement actives, if procurement starts before the MoC is approved
then this is done as a deviation from this procedure and is at the budget holders risk.
5. Authorize - the change for startup/ use on site, the authorizer will
a. Ensure that all pre implementation actions have been completed to their satisfaction and that it is
safe for use/ startup.
6. Close out - close out the change, the closer will
a. Ensure that all post implementation actions have been closed to their satisfaction
Coordination of the MoC will be the responsibility of the coordinator whose responsibility is to work with all those
who are involved in the MoC to ensure that the MoC follows the process correctly, that all the correct information is
available, clearly identified, filed and that pre and post implementation actions are correctly identified and
completed. The coordinator can be changed at the approve stage if the key approver believes that responsibilities
are best executed by another member of the team
The level of assurance will be appropriate to the level of risk associated with the MoC implementation.
Note: For detail see specific guidance given for each change type.
4.2
MoC Compliance Check
A Bi weekly compliance check will be used to confirm that the MoC procedure is being correctly followed, focusing
on:
Level of risk associated with the change.
Appropriate verification, review, approval, authorization and close out of the change.
Overview of all MoC Key Indicators.
Note: This is the responsibility of the MoC team to gather and present this information
Document number
Document Title
Applies to
Notes
MOC-FRM-023
MOC AUDIT TEMPLATE
AZSPU
Used to consistently audit MoC implementation
The MoC system team leader in consultation with the Functional Vice President and the Engineering Authority will
organize an annual audit of MoCs passed the approved stage
Note: MoCs at the earlier stages of the MoC process are going through the normal verify and review processes for quality and
accuracy and should not be audited while still under the early stages of development
The compliance check team as a minimum will consist of
TL - MoC system team leader.
Persons who can independently audit the MoC
Person with Line responsibility for the Operating area
Site persons affected by the MoC if required
Others if required, as identified by the TL
The Functional Vice President is accountable for ensuring that an appropriate annual compliance check is done for
their areas of responsibility.
AzSPU-GEN-PRC-001-A2
Page 10 of 102
The Engineering Authority is accountable for ensuring that the annually technical audit is completed for MoC (SRP
5.0.0001)
Note: It is recommended that compliance checks are scheduled using the computerized maintenance management system or
some other operating area scheduling tool.
5 Managing Risk
A key component for managing change is to understand the hazards and the associated risks. As the risk increases
the verification process required increases. Specific guidance on risk can be found in the sections for each of the
MoC types.
This procedure identifies the minimum MoC review and approval requirements for the different levels of risk as
defined under each MoC type. In reality the risk will have many different levels. To ensure that risk is appropriately
managed on BP operating areas requires appropriate review and approval by BP competent persons and
management personnel of the site(s) that are affected by the change.
It is the job of the MoC key verifier to ensure that the hazard and risk has been properly evaluated as per OMS
section 3 with the correct personnel around a table and that appropriate reviewers and
approvers have been
identified considering work scopes, competencies and responsibilities.
Hazards and Risk should be considered for Personnel Safety Process Safety
HAZARD & RISK
TOOLS
OMS REF
AREAS
Personal safety
Task Risk Assessment
Process safety
ISD (Inherently Safer Design)
GRP3.1 001
HAZID (Hazard Identification)
WHAT IF
HAZOP (hazard and operability)
LOPA (layer of protection Analysis) MAR (major accident and risk)
PSSR (Pre Start up Safety Review) QRA (Quantified Risk Assessment)
SIL (Safety Integrity Level)
Health and industrial
COSHH Control of substances hazardous to health
GRP 3.4-001
hygiene
OGP/ IPIECA Guide to health impact assessments
GRP 3.4-001
AIHA Exposure assessment process
GRP 3.4-001
HS&E Methods for determination of Hazardous substances
GRP 3.4-001
Fitness for task and health surveillance
industrial hygiene
Asbestos
Fatigue
Security
SIS security of information standard
GRP 3.5-001
DSS Digital Systems and Security
Environment
Emission to air
GRP 3.6-0001
Dischargers to Water and Land
Handling disposal of waste
Transport
MAR major accident risk process
GRP 3.7-0001
Marine operations
GRP 3.7-0002
Travel policy
GRP 5.6-0001
Aviation
Driving safety
Note: See MoC personnel register.
Document
Document Title
Notes
number
Assessment , prioritization
This will be used along with the guidance in each of the MoC
GDP 3.1-0001
and management of risk
type to drive the level of verification required
AzSPU-GEN-PRC-001-A2
Page 11 of 102
Document
Document Title
Notes
number
AzSPU Guidance on Technical
Hazard and Risk Processes to
MoC Appendix 1
Used to assess the MoC risk level
be used within MoC Appendix
1
Segment Recommended
Definitions For Modifications Which Alter The Operation Of
SRP 5.0-0001
Practice for Engineering
Existing Equipment
Management
5.1
Risk Levels
Risk ranking is a GDP 3.1-0001 matrix guided representation of the single most significant risk identified during a
risk assessment of the hazards introduced by the change. This includes design risks and extraordinary
implementation risks.
5.1.1 Insignificant Risk
Do not require an MoC
See the specific MoC decision tree for guidance
5.1.2 Risk level 1- White
Change identified as low risk has little or no impact on process safety or operations (Level 1 White as defined in
the OMS risk matrix (GDP 3.1 001 Annex 3 risk matrix)), no deviation from company engineering standards (ETP or
STP), minor organizational impact and minimal business risk.
See the specific MoC type for minimum sign off requirements
5.1.3 Risk Level 2- Turquoise
Change identified as risk level 2 (turquoise) has minimum impact on process safety or operations (Level 2
Turquoise as defined in the OMS risk matrix (GDP 3.1 001 Annex 3 risk matrix)), may have a degree of technical
complexity and minimal business risk.
See the specific MoC type sign minimum sign off requirements
5.1.4 Risk Level 3 - Blue
Change identified as risk level 3 (blue) has the potential for significant impact on process safety or operations
(Level 3 Blue as defined in the OMS risk matrix (GDP 3.1 001 Annex 3 risk matrix)))), significant organizational impact
or significant business risk.
See the specific MoC type for minimum sign off requirements
5.1.5 Risk Level 4- Purple
Change identified as risk level 4 (purple) has the potential for catastrophic impact on process safety or operations
(Level 4 Purple and above as defined in the OMS risk matrix (GDP 3.1 001 Annex 3 risk matrix))
See the specific MoC type for minimum sign off requirements
6 Priority
Document
Document Title
Notes
number
This tool is the same as the one used for EQ and is used to
MOC-FRM-008
MoC prioritization tool
ensure that all MoCs are consistently categorized and prioritized
Priority ranking is a GDP 3.1-0001 matrix guided representation of the importance of the change. The ranking is
selected from the matrix based on the information provided in the Justification section of the eMOC.
AzSPU-GEN-PRC-001-A2
Page 12 of 102
To assist work prioritization it is mandated that the MoC is given a priority. Prioritization is to be determined using
the IFP prioritization tool which aligns with MAXIMO and EQ.
7 Competency and Training
Competency for MoC has two areas; knowledge of how to use the e-MoC tool, and role knowledge to be able to
execute the intent of MoC
E-MoC Tool.
The tool is a software based system and is relatively intuitive. Online training and assessment will be
required for all new users and recommended for existing users
Additional training will be available on request.
MoC Role Knowledge.
Critical to this process is the Key Verifier who confirms the MoC roles to individuals. They are making the
judgment if the individual has the competency, experience and authority to execute the role as per the
responsibilities identified within the roles and responsibilities list of each MoC type
To assist with this, each area is to have a register of persons that have been assessed as competent to
complete the management of change process as a verifier / reviewer/ approver/ authorizer for each MoC
type and location
Training and assessment is a normal part of role development. It is the responsibility of line management to
assure the competency of their personnel
Persons required to confirm that GOC elements are adequately completed are to have GOC training and
assessment (see MoC type for guidance for which MoC types require GOC)
Note: it is a requirement that those who coordinate technical MoC will have completed GOC training and assessment
Applicable to
This document is applicable to the following job functions:
Note: Due to the range of different job titles within the Operating areas at the time of writing, the Job functions have had to be
rationalized to align the procedure with the e-MoC tool.
MoC Group
Typical Job Function
(DC&I) AFFM
D&C ADVANCE FLUIDS FACILITY MANAGER
KCAD Discipline Responsible Engineers (ELECTRICAL/ INST/ CONTROL/ SIS/ MECHANICAL ETC)
(DC&I) DRE (DISCIPLINE) (KCAD)
(as found in the TA/ DRE register)
(DC&I) DRE (INSTRUMENT/
KCAD Discipline Responsible Engineers (instrumentation / control and safety instrumented system)
CONTROL/ SIS) (KCAD)
(as found in the TA/ DRE register)
(DC&I) EIA
D&C EQUIPMENT INTEGRITY ASSURANCE
(DC&I) EM (DISCIPLINE)
D&C ENGINEERING MANAGER(DRILLING / COMPLETIONS/ INTERVENTIONS ETC)
(DC&I) ENG (DISCIPLINE)
D&C ENGINEER (DRILLING / COMPLETIONS/ INTERVENTIONS ETC)
(DC&I) ENG CHALLENGER
D&C CHALLENGER ENGINEER
(DC&I) ENG Snr (DISCIPLINE)
D&C Senior ENGINEER (DRILLING / COMPLETIONS/ INTERVENTIONS ETC)
(DC&I) ENGINEER (KCAD)
KCAD ENGINEER
(DC&I) ENGINEER (SYSTEMS)
KCAD SYSTEMS ENGINEER (DRILL VIEW ETC)
(KCAD)
(DC&I) ETL (DISCIPLINE)
D&C ENGINEERING TEAM LEADER (DRILLING / COMPLETIONS/ INTERVENTIONS ETC)
(DC&I) HSE TL
HSE TEAM LEADER D&C
(DC&I) MAINT SUPERINTENDANT
KCAD MAINTENACE SUPERINTENDANT
(KCAD)
(DC&I) MAINT
KCAD MAINTENANCE SUPERVISOR
SUPERVISOR(KCAD)
(DC&I) RIG
KCAD RIG SUPERINTENDANT
SUPERINTENDANT(KCAD)
(DC&I) RMS
D&C RIG MAINTENANCE SPECIALIST
(DC&I) RMTL
D&C RIG MAINTENANCE TEAM LEADER
D&C TECHNICAL AUTHORITY ARE EMPLOYED IN VARIOUS ACTIVITIES WHERE APPROVE & TA
(DC&I) TA
WILL BE ADDED BEHIND THE MAIN JOB TITLE
(DC&I) TA INSTRUMENT/
KCAD TECHNICAL AUTHROITY FOR INSTRUMENT CONTROL SAFETY INSTRUMENTED SYSTEMS
CONTROL /SIS (KCAD)
(as found in the TA/ DRE register)
(DC&I) TL ENG (KCAD)
KCAD ENGINEERING TEAM LEADER
(DC&I) TL MAINT (KCAD)
KCAD MAINTENANCE TEAM LEADER
(DC&I) VP & WEA
D&C VICE PRESIDENT & WELL ENGINEERING AUTHORITY
(DC&I) WITL
D&C WELL INTEGRITY TEAM LEADER
(DC&I) WOM
D&C WELL OPERATIONS MANAGER
(DC&I) WSL
D&C WELL SITE LEADER
AzSPU-GEN-PRC-001-A2
Page 13 of 102
MoC Group
Typical Job Function
(DC&I) WSL SNR
D&C SENIOR WELL SITE LEADER
(DC&I) WTL
D&C WELLS TEAM LEADER
ACET Administrator
ACET DATA CONTROL
ACET Systems Lead
(OPERATIONS) AREA INSPECTION AUTHORITY
AIA
(MIDSTREAM SANGACHAL) AREA INSPECTION AUTHORITY
(MIDSTREAM Export systems (Az/ Geo/Turk)); SENIOR ASSET INSPECTION ENGINEER
Area Operations Manager Shah Deniz
Area Operations Manager Azeri
Area Operations Manager DWG/Chirag
AOM
Sangachal Terminal AOM
Azerbaijan Exports AOM
Exports Systems Manager
Base Management Manager
Production and Res Perf. TL
BMM
Manager, Base Management
DWG Base Mgmt TL
DOCUMENT AUTHORITY
Final authority on documentation
Document control will maintain documentation data base (document numbering and version
DOCUMENT COORDINATOR
control)
DOCUMENT CUSTODIAN
Will maintain the document
OWNS THE DOCUMENT AND IS RESPONSIBLE TO ENSURE THAT IT IS APPROPRIATELY
DOCUMENT OWNER
MAINTAINED
DISCIPLINE RESPONSIBLE ENGINEERS (ELECTRICAL/ INST/ CONTROL/ SIS/ MECHANICAL ETC)
DRE (DISCIPLINE)
(as found in the TA/ DRE register)
DRE (ELECTRICAL)
DISCIPLINE RESPONSIBLE ENGINEER ELECTRICAL (as found in the TA/ DRE register)
DRE (INSTRUMENT/ CONTROL/
DISCIPLINE RESPONSIBLE ENGINEER INSTRUMENT / CONTROL / SAFETY INSTRUMENTED
SIS)
SYSTEMS (as found in the TA/ DRE register)
DRE (MECHANICAL)
DISCIPLINE RESPONSIBLE ENGINEER MECHANICAL (as found in the TA/ DRE register)
DRE (PRODUCTION CHEMIST)
DISCIPLINE RESPONSIBLE ENGINEER PRODUCTION CHEMIST (as found in the TA/ DRE register)
E&P VP
EXPLORATION AND PRODUCTION SEGMENT VICE PRESIDENT
EA
ENGINEERING AUTHORITY
CONTROLS THE MASTER EQUIPMENT LIST AS HELD IN EWAREHOUSE
Eng & Data Coordinator
Offshore Data Lead
Project Data Coordinator
ENG DATA COORDINATOR
Eng & Data Coordinator
Eng & Data Coordinator
Eng & Data Mgmt Team Leader
Midstream Data Lead
ENGINEER (DISCIPLINE)
ENGINEERS WITHIN THE ORGANISATION
(OPERATIONS) ABB CONTRACTOR
(MIDSTREAM SANGACHAL) ICSS SPECIALIST
ENGINEER (SYSTEMS)
(MIDSTREAM EXPORTS AZERBAIJAN) ABB CONTRACTOR
(MIDSTREAM EXPORTS AZERBAIJAN) ABB CONTRACTOR
OPERATIONS:
ENVIRONMENTAL ADVISOR (CHIRAG & DWG)
ENVIRONMENTAL ADVISOR (AZERI)
ENVIRONMENTAL ADVISOR (SD & LOGISTICS)
MIDSTREAM Sangachal;
ST ENVIRONMENT ADVISOR
ENVIRONMENTAL ADVISOR
MIDSTREAM EXPORTS AZERBAIJAN;
AZ EXP ENVIROMENT ADVISOR
MIDSTREAM EXPORTS GEORGIA
GEO EXP ENVIRONMENT OFFICER
OPERATIONS:
Offshore installation manager (Azeri/ Chirag & DWG/ SDA)
MIDSTREAM Sangachal:
Operations superintendent (gas / oil/ utilities)
MIDSTREAM Export systems (Az/ Geo/Turk);
Export operations superintendant
Facility Manager
MIDSTREAM Exports Azerbaijan:
PSA2/IPA1 Site Controller
RoW and BV Operations Supervisors
WREP Site Controllers
MIDSTREAM Exports Georgia:
OPERATIONS SUPERVISOR SUPSA TERMINAL
AzSPU-GEN-PRC-001-A2
Page 14 of 102
MoC Group
Typical Job Function
PSG1 & AREA 72 SITE CONTROLLER
PSG2 & AREA 75 SITE CONTROLLER
A80 & EDDF SUPERVISOR
WREP SUPERVISOR GEORGIA OPS PS15, PRS1 PRS2
WREP SUPERVISOR GEORGIA OPS, PS11 PS 13
AGT ROW SUPERVISOR
WREP ROW SUPERVISOR
OPERATIONS:
Offshore operations engineer
MIDSTREAM Sangachal:
N/A facility manager will complete this function
MIDSTREAM Export systems (Az/ Geo/Turk);
Facility Ops Engineer
Operations engineer
MIDSTREAM Exports Azerbaijan:
N/A facility manager will complete this function
MIDSTREAM Exports Georgia:
N/A facility manager will complete this function
OPERATIONS:
OTL (Azeri/ Chirag & DWG/ SDA)
MIDSTREAM Sangachal:
AREA AUTHORITY (OPS SUPER, OIL)
MIDSTREAM Export systems (Az/ Geo/Turk);
Operations engineer (FACILITY MANAGER)
FACITLIY OPS SUPERVISORS
MIDSTREAM Exports Azerbaijan:
PSA2 OPERATIONS SUPERVISORS
IPA1 OPERATIONS SUPERVISORS
RoW and BV Operations Supervisors (FACILITY MANAGER)
WREP Site Controllers ((FACILITY MANAGER)
MIDSTREAM Exports Georgia:
N/A facility manager will complete this function
(OPERATIONS) GOC ENGINEER
(MIDSTREAM SANGACHAL) GOC COORDINATOR
GOC COORDINATOR
(MIDSTREAM EXPORTS AZERBAIJAN) SENIOR GOC ENGINEER
(MIDSTREAM EXPORTS AZERBAIJAN) N/A
H&S Team Leader Shah Deniz
H&S Team Leader Azeri
H&S Team Leader Logistics/Infrastructure
Az Exp H&S Team Leader
H&S TL/ ENV & COMPLIANCE TL
Geo Exp H&S Team Leader
ST Site H&S Advisor TL
H&S Team Leader Chirag & DWG
H&S Team Leader
HR MANAGER
Human resources manager
HR SPECIALIST
Human resources specialist
HSE Compliance Advisors within AzSPU HSE Compliance Team
HSE Compliance Advisor
ST Compliance Advisor
HSE COMPLIANCE ADVISOR
Az Exp Compliance Lead
HSE Compliance Specialist
Offshore Compliance Advisor
Waste Management H&S Advisor
Logistics/Infrastructure H&S Lead
HSEA
Chirag & DWG H&S Advisor
Geo Exp Site H&S Advisor TL
AzSPU-GEN-PRC-001-A2
Page 15 of 102
MoC Group
Typical Job Function
MA
MARINE AUTHORITY
MAINTENANCE ENGINEER IN THE RELIABLITY MAINTENANCE TEAM
MAINTENANCE ENGINEER
IN MID STREAM NOT APPLYING GMS THEN THIS MAY BE THE MAINTENANCE SUPERVISOR
MANAGER
DEPARTMENT MANAGER
MOC/EQ ADVISOR
MOC/ EQ TEAM
MOC SYSTEMS TEAM LEADER
OMA
OPERATIONS MARINE AUTHORITY
RMM
Reservoir Management Manager
SENIOR Inspection Engineer
Senior inspection engineers as contracted
(contractor)
SETA
Global Segment Engineering Technical Authority
SPUL
STRATEGIC PERFORMANCE UNIT LEADER
TECHNICAL AUTHORITY MATERIALS & CORROSION MANAGEMENT (as found in the TA/ DRE
TA (CORROSION)
register)
DISCIPLINE TECHNICAL AUTHORITIES (ELECTRICAL/ INST/ CONTROL/ SIS/ MECHANICAL ETC)
TA (DISCIPLINE)
(as found in the TA/ DRE register)
TA (INPSECTION)
TECHNICAL AUTHORITY INSPECTION (as found in the TA/ DRE register)
TA (PROCESS SAFETY)
PROCESS SAFETY TECHNCIAL AUTHORITY
TA (PROCESS)
TECHNICAL AUTHORITY PROCESS (as found in the TA/ DRE register)
TL
TEAM LEADER
TL- IT&S
IT&S team leader and business information manager
BIM OFFSHORE OPERATIONS AND DRILLING
BIM FUNCTIONS
TL- IT&S BIM
BIM MIDSTREAM
BIM RESOURCES
OPERATIONS:
AESTL (AZERI/ CHIRAG & DWG/ SDA)
DISCIPLINE ENGINEERING TL
MIDSTREAM SANGACHAL:
ENGINEERING MANAGER SANGACHAL TERMINAL
TL-Eng
MIDSTREAM Export systems (Az/ Geo/Turk);
ENGINEERING MANAGER
MIDSTREAM Exports Azerbaijan:
N/A
MIDSTREAM Exports Georgia:
N/A
(COD) ENGINEERING MANAGER (SMALL PROJECTS)
TL-MODS
(OPERATIONS) PROJECTS AND MODS TL
VP
VICE PRESIDENT
DRE (PRISM)
DISCIPLINE RESPONSIBLE ENGINEER FOR PRISM SYSTEMS (as found in the TA/ DRE register)
ENGINEER (PIN)
PIN SUPPORT ENGINEER
APPLICATIONS MANAGER (IT&S)
APPLICATIONS MANAGER (IT&S)
REGIONAL FIELD DIGITAL
INFRASTRUCTURE MANAGER
REGIONAL FIELD DIGITAL INFRASTRUCTURE MANAGER (IT&S)
(IT&S)
MAXIMO maintenance coordinator
MAXIMO maintenance coordinator (activity planning team)
Operations;
Site Scheduler CA
Site Scheduler WA
Site Scheduler EA
Site Scheduler DWG
Site Scheduler CHIRAG
Site Scheduler SHAH DENIZ
MIDSTREAM SANGACHAL;
Site Scheduler
MAINTENANCE SCHEDULER (GAS)
MAINTENANCE PLANNER (OIL)
MIDSTREAM EXPORTS SYSTEMS;
N/A
MID STREEAM EXPORTS AZERBAIJAN
PLANNER / SCHEDULER
MID STREAM EXPORTS AZERBAIJAN
PLANNER
DRE(PROCESS)
DISCPLINE REPSONSIBLE ENGINEER FOR PROCESS (as found in the TA/ DRE register)
TA (PROD CHEMIST & FLOW
TECHNICAL AUTHORITY PRODUCTION CHEMIST & FLOW ASSURANCE (as found in the TA/ DRE
ASSURANCE)
register)
AzSPU-GEN-PRC-001-A2
Page 16 of 102
AzSPU-GEN-PRC-001-A2
Page 17 of 102
8 Abbreviations and Definitions
This table explains any terminology used within the text that is considered to require clarification. This can be useful
in simplifying the text by assigning abbreviations for repetitive terms.
ACC
Authorization for Chemical Change
ADES
Contracting company for Sumgayit Waste disposal Site 2
AWS
Contacting company for Sumgayit Waste disposal Site 2
BHA
Bottom Hole Assembly
BiL
Botas International Ltd - the BTC operator in Turkey
BTC
Baku Tbilisi Ceyhan oil export pipeline
CMMS
Computerized Maintenance Management system
CSM
Contacting company for logistics supply Base at SPS
D,C&I
Drilling, Completions and Interventions
DCT
Digital Communication Technology
DRE
Discipline Responsible Engineer
EA
Engineering Authority
Emergency change
Change which is required for safe operation in these cases a formal MoC will be raised within 96hrs.
e-MoC
Electronic management of change database tool
ESD
Emergency Shut Down
ETP
Engineering Technical Practice
F&G
Fire and Gas
GOC
Guidance on Certification
HAZOP
Hazard and Operability Study
HOD
Head of discipline
HSSE
Heath Safety Security Environment
JP
Job Plan
Maint
Maintenance
MoC
Management of Change
Mods
Modifications
Ops
Operations
P&ID
Piping and instrument diagram
Permanent change
Change that will be in place for more than 90 days
PFD
Process flow diagram
PM
Planned Maintenance
PSV
Pressure Safety Valve
PUL
Performance Unit Leader; the operating area manager
SAFOP
Safety and Operability
SCE
Safety Critical Equipment
SCP
South Caucasus gas export Pipeline
SIL
Safety Integrity Level
SNR
Senior
TA
Technical Authority
TS (Expert)
Technical Specialist (Expert) with respect to PSCM issues.
Temporary Change
Change that is intended to be in place for less than 90 days.
TL
Team Leader
TTMHC
Contracting company for Sumgayit Waste disposal Site 1
WREP
Western Route Export Pipeline
WSL
Well site leader
VP
Vice President AzSPU
E&P VP
GOBAL SEGEMENT VICE PRESIDENT E&P
ACET
Asset Condition Evaluation Tool
SDA
Shah Deniz Alpha
PRISM
Production Reporting and Information Systems Management
9 References
Document number
Document title
Applies to
MoC register
AzSPU
Technical, process software,
GP 48-02
Hazard and Operability (HAZOP) study
chemical
Technical, process software,
AZ-GP 48-02-1
Hazard and Operability (HAZOP) study (AzSPU STP)
chemical
MOC-FRM-003
Technical MoC document check list
Technical
AzSPU-GEN-PRC-001-A2
Page 18 of 102
Document number
Document title
Applies to
MOC-FRM-008
MoC prioritization tool
AzSPU
Process software MoC change impact assessment &
MOC-FRM-009
Process software
document checklist
MOC-FRM-011
Chemical MoC check list
Chemical
MOC-FRM-013
Tag request from
Technical,Process software
MOC-FRM-014
Maintenance MOC PM and JP change form
Maintenance
MOC-FRM-015
Maint MoC PSV deferral
Maintenance
MOC-FRM-019
Organization MoC handover form
Organizational
MOC-FRM-020
Organization MoC risk and mitigation
Organizational
MOC-FRM-021
Organization MoC risk matrix
Organizational
MOC-FRM-022
Organization MoC close out review
Organizational
MOC-FRM-023
MoC audit template
AzSPU
MOC-FRM-024
Tech MoC PSSR check list
Technical
MOC-FRM-025
HSSE Compliance Form
Technical, chemical
Recommended practice for the risk-based inspection (RBI)
MOC-FRM-GN-008
Maintenance
of relief valves
SHDU-ENG-PRC-001
Weight change procedure for Shah Deniz platform
AzSPU
UNIF ENG PRC 142
Weight change procedure for ACG platforms
AzSPU
UNIF-ENG- REG-021
Production chemical register
Chemical
Engineering maintenance common documents
UNIF-ENG-PRC-022
BU
implementation procedure
UNIF-ENG-REG-005
EA/TA/DRE register
AzSPU
UNIF-ENG-WCS-001
Weight change sheet
Technical, chemical
UNIF-ITS- REG-001
AzSPU software applications register
IT&S
UNIF-OPS-PRC-001
Documentum document control procedure
Document
Technical, process software,
BP-CDZZZZ-PM-GLN-0001
Guidance on certification (GOC)
chemical
AzSPU HSE document management procedure and HSSE
AZSPU-HSSE-DOC-00025-2
Document
document template
Safety Critical Equipment (SCE) Management Strategy in
Guidance on how to identify SCE
AzSPU-GP-32-3001
AzSPU
equipment
MOC-FRM-026
Documentum controlled document template
Document
AzSPU Guidance on Technical Hazard and Risk Processes to
MoC Appendix 1
AzSPU
be used within MoC Appendix 1
AzSPU-GEN-PRC-001-A2
Page 19 of 102
10 Specific Guidance - Technical MoC
Technical Change is a permanent, temporary or emergency physical change that affects process or facilities of the BP operated
operating areas.
10.1 Technical MoC - Roles and Responsibilities
THOSE IDENTIFED BY A * ARE A MINIMUM REQUIREMENT FOR RISK LEVEL 1
Risk
MoC Stage /Role
JOB FUNCTION
Responsibility
Level
Create the eMOC choosing the affected Area and Facility and will choose the correct template for the MoC type process to be
followed (the use of a technical template is a mandatory requirement).
Will identify the scope of work (identifies the change which identifies and describes all work necessary to produce the change.
The scope establishes the tone for the remainder of the planning efforts and therefore should be sufficiently detailed.).
Will provide a justification for the work (this section details why the change is required)
Will provide details of other options considered.
Where the change is required due to some other business process, Engineering Query, incident report etc, the initiator should
ANYONE
reference this process.
Initiate
(IF AN EQ REQUIRES A MOC
1/2/3/4
The initiator is required to identify the Change Verifier (Facility Manager & TL Eng) as per the specific guidance for the
THEN THE EQ RESPONDER
technical MoC.
SHOULD INITIATE THE MOC)
The initiator is required to suggest a priority as per the definition in this procedure
The initiator will attach all relevant documentation as applicable to MoC for information at REV A (later versions may be used if
available)
The EQ system is used by the operating area operations teams to formally raise technical questions and should be linked if
available. Operating areas may cancel an MoC that has not been agreed using the EQ or other operating area system.
AzSPU-GEN-PRC-001-A2
Page 20 of 102
Risk
MoC Stage /Role
JOB FUNCTION
Responsibility
Level
Verify or cancel MoC on behalf of the local operations
The initiator is required to identify other reviewers and approvers and authorizers as defined as a minimum requirement under
FACILITY MANAGER
1/2/3/4
each MoC type
Confirm level of priority using the prioritization tool based on the anticipated benefit of the change
(If the change is to be rejected) Will cancel the MoC giving a reason
Verify or cancel MoC on behalf of the local operations, confirm the risk level
It should be noted verification should not be given until the person (s) nominated as responsible for the detail design has
completed all the necessary activities to ensure that
The change is described clearly and adequately avoid any possible confusion
The justification for the change is clear and adequate
All options have been considered and documented in the MoC (as appropriate)
Budget is approved and a cost center is identified (as appropriate)
Any post start up reviews that may be required to assess the success of the change (as appropriate) have been
identified.
All persons who are required to execute the various stages of the MoC have been identified
Priority level as per the IFP matrix has been confirmed
Person responsible for the detailed design and will ensure that all a full design work pack is assembled and attached
with all document marked up REV A dated and signed
*TL- ENG
1/2/3/4
The full scope of work is agreed and appropriate documentation is in place
(KEY VERIFIER)
Identify any hazards and assess risk associated with change as per the OMS requirements
Verify
Note the Engineer nominated for design should always be identified as a verifier
Once the design is in place is responsible to identify hazard and assess risk using the appropriate management of risk process
(GRP3.1-001 selection of Hazards Evaluation & Risk assessment techniques) this process should involve the appropriate
reviews as required, this should be done with appropriate persons around a table. This allows the key verifier to confirm or
change the risk level (this includes deviations from company or industry standards or practices and any compliance issues).
Details of the risk assessment process used and a summary of the results will be recorded in the risk statement in the MoC
initiation page. Detail record will be attached or linked to the MoC.
To ensure that the hazard identification and risk assessment process is formally recorded and attached or linked to the MoC
for future reference
If the change is to be rejected will cancel the MoC giving a reason
Accountable for all identified requirements at this stage of the MoC
*ENGINEER (DISCIPLINE)
Responsible for the detail design associated with the change and will not verify the MoC until this has been provided.
Nominated person or persons
Will ensure that all affected drawings are checked out from documentum as required by this procedure.
1/2/3/4
responsible for the detailed
design as assigned by the TL
-Eng
1/2/3/4
TL-MODS
Verify or cancel Brownfield MoC Identify the Brownfield Coordinator
Verify or cancel Risk level 3 or 4 MoC
3/4
AOM
If the change is to be rejected will cancel the MoC giving a reason
AzSPU-GEN-PRC-001-A2
Page 21 of 102
Risk
MoC Stage /Role
JOB FUNCTION
Responsibility
Level
To hold the MoC by checking the hold tick box the MoC until all information and data is fully available
To manage the MoC through the process ensuring that correct persons are notified, that comments are answered and the MoC
is properly planned, executed and closed out (as part of this will facilitate any interaction between reviews and designers)
To ensure that all documents as required by the MoC are properly filed and organized (documents to be sectioned by, for
design(rev A )/ for construction(rev C) /red line (R), red line as-built (R with as built stamp) Note that drawings attached for
information will need to be in Documentum MoC folder named for review/ information
Note that for drawings to be actioned by DCMT will need to be transferred to an MoC folder named For Issue.
Note that for data and maintenance / inspection requirements documents (request forms, tdt‟s) need to be added to
Documentum MoC folder, Eng Data & Maintenance & Inspection to be actioned by the MAXIMO Maintenance Coordinator and
Coordinator
1/2/3/4
ANYONE AUTHORIZED
the Eng Data Coordinator
To ensure that all pre-implementation and post implementation actions have been identified and completed.
The Coordinator will also raise Chemical/ Software MoC as required to support the Technical MoC (note that data /
maintenance and document changes that form part of the Technical MoC do not require an additional MoC to be raised)
To ensure that all tags, line numbers and cable numbers have been booked out of eWarehouse
To ensure that all equipment has been properly identified and tags, cable numbers and line numbers have been reserved in
eWarehouse. All necessary information is fed back before authorization
To ensure that the any weight changes associated with platform loading are identified recorded and submitted. Governing
procedures SHDU-ENG-PRC-001 and UNIF ENG PRC -142
The primary technical reviewer and will review against statutory and ETP requirements and engineering practice. All discipline
1/2/3/4
*DRE (DISCIPLINE)
to be included as required. Any changes affecting the P&ID‟s or PFD‟s must be reviewed by a DRE (Process)
Platform Weight changes must be reviewed by the DRE (structures)
1/2/3/4
HSEA
As required For changes affecting HSSE issues
1/2/3/4
AIA
Changes affecting static mechanical equipment future inspection requirements (including piping)
1/2/3/4
TA (PROCESS SAFETY)
Must review if a HAZOP is required
Reviewer
1/2/3/4
FACILITY OPS ENGINEER
As required for changes affecting the process operability
1/2/3/4
OMA
Must review for changes containing a Marine Element
Will communicate on-site operational changes to the HSE Compliance Advisors through completion of the first section of the
*H&S TL / ENV &
1/2/3/4
HSE Compliance Form and will update the facility APS list (if relevant) Will add a pre -implementation action for the HSE
COMPLIANCE TL
Compliance Advisor to determine and advise any compliance implications.
Independent Discipline Technical Review of `Medium and Risk level 3 (blue) MoC. Will not start the review process until the
2/3/4
TA-DISCIPLINE
Discipline Responsible Engineer has done the initial review.
1/2/3/4
*TL-ENG
Confirms that actions raised during the review stage have been addressed to their satisfaction
Approves for execution under control of operations team confirming that construction may start using normal site control
1/2/3/4
*FACILITY MANAGER
procedures.
1/2/3/4
TL-MODS
Approves Brownfield MoC
1/2/3/4
MA
Approves changes containing a Marine Element
Approve
3/4
AOM
Operating area Approval Risk level 3 or 4 MoC
3/4
Engineering services manager
Independent Approval Risk level 3 or 4 MoC
3/4
EA
Independent Approval Risk level 3 or 4 MoC
4
VP
Independent Approval for Risk level 4 MoC
4
E&P VP OR CHIEF ENGINEER
Independent Approval for Risk level 4 MoC
AzSPU-GEN-PRC-001-A2
Page 22 of 102
Risk
MoC Stage /Role
JOB FUNCTION
Responsibility
Level
To ensure that all drawings and formal procedures requested have been checked out of documentum against the MoC
To ensure that there is a construction work pack and all necessary GOC certificates have been generated and pre-populated
with the data from eWarehouse
To ensure that any Software changes have been captured by a Process Software MoC and the MoC link attached to the
Technical MoC
To ensure that any Chemical changes have been captured by a Chemical MoC and the MoC link attached to the technical MoC
To confirms Tags / Line numbers / Cable numbers have been reserved and associated design data has been given to the ENG
& DATA COORDINATOR
1/2/3/4
*COORDINATOR
To confirms that any weight changes have been recorded and submitted. Governing procedures SHDU-ENG-PRC-001 and UNIF
ENG PRC -142
All pre start up checks and GOC documentation has been completed. The SH1 form with punch lists have been signed and that
there are no out standing
“A punchlist items” on the punch list
To ensure that affected drawings have been marked up as redlined drawings, stamped AS BUILT dated/ signed / Job Title
To ensure that all supplementary MoCs have Post Implement close out actions attached
To confirm that all redlined “ As built “REV R documents have been placed in the documentum MoC folder For Issue
To ensure that the HAZARD identification / RISK assessment process can be accessed from the MoC (if the MoC form isn‟t
used then a link is to be provided)
Pre Implement
To apply maintenance requirements as per generic maintenance strategy and maintenance manuals. Identify maintenance to
be planned including job plans, frequency, first start dates, locations any drawings to be linked to MAXIMO. The maintenance
1/2/3/4
MAINTENANCE ENGINEER
requirements will be attached to the MoC to allow the MAXIMO maintenance coordinator to clearly understand what needs to
be uploaded into MAXIMO
To review the construction pack including the resource and scheduling that have been identified as required by the maximo
1/2/3/4
*MTL
work order to support this activity
To apply inspection requirements as per integrity strategy and will identify job plans, frequency, first start dates, locations any
1/2/3/4
AIA
drawings to be linked to MAXIMO. The MAXIMO schedule requirements will be attached to the MoC to allow the MAXIMO
maintenance coordinator to clearly understand what needs to be uploaded into MAXIMO
To ensure that all eWarehouse data has been identified, supplied and uploaded in to eWarehouse (identified by the MoC
1/2/3/4
ENG DATA COORDINATOR
number). (The identification of tags, cable and line data early is important to allow the other process that require this data to
be operated correctly- it is anticipated that data is as built)
Ensure that all appropriate GOC requirements have be identified and certification is available in the construction pack (as
1/2/3/4
GOC COORDINATOR
required)
To review the operational changes communicated in the HSE Compliance Form and facilitate the process to determine whether
1/2/3/4
HSE COMPLIANCE ADVISOR
there are any compliance implications, this may lead to update of Compliance Task Manager (CMT) tasks
The authorizer is accountable for ensuring that all pre implement actions have been identified and closed out to their
Authorize
1/2/3/4
FACILITY MANAGER
satisfaction, before start up. Authorize MoC for startup on site.
AzSPU-GEN-PRC-001-A2
Page 23 of 102
Risk
MoC Stage /Role
JOB FUNCTION
Responsibility
Level
Ensure that all redline drawings have been reviewed and verified as REV R drawings to be actioned by DMT are in the MoC
folder named For Issue
Ensure GOC documentation is completed including any post SH1 requirements and that any outstanding “B punch list items“
have been raised as correctives in MAXIMO
1/2/3/4
*COORDINATOR
Ensure that any eWarehouse maintenance and inspection required data has been provided for the Master Equipment list,
actioned by MAXIMO Maintenance coordinator and the data will need to be transferred to an MoC folder named Eng Data,
Maintenance & Inspection
Confirm that the change performance has been acceptable and if applicable any lessons learnt are issued
1/2/3/4
COORDINATOR
Confirm temporary change in place (only applicable to temporary changes)
1/2/3/4
COORDINATOR
Confirm temporary change removed (only applicable to temporary changes)
DRE (INSTRUMENT/
1/2/3/4
Ensure that any software changes have been captured by a PROCESS SOFTWARE MoC and have been closed out
Post implement
CONTROL/ SIS)
DRE (PROCUCTION
1/2/3/4
Ensure that any CHEMICAL changes have been captured by a CHEMICAL MoC and have been closed out
CHEMIST)
Confirm that all “as built- final “ documents and procedures found in the for issue folder updated in Documentum main area
1/2/3/4
DOCUMENT COORDINATOR
and when back drafting is completed then rev Z drawings will also be upload at the next revision
Confirm that any “as built data Rev R as found in MoC folder named Eng Data, Maintenance & Inspection - is updated in
1/2/3/4
ENG DATA COORDINATOR
eWarehouse
Confirm that any “as built data final” are updated in ACET, the ACET coordinator will identity any other inspection
1/2/3/4
ACET DATA CONTROL
requirements once the RBI process has been done The inspection requirements will be attached to the MoC to allow the
MAXIMO maintenance coordinator to clearly understand what needs to be uploaded into MAXIMO
MAXIMO MAINTENANCE
Confirm that any maintenance inspection requirement identified by the maintenance Engineer or AIA have been executed in
1/2/3/4
COORDINATOR
MAXIMO
1/2/3/4
*COORDINATOR
Confirm that all post implementation actions have been completed as identified in this procedure
Close out
1/2/3/4
*MOC/ EQ TEAM
Confirm that all post implementation actions have been completed as identified in this procedure
Note: At any stage reviewers, approvers, post and pre implementation actions, may be added to the MoC, if considered necessary
Note: pre and post implementation actions can not be deleted - however in the event that the action is applicable, but due to circumstances that are out with the control of the site (ie net work
failure / documentum offline etc) the facility manager can agree to accept sign off of specific pre-implement requirements as long as they have been replicated in post implement section of the
MOC. The reason for this is to be noted in th e action comment field. The only exception to this is the requirement for GOC SH1 to be signed and all A punch list items closed
Note: All weight changes offshore in excess of 100kg should be recorded on the weight change form and submitted to the custodian of the weight change register: - Governing procedures SHDU-
ENG-PRC-001 and UNIF ENG PRC -142
Note: Installation and equipment installed on site shall be proven using the GOC technical check sheets. If the site does not have a GOC database then the MoC number will be used as the
reference number
AzSPU-GEN-PRC-001-A2
Page 24 of 102
10.2 Technical MoC - Templates
The following will be linked directly to the MoC template to assist with the uniform creation of MoC
Document number
Document Title
Applies to
Notes
TECHNICAL MoC
This is used to capture which changes are affected
MOC-FRM-003
DOCUMENT CHECK
TECHNICAL
by the MoC and should be completed before the
LIST
review
TECHNICAL MoC PSSR
Process start up safety review to be completed
MOC-FRM-024
TECHNICAL
CHECK LIST
before authorization
Used to communicate on-site operational changes to
HSSE COMPLIANCE
TECHNICAL,
the AzSPU HSE Compliance Team so that they can
MOC-FRM-025
FORM
CHEMICAL, DC&I
determine HSE compliance implications. Must be
completed before close out.
WEIGHT CHANGE
TECHNICAL,
To be completed for all weight changes on the
UNIF-ENG-WCS-001
SHEET
CHEMICAL
platforms in excess of 100kG
AZ GDP3.1-001 risk
RISK MATRIX
To be use to assess risk level, as required
matrix
10.3 Technical MoC - Risk / Hazard Guidance
Risk Level
Hazard Statement
Managed within the operating area no technical MoC required
Like-for-like replacement (with the exception of equipment which requires a maintenance MoC to
Technical -
maintain a unique identification number (serial number) required for inspection purposes)
Insignificant
Replacement in kind
(maintenance MoC required to update eWarehouse and any new maintenance
risk
requirements)
Managed within the Operating area - Technical MoC required
MoC with a risk level 1 (OMS Risk Matrix)
No or little impact on process safety.
No change in Metallurgy
No change in Cause and Affect table
Technical -
No excursions from accepted operating Envelope
Risk level 1
No detailed design requirement for a HAZID HAZOP SIL review
(white)
No deviation from Company and/or international standards.
MoCs that are duplicated for the purpose of repeat modifications on identical equipment but different
trains that have appropriate risk assessment review and approval on the first MoC, can be managed as
risk level 1 as long as the initial MoC that has captured the full review and approve cycle is clearly
referenced and linked
Managed within the Operating area but will have independent technical review and risk level 2 approvals. - MoC
required
MoC with a risk level 2 (OMS Risk Matrix)
Minimal impact on process safety.
Require approved deviations from Company and or international standards.
Change of service (eg changing the service of a tank from crude to produced water)
Affects safety critical or SIL rated equipment.
Technical -
Includes alterations to the pressure system envelope.
Risk level 2
(turquoise)
Significant changes to the approved P&ID or PFD or C&E.
May affect Hazardous area classification.
Includes changes to Class 1 and Class 2 meters.
Includes significant weight changes on the platform > 500kg.
Includes changes to HV systems or main Electrical Distribution Systems.
AzSPU-GEN-PRC-001-A2
Page 25 of 102
Risk Level
Hazard Statement
Managed within the Operating area but will have independent technical review and risk level 3 approval. - MoC
required
MoC with a risk level 3 (OMS Risk Matrix)
Has significant impact on process safety.
Technical -
Involves hot tapping / live work / diving operations.
Risk level 3
(Blue)
Involves operation of equipment out side of normal operating parameters as identified on the P&ID or
PFD.
Involves change to pressure relief systems.
Require approved deviations from Group, Segment and AzSPU mandated ETP and STP‟s
Managed within the Operating area but will have independent technical review and risk level 4 approval. - MoC
Technical -
required
Risk level 4 -
MoC with a risk level 4 (OMS Risk Matrix)
(Purple)
Note: This risk associated directly with making the change and should not be confused with MoC priority
10.4 Technical MoC - Documentation
At the heart of any change is the control of documents, procedures and drawings. Everyone needs to understand
the status of these documents at three key stages of change.
Note: It is essential that the Master document data-base is kept up to date
Stage
Requirement
All documents/drawings subject to change need to be checked out of documentum and a note
added to document data-base stating that the document/ drawing is affected by MoC ref number
Verify (Design)
Initial design document should include in the document name
- Rev A
Final design documents for review should include in the document name - Rev A
Within Documentum a MoC folder within a folder named for review / information should contain
the following
Authorisation (pre-start up)
Construction documents should include in the document name
- Rev C
As Built documents for review should include in the title - Rev R
Within Documentum a MoC folder within a folder named for issue should contain the following
Final As Built document should include in the document name
- Rev R (with an as-built stamp
Closure (post-start up)
dated and signed)
DMT will action all documents found in the “for issue folder” and updated the master document
area and action any back drafting that needs to be done.
10.5 Technical MoC - Key Indicators
Number of days to close out an MoC after Authorization. This indicates how long it takes to get accurate
documents into the system.
Number of MoCs authorized to start up at any one time - A high number indicates increased risk depending
on the sites ability to manage many simultaneous changes.
Number of MoCs in Review and Approve stages - This indicates the loading on the teams.
AzSPU-GEN-PRC-001-A2
Page 26 of 102
10.6 Technical MoC - Process Flow Diagram
Technical MoC
Use template describe, detail
Identify
scope, justify estimate cost attach
the need
Anyone (if a EQ was
supporting documentation assign
for change
used the EQ responder
category, priority and risk level
yes
to initiate
canel
Confirm that the change is
FACILITY MANAGER
required and all info is included
TL -ENG
no
no
ENGINEER (DESIGN)
OTHERS AS
modify
REQUIRED
Complete the MoC detail ensuring that all effected
RISK LEVEL 3 OR 4
documents are check out from documentum
AOM
Design complete Identify hazards Assess risk
Confirm risk, category and priority identified
correctly
DRE(DISCIPLINE)
H&S TL/ ENV &
COMPLIANCE TL
Change accepted and meets
NO
OTHERS AS
standards
REQUIRED
RISK LEVEL 2, 3 OR 4
YES
NO
TA
TL-ENG
FACILITY MANGER
Change accepted and all
OTHERS AS
issued addressed
REQUIRED
RISK LEVEL 3 OR 4
AOM, EA
RISK LEVEL 4
YES
VP & E&P VP
Hazard and risk has been assessed recorded in MoC
COORDINATOR
Ensure that tags / cable/ line number have been added to E-warehouse
MAINTENANCE
Ensure that child MOC that are required have been raised that weight changes reported.
ENGINEER
Maintenance / inspection requirements identified and added to the documentum
MAINTENANCE
folder for Data/ maintenance/ inspection
SUPERVISOR
AIA
ENG HSE DATA
Construction work pack with documents Rev C GOC
Ensure that all construction
CONTROLLER
certificates available
documents have been as built rev
HSE Compliance
Construct/ install/ pre commission GOC SH1 PL1 (A
R are scanned and uploaded into
Advisor
items) signed off. PSSR completed (check that any child
documentum For Issue Folder
OTHERS as required
MoC are complete if appropriate)
Commission
Ensure that all pre
Put to service
FACILITY MANAGER
implementation actions
Authorised
yes
Performance test
have been completed
Issue any lessons learnt
Ensure that all final document dated and signed are transferred to the for issue folder in
COORNINATOR
documentum and all as built data is in the data / maintenance / inspection folder
DOCUMENT
Maintenance / inspection requirements have been actioned
COORDINATOR
ENG HSE DATA
CONTROLLER
ACET DATA CONTROL
Data/ Maintenance / inspection requirements have been actioned
MAXIMO
All document have been upload in the master document area ( and back drafting arranged)
MAINTENANCE
COORDINATOR
no
All post implment
COORDINATOR
actions complete
close
MOC/EQ TEAM
yes
AzSPU-GEN-PRC-001-A2
Page 27 of 102
11 Specific Guidance - Technical MoC (DC&I Facilities)
Technical Change is a permanent, temporary or emergency change that affects drilling process or facilities of the BP operated operating areas
11.1 Technical MoC (DC&I Facilities) - Roles and Responsibilities
THOSE IDENTIFED BY A * ARE A MINIMUM REQUIREMENT FOR RISK LEVEL 1
MoC Stage/Role
Risk
Job function
Responsibility
Create the eMOC choosing the affected Area and Facility and will choose the correct template for the MoC type process to
be followed (the use of a template is a mandatory requirement).
Will identify the scope of work (identifies the change which identifies and describes all work necessary to produce the
change. The scope establishes the tone for the remainder of the planning efforts and therefore should be sufficiently
detailed.).
Will provide a justification for the work (this section details why the change is required)
*ANYONE
Will provide details of other options considered.
Initiate
(if a SEQ requires a MoC then the
Where the change is required due to some other business process, Engineering Query, incident report etc, the initiator
1/2/3/4
SEQ responder should initiate the
should reference this process.
MoC)
The initiator is required to identify the Verifiers ((DC&I) WSL & (DC&I) TL-ENG (KCAD) as per the specific guidance for the
MoC.
The initiator is required to suggest a priority as per the definition in this procedure
The initiator will attach all relevant documentation as applicable to MoC for information at REV A (LATER VERSIONS MAY
BE USED IF AVALIBLE)
The SEQ system is used by the Drilling operations teams to formally raise technical questions and should be linked if
available. A MoC that has not been agreed using the SEQ or other system may be cancelled.
AzSPU-GEN-PRC-001-A2
Page 28 of 102
Verify or cancel MoC on behalf of the local operations
1/2/3/4
*(DC&I) WSL
Confirm level of priority using the prioritization tool based on the anticipated benefit of the change
Will cancel the MoC giving a reason If the change is to be rejected.
To verify or cancel MoC on behalf of the local operations, confirm the risk level
The initiator is required to identify other reviewers and approvers and authorizers as defined as a minimum requirement
under each MoC type
It should be noted verification should not be given until the person (s) nominated as responsible for the detail design has
complete all the necessary activity to ensure that
The change is described clearly and adequately to avoid any possible confusion
The justification for the change is clear and adequate
All options have been considered and documented in the MoC (as appropriate)
Budget is approved and a cost center is identified (as appropriate)
Any post start up reviews that may be required to assess the success of the change (as appropriate) have been
identified
All persons who are required to execute the various stages of the MoC have been identified
The priority level as per the IFP matrix has been confirmed
Person responsible for the detailed design and will ensure that a full design work pack is assembled and attached
*(DC&I) TL-ENG (KCAD)
with all document marked up REV A dated and signed
1/2/3/4
Key Verifier
Note: the Engineer nominated for design should always be identified as a verifier
Verify
The full scope of work is agreed and appropriate documentation is in place
Identify any hazards and assess risk associated with change as per the OMS requirements
Once the design is in place is responsible to identify hazard and assess risk using the appropriate management of risk
process (GRP3.1-001 selection of Hazards Evaluation & Risk assessment techniques) this process should involve the
appropriate reviews as required, this should be done with appropriate persons around a table. Allowing the key verifier to
confirm or change the risk level (this includes deviations from company or industry standards or practices and any
compliance issues). Details of the risk assessment process used and a summary of the results will be recorded in the risk
statement in the MoC initiation page. Detail record will be attached or linked to the MoC.
To ensure that the hazard identification and risk assessment process is formally recorded and attached or linked to the
MoC for future reference
If the change is to be rejected will cancel the MoC giving a reason
Accountable for all identified requirements at this stage of the MoC
*(DC&I) ENGINEER (KCAD)
nominated person or persons
Responsible for the detail design associated with the change and will not verify the MoC until this has been provided.
1/2/3/4
responsible for the detailed design as
Will ensure that all affected drawings are checked out from documentum as required by this procedure.
assigned by the
2/3/4
(DC&I) RMTL
VERIFY OR CANCEL
3/4
(DC&I) WTL
Verify or cancel Risk level 3 or 4 MoC
3/4
(DC&I) WOM
Verify or cancel Risk level 3 or 4 MoC
AzSPU-GEN-PRC-001-A2
Page 29 of 102
To hold the MoC by checking the hold tick box the MoC until all information and data is fully available
To manage the MoC through the process ensuring that correct persons are notified, that comments are answered and the
MoC is properly planned, executed and closed out (as part of this will facilitate any interaction between reviews and
designers)
To ensure that all documents as required by the MoC are properly filed and organized (documents to be sectioned by, for
design(rev A )/ for construction(rev C) /red line (R), red line as-built (R with as built stamp) Note that drawings attached
for information will need to be in an Documentum MoC folder named for review/ information
Note that for drawings to be actioned by DCMT will need to be transferred to an MoC folder named for issue.
Note that for data and maintenance requirements documents (request forms, tdt‟s) will need to be in an Documentum MoC
Coordinator
1/2/3/4
*(DC&I) DRE (Discipline) (KCAD)
folder, Eng Data & Maintenance & Inspection to be actioned by the MAXIMO Maintenance Coordinator and the Eng HSE
Data coordinators
To ensure that all pre-implementation and post implementation actions have been identified and completed.
The Coordinator will also raise Chemical/ Software MoC as required to support the Technical MoC (note that eWarehouse /
maintenance and document changes that form part of the Technical MoC do not require an additional MoC to be raised)
To ensure that all tags, line numbers and cable numbers have been booked out of eWarehouse
To ensure that all equipment has been properly identified and tags cable numbers and line numbers have been reserved in
eWarehouse. All necessary information is fed back before authorization
Will ensure that the any weight changes associated with platform loading are identified recorded and submitted. Governing
procedures SHDU-ENG-PRC-001 and UNIF ENG PRC -142
The primary technical reviewer and will review against statutory and ETP requirements and engineering practice. All
1/2/3/4
*(DC&I) DRE (Discipline) (KCAD)
discipline to be included as required. Any changes affecting the P&ID‟s or PFD‟s must be reviewed by a DRE (Process)
Platform Weight changes must be reviewed by the DRE(structures)
Will communicate on-site operational changes to the HSE Compliance Advisors through completion of the first section of
1/2/3/4
*(DC&I) H&S TL
the HSE Compliance Form and will update the facility APS list (if relevant) Will add a pre-implementation action for the HSE
Compliance Advisor to determine and advise any compliance implications.
1/2/3/4
(DC&I) HSEA
For changes affecting HSE issues
Reviewer
(DC&I) MAINT SUPERINTENDENT
1/2/3/4
For changes affecting maintainability or operability of the equipment
(KCAD)
1/2/3/4
AIA
Changes affecting static mechanical equipment future inspection requirements. (including piping)
2/3/4
TA (process safety)
Must review if a HAZOP is required
1/2/3/4
OMA
For changes containing a Marine Element
Independent Discipline Technical Review for MoC with a risk level of greater than 2 Will not start the review process until
2/3/4
TA (DISCIPLINE)
the DRE has done the initial review
1/2/3/4
*(DC&I) TL-ENG (KCAD)
Confirms that actions raised during the review stage have been addressed.
Approves for execution under control of drilling team confirming that construction may start using normal site control
1/2
*(DC&I) WSL Snr
procedures.
1/2/3/4
MA
For all changes containing a Marine Element
3/4
(DC&I) WTL
(DC&I) WTL SNR for Risk level 3 and 4MoC
Approve
3/4
Engineering services manager
Independent Approval Risk level 3 or 4 MoC
3/4
(DC&I) RMTL
(DC&I) Rig Maintenance Team leader)
3/4
EA
Independent Approval for Risk level 3 and 4 MoC
4
VP
Approval for Risk level 4 MoC
4
E&P VP
Approval for Risk level 4 MoC
AzSPU-GEN-PRC-001-A2
Page 30 of 102
To ensure that all drawings and formal procedures requested have been checked out of documentum against the MoC
To ensure that there is a construction work pack and all necessary GOC certificates have been generated and pre-
populated with the data from eWarehouse
To ensure that any Software changes have been captured by a Process Software MoC and the MoC link attached to the
Technical MoC
To ensure that any Chemical changes have been captured by a Chemical MoC and the MoC link attached to the technical
MoC
To confirm Tags / Line numbers / Cable numbers have been reserved and associated design data has been given to the
ENG DATA COORDINATORS
1/2/3/4
*COORDINATOR
To confirm that any weight changes have been recorded and submitted. Governing procedures SHDU-ENG-PRC-001 and
UNIF ENG PRC -142
All pre start up checks and GOC documentation has been completed. The SH1 form with punch lists have been signed and
that there are no outstanding
“A punch list items” on the punch list
To ensure that affected drawings have been marked up as redlined drawings stamped AS BUILT dated/ signed / Job Title
To ensure that all supplementary MoC have Post Implement close out actions attached
To Confirm that all redlined “ As built “REV R documents has been placed in the Documentum MoC folder For Issue Ensure
that the HAZARD identification / RISK assessment process can be accessed from the MoC (if the MoC form isn‟t used then a
link is to be provided
Pre Implement
To apply maintenance requirements as per generic maintenance strategy and maintenance manuals. Identify maintenance
to be planned including job plans, frequency, first start dates, locations any drawings to be linked to MAXIMO. The
1/2/3/4
(DC&I) TL- MAINT (KCAD)
maintenance requirements will be attached to the MoC to allow the MAXIMO maintenance coordinator to clearly understand
what needs to be uploaded into MAXIMO
To apply inspection requirements as per integrity strategy and will identify job plans, frequency, first start dates, locations
1/2/3/4
AIA
any drawings to be linked to MAXIMO. The MAXIMO schedule requirements will be attached to the MoC to allow the
MAXIMO maintenance coordinator to clearly understand what needs to be uploaded into MAXIMO
To review the construction pack including the resource and scheduling that have been identified requirements by the
1/2/3/4
(DC&I) TL- MAINT (KCAD)
maximo work order to support this activity
1/2/3/4
ENG DATA COORDINATOR
To ensures that all eWarehouse data has been supplied and uploaded in to eWarehouse
To ensure that all appropriate GOC requirements have be identified and certification is available in the construction pack
1/2/3/4
GOC Coordinator
(as required)
To review the operational changes communicated in the HSE Compliance Form and facilitate the process to determine
1/2/3/4
HSE COMPLIANCE ADVISOR
whether there are any compliance implications, this may lead to update of Compliance Task Manager (CTM) tasks.
*(DC&I) RIG SUPERINTENDENT
The authorizer is accountable for ensuring that all pre implement actions have been identified and closed out to their
1/2/3/4
Authorize
(KCAD)
satisfaction, before start up.
1/2/3/4
*FACILITY MANAGER
Authorize MoC for startup on site.
AzSPU-GEN-PRC-001-A2
Page 31 of 102
Ensure that all redline drawings have been reviewed and verified as REV R drawings to be actioned by DCMT are in the
1/2/3/4
*COORDINATOR
MoC folder named For Issue Ensure GOC documentation is completed including any post SH1 requirements
Confirm that the change performance has been acceptable and if applicable any lessons learnt are issued
Confirm any outstanding “B punch list items“ have been raised as correctives in maximo
Ensure that any eWarehouse maintenance and inspection required data has been provided for the Master Equipment list is
1/2/3/4
*(DC&I) TL- MAINT (KCAD
REV R “AS BUILT-final” actioned by Maximo Maintenance coordinator and the Eng Data coordinator will need to be
transferred to an MoC folder named Eng Data, Maintenance & Inspection
1/2/3/4
COORDINATOR
Confirm temporary change in place (only applicable to temporary changes)
1/2/3/4
COORDINATOR
Confirm temporary change removed (only applicable to temporary changes)
Post implement
(DC&I) DRE (INSTRUMENT/
1/2/3/4
Ensure that any software changes have been captured by a PROCESS SOFTWARE MoC and have been closed out
CONTROL/ SIS) (KCAD)
1/2/3/4
DRE (PROCUCTION CHEMIST)
Ensure that any CHEMICAL changes have been captured by a CHEMICAL MoC and have been closed out
Confirm that all “as built- final “ documents and procedures found in the for issue folder updated in Documentum main
1/2/3/4
DOCUMENT COORDINATOR
area and when back drafting is completed then rev Z drawings will also be upload at the next revision
Confirm that any “as built data Rev R as found in MoC folder named Eng Data, Maintenance & Inspection - is updated in
1/2/3/4
ENG DATA COORDINATOR
eWarehouse
Confirm that any “as built data final” are updated in ACET, the ACET coordinator will identity any other inspection
1/2/3/4
ACET DATA CONTROL
requirements once the RBI process has been done The inspection requirements will be attached to the MoC to allow the
MAXIMO maintenance coordinator to clearly understand what needs to be uploaded into MAXIMO
MAXIMO MAINTENANCE
1/2/3/4
Confirm that any maintenance inspection requirement identified have been executed in MAXIMO
COORDINATOR
1/2/3/4
*COORDINATOR
Confirm that all post implementation actions have been completed as identified in this procedure
Close out
1/2/3/4
*(DC&I) RMTL
Confirm that the Drilling operator has finished this modification to his satisfaction on behalf of BP
1/2/3/4
*MOC/ EQ TEAM
Confirm that all post implementation actions have been completed as identified in this procedure
Note: At any stage reviewers, approvers, post and pre implementation actions, may be added to the MoC, if considered necessary
Note: pre and post implementation actions can not be deleted - however in the event that the action is applicable, but due to circumstances that are out with the control of the site (ie net work
failure / documentum offline etc) the facility manager can agree to accept sign off of specific pre-implement requirements as long as they have been replicated in post implement section of the
MOC. The reason for this is to be noted in the action comment field. The only exception to this is the requirement for GOC SH1 to be signed and all A punch list items closed
Note: All weight changes offshore in excess of 100kg (should be recorded on the weight change form and submitted to the custodian of the weight change register: - Governing procedures SHDU-
ENG-PRC-001 and UNIF ENG PRC -142
Note: Installation and equipment installed on site shall be proven using the GOC technical check sheets. If the site does not have a GOC database then the MoC number will be used as the
reference number
AzSPU-GEN-PRC-001-A2
Page 32 of 102
11.2 Technical MoC (DC&I Facilities) - Templates
The following will be linked directly to the MoC template to assist with the uniform creation of MoC
Document number
Document Title
Applies to
Notes
TECHNICAL MoC
This is used to capture which changes are affected by the
MOC-FRM-003
TECHNICAL
DOCUMENT CHECK
MoC and should be completed before the review
LIST
Process start up safety review to be completed before
TECHNICAL MoC
TECHNICAL
MOC-FRM-024
authorization
PSSR CHECK LIST
Used to communicate on-site operational changes to the
TECHNICAL,
AzSPU HSE Compliance Team so that they can determine
HSSE COMPLIANCE
MOC-FRM-025
CHEMICAL, DC&I
HSE compliance implications. Must be completed before
FORM
close out
TECHNICAL,
To be completed for all weight changes on the platforms in
WEIGHT CHANGE
UNIF-ENG-WCS-001
CHEMICAL
excess of
100kG
SHEET
11.3 Technical MoC (DC&I Facilities) - Risk / Hazard Guidance
Risk Level
Hazard Statement
Managed within the operating area no technical MoC required
Like-for-like replacement (with the exception of equipment which requires a maintenance MoC to
Technical -
maintain a unique identification number (serial number) required for inspection purposes)
Insignificant
Replacement in kind
(maintenance MoC required to update eWarehouse and any new maintenance
Risk
requirements)
Managed within the Operating area - Technical MoC required
MoC with a risk level 1 (OMS Risk Matrix)
No or little impact on process safety.
Technical -
No change in Metallurgy
Risk level 1
No change in Cause and Affect table
(white)
No excursions from accepted operating Envelope
No detailed design requirement for a HAZID HAZOP SIL review
No deviation from Company and/or international standards.
Managed within the Operating area but will have independent technical review and risk level 2 approvals. - MoC
required
MoC with a risk level 2 (OMS Risk Matrix)
Minimal impact on process safety.
Require approved deviations from Company and or international standards.
Change of service (eg changing the service of a tank from crude to produced water)
Technical -
Affects safety critical or SIL rated equipment.
Risk level 2
(turquoise)
Includes alterations to the pressure system envelope.
Significant changes to the approved P&ID or PFD or C&E.
May affect Hazardous area classification.
Includes changes to Class 1 and Class 2 meters.
Includes significant weight changes on the platform > 500kg.
Includes changes to HV systems or main Electrical Distribution Systems.
AzSPU-GEN-PRC-001-A2
Page 33 of 102
Risk Level
Hazard Statement
Managed within the Operating area but will have independent technical review and risk level 3 approval. - MoC
required
MoC with a risk level 3 (OMS Risk Matrix)
Has significant impact on process safety.
Technical -
Involves changes to well control equipment
Risk level 3
Involves hot tapping / live work / diving operations.
(Blue)
Involves operation of equipment out side of normal operating parameters as identified on the P&ID or
PFD .
Involves change to pressure relief systems.
Require approved deviations from Group, Segment and AzSPU mandated ETP and STP‟s
Technical -
Managed within the Operating area but will have independent technical review and risk level 4 approval. - MoC
Risk level 4 -
required
(Purple)
MoC with a risk level 4 (OMS Risk Matrix)
Note: This risk associated directly with making the change and should not be confused with MoC priority
11.4 Technical MoC (DC&I Facilites) - Documentation
At the heart of any change is the control of documents, procedures and drawings. Everyone needs to understand
the status of these documents at three key stages of change.
Note: it is essential that the Master document data-base a is kept up to date
Stage
Requirement
All documents/drawings subject to change need to be checked out of documentum and a note
added to document data-base stating that the document/ drawing is affected by MoC ref
Verify (Design)
number
Initial design document should include in the document name
- Rev A
Final design documents for review should include in the title - Rev A
Within documentum a MoC folder within a folder named for review / information should
contain the following
Authorisation (pre-start up)
Construction documents should include in the document name
- Rev C
As Built documents for review should include in the title - Rev R
Within documentum a MoC folder within a folder named for issue should contain the following
Final As Built document should include in the document name
- Rev R (with an As-built stamp
Closure (post-start up)
dated and signed)
DCMT will action all documents found in the “for issue folder” and updated the master
document area and action any back drafting that needs to be done.
11.5 Technical MoC (DC&I Facilities) - Key Indicators
Number of days to close out an MoC after authorized, this indicates how long it takes to get accurate
documents in the system
Number of MoCs authorized to start up at any one time - A high number indicates increased risk depending
on the sites ability to manage many simultaneous changes
Number of MoCs in Review and Approve stages - This indicates the loading of the facility teams
AzSPU-GEN-PRC-001-A2
Page 34 of 102
11.6 Technical MoC (DC&I Facilities) - Process Flow Diagram
Technical MoC (DC&I FACILITIES)
Use template describe, detail
Identify
scope, justify estimate cost attach
the need
supporting documentation assign
Anyone (if a SEQ was used
for change
category, priority and risk level
the SEQ responder to initiate
yes
canel
Confirm that the change is
(DC&I) WSL
required and all info is included
(DC&I) TL-ENG (KCAD)
no
no
(DC&I) ENGINEER (KCAD)
(DC&I) RMS
modify
OTHERS AS REQUIRED
Complete the MoC detail ensuring that all effected
RISK LEVEL 3 OR 4
documents are check out from documentum
(DC&I) WTL
(DC&I) WOM
Design complete Identify hazards Assess risk
Confirm risk, category and priority identified
correctly
(DC&I) DRE (DISCIPLINE)
(KCAD)
Change accepted and meets
NO
DC&I H&S TL
standards
OTHERS AS REQUIRED
RISK LEVEL 2, 3 OR 4
TA
YES
NO
(DC&I) TL-ENG (KCAD)
(DC&I) WSL SNR (KCAD)
OTHERS AS REQUIRED
Change accepted and all
RISK LEVEL 3 OR 4
issued addressed
(DC&I) WTL
(DC&I) WOM
(DC&I) RMTL
YES
RISK LEVEL 4
VP & E&P VP
Hazard and risk has been assessed recorded in MoC
Ensure that tags / cable/ line number have been added to E-warehouse
COORDINATOR
Ensure that child MOC that are required have been raised that weight changes reported.
(DC&I) TL-MAINT(KCAD)
Maintenance / inspection requirements identified and added to the documentum
AIA
folder for Data/ maintenance/ inspection
ENG HSE DATA
CONTROLLER
Construction work pack with documents Rev C GOC
Ensure that all construction
HSE COMPLIANCE
certificates available
documents have been as built rev
ADVISOR
Construct/ install/ pre commission GOC SH1 PL1 (A
R are scanned and uploaded in to
documentum for review and
OTHERS
items) signed off. PSSR completed (check that any child
information folder,
MoC are complete if appropriate)
Commission
(DC&I) RIG
Ensure that all pre
Put into service
SUPERINTENDENT (KCAD)
implementation actions
Authorised
yes
Performance test
FACILITY MANAGER
have been completed
Issue any lessons learnt
Ensure that all final document dated and signed are transferred to the for issue folder in
COORNINATOR
documentum and all as built data is in the data / maintenance / inspection folder
DOCUMENT
Maintenance / inspection requirements have been actioned
COORDINATOR
ENG HSE DATA
CONTROLLER
Data/ Maintenance / inspection requirements have been actioned
ACET DATA CONTROL
All document have been upload in the master document area ( and back drafting arranged)
MAXIMO MAINTENANCE
COORDINATOR
no
COORDINATOR
All post implment
(DC&I) RMTL
actions complete
close
MOC/EQ TEAM
yes
AzSPU-GEN-PRC-001-A2
Page 35 of 102
12 Specific Guidance - Process Software MoC
Process Software MoC covers the management change associated with process software and electrical protection settings.
Note: Although a Process Software MoC can involve minor physical changes these are restricted to modifications “within the system” e.g. internal panel wiring / relays / additions of an hardwired
intertrips where the I/O for both Nodes would be existing / Firmware upgrades. All would be allowed as long as the correct review is completed by the correct reviewers. External connections to
other sub-systems should be considered to be covered under a separate technical MoC
The person who verifies these modifications needs to decide if a Technical MoC needs to be raised to cover these changes as identified by the scope, and should also consider any impact on
ancillary systems such as HVAC or F&G systems which would also required to be considered and as such would need Technical MoC.
Note: Offline back ups will be managed for each facility by the DRE (INSTRUMENT/ CONTROL/ SIS)
Note: This MoC type will be used for PRISM software changes
12.1 Process Software MoC - Roles and Responsibilities
THOSE IDENTIFED BY A * ARE A MINIMUM REQUIREMENT FOR RISK LEVEL 1
MoC Stage/
Risk
Job Function
Responsibility
Role
Create the eMOC choosing the affected Area and Facility and will choose the Process software template the use of a
template is a mandatory requirement).
*ANYONE
To identify the scope of work (identifies the change which identifies and describes all work necessary to produce the
(if EQ requires a MoC then the EQ
change. The scope establishes the tone for the remainder of the planning efforts and therefore should be sufficiently
responder should initiate the MoC)
detailed.).
To provide a justification for the work (this section details why the change is required)
Before initiating it is advised to review
To provide details of other options considered.
Initiate
1/2/3/4
the scope with the DRE
Where the change is required due to some other business process, Engineering Query, incident report etc, the initiator
(INSTRUMENT/ CONTROL/ SIS)
shall reference this process.
The initiator is required to identify the Key Verifier as identified in the procedure and identify others as required by the
or
procedures
ENGINEER (PIN) OR DRE (PRISM) for
To suggest priority
PRISM software changes
The EQ system is used by the operating area operations teams to formally raise technical questions and should be linked if
available. Operating areas may cancel a MoC that has not been agreed using the EQ or other operating area system.
AzSPU-GEN-PRC-001-A2
Page 36 of 102
MoC Stage/
Risk
Job Function
Responsibility
Role
To verify or cancel MoC on behalf of the local operations, confirm the risk level
It should be noted verification should not be given until the person (s) nominated as responsible for the detail design has
complete all the necessary activity to provide to ensure that (note that this may be the DRE (instrument / control/ sis) or
another)
change is described clearly and adequately to avoid any possible confusion
The full scope of work is agreed and appropriate documentation is in place
The justification for the change is clear and adequate
*DRE (INSTRUMENT/ CONTROL/ SIS)
All options have been considered and documented in the MoC (as appropriate)
Budget is approved and a cost center is identified (as appropriate)
Or DRE (ELECTRICAL) for electrical
Any post start up reviews that may be required to assess the success of the change (as appropriate) have been
protection changes
identified
Identify who is required to execute the various stages of the MoC
1/2/3/4
Priority levels are correct
ENGINEER (PIN)) OR DRE (PRISM) for
PRISM SOFTWARE CHANGES
Once the design is in place is responsible to identify hazard and assess risk using the appropriate management of risk
process (GRP3.1-001 selection of Hazards Evaluation & Risk assessment techniques) this process should involve the
(key Verifier)
appropriate reviews as required, this should be done with appropriate persons around a table. Allowing the key verifier to
confirm or change the risk level (this includes deviations from company or industry standards or practices and any
Verify
compliance issues). Details of the risk assessment process used and a summary of the results will be recorded in the risk
statement in the MoC initiation page. Detail record will be attached or linked to the MoC.
To ensure that the hazard identification and risk assessment process is formally recorded and attached or linked to the
MoC for future reference
Will cancel the MoC giving a reason, if the change is to be rejected
Accountable for all identified requirements at this stage of the MoC
*ENGINEER
Responsible for the detail design associated with the change and will not verify the MoC until this has been provided.
nominated person or persons
Will ensure that all affected drawings are checked out from documentum as required by this procedure.
1/2/3/4
responsible for the detailed design as
assigned by the verifier
1/2/3/4
TL-MODS
Verify or cancel Brownfield MoC
3/4
TL-ENG
Verify or cancel Risk level 3 or 4 MoC
AzSPU-GEN-PRC-001-A2
Page 37 of 102
MoC Stage/
Risk
Job Function
Responsibility
Role
To hold the MoC by checking the hold tick box the MoC until all information and data is fully available
To manage the MoC through the process ensuring that correct persons are notified, that comments are answered and the
MoC is properly planned, executed and closed out (as part of this will facilitate any interaction between reviews and
*DRE (INSTRUMENT/ CONTROL/ SIS)
designers)
To ensure that all documents as required by the MoC are properly filed and organized (documents to be sectioned by, for
Engineer (I&C, Systems)
design(rev A )/ for construction(rev C) /red line (R), red line as-built (R with as built stamp) Note that drawings attached
for information will need to be in an Documentum MoC folder named for review/ information. Software impact assessment
Or DRE (ELECTRICAL) for electrical
form completed and all affected documentation listed within
Coordinator
1/2/3/4
protection changes
Note that for drawings to be actioned by DCMT will need to be transferred to a documentum MoC folder named “for
issue”.
Note that for data documents (request forms, tdt‟s) will need to be in an Documentum MoC folder named “Eng Data &
ENGINEER (PIN)) OR DRE (PRISM) for
Maintenance & Inspection”, to be actioned by the MAXIMO Maintenance Coordinator and the Eng Data coordinator
PRISM SOFTWARE CHANGES
To ensure that all pre-implementation and post implementation actions have been identified and completed.
The Coordinator will also raise a Technical MoC if required and provide links between the two
To ensure that all soft tags, reserved in eWarehouse as required
and all necessary information is fed back before authorization
The primary technical reviewer and will review against statutory and ETP requirements and engineering practice. Any
changes affecting the P&ID‟s or PFD‟s must be reviewed by a DRE (Process)
Identify any Factory acceptance testing required
Review the test procedures
1/2/3/4
*DRE (DISCIPLINE)
DRE PRISM to review all PRISM software changes
Note: Software MoC that requires maintenance changes will also have a technical MoC and the DRE / maintenance
engineer shall identify maintenance requirement there.
Independent Discipline Technical Review for MoC with a risk level of greater than 2 Will not start the review process until
2/3/4
TA-DISCIPLINE
the DRE has done the initial review
Reviewer
Independent Discipline Technical Review for MoC with a risk level of greater than 2. MoC with impact on process safety
2/3/4
TA (PROCESS)
including emergency response plans or changes affecting the P&ID‟s. Will not start the review process until the DRE has
done the initial review
2/3/4
TA (process safety)
Will review any change that requires a HAZOP
PRISM SOFTWARE CHANGE
1/2/3/4
DRE (PRISM)
PRISM SERVER CHANGES WILL REVIEW
PRISM SOFTWARE CHANGE
1/2/3/4
ENGNEER (PIN)
PRISM SERVER CHANGES WILL REVIEW
DRE (INSTRUMENT/ CONTROL/ SIS)
PRISM SOFTWARE CHANGE
1/2/3/4
WILL REVIEW LDS SERVER (PIN) & CIMIO SERVER (PCN) CHANGES
PRISM SOFTWARE CHANGE
1/2/3/4
APPLICATIONS MANAGER (IT&S)
PIN INFRASTRUCTURE CHANGES & ISIS & D2D SERVER (PIN) CHANGES WILL REVIEW
AzSPU-GEN-PRC-001-A2
Page 38 of 102
MoC Stage/
Risk
Job Function
Responsibility
Role
REGIONAL FIELD DIGITAL
PRISM SOFTWARE CHANGE
1/2/3/4
INFRASTRUCTURE MANAGER (IT&S)
PIN INFRASTRUCTURE CHANGES WILL REVIEW
1/2/3/4
*FACILITY OPS ENGINEER
Approves for execution under control of operations team
1/2/3/4
TL-MODS
Approves Brownfield MoC
3/4
TL-ENG
Confirms that actions raised during the review stage have been addressed.
3/4
AOM
Operating area Approval Risk level 3 and 4 MoC
REGIONAL FIELD DIGITAL
PRISM SOFTWARE CHANGE
1/2/3/4
INFRASTRUCTURE MANAGER (IT&S)
ISIS & D2D SERVER (PIN) CHANGES WILL APPROVE
Approve
DRE SNR (INSTRUMENT/ CONTROL/
1/2/3/4
SIS)
PRISM SOFTWARE CHANGE
WILL APPROVE PRISM / PIN INFRASTRUCTURE/LDS/CIMIO SERVIER CHANGES
3/4
Engineering services manager
Independent Approval Risk level 3 or 4 MoC
3/4
EA
Independent Approval for Risk level 3 and 4 MoC
4
VP
Approval for Risk level 4 MoC
4
E&P VP OR CHIEF ENGINEER
Independent Approval for Risk level 4 MoC
Perform offline FAT for complex modifications (as indicated by DRE) any outstanding punchlist items are documented and
attached to the MOC
To ensure that all drawings and formal procedures identified as affected documents within MOC-FRM-009 have been
checked out of Documentum against the MoC
To ensure that there is a work pack and all necessary GOC certificates have been generated, pre-populated with the data
from eWarehouse
To ensure that any TECHNCIAL MoC is “Approved”
1/2/3/4
*COORDINATOR
To confirm SOFT Tags have been reserved and associated design data has been given to the ENG DATA COORDINATOR
All pre Software Load checks have been completed (Program versions, CPU Loading etc)
P&ID Updates have been signed off by Senior Process DRE
re Implement
Rev A Documents are updated to Rev C (post review) and attached to the MOC Folder
Ensure that the test procedure has been approved by DRE
Ensure that the HAZARD identification / RISK assessment process can be accessed from the MoC (if the MoC form isn‟t
used then a link is to be provided
1/2/3/4
ENG DATA COORDINATOR
Ensures that all new eWarehouse tags have been reserved
Ensure that all drawings and formal procedures requested have been checked out of Documentum against the MoC
1/2/3/4
DOCUMENT COORDINATOR
AzSPU-GEN-PRC-001-A2
Page 39 of 102
MoC Stage/
Risk
Job Function
Responsibility
Role
The authorizer is accountable for ensuring that all pre implement actions have been identified and closed out to their
Authorize
1/2/3/4
*FACILITY MANAGER
satisfaction and Authorizes the MoC for software down load and testing controlled by ISSOW
Confirm Down load complete
1/2/3/4
*Engineer (systems) or Engineer (PIN)
Confirm testing successful and attach test records to the MoC
Ensure that all redline drawings have been reviewed and verified as REV R drawings to be actioned by DMT are in the
MoC folder named For Issue Ensure GOC documentation is completed including any post SH1 requirements and that any
outstanding “B punch list items“ have been raised as correctives in MAXIMO
1/2/3/4
*COORDINATOR
Ensure that any eWarehouse required data has been provided for the Master Equipment list, the Eng Data coordinator will
Post implement
need it to be transferred to an MoC folder named Eng Data, Maintenance & Inspection
Confirm that the change performance has been acceptable and if applicable any lessons learnt are issued
1/2/3/4
COORDINATOR
CONFIRM TEMPORARY CHANGE IN PLACE (IF APPLICABLE)
1/2/3/4
COORDINATOR
CONFIRM TEMPORARY CHANGE REMOVED (IF APPLICABLE)
1/2/3/4
*FACILITY OPS ENGINEER
Confirm that operating guidelines procedures have been updated (If applicable)
1/2/3/4
Eng Data coordinator
Ensure that all as built data has been updated in eWarehouse
1/2/3/4
*COORDINATOR
Confirm that all post implementation actions have been completed
Close out
1/2/3/4
*MOC/ EQ TEAM
Confirm that all post implementation actions have been completed as identified in this procedure
Note: At any stage reviewers and approvers may be added to the MoC if considered necessary
Note: Any documents/data updates should be handled under the umbrella of the Technical MoC unless the Process Software MoC is stand alone.
AzSPU-GEN-PRC-001-A2
Page 40 of 102
12.2 Process Software MoC - Templates
The following will be linked directly to the MoC template to assist with the uniform creation of MoC
Document
Document Title
Applies to
Notes
number
PROCESS SOFTWARE MoC
CHANGE IMPACT
PROCESS
This software impact assessment and document check list
ASSESSMENT and
MOC-FRM-009
SOFTWARE
should be completed before authorization
document check list
combined
Note: Installation and equipment installed on site shall be proven using the GOC technical check sheets if the site does not have
a GOC database then the MoC number will be used as the reference number
12.3 Process Software MoC - Risk / Hazard Guidance
Risk Level
Hazard Statement
Managed within the Assets and don‟t required eMoC
Corrections to error in graphics
Correction to reports
Modifying trend sets
Changing tuning constants (record on separate logs)
Software - Insignificant risk
Dead bands on alarms and trips
Operator adjustable deviation alarms
Coefficients for inferred flow, well flow & DP calculations which are not reported in PRS
Offline back ups will be managed for each facility by the DRE (INSTRUMENT/ CONTROL/ SIS)
Managed within the Operating area:
MoC with a Risk level 1 (OMS Risk Matrix)
No or little impact on process safety.
No deviation from Company and or international standards.
Software - Risk Level 1 (white)
Includes adding tags or overviews to an operators display, mapping tags to a communications link
or a PLC, changing a display layout or a tag descriptor to match design documents, adjusting a
range to a transmitter, adjusting alarm settings, System Software Upgrades.
Coefficients for inferred flow, well flow & DP calculations which are reported in PRS
Software change that is part of an approved technical MoC.
Managed within the Operating area but will have independent technical review:
MoC with a Risk level 2 (OMS Risk Matrix)
Minimal impact on process safety.
Involves changes to pressure relief systems Includes adjusting trip settings within rated technical
Software- Risk level 2
limits.
(turquoise)
Removal of trips settings
Includes a change that affects a SIL rated device.
Includes changes to the operating areas PSD, ESD or F&G logic. C&E
Changes that affect the electrical trip discrimination.
Managed within the Operating area but will have independent technical review and independent approval:
MoC with a Risk level 3 (OMS Risk Matrix)
Software- Risk level 3 (blue)
Has significant impact on process safety.
Involves operation of equipment out-with normal operating parameters as identified on the P&ID
or PFD.
Managed within the Operating area but will have independent technical review and risk level 4 approval. -
Technical - Risk level 4 (Purple)
MoC required
MoC with a risk level 4 (OMS Risk Matrix)
Note: This risk associated directly with making the change and should not be confused with MoC priority
AzSPU-GEN-PRC-001-A2
Page 41 of 102
12.4 Process Software MoC - Documentation
At the heart of any change is the control of documents, procedures, software and drawings. Everyone needs to
understand the status of these items at three key stages of change.
Note: it is essential that the Master document data-base a is kept up to date
Stage
Requirement
All documents/drawings subject to change need to be checked out of documentum and a note
added to document data-base stating that the document/ drawing is affected by MoC ref
Verify (Design)
number
Initial design document should include in the document name
- Rev A
Final design documents for review should include in the title - Rev A
Within Documentum a MoC folder within a folder named for review / information should contain
the following
Authorisation (pre-start up)
Construction documents should include in the document name
- Rev C
As Built documents for review should include in the document name - Rev R
Within Documentum a MoC folder within a folder named for issue should contain the following
Final As Built document should include in the document name
- Rev R (with an as-built stamp
Closure (post-start up)
dated and signed)
DCMT will action all documents found in the “for issue folder” and updated the master document
area and action any back drafting that needs to be done.
12.5 Process Software MoC - Key Indicators
Number of days to close out an MoC after authorization. This indicates how long it takes to get accurate
documents into the system.
Number of MoCs authorized to start up at any one time - A high number indicates increased risk depending
on the sites ability to manage many simultaneous changes.
Number of MoCs in review and approve stages - This indicates the loading on the facility teams.
AzSPU-GEN-PRC-001-A2
Page 42 of 102
12.6 Process Software MoC - Process Flow Diagram
Process Software MoC
Use template describe, detail
Identify
scope, justify estimate cost attach
the need
supporting documentation assign
Anyone (if an EQ was used
for change
category, priority and risk level
the EQ responder to initiate
yes
canel
Confirm that the change is
required and all info is included
no
no
DRE (INSTRUMENT/
CONTROL / SIS) OR DRE
(ELEC)
modify
Complete the MoC detail ensuring that all effected
ENGINEER
documents are check out from documentum
OTHERS AS REQUIRED
RISK LEVEL 3 OR 4
TL-ENG
Design complete Identify hazards Assess risk
RMS
Confirm risk, category and priority identified
correctly
DRE (DISCIPLINE)
Change accepted and meets
NO
OTHERS AS REQUIRED
standards
RISK LEVEL 2, 3 OR 4
TA
YES
NO
FACILITY OPS ENGINEER
OTHERS AS REQUIRED
Change accepted and all
RISK LEVEL 3 OR 4
issued addressed
TL-ENG
AOM
EA
RISK LEVEL 4
YES
VP & E&P VP
Hazard and risk has been assessed recorded in MoC
Ensure that soft tags have been added to E-warehouse
Ensure that child MOC that are required have been raised and soft tag data added to
documentum folder for Data/ maintenance/ inspection
COORDINATOR
Construction work pack with documents Rev C GOC
Ensure that all construction
documents are uploaded in to
certificates available (including test reviewed test
procedures
documentum for review and
information folder,
Construct/ install/ pre commission GOC SH1 PL1 (A
Confirm all fats and offline test
items) signed off. PSSR completed (check any technical
MoC is cross referenced for appropriate coordination)
complete
Down load software
Ensure that all pre
Commission
FACILITY MANGER
implementation actions
Authorised
yes
Put into service
have been completed
Performance test
Issue any lessons learnt
Confirm down load complete and testing is successful
Ensure that all final document dated and signed are transferred to the for issue folder in
documentum and all as built data is in the data / maintenance / inspection folder
COORDINATOR
ENGINEER (I&C,
SYSTEMS)
Data requirements have been actioned
FACILITY OPS ENGINEER
All document have been upload in the master document area
no
All post implment
COORDINATOR
actions complete
close
MOC/EQ TEAM
yes
AzSPU-GEN-PRC-001-A2
Page 43 of 102
13 Specific Guidance - Process Software MoC (DC&I Facilities)
Process Software MoC (DC&I Facilities) covers the management change associated with process software and electrical protection settings as they affect Drilling Facilities.
Note: Although a Process Software MoC can involve minor physical changes these are restricted to modifications “within the system” e.g. internal panel wiring / relays / additions of an hardwired
intertrips where the I/O for both Nodes would be existing / Firmware upgrades. All would be allowed as long as the correct review is completed by the correct reviewers. External connections to
other sub-systems should be considered to be covered under a separate technical MoC
The person who verifies these modifications needs to decide if a Technical MoC needs to be raised to cover these changes as identified by the scope, and should also consider any impact on
ancillary systems such as HVAC or F&G systems which would also required to be considered and as such would need Technical MoC.
Note: Offline back ups will be managed for each facility by the DRE (INSTRUMENT/ CONTROL/ SIS)
13.1 Process Software MoC (DC&I Facilities) - Roles and Responsibilities
THOSE IDENTIFED BY A * ARE A MINIMUM REQUIREMENT FOR RISK LEVEL 1
MoC
Risk
JOB FUNCTION
Responsibility
Stage/Role
Create the eMOC choosing the affected Area and Facility and will choose the Process software template the use of a
template is a mandatory requirement).
*ANYONE
To identify the scope of work (identifies the change which identifies and describes all work necessary to produce the
(if an SEQ requires an MoC then the
change. The scope establishes the tone for the remainder of the planning efforts and therefore should be sufficiently
SEQ responder should initiate the
detailed.).
MoC)
To provide a justification for the work (this section details why the change is required)
Initiate
To provide details of other options considered.
1/2/3/4
Before initiating it is advised to
Where the change is required due to some other business process, Engineering Query, incident report etc, the initiator shall
review the scope with the (DC&I)
reference this process.
DRE (INSTRUMENT/ CONTROL/ SIS)
The initiator is required to identify the Key Change Verifier (DC&I) DRE (instrument/ control /SIS) (KCAD) and identify
(KCAD)
others as required by the procedures
To suggest priority
The SEQ system is used by the drilling area operations teams to formally raise technical questions and should be linked if
available. Operating areas may cancel an MoC that has not been agreed using the EQ or other operating area system.
AzSPU-GEN-PRC-001-A2
Page 44 of 102
MoC
Risk
JOB FUNCTION
Responsibility
Stage/Role
Verify or cancel MoC on behalf of the local operations, confirm the risk level
It should be noted verification should not be given until the person (s) nominated as responsible for the detail design has
complete all the necessary activity to provide to ensure that (note that this may be the DRE (instrument / control/ sis) or
another)
change is described clearly and adequate to avoid any possible confusion
The full scope of work is agreed and appropriate documentation is in place
The justification for the change is clear and adequate
* (DC&I) DRE (INSTRUMENT/
That all options have been considered and documented in the MoC (as appropriate)
CONTROL/ SIS) KCAD
That budget is approved and a cost center is identified (as appropriate)
OR (DC&I) ENGINEER (SYSTEMS)
Identify any post start up reviews that may be required to assess the success of the change (as appropriate)
KCAD
Identify who is required to execute various stages of the MoC
1/2/3/4
Priority levels are correct
Or (DC&I) DRE (ELECTRICAL) (KCAD)
Once the design is in place is responsible to identify hazard and assess risk using the appropriate management of risk
for electrical protection changes
process (GRP3.1-001 selection of Hazards Evaluation & Risk assessment techniques) this process should involve the
Verify
appropriate reviews as required, this should be done with appropriate persons around a table. Allowing the key verifier to
confirm or change the risk level (this includes deviations from company or industry standards or practices and any
compliance issues). Details of the risk assessment process used and a summary of the results will be recorded in the risk
statement in the MoC initiation page. Detail record will be attached or linked to the MoC.
Ensure that the hazard identification and risk assessment process is formally recorded and attached or linked to the MoC
for future reference
If the change is to be rejected cancel the MoC giving a reason
Accountable for all identified requirements at this stage of the MoC
* (DC&I) ENGINEER (KCAD)
nominated person or persons
Responsible for the detail design associated with the change and will not verify the MoC until this has been provided.
1/2/3/4
responsible for the detailed design as
Will ensure that all affected drawings are checked out from documentum as required by this procedure.
assigned by the verifier
3/4
(DC&I) RMS
Verify or cancel Risk level 3 or 4 MoC
3/4
(DC&I)TL-ENG (KCAD)
Verify or cancel Risk level 3 or 4 MoC
To hold the MoC by checking the hold tick box the MoC until all information and data is fully available
To manage the MoC through the process ensuring that correct persons are notified, that comments are answered and the
MoC is properly planned, executed and closed out(as part of this will facilitate any interaction between reviews and
designers)
Will ensure that all documents as required by the MoC are properly filed and organized (documents to be sectioned by, for
design(rev A )/ for construction(rev C) /red line (R), red line as-built (R with as built stamp) Note that drawings attached
* (DC&I) Engineer (KCAD)
for information will need to be in an Documentum MoC folder named for review/ information
Coordinator
1/2/3/4
Note that for drawings to be actioned by DCMT will need to be transferred to a documentum MoC folder named for issue.
Note that for data documents (request forms, tdt‟s) will need to be in an Documentum MoC folder Eng Data & Maintenance
& Inspection to be actioned by the MAXIMO Maintenance Coordinator and the Eng Data coordinators
Ensure that all pre-implementation and post implementation actions have been identified and completed.
The Coordinator will also raise a Technical MoC if required
Will ensure that all soft tags, reserved in eWarehouse as required
and all necessary information is fed back before authorization
AzSPU-GEN-PRC-001-A2
Page 45 of 102
MoC
Risk
JOB FUNCTION
Responsibility
Stage/Role
The primary technical reviewer and will review against statutory and ETP requirements and engineering practice. Any
changes affecting the P&ID‟s or PFD‟s must be reviewed by a DRE (Process)
Identify any Factory acceptance testing required
1/2/3/4
* (DC&I) DRE (DISCIPLINE) (KCAD)
Review the test procedures
Note Software MoC that requires maintenance changes will also have a technical MoC and the DRE / maintenance engineer
shall identify maintenance requirement there.
* (DC&I) MAINT
1/2/3/4
Will review any change
SUPERINTENDENT(KCAD)
Reviewer
Independent Discipline Technical Review for MoC with a risk level of greater than 2 Will not start the review process until
2/3/4
TA-DISCIPLINE
the DRE has done the initial review
Independent Discipline Technical Review for MoC with a risk level of greater than 2. MoC with impact on process safety
2/3/4
TA (PROCESS)
including emergency response plans or changes affecting the P&ID‟s. Will not start the review process until the DRE has
done the initial review
1/2/3/4
TA (process safety)
Will review any change that requires a HAZOP
1/2
* (DC&I) WSL SNR
Confirms that actions raised during the review stage have been addressed.
3/4
(DC&I) TL-ENG (KCAD)
Operating area Approval Risk level 3 or 4 MoC
3/4
(DC&I) WTL
Operating area Approval Risk level 3 or 4 MoC
3/4
(DC&I) RMTL
Operating area Approval Risk level 3 or 4 MoC
Approve
3/4
Engineering services manager
Independent Approval for Risk level 3 or 4 MoC
3/4
EA
Independent Approval for Risk level 3 or 4 MoC
4
VP
Independent Approval for Risk level 4 MoC
4
E&P VP OR CHIEF ENGINEER
Independent Approval for Risk level 4 MoC
Perform offline FAT for complex modifications (as indicated by DRE)
Ensure that all drawings and formal procedures requested have been checked out of documentum against the MoC
Ensure that there is a work pack with all necessary construction documents, GOC certificates have been generated pre-
populated with the data from eWarehouse
Ensure that any TECHNCIAL changes have been captured by a TECHNICAL MoC and the MoC link attached to the MoC
Confirms SOFT Tags have been reserved and associated design data has been given to the ENG DATA COORDINATOR
All pre SOFTWARE LOAD checks and GOC documentation has been completed and the SH1 form with punch lists have been
signed and that there are no out standing
“A punch list items” on the punch list
1/2/3/4
*COORDINATOR
Note: after software load the system testing should be documented on a plant performance certificate (with any detailed
Pre-implement
testing documentation attached)
Ensure that affected drawings have been marked up as red lined drawings stamped AS BUILT dated/ signed / Job Title
Ensure that all supplementary MoC have Post implement close out actions attached
Confirm that all Red lined “ As built “”REV R documents in the Documentum MoC folder for issue
Ensure that the HAZARD identification / RISK assessment process can be accessed from the MoC (if the MoC form isn‟t
used then a link is to be provided)
1/2/3/4
*(DC&I) Engineer (systems) (KCAD)
Confirm that all operating guidelines procedures have been updated
1/2/3/4
ENG DATA COORDINATOR
Ensures that all EWarehouse data has been supplied and uploaded in to eWarehouse
AzSPU-GEN-PRC-001-A2
Page 46 of 102
MoC
Risk
JOB FUNCTION
Responsibility
Stage/Role
Ensure that all drawings and formal procedures requested have been checked out of documentum against the MoC
1/2/3/4
DOCUMENT COORDINATOR
Confirm that all Red lined documents and procedures are updated in Documentum
*(DC&I) RIG SUPERINTENDENT
The authorizer is accountable for ensuring that all pre implement actions have been identified and closed out to their
Authorize
1/2/3/4
(KCAD)
satisfaction and Authorizes the MoC for software down load and testing controlled by ISSOW
1/2/3/4
*(DC&I) Engineer (systems) KCAD
Confirm Down load complete
1/2/3/4
*(DC&I) Engineer (systems) KCAD)
Confirm testing successful and attach test records to the MoC
Ensure that all redline drawings have been reviewed and verified as REV R drawings to be actioned by DCMT are in the
MoC folder named For Issue
Ensure GOC documentation is completed including any post SH1 requirements and that any outstanding “B punch list
1/2/3/4
*COORDINATOR
items“ have been raised as correctives in MAXIMO
Ensure that any eWarehouse required data has been provided for the Master Equipment list, the Eng Data coordinators will
Post implement
need it to be transferred to an MoC folder named Eng Data, Maintenance & Inspection
Confirm that the change performance has been acceptable and if applicable any lessons learnt are issued
1/2/3/4
COORDINATOR
CONFIRM TEMPORARY CHANGE IN PLACE (IF APPLICABLE)
1/2/3/4
COORDINATOR
CONFIRM TEMPORARY CHANGE REMOVED (IF APPLICABLE)
Confirm that all “as built- final “ documents and procedures as found in the for issue folder updated in Documentum main
1/2/3/4
DOCUMENT Coordinator
area and when back drafting is completed then rev Z drawings will also be upload at the next revision
1/2/3/4
Eng Data coordinator
Ensure that all as built data has been updated in EWarehouse
1/2/3/4
*COORDINATOR
Confirm that all post implementation actions have been completed
Close out
1/2/3/4
*(DC&I) RMTL
Confirm that the Drilling operator has finished this modification to his satisfaction on behalf of BP.
1/2/3/4
*MOC/ EQ TEAM
Confirm that all post implementation actions have been completed as identified in this procedure
Note: At any stage reviewers and approvers may be added to the MoC if considered necessary
Note: The KCAD Minor Mod Workpack shall include all the supporting documentation relative to the change, such as: Control Narrative, Logic Diagrams, Test Procedures and GoC check sheets.
The MMWpk will be an attachment to the MoC.
AzSPU-GEN-PRC-001-A2
Page 47 of 102
13.2 Process Software MoC (DC&I Facilities) - Templates
The following will be linked directly to the MoC template to assist with the uniform creation of MoC
Document
Document Title
Applies to
Notes
number
PROCESS SOFTWARE MoC
CHANGE IMPACT
PROCESS
This software impact assessment and document check
MOC-FRM-009
ASSESSMENT and document
SOFTWARE
list should be completed before authorization
check list combined
Note: Installation and equipment installed on site shall be proven using the GOC technical check sheets if the site does not have
a GOC database then the MoC number will be used as the reference number
13.3 Process Software MoC (DC&I Facilities) - Risk / Hazard Guidance
Risk Level
Hazard Statement
Managed within the Assets and don‟t required eMoC
Corrections to error in graphics
Correction to reports
Modifying trend sets
Changing tuning constants (record on separate logs)
Software - Insignificant risk
Dead bands on alarms and trips
Operator adjustable deviation alarms
Coefficients for inferred flow, well flow & DP calculations which are NOT reported in PRS
Offline back ups will be managed for each facility by the DRE (INSTRUMENT/ CONTROL/
SIS)
Managed within the Operating area:
MoC with a Risk level 1 (OMS Risk Matrix)
No or little impact on process safety.
No deviation from Company and or international standards.
Software - Risk Level 1
Includes adding tags or overviews to an operators display, mapping tags to a
(white)
communications link or a PLC, changing a display layout or a tag descriptor to match
design documents, adjusting a range to a transmitter, adjusting alarm settings, System
Software Upgrades.
Software change that is part of an approved technical MoC.
Managed within the Operating area but will have independent technical review:
MoC with a Risk level 2 (OMS Risk Matrix)
Minimal impact on process safety.
Involves changes to pressure relief systems Includes adjusting trip settings within rated
Software- Risk level 2
technical limits.
(turquoise)
Removal of trips settings
Includes a change that affects a SIL rated device.
Includes changes to the operating areas PSD, ESD or F&G logic. C&E
Changes that affect the electrical trip discrimination.
Managed within the Operating area but will have independent technical review and independent
approval:
MoC with a Risk level 3 (OMS Risk Matrix)
Involves changes to the well control system.
Software- Risk level 3 (blue)
Has significant impact on process safety.
Involves operation of equipment out-with normal operating parameters as identified on
the P&ID or PFD.
Managed within the Operating area but will have independent technical review and risk level 4
Technical - Risk level 4
approval. - MoC required
(purple)
MoC with a risk level 4 (OMS Risk Matrix)
Note: This risk associated directly with making the change and should not be confused with MoC priority
AzSPU-GEN-PRC-001-A2
Page 48 of 102
13.4 Process Software MoC (DC&I Facilities) - Documentation
At the heart of any change is the control of documents, procedures, software and drawings. Everyone needs to
understand the status of these items at three key stages of change.
Note: it is essential that the Master document data-base a is kept up to date
Stage
Requirement
All documents/drawings subject to change need to be checked out of Documentum and a note
added to document data-base stating that the document/ drawing is affected by MoC ref
Verify (Design)
number
Initial design document should include in the document name
- Rev A
Final design documents for review should include in the document name
- Rev A
Within Documentum a MoC folder within a folder named for review / information should contain
the following
Authorisation (pre-start up)
Construction documents should include in the document name
- Rev C
As Built documents for review should include in the title - Rev R
Within Documentum a MoC folder within a folder named for issue should contain the following
Final As Built document should include in the document name
- Rev R (with an As built stamp
Closure (post-start up)
dated and signed)
DCMT will action all documents found in the “for issue folder” and updated the master document
area and action any back drafting that needs to be done.
13.5 Process Software MoC (DC&I Facilities) - Key Indicators
Number of days to close out a MoC after start up. This indicates how long it takes to get accurate
documents into the system.
Number of MoC authorized to start up at any one time - A high number indicates increased risk depending
on the sites ability to manage many simultaneous changes.
Number of MoC in review and approve stages - This indicates the loading on the facility teams.
AzSPU-GEN-PRC-001-A2
Page 49 of 102
13.6 Process Software MoC (DC&I Facilities) - Process Flow Diagram
Process Software MoC (DC&I facilities)
Use template describe, detail
Identify
scope, justify estimate cost attach
the need
supporting documentation assign
Anyone (if a SEQ was used
for change
category, priority and risk level
the SEQ responder to initiate
yes
canel
Confirm that the change is
required and all info is included
no
no
(DC&I) DRE (INSTRUMENT/
CONTROL / SIS)(KCAD) OR
(DC&I) DRE (ELEC)
modify
Complete the MoC detail ensuring that all effected
(DC&I) ENGINEER (KCAD)
documents are check out from documentum
OTHERS AS REQUIRED
RISK LEVEL 3 OR 4
(DC&I) TL-ENG (KCAD)
Design complete Identify hazards Assess risk
(DC&I) RMS
Confirm risk, category and priority identified
correctly
(DC&I) DRE (DISCIPLINE)
(KCAD)
(DC&I) MAINT
Change accepted and meets
NO
SUPERVISOR (KCAD)
standards
OTHERS AS REQUIRED
RISK LEVEL 2, 3 OR 4
NO
TA
YES
(DC&I) WSL SNR
OTHERS AS REQUIRED
Change accepted and all
RISK LEVEL 3 OR 4
issued addressed
(DC&I) TL-ENG (KCAD)
(DC&I) WTL, (DC&I) RMTL
EA
YES
RISK LEVEL 4
VP & E&P VP
Hazard and risk has been assessed recorded in MoC
Ensure that soft tags have been added to E-warehouse
Ensure that child MOC that are required have been raised and soft tag data added to
documentum folder for Data/ maintenance/ inspection
COORDINATOR
(DC&I) ENGINEER
Ensure that all construction
(SYSTEMS)( KCAD)
Construction work pack with documents Rev C GOC
documents have been as built rev
certificates available (including test reviewed test
R are scanned and uploaded in to
procedures
documentum for review and
Construct/ install/ pre commission GOC SH1 PL1 (A
information folder,
items) signed off. PSSR completed (check any technical
Confirm all fats and offline test
MoC is cross referenced for appropriate coordination)
complete
Down load software
Ensure that all pre
Commission
(DC&I) RIG
implementation actions
Authorised
yes
Put into service
SUPERINTENDENT (KCAD)
have been completed
Performance test
Issue any lessons learnt
Confirm down load complete and testing is successful
Ensure that all final document dated and signed are transferred to the for issue folder in
documentum and all as built data is in the data / maintenance / inspection folder
COORDINATOR
(DC&I) ENGINEER
(SYSTEMS)( KCAD)
Data requirements have been actioned
All document have been upload in the master document area ( and back drafting arranged)
no
COORDINATOR
All post implment
(DC&I) RMTL
actions complete
close
MOC/EQ TEAM
yes
AzSPU-GEN-PRC-001-A2
Page 50 of 102
14 Specific Guidance - Chemical MoC
A chemical change is defined as one of the following:
Introduction of a new chemical where no chemical is currently in use.
Removal of a chemical in use.
Introduction of any fluid into the production stream not related to production (e.g. commission fluids, drilling
fluids etc)
DC&I drilling fluids inclusion into the topsides will be covered by eMOC. However this will be managed as
follows:
A single temporary (annual refresh) eMOC will be put in place to cover all typical fluid flow-back
scenarios, and topsides safeguards to be in place. The individual facility and drilling operating
procedures will be updated as a result to reflect the actions to be taken in each scenario.
A hazard assessment will be conducted put in place a “Rule Set” for typical drilling fluid
flow-backs
This assessment will be refreshed annually along with the temporary MoC
Any fluid flowback not covered by the generic eMOC will be subjected to a separate eMOC prior to
the operation being conducted. The rule set for when a separate eMOC is needed can be defined,
but will be along the lines of:
New operation
New fluids
Existing fluid, but beyond defined limits (of rate/composition/total volume, etc)
Replacing an existing chemical with a new one.
Changing the composition of an existing chemical, including changes in concentration or generic chemistry.
Change of use, where an existing chemical is to be used for a different duty.
Change in injection rates outside the previously assessed range. This applies to significant changes (>20%)
and does not include minor adjustments as part of ongoing optimization.
Although the requirements are the same, a chemical trial will be implemented as a temporary e-MoC
Note: The Chemical MoC will be raised from the point of injection site. TA will ensure that reviewers (Facility Ops Engineers)
from the all affected sites (it there are any) such as Sangachal Terminal; BTC; WREP; SCP are added as needed.
Note: Although a chemical MoC can involve minor physical changes, it is not intended to replace the Technical MoC if permanent
hardware changes are required. The BP production chemist who verifies these modifications needs to decide if a Technical MoC
needs to be raised to cover these hardware changes such as changing an injection location.
Note: Any changes to Flow Assurance and Production Chemistry management strategies that do not involve a chemical change
(e.g. pigging frequency for wax management; producing under different operational conditions for hydrate management) will be
covered by Documentation MoC or Maintenance and Inspection MoC).
Note: Flow Assurance/Production Chemistry Management strategies will be covered by AzSPU Site Technical Practices and any
changes to these will be controlled by Documentation MoC.
Note: Lab procedures will be controlled by Documentation MoC.
AzSPU-GEN-PRC-001-A2
Page 51 of 102
14.1 Chemical MoC - Roles and Responsibilities
THOSE IDENTIFED BY A * ARE A MINIMUM REQUIREMENT FOR RISK LEVEL 1
MoC
Risk
Job Function
Responsibility
Stage/Role
Create the eMOC choosing the affected Area and Facility and will choose the Chemical template the use of a template is a mandatory
requirement).
Will identify the scope of work (identifies the change which identifies and describes all work necessary to produce the change. The scope
establishes the tone for the remainder of the planning efforts and therefore should be sufficiently detailed.).
*ANYONE
Will provide a justification for the work (this section details why the change is required)
(if a EQ requires an
Will provide details of other options considered.
Initiate
2/3/4
MoC then the EQ
Where the change is required due to some other business process, Engineering Query, incident report etc, the initiator shall reference this
responder should
process.
initiate the MoC)
The initiator is required to identify the Key Change Verifier DRE (production chemist) and identify others as required by the procedures
Will suggest priority
The EQ system is used by the operating area operations teams to formally raise technical questions and should be linked if available.
Operating areas may cancel an MoC that has not been agreed using the EQ or other operating area system.
AzSPU-GEN-PRC-001-A2
Page 52 of 102
MoC
Risk
Job Function
Responsibility
Stage/Role
To verify or cancel MoC on behalf of the local operations
*FACILITY OPS
2/3/4
Confirm level of priority using the prioritization tool based on the anticipated benefit of the change
ENGINEER
Will cancel the MoC giving a reason if the change is to be rejected
To verify or cancel MoC on behalf of the local operations, confirm the risk level
It should be noted verification should not be given until the detail design has completed, the verifier will ensure that
The change is described clearly and adequate to avoid any possible confusion
The full scope of work is agreed and appropriate documentation is in place
The justification for the change is clear and adequate
That all options have been considered and documented in the MoC (as appropriate)
That budget is approved and a cost center is identified (as appropriate)
Verify
Identify any post start up reviews that may be required to assess the success of the change (as appropriate)
Identify who is required to execute various stages of the MoC
*DRE (PRODUCTION
Priority levels are correct
2/3/4
CHEMIST)
Once the design is in place is responsible to identify hazard and assess risk using the appropriate management of risk process (GRP3.1-001
selection of Hazards Evaluation & Risk assessment techniques) this process should involve the appropriate reviews as required, this should
be done with appropriate persons around a table. Allowing the key verifier to confirm or change the risk level (this includes deviations
from company or industry standards or practices and any compliance issues). Details of the risk assessment process used and a summary
of the results will be recorded in the risk statement in the MoC initiation page. Detail record will be attached or linked to the MoC
To ensure that the hazard identification and risk assessment process is formally recorded and attached or linked to the MoC for future
reference
If the change is to be rejected cancel the MoC giving a reason
Accountable for all identified requirements at this stage of the MoC
AzSPU-GEN-PRC-001-A2
Page 53 of 102
MoC
Risk
Job Function
Responsibility
Stage/Role
To hold the MoC by checking the hold tick box the MoC until all information and data is fully available
To manage the MoC through the process ensuring that correct persons are notified, that comments are answered and the MoC is properly
planned, executed and closed out (as part of this will facilitate any interaction between reviews and designers)
To ensure that all documents as required by the MoC are properly filed and organized (documents to be sectioned by, for design(rev A )/
for construction(rev C) /red line (R), red line as-built (R with as built stamp) Note that drawings attached for information will need to be in
*DRE (PRODUCTION
Coordinator
2/3/4
an Documentum MoC folder named for review/ information
CHEMIST)
Note that for drawings to be actioned by DCMT will need to be transferred to an MoC folder named for issue.
To ensure that all pre-implementation and post implementation actions have been identified and completed.
The Coordinator will also raise Technical MoC as required to support the Chemical MoC (note that eWarehouse / maintenance and
document changes that form part of the technical MoC do not require additional MoC to be raised)
To ensure that the any weight changes associated with platform loading are identified recorded and submitted. Governing procedures
SHDU-ENG-PRC-001 and UNIF ENG PRC -142
*TA-(PRODUCTION
2/3/4
Review the change giving reasons for any rejection
CHEMISTRY)
*FACILITY OPS
2/3/4
Review the change giving reasons for any rejection
SUPERVISOR
*ENVIROMENTAL
2/3/4
Review the change giving reasons for any rejection with respect to the environmental impact
ADVISOR
2/3/4
*HSEA
Review the change giving reasons for any rejection
*FACILITY OPS ENG
2/3/4
Must review all changes affecting Oil or Gas export route (i.e. SCP BTC WREP)
(EXPORT)
2/3/4
*DRE (PROCESS)
Review the change giving reasons for any rejection
2/3/4
*TA (PROCESS)
Review the change giving reasons for any rejection
Will communicate on-site chemical changes to the HSE Compliance Advisors through completion of the first section of the HSE Compliance
*H&S TL / ENV &
Reviewer
2/3/4
Form and will update the facility APS list (if relevant) Will add a pre-implementation action for the HSE Compliance Advisor to determine
COMPLIANCE TL
and advise any compliance implications.
Review the construction pack and the resource and scheduling that have been identified as required by the maximo work order to support
2/3/4
MTL
this activity (if applicable)
2/3/4
TA (PROCESS safety)
To review if a HAZOP was required
2/3/4
TA-(CORROSION)
Review the change giving reasons for any rejection
2/3/4
TA-(INSPECTION)
Review the change giving reasons for any rejection
DOWN STREAM
2/3/4
FACILITY OPS
Review the change giving reasons for any rejection
ENGINEERS
Review the change giving reasons for any rejection
2/3/4
DRE (DISCIPLINE)
Platform Weight changes must be reviewed by the DRE(structures)
2/3/4
OMA
Review where the change has a Marine Element (Bulk transport by vessel)
AzSPU-GEN-PRC-001-A2
Page 54 of 102
MoC
Risk
Job Function
Responsibility
Stage/Role
2/3/4
MA
Where the change has a Marine Element
2/3/4
*FACILITY MANAGER
APPROVE the change giving reasons for any rejection
3/4
AOM
APPROVE the change giving reasons for any rejection
3/4
EA
APPROVE the change giving reasons for any rejection
Approve
Engineering services
3/4
Independent Approval for Risk level 3 or 4 MoC
manager
4
VP
APPROVE the change giving reasons for any rejection
E&P VP OR CHIEF
4
APPROVE the change giving reasons for any rejection
ENGINEER
To ensure that all drawings and formal procedures requested have been checked out of documentum against the MoC
To ensure that there is a work pack
To ensure that any TECHNCIAL changes have been captured by a Technical MoC and the MoC link attached to the MoC
To ensure that affected documents have been marked up as redlined drawings, stamped AS BUILT dated/ signed / Job Title
2/3/4
*COORDINATOR
To ensure that all supplementary MoC have Post Implement close out actions attached
Pre implement
To confirm that all Red lined “As built ” REV R documents has been placed in the Documentum MoC folder for issue
To ensure that the HAZARD identification / RISK assessment process can be accessed from the MoC (if the MoC form isn‟t used then a link
is to be provided
To review the operational changes communicated in the HSE Compliance Form and facilitate the process to determine whether there are
HSE COMPLIANCE
1/2/3/4
any compliance implications, this may lead to update of Compliance Task Manager (CTM) tasks.
ADVISOR
To ensure that all pre-implementation actions have been identified and completed. Authorize MoC for startup on site.
*FACILITY OPS
Authorize
2/3/4
Site will use the normal Control of work systems for the work done on site
ENGINEER
Ensure that performance is monitored and reported
2/3/4
*COORDINATOR
Confirm that the change performance has been acceptable and if applicable any lessons learnt are issued
*DOCUMENT
Confirm that all “as built/final “ documents and procedures as found in the for issue folder updated in Documentum main area and when
2/3/4
COORDINATOR
back drafting is completed then rev Z drawings will also be upload at the next revision
Post Implement
1/2/3/4
COORDINATOR
Confirm temporary change in place (only applicable to temporary changes)
1/2/3/4
COORDINATOR
Confirm temporary change removed (only applicable to temporary changes)
2/3/4
OMA
To ensure that all changes required by the Marine Element have been closed out
To ensure that all post-implement actions have been completed and As built documents have been identified and that the production
2/3/4
*COORDINATOR
Close out
chemicals register has been updated (UNIF-ENG-REG-021)
1/2/3/4
*MOC/ EQ TEAM
Confirm that all post implementation actions have been completed as identified in this procedure
Note: At any stage reviewers approvers post and pre implementation actions may be added to the MoC, if considered necessary
Note: All weight changes offshore in excess of 100kg should be recorded on the weight change form and submitted to the custodian of the weight change register: - Governing procedures SHDU-
ENG-PRC-001 and UNIF ENG PRC -142
Note: Installation and equipment installed on site shall be proven using the GOC technical check sheets if the site does not have a GOC database then the MoC number will be used as the
reference number
AzSPU-GEN-PRC-001-A2
Page 55 of 102
14.2 Chemical MoC - Templates
The following will be linked directly to the MoC template to assist with the uniform creation of MoC
Document number
Document Title
Applies to
Notes
CHEMICAL MoC
The chemical MoC check list should be completed before
MOC-FRM-011
CHEMICAL
CHECK LIST
the MoC is closed out
Used to communicate on-site operational changes to the
HSSE COMPLIANCE
TECHNICAL,
AzSPU HSE Compliance Team so that they can determine
MOC-FRM-025
FORM
CHEMICAL, DC&I
HSE compliance implications. Must be completed before
close out.
PRODUCTION
UNIF-ENG- REG-021
CHEMICAL
To be updated before chemical MoC is closed out
CHEMICAL REGISTER
WEIGHT CHANGE
TECHNICAL,
To be completed for all weight changes on the platforms
UNIF-ENG-WCS-001
SHEET
CHEMICAL
in excess of 100kG
14.3 Chemical MoC - Risk / Hazard Guidance
Risk Level
Hazard Statement
No MoC required
Chemical- insignificant risk
Managed within the Operating area - technical MoC required
Chemical- Risk level 1
MoC with a risk level 1 (OMS Risk Matrix)
(white)
Managed within the Operating area will have independent technical review
MoC with a risk level 2 (OMS Risk Matrix)
Involves the introduction (includes changes in concentration, generic chemistry)/
Chemical- Risk level 2
removal of a chemical.
(turquoise)
Involves increasing/ reducing the injection rate (>20%) of an existing chemical.
Involves using an existing chemical for a new duty. Will have minimal adverse impact
on process safety and technical integrity.
Managed within the Operating area but will have independent technical review and risk level 3
Chemical- Risk level 3 (blue)
approval. - MoC required
MoC with a risk level 3 (OMS Risk Matrix)
Managed within the Operating area but will have independent technical review and risk level 4
Technical - Risk level 4 -
approval. - MoC required
(Purple)
MoC with a risk level 4 (OMS Risk Matrix)
Note: This risk associated directly with making the change and should not be confused with MoC priority
14.4 Chemical MoC - Documentation
At the heart of any change is the control of documents, procedures and drawings. Everyone needs to understand
the status of these items at three key stages of change.
Note Documentum is the Master document data-base and it is therefore essential that this data-base is kept up to date
Stage
Requirement
All documents/drawings subject to change need to be checked out of Documentum and a note
added to document data-base stating that the document/ drawing is affected by MoC ref
Verify (Design)
number
Initial design document should include in the document name
- Rev A
Final design documents for review should include in the title - Rev A
Within Documentum a MoC folder within a folder named for review / information should contain
the following
Construction documents should include in the document name
- Rev C
Authorisation (pre-start up)
As Built documents for review should include in the title - Rev R
Authorization for Chemical Change Check List and HSSE Compliance Sheet to be completed pre
start up
AzSPU-GEN-PRC-001-A2
Page 56 of 102
Stage
Requirement
Within Documentum a MoC folder within a folder named for issue should contain the following
Final As Built document should include in the document name
- Rev R (with an As built stamp
dated and signed)
DCMT will action all documents found in the “for issue folder” and updated the master document
area and action any back drafting that needs to be done.
Lessons learned are documented.
COSHH is updated if applicable.
Closure (post-start up)
Ops Procedures is updated if applicable.
Inspection Strategy is updated if applicable.
Corrosion Management Strategy is updated if applicable.
Production Chemicals Register is updated following any chemical change.
Copies of MSDS and risk assessment documents will be distributed to: storage area; point of
use; site medical staff; site HSSE representative; facility library; facility laboratory and supplied
during transportation.
14.5 Chemical MoC - Key Indicators
Number of days to close out an MoC after authorization. This indicates how long it takes to get accurate
documents into the system.
Number of MoCs authorized to start up at any one time - A high number indicates increased risk depending
on the sites ability to manage many simultaneous changes.
Number of MoCs in review and approve stages - This indicates the loading on the facility teams.
AzSPU-GEN-PRC-001-A2
Page 57 of 102
14.6 Chemical MoC - Process Flow Diagram
Chemical MoC
Use template describe, detail
Identify
scope, justify estimate cost attach
the need
supporting documentation assign
Anyone (if a EQ was used the EQ
for change
category, priority and risk level
responder to initiate
yes
canel
Confirm that the change is
required and all info is included
no
no
FACILITY OPS ENGINEER
DRE (PRODUCTION CHEMIST)
modify
Complete the MoC detail ensuring that all effected
documents are check out from documentum
Design complete Identify hazards Assess risk
Confirm risk, category and priority identified
correctly
TA (PRODUCTION CHEMISTRY),
FACILITY OPS ENGINEER
ENVIRONMENTAL ADVISOR,
Change accepted and meets
NO
H&S TL / Env & Compliance
standards
TL FACILITY OPS ENG
(EXPORT), DRE( PROCESS,
TA(PROCESS, , OTHERS AS
YES
NO
REQUIRED
FACILITY MANGER
OTHERS AS REQUIRED
Change accepted and all
RISK LEVEL 3 OR 4
issued addressed
AOM, EA
RISK LEVEL 4
VP, E&P VP
YES
Hazard and risk has been assessed recorded in MoC
Ensure technical MOC that are required have been raised that weight changes reported.
COORDINATOR
HSE Compliance Advisor
Ensure all documents are as built
OTHERS
Construction work pack with documents Rev C GOC
certificates available
rev R are scanned and uploaded
PSSR completed (check that any technical MoC are
in to documentum for review and
complete if appropriate)
information folder,
Commission
Ensure that all pre
Put into service
FACILITY OPS ENGINEER
implementation actions
Authorised
yes
Performance test
have been completed
Issue any lessons learnt
Ensure that all final document dated and signed are transferred to the for issue folder in
documentum
COORNINATOR
DOCUMENT COORDINATOR
ENG HSE DATA CONTROLLER
ACET DATA CONTROL
MAXIMO MAINTENANCE
All documents have been upload in the master document area
COORDINATOR
no
All post implment
COORDINATOR
actions complete
close
MOC/EQ TEAM
yes
AzSPU-GEN-PRC-001-A2
Page 58 of 102
15 Specific Guidance - Maintenance & Inspection MoC
A Maintenance MoC will be required for:
Creation of New PM/ change of Frequency/ change of Job Plan or routestop Job Plan/change of Location or
Route Location/ Deferral or Suspension of Preventive Maintenance (PM) records in MAXIMO
Note1: If a tag has been decommissioned then suspension of related PM/WO records will be covered by the
Technical MOC. Maintenance MoC will be issued only if there is no Technical MOC.
Note2: If a PM is to be suspended then its live work orders must be cancelled in MAXIMO by adding MoC
number as a reference to the work order and attaching the list of work orders to the MOC
Cancellation/Change of Target Completion Date (Deferral) of SCE Work Orders.
Note1: Corrective (CO) and Breakdown (BR) SCE work orders will require MoC only if they have already
Approved. SCE PM and PdM work orders will need MoC regardless of their statuses
Note2: Principally Target Dates of non-SCE Work Orders should not be changed and they should be seen as
backlog. Cancellation or deferral of significant amount of non-SCE work orders resulted by the operational
circumstances should be captured through a Maintenance MOC.
Creation of a new Job Plan/Change to the Master Job Plan details
Creation / Modification of a Planned Maintenance Routine (PMR or work scope document) in MAXIMO and
Document Management System (DMS)
Creation of the new/modification of the existing Location and Equipment records in eWarehouse and
MAXIMO will be covered through respective Technical MOCs. If no Technical MoC exists then a Maintenance
MoC will be raised to capture amendment requests for the existing records.
A Maintenance MoC will not be required for updating of the following data fields
Changes to Location/Equipment Descriptions, Location hierarchy-Parent/Child relationships, Location Priority,
GL Account
Changes to Job Plan Descriptions, Supervisor, Materials, Durations, Resources - not applicable to master Job
Plan
If a Technical MoC requires creation of a new/amendment of the existing maintenance subjects, like PM, JP,
PMR e.q. then Pre and Post Implementation stages of the same MoC will cover these activities. Coordinator
of the Technical MoC will identify Responsible people for these actions from “R&M” and “System and Tools”
teams. For RBI activities Inspection Engineers should be contacted. No Maintenance MoC will be initiated in
this case.
AzSPU-GEN-PRC-001-A2
Page 59 of 102
15.1 Maintenance & Inspection MoC - Roles and Responsibilities
MoC Stage /
Risk
Job Function
Responsibility
Role
To initiate the Maintenance e-MoC providing description and justification and any other information required by the change.
Initiate
1/2/3/4
ANYONE AUTHORIZED
The attached maintenance forms identify the information required maintenance change
To identify the minimum requirement for verification stage based on the below categories
Minimum requirement for Maintenance PM/JP/PMR modifications.
ME must ensure that requests are inline with Maintenance Strategy requirements. Any exclusion to the strategy is to be captured
1/2/3/4
Maintenance Engineer(ME)
for the next review of strategy documents. Standardization is to be followed as much as possible
Verifies the MOC, identifies applicable priority and risk levels, assigns responsible person for each stage of the MOC. Ensures that
necessary data is available and correct
Minimum requirement for
Inspection (RBI) PM/JP/PMR modifications
Deferral of Mechanical Equipment Inspection/Corrosion Activities (see Table1.4, Risk Level 2 requirements)
1/2/3/4
Area Inspection Authority
Verifies the MOC, identifies applicable priority and risk levels, assigns responsible person for each stage of the MOC. Ensures that
necessary data is available and correct
Verify
Minimum requirement for Adding/Removing Tags.
1/2/3/4
Data Coordinator
Covers updates to location / equipment details, SCE, EX, failure class, location status
If the request covers maintainable tags then ME must be added as the second verifier
Minimum requirement for Deferral/Cancellation of SCE WOs.
Facility must confirm that request for deferral/cancellation of SCE work orders is valid
1/2/3/4
Facility Ops Engineer/OOE
Verifies the MOC, identifies applicable priority and risk levels. The coordinator assigns necessary person for each stage. If the
request needs changes to Maintenance Strategy then ME must be added as the second verifier.
1/2/3/4
DRE (mechanical)
Responsible for completion of PSV deferral forms
MAXIMO maintenance coordinator will coordinate any maintenance MoC except SCE WO Cancellations and Deferrals
Maintenance Coordinator
Site Scheduler will coordinate Deferral and cancellation of SCE WO
Coordinator
1/2/3/4
or Site Scheduler
The coordinator will ensure that the provided data is enough to processes the MoC, if not then the coordinator is fully responsible
for adding names of those who can provide the required input
Minimum requirement for all maintenance strategy related MOCs and SCE Deferrals
1/2/3/4
Maintenance Engineer(ME)
Reviews change requests as per Maintenance Strategy and collects necessary justification of the SCE Deferrals, involve TAs if
required. Please note that by default all SCE deferrals will be risk ranked blue (high risk).
Provides assistance to Maintenance Engineer and TA wherever required
1/2/3/4
DRE (Discipline)
Changes affecting subsea installations must be reviewed the DRE (offshore pipelines) or DRE (subsea) including corrosion
Reviewer
protection systems and pigging
Minimum requirement for Deferral/Cancellation of SCE Inspection(RBI) WOs
To review any change to inspection /corrosion management Failure Class fields, Location Status, Deferral and Cancellation of
1/2/3/4
AIA
inspection/ corrosion management WOs, suspension of PM Creation of new PM/ JP/ PMR changes to existing PM & Route locations,
frequency, CFW, PMR Content
AzSPU-GEN-PRC-001-A2
Page 60 of 102
MoC Stage /
Risk
Job Function
Responsibility
Role
1/2/3/4
TL-SO
To review any change to subsea equipment maintenance
Independent Technical Review for Deferral and Cancellation of inspection WO (for risk level 2 (turquoise) and above) changes
2/3/4
TA-INPECTION
associated with static mechanical equipment i.e. piping, vessels, etc.
TA will not start the review process until the AIA has done the initial review
Independent Technical Review for risk level 2 (turquoise and above) changes, i.e. Deferral and Cancellation of SCE WOs,
2/3/4
TA-DISCIPLINE
suspension of PM Creation of new PM/ JP/ PMR, changes to existing PM & Route locations, frequency, CFW, PMR Content, changes
to SCE flag. TA will not start the review process until the DRE (discipline) has done the initial review.
1/2/3/4
Coordinator
Approve Maintenance change ( except SCE deferrals and cancellation)
2/3/4
FACILITY MANAGER
Minimum Requirement: Approve deferrals of SCE /or inspection/ corrosion management WO
3/4
AOM or SOM for subsea
Approve second deferrals of SCE /or inspection/ corrosion management WO
Approve
3/4
Engineering services manager
Approve second deferrals of SCE /or inspection/ corrosion management WO
3/4
EA
Approve second deferrals of SCE /or inspection/ corrosion management WO
4
VP
Approve third deferrals of SCE /or inspection/ corrosion management WO
Authorize
1/2/3/4
Coordinator
Authorize for execution.
Area scheduler changes target completion dates of SCE work orders and Start(due) dates of PMs if required, cancels SCE WOs and
suspends their PMs if required
Maximo Maintenance Coordinator updates MAXIMO with any changes related to PM/JP/PMRs
1/2/3/4
Coordinator
Close out
Data Coordinator changes location/ equipment details in eWarehouse / MAXIMO
To ensure that any final as built documentation is updated in documentum
To ensure that all post implementation actions have been completed
1/2/3/4
MOC/ EQ TEAM
Confirm that all post implementation actions have been completed as identified in this procedure
Note: At any stage reviewers and approvers may be added to the MoC if considered necessary
Note: Initiator and Verifier can be the same person
AzSPU-GEN-PRC-001-A2
Page 61 of 102
15.2 Maintenance MoC Attachments - Templates
The following will be linked directly to the MoC template to assist with the uniform creation of MoC
Document
Document Title
Notes
number
To be completed when the master equipment list is to be updated ie
MOC-FRM-013
TAG REQUEST FROM
removing or adding tags
MOC-FRM-015
MAINT MoC PSV DEFERRAL
To be completed for PSV maintenance deferral
The attached data forms will be used to uniformly capture the data for maintenance changes
Master Equipment List Form - for changes to the master equipment register.
Note: If equipment is approved to be removed from the master equipment list then the associated maintenance may
also be removed from CMMS. New equipment should be assigned maintenance in line with the maintenance guidelines
or manufacturer‟s recommendations and approved using the eMoC maintenance form
Safety Critical PSV‟s and SIL rated equipment will have gone through risk based analysis to establish the
inspection / testing frequency, and deferral is unlikely to be approved unless it can be shown that on similar
equipment, in the same duty, the performance can justify a deferral. To allow proper assessment, the
original assessments need to be provided with any information that would support deferral.
Note: The deferral of PSV inspection requires that the risk is reviewed using the RBI practice and this should be
attached to the deferral of maintenance MoC.
15.3 Maintenance MoC Attachments- Guidance Notes
The following will be linked directly to the MoC template to assist with the uniform creation of MoC
Document number
Document Title
Notes
RECOMMENDED PRACTICE FOR THE RISK-
MOC-FRM-GN-008
BASED INSPECTION (RBI)
Guidance on the RBI for relief valves
OF RELIEF VALVES
Guidance on how to identify SCE document
AzSPU-GP-32-3001
SCE Identification Document
Hyperlink to the document
15.4 Maintenance & Inspection MoC - Risk / Hazard Guidance
Risk Level
Hazard Statement
Managed within the Operating area: No MoC required
Changes to Location/Equipment Descriptions, Location hierarchy -Parent/Child relationships,
Location Priority, GL Account
Changes to Job Plan Descriptions, Supervisor, Materials, Durations, Resources - not applicable to
master Job Plan
Maintenance &
Inspection-
If a Technical MoC requires creation of a new/amendment of the existing maintenance subjects,
Insignificant risk
like PM, JP, PMR e.q. then Pre and Post Implementation stages of the same MoC will cover these
activities. Coordinator of the Technical MoC will identify Responsible people for these actions
from “R&M” and “System and Tools” teams. For RBI activities Inspection Engineers should be
contacted. No Maintenance MoC will be initiated in this case.
AzSPU-GEN-PRC-001-A2
Page 62 of 102
Risk Level
Hazard Statement
Managed within the Operating area - MoC required
MoC with a risk level 1 (OMS Risk Matrix)
Includes the creation of new tags.
Like-for-like changes which require identification unique equipment identifier (serial number) as
mandated from ETP GP 31-30 for purposes of the inspection and testing program and to provide
Maintenance &
traceability. To be identified must have a Maintenance MoC to update eWarehouse (eg Process
Inspection -Risk
level 1 (white)
Pressure Vessels, Towers, Heat Exchangers and tube bundles, Fired Heaters and Boilers, Pump
and Compressor Casings, Storage Tanks, Relief Valves, Bursting discs, Vacuum Breakers, Flare
Tips, Lifting Equipment.)
Replacement in kind a Maintenance MoC to update eWarehouse
Includes optimization of CMMS planning fields or deferral of non safety critical equipment
Managed within the Operating area but will have independent technical review and risk level 2 approvals. -
MoC required
MoC with a risk level 2 (OMS Risk Matrix)
Includes the deferral of Safety Critical Equipment
Maintenance &
Includes the deferral or inspection and testing of mechanical static equipment (eg piping, vessels,
Inspection Risk
structures, etc)
level 2
Includes the deferral of corrosion management activities (eg monitoring, mitigation or control eg
(turquoise)
pipeline pigging)
Modification of the technical content of job plans
Changing job plan frequencies.
Application of new maintenance routines
Managed within the Operating area but will have independent technical review and risk level 3 approval. -
MoC required
MoC with a risk level 3 (OMS Risk Matrix)
Maintenance &
Includes the second deferral of Safety Critical Equipment
Inspection Risk
Includes the second deferral or inspection and testing of mechanical static equipment (eg piping,
level 3 (blue)
vessels, structures, etc)
Includes the second deferral of corrosion management activities (eg monitoring, mitigation or
control eg pipeline pigging)
Managed within the Operating area but will have independent technical review and risk level 4 approval. -
MoC required
MoC with a risk level 4 (OMS Risk Matrix)
Maintenance &
Includes the third deferral of Safety Critical Equipment
Inspection Risk
Includes the third deferral or inspection and testing of mechanical static equipment (eg piping,
level 4 (Purple)
vessels, structures, etc)
Includes the third deferral of corrosion management activities (eg monitoring, mitigation or
control eg pipeline pigging)
Note: This risk associated directly with making the change and should not be confused with MoC priority
15.5 Maintenance & Inspection MoC - Documentation
At the heart of any change is the control of documents and data. Everyone needs to understand the status of these
items at three key stages of change.
Note: Documentum is the Master document data-base, EWarehouse is the Master Equipment data-base, and MAXIMO is the
Master maintenance system. It is essential that these are kept up to date.
Stage
Requirement
Verify (Design)
Authorisation (pre-start up)
Job Plans have been updated within Documentum, E Warehouse has been updated and all
Closure (post-start up)
data required has been added.
Note Master Generic Job plans affecting other operating areas should not be changed unless all of the operating areas have
agreed the change
AzSPU-GEN-PRC-001-A2
Page 63 of 102
15.6 Maintenance & Inspection - Key Indicators
Number of days to close out a MoC after authorization. This indicates how long it takes to get accurate
documents into the system.
Number of MoC authorized to start up at any one time - A high number indicates increased risk depending
on the sites ability to manage many simultaneous changes.
Number of MoC in review and approve stages - This indicates the loading on the facility teams.
AzSPU-GEN-PRC-001-A2
Page 64 of 102
15.7 Maintenance & Inspection - Process Flow
Maintenance and Inspection MoC
Use template describe, detail
Identify
scope, justify attach supporting
the need
documentation assign category,
for change
Anyone
priority and risk level
yes
canel
Confirm that the change is
required and all info is included
no
no
FACILITY OPS ENGINEER
OTHERS AS REQUIRED
modify
Complete the MoC detail ensuring that all effected
documents are check out from documentum
IDENTIFY WHO IS RESPONSIBLE FOR
SIGNING OFF EACH STAGE OF THE THE MOC
Change accepted and meets
NO
standards
DRE (DISCIPLINE)
OTHERS AS REQUIRED
YES
NO
COORDINATOR
RISK LEVEL 3 OR 4
Change accepted and all
AOM
issued addressed
RISK LEVEL 4
VP, E&P VP
YES
ANY PRE IMPLEMENTATION ACTIONS ARE COMPLETE
COORDINATOR
COORDINATOR
AUTHORISE
ALL UPDATED TO MAXIMO COMPLETED
ALL UPDATED TO E-WAREHOUSE COMPLETED
COORNINATOR
DOCUMENT COORDINATOR
ENG HSE DATA CONTROLLER
All documents have been upload in the master document area
no
All post implment
COORDINATOR
actions complete
close
MOC/EQ TEAM
yes
AzSPU-GEN-PRC-001-A2
Page 65 of 102
16 Specific Guidance - Maintenance & Inspection MoC (DC&I Facilities)
A Maintenance MoC will be created for:
Creation / Amendment of Frequency or Job Plan or route stop Job Plan/amendment of Location or Route
Location/ Deferral / Suspension of Preventive Maintenance (PM) record in MAXIMO
Note1: If a tag has been decommissioned then suspension of related PM/WO records will be covered by the
Technical MOC. Maintenance MoC will be issued only if there is no Technical MOC.
Note2: If a PM is to be suspended then its live work orders must be cancelled in MAXIMO by adding MoC
number as a reference to the work order and attaching the list of work orders to the MOC
Cancellation/Change of Target Completion Date (Deferral) of SCE Work Orders.
Note1: Corrective (CO) and Breakdown (BR) SCE work orders will require MoC only if they have already
Approved. SCE PM and PdM work orders will need MoC regardless of their statuses
Note2: Principally Target Dates of non-SCE Work Orders should not be changed and they should be seen as
backlog. Cancellation or deferral of significant amount of non-SCE work orders resulted by the operational
circumstances should be captured through a Maintenance MOC.
Creation of a new/Change of Condition for Work field of a Job Plan record in MAXIMO
Creation / Modification of a Planned Maintenance Routine (PMR or work scope document) in MAXIMO and
Document Management System (DMS)
Creation of the new/modification of the existing Location and Equipment records in eWarehouse and
MAXIMO will be covered through respective Technical MOCs. If no Technical MoC exists then a Maintenance
MoC will be raised to capture amendment requests for the existing records.
A Maintenance MoC will not be required for updating of the following data fields
Changes to Location/Equipment Descriptions, Location hierarchy-Parent/Child relationships, Location
Priority, GL Account
Changes to Job Plan Descriptions, Supervisor, Materials, Durations, Resources - not applicable to master Job
Plan
If a Technical MoC requires creation of a new/amendment of the existing maintenance subjects, like PM, JP,
PMR e.q. then Pre and Post Implementation stages of the same MoC will cover these activities. Coordinator
of the Technical MoC will identify Responsible people for these actions from “R&M” and “System and Tools”
teams. For RBI activities Inspection Engineers should be contacted. No Maintenance MoC will be initiated in
this case.
AzSPU-GEN-PRC-001-A2
Page 66 of 102
16.1 Maintenance & Inspection MoC (DC&I Facilities) - Roles and Responsibilities
THOSE IDENTIFED BY A * ARE A MINIMUM REQUIREMENT FOR RISK LEVEL 1
MoC
Risk
JOB FUNCTION
Responsibility
Stage/Role
To initiate the Maintenance e-MoC providing description and justification and any other information required by the change.
Initiate
1/2/3/4
*ANYONE AUTHORIZED
The attached maintenance forms identify the information required maintenance change
To identify the MoC verifier Facility Operations Engineer or TL-ops
Facility must confirm that request for deferral or cancellation of SCE work orders are valid
(DC&I) RIG
To verify the Maintenance e-MoC change can go ahead
1/2/3/4
SUPERINTENDENT (KCAD)
To identify the applicable priority and risk levels
To identify who is responsible for signing off each stage of the MoC
Maintenance Engineer is to ensure that data required for creation/suspension/amendment of maintenance subjects-PM/JP/PMR is in
1/2/3/4
*(DC&I) TL-MAINT (KCAD)
place. Coordinator may require additional information and Maintenance Engineer is responsible to provide it
Verify
Senior Inspection Engineer is to ensure that data required for creation/suspension/amendment of maintenance subjects-PM/JP/PMR
Senior Inspection Engineer
is in place. Coordinator may require additional information and Senior Inspection Engineer is responsible to provide it. (note only
(Contractor)
applies to static mechanical pressure systems)
To verify any request for adding / removing tags up dating data
(location / equipment details, SCE, EX, failure class, location
1/2/3/4
ENG DATA COORDINATOR
status affecting the Master equipment lists may hold the MoC until all the info is available )
MAXIMO maintenance coordinator will coordinate any Maintenance MoC except SCE WO Cancellations and Deferrals
*MAXIMO Maintenance
Site Scheduler will coordinate Deferral and cancellation of SCE WO
Coordinator
1/2/3/4
Coordinator
The coordinator will ensure that the provided data is enough to processes the MoC, if not then the coordinator is fully responsible
or Site Scheduler
for adding names of those who can provide the required input
*(DC&I) MAINTENANCE
To review any change to SCE, EX, Failure Class fields, Location Status, Deferral and Cancellation of SCE WOs, suspension of PM
1/2/3/4
SUPERINTENDENT (KCAD)
Creation of new PM/ JP/ PMR changes to existing PM & Route locations, frequency, CFW, PMR Content
To review any change to inspection /corrosion management Failure Class fields, Location Status, Deferral and Cancellation of
1/2/3/4
AIA
inspection/ corrosion management WOs, suspension of PM Creation of new PM/ JP/ PMR changes to existing PM & Route locations,
frequency, CFW, PMR Content . (note only applies to static mechanical pressure systems)
To review any change to MAINTENANCE management Failure Class fields, Location Status, Deferral and Cancellation of inspection/
2/3/4
(DC&I)RMS
corrosion management WOs, suspension of PM Creation of new PM/ JP/ PMR changes to existing PM & Route locations, frequency,
Reviewer
CFW, PMR Content
Independent Technical Review for Deferral and Cancellation of inspection WO associated with static mechanical equipment ie
2/3/4
TA-INPECTION
piping, vessels, structures etc. TA will not start the review process until the AIA has done the initial review
Independent Technical Review for risk level 2 (turquoise) changes, i.e. Deferral and Cancellation of SCE WO, suspension of PM
2/3/4
TA-DISCIPLINE
Creation of new PM/ JP/ PMR, changes to existing PM & Route locations, frequency, CFW, PMR Content.
TA will not start the review process until the DRE has done the initial review
AzSPU-GEN-PRC-001-A2
Page 67 of 102
MoC
Risk
JOB FUNCTION
Responsibility
Stage/Role
1/2/3/4
Coordinator
Approve Maintenance change ( except SCE deferrals and cancellation)
2/3/4
FACILITY MANAGER
Minimum Requirement: Approve deferrals of SCE /or inspection/ corrosion management WO
3/4
(DC&I) RMTL
Approve second deferrals of SCE /or inspection/ corrosion management WO
Approve
Engineering services
3/4
Approve second deferrals of SCE /or inspection/ corrosion management WO
manager
3/4
EA
Approve second deferrals of SCE /or inspection/ corrosion management WO
4
VP
Approve third deferrals of SCE /or inspection/ corrosion management WO
Authorize
1/2/3/4
*Coordinator
To ensure that any assigned pre-implement requirements have been met
Coordinator-Area scheduler changes target completion dates of SCE work orders and Start(due) dates of PMs if required, cancels
SCE WOs and suspends their PMs if required
Coordinator- Maintenance Planner updates MAXIMO with any changes related to PM/JP/PMRs
1/2/3/4
*Coordinator
Coordinator-Data Lead/Data Coordinator confirms that all Master
To equipment List Changes have been completed (
Close out
To ensure that any final as built documentation is updated in documentum
To ensure that all post implementation actions have been completed
1/2/3/4
ENG DATA COORDINATOR
Confirms that Adds/ amends location/ equipment details in e Ware house
1/2/3/4
*MOC/ EQ TEAM
To confirm that all post implementation actions have been completed as identified in this procedure
Note: At any stage reviewers and approvers may be added to the MoC if considered necessary
AzSPU-GEN-PRC-001-A2
Page 68 of 102
16.2 Maintenance & Inspection MoC (DC&I Facilities) - Templates
Document
Document Title
Applies to
Notes
number
To be completed when the master equipment list is to be
MOC-FRM-013
TAG REQUEST FROM
MAINTENANCE
updated i.e. removing or adding tags
MOC-FRM-015
MAINT MoC PSV DEFERRAL
MAINTENANCE
To be completed for PSV maintenance deferral
Maintenance MOC PM and
MOC-FRM-014
MAINTENANCE
To be completed when changes to MAXIMO are required
JP change form
The attached data forms will be used to uniformly capture the data for maintenance changes
Master Equipment List Form - for changes to the master equipment register.
Note: If equipment is approved to be removed from the master equipment list then the associated maintenance may
also be removed from CMMS. New equipment should be assigned maintenance in line with the maintenance guidelines
or manufacturer‟s recommendations and approved using the eMoC maintenance form
Safety Critical PSV‟s and SIL rated equipment will have gone through risk based analysis to establish the
inspection / testing frequency, and deferral is unlikely to be approved unless it can be shown that on similar
equipment, in the same duty, the performance can justify a deferral. To allow proper assessment, the
original assessments need to be provided with any information that would support deferral.
Note: The deferral of PSV inspection requires that the risk is reviewed using the RBI practice and this should be
attached to the deferral of maintenance MoC.
16.3 Maintenance & Inspection MoC (DC&I Facilities) - Risk / Hazard Guidance
Risk Level
Hazard Statement
Managed within the Operating area: No MoC required
Changes to Location/Equipment Descriptions, Location hierarchy - Parent/Child relationships,
Location Priority, GL Account
Changes to Job Plan Descriptions, Supervisor, Materials, Durations, Resources - not applicable to
Maintenance &
master Job Plan
Inspection-
If a Technical MoC requires creation of a new/amendment of the existing maintenance subjects,
Insignificant risk
like PM, JP, PMR e.q. then Pre and Post Implementation stages of the same MoC will cover these
activities. Coordinator of the Technical MoC will identify Responsible people for these actions
from “R&M” and “System and Tools” teams. For RBI activities Inspection Engineers should be
contacted. No Maintenance MoC will be initiated in this case.
Managed within the Operating area -MoC required
MoC with a risk level 1 (OMS Risk Matrix)
Includes the creation of new tags.
Like-for-like changes which require identification unique equipment identifier (serial number) as
mandated from ETP GP 31-30 for purposes of the inspection and testing program and to provide
Maintenance &
traceability. To be identified must have a maintenance MoC to update eWarehouse (eg Process
Inspection - Risk
level 1 (white)
Pressure Vessels, Towers, Heat Exchangers and tube bundles, Fired Heaters and Boilers, Pump
and Compressor Casings, Storage Tanks, Relief Valves, Bursting discs, Vacuum Breakers, Flare
Tips, Lifting Equipment.) update eWarehouse & ACET
Replacement in kind Maintenance MoC to update eWarehouse ACET
Includes optimization of CMMS planning fields or deferral of non safety critical equipment
AzSPU-GEN-PRC-001-A2
Page 69 of 102
Risk Level
Hazard Statement
Managed within the Operating area but will have independent technical review and risk level 2 approvals. -
MoC required
MoC with a risk level 2 (OMS Risk Matrix)
Includes the deferral of Safety Critical Equipment
Maintenance &
Includes the deferral or inspection and testing of mechanical static equipment (eg piping, vessels,
Inspection - Risk
structures, etc)
level 2
Includes the deferral of corrosion management activities (eg monitoring, mitigation or control eg
(turquoise)
pipeline pigging)
Modification of the technical content of job plans
Changing job plan frequencies.
Application of new maintenance routines/ or inspections
Managed within the Operating area but will have independent technical review and risk level 3 approval. -
MoC required
MoC with a risk level 3 (OMS Risk Matrix)
Maintenance &
Includes the second deferral of Safety Critical Equipment
Inspection - Risk
Includes the second deferral or inspection and testing of mechanical static equipment (eg piping,
level 3 (blue)
vessels, structures, etc)
Includes the second deferral of corrosion management activities (eg monitoring, mitigation or
control eg pipeline pigging)
Managed within the Operating area but will have independent technical review and risk level 4 approval. -
MoC required
MoC with a risk level 4 (OMS Risk Matrix)
Maintenance &
Includes the third deferral of Safety Critical Equipment
Inspection Risk
Includes the third deferral or inspection and testing of mechanical static equipment (eg piping,
level 4 (Purple)
vessels, structures, etc)
Includes the third deferral of corrosion management activities (eg monitoring, mitigation or
control eg pipeline pigging)
Note: This risk associated directly with making the change and should not be confused with MoC priority
16.4 Maintenance & Inspection MoC (DC&I Facilities) - Documentation
At the heart of any change is the control of documents and data. Everyone needs to understand the status of these
items at three key stages of change.
Note: Documentum is the Master document data-base, eWarehouse is the Master Equipment data-base, and MAXIMO is the
Master maintenance system. It is essential that these are kept up to date.
Stage
Requirement
Verify (Design)
Authorisation (pre-start up)
Job Plans have been updated within documentum, eWarehouse has been updated and all
Closure (post-start up)
data required has been added.
Note Master Generic Job plans affecting other operating areas should not be changed unless all of the operating areas have
agreed the change
16.5 Maintenance & Inspection MoC (DC&I Facilities) - Key Indicators
Number of days to close out an MoC after authorization. This indicates how long it takes to get accurate
documents into the system.
Number of MoCs authorized to start up at any one time - A high number indicates increased risk depending
on the sites ability to manage many simultaneous changes.
Number of MoCs in review and approve stages - This indicates the loading on the facility teams.
AzSPU-GEN-PRC-001-A2
Page 70 of 102
16.6 Maintenance & Inspection MoC (DC&I Facilities) - Process Flow
Maintenance and Inspection MoC (DC&I FACILITIES)
Use template describe, detail
Identify
scope, justify attach supporting
the need
documentation assign category,
for change
Anyone
priority and risk level
yes
canel
Confirm that the change is
required and all info is included
no
no
(DC&I) RIG SUPERINTENDENT
(KCAD)
modify
Complete the MoC detail ensuring that all effected
documents are check out from documentum
IDENTIFY WHO IS RESPONSIBLE FOR
SIGNING OFF EACH STAGE OF THE THE MOC
Change accepted and meets
NO
(DC&I) DRE (DISCIPLINE)
standards
(DC&I) RMS
OTHERS AS REQUIRED
YES
NO
COORDINATOR
Change accepted and all
RISK LEVEL 3 OR 4
issued addressed
(DC&I) RMTL
YES
ANY PRE IMPLEMENTATION ACTIONS ARE COMPLETE
COORDINATOR
COORDINATOR
AUTHORISE
ALL UPDATED TO MAXIMO COMPLETED
ALL UPDATED TO E-WAREHOUSE COMPLETED
COORNINATOR
DOCUMENT COORDINATOR
ENG HSE DATA CONTROLLER
All documents have been upload in the master document area
no
All post implment
COORDINATOR
actions complete
close
MOC/EQ TEAM
yes
AzSPU-GEN-PRC-001-A2
Page 71 of 102
17 Specific Guidance - Drilling, Completions & Interventions MoC
The MoC objective is to assure that changes to wells, statements of requirements (SOR), basis of design criteria or
downhole equipment receive adequate review and approval
Note: Organizational MoC will be used to manage DC&I organizational changes
Note: DC&I Deviation MoC will be used to manage DC&I deviations from practice
The MoC is intended to be used when changes are made to the well critical documents described before. It is not
intended to be used for revising draft SoR or work programs or for a typical day-to-day revision to drilling -
completion - sub sea parameters that are within the scope of the original plan.
In summary, The MoC is in place to provide assurance that there is a systematic and adequate approach to
implement a change within the wells team in the AzSPU. The system is based on identifying, documenting and
performing adequate risk assessment and cost benefit analysis to understand and document any potential
implications prior to make a final change.
When assessing a potential change, consideration must be given to the fact that other individuals or groups may be
still using an initial and different plan as a building block for their work. If a recommendation is made to change the
plans or key documents, the full implications of the change must be thought through and the MoC must be
distributed to the appropriate personnel.
Plans can and should be changed as new technology, or new information becomes available. Changing plans
because of personal preferences, especially when new members join the team, should be avoided.
Changes are often made to the agreed drilling, completions and sub sea operations procedures as events unfold
differently to that envisioned in the plan. The intent of this process is that changes be handled in the appropriate
manner. Changes must follow a proper MoC process.
AzSPU-GEN-PRC-001-A2
Page 72 of 102
17.1 Drilling, Completions & Interventions MoC - Roles and Responsibilities
THOSE IDENTIFED BY A * ARE A MINIMUM REQUIREMENT FOR RISK LEVEL 1
MoC Stage
Risk
Job Function
Responsibility
To initiate the eMoC providing description and justification and any other information required by the change, e.g. Description of
operations and/or changes, advantages and disadvantages, estimated cost & time and relevant risk assessment with clear
Initiate
1/2/3/4
*(DC&I) ENG (DISCIPLINE)
recommendations and conclusions.
Identify the MoC verifier
Verification of the change proposed.
*(DC&I) ENG Snr
Verify
1/2/3/4
To identify priority level and risk level.
(DISCIPLINE)
To identify who needs to sign off each stage of the MoC
To manage the MoC through the process ensuring that correct persons are notified and that comments are answered and the MoC is
Coordinator
1/2/3/4
*(DC&I) ENG (DISCIPLINE)
properly closed out as per the procedure
1/2/3/4
*(DC&I) ETL (DISCIPLINE)
REVIEW
1/2/3/4
(DC&I) WITL
REVIEW ANY MoC HAVING LIFE CYCLE AND WELL INTEGRITY IMPACT
1/2/3/4
BMM
REVIEW SOR OR BOD CHANGES DURING DEFINE
1/2/3/4
(DC&I) TA
REVIEW AFTER BASIS OF DESIGN IS FINALISED
1/2/3/4
RMM
REVIEW SOR OR BOD CHANGES DURING DEFINE
Reviewer
To communicate on-site operational changes to the HSE Compliance Advisors through completion of first section of HSE Compliance
1/2/3/4
*(DC&I) H&S TL
Form and will update facility APS list (if relevant) Will add a pre -implementation action for the HSE Compliance Advisor to determine
and advise any compliance implications.
1/2/3/4
*(DC&I) WTL
Review - State reason for any rejections
1/2/3/4
*(DC&I) WOM
Approve - State reason for any rejections
1/2/3/4
*(DC&I) EM (Discipline)
Approve - State reason for any rejections
Approve
3/4
(DC&I )VP & WEA
Tier 4 Approve - State reason for any rejections
4
E&P VP
RISK LEVEL 4 APPROVAL
To review the operational changes communicated in the HSE Compliance Form and facilitate the process to determine whether there
Pre-implement
1/2/3/4
HSE COMPLIANCE ADVISOR
are any compliance implications, this may lead to update of Compliance Task Manager (CTM) tasks.
Authorize
1/2/3/4
*(DC&I) WSL SNR
To ensure that pre-implementation requirements have been met
1/2/3/4
*COORDINATOR
To confirm that the change performance has been acceptable and if applicable any lessons learnt are issued
Post Implement
1/2/3/4
COORDINATOR
To confirm temporary change in place (only applicable to temporary changes)
1/2/3/4
COORDINATOR
To confirm temporary change removed (only applicable to temporary changes)
To ensure that all post implementation actions have been completed, relevant documentation has been updated and lessons learned
1/2/3/4
*COORDINATOR
Close out
issued
1/2/3/4
*MOC/ EQ TEAM
To confirm that all post implementation actions have been completed as identified in this procedure
Note: At any stage reviewers and approvers may be added to the MoC if considered necessary
AzSPU-GEN-PRC-001-A2
Page 73 of 102
17.2 Drilling, Completions & Interventions MoC - Templates
The following will be linked directly to the MoC template to assist with the uniform creation of MoC
Document
Document Title
Applies to
Notes
number
Used to communicate on-site operational changes to
TECHNICAL, CHEMICAL,
the AzSPU HSE Compliance Team so that they can
MOC-FRM-025
HSSE COMPLIANCE FORM
DC&I
determine HSE compliance implications. Must be
completed before close out.
17.3 Drilling, Completions & Interventions MoC - Risk / Hazard Guidance
Risk Level
Hazard Statement
Managed within the operating area no MoC required
And will be documented with a note in the Well file
Drilling and
Examples bit selections, drilling rate wiper trips all within program guidelines. This is
Completions-
Insignificant Risk
documented in a ops note that is a note from the programme writer on a clarification
(Tier 1)
point in the program , it should still be within the bounds of the signed off programme
and therefore does not need to be signed off
Managed within the Operating area - MoC required
MoC with a risk level 1 (OMS Risk Matrix)
Drilling and
Decisions with a potential impact of grater than 2 day of unplanned activities, but
Completions- Risk
minimum potential impact on well objectives
level 1 (white)
Examples cement casing early due to lost returns, work to cure moderate losses, mud /
(DC&I Tier 2)
brine weight properties changes inside of program guide lines. Will be document as an
ops note
Managed within the Operating area but will have independent technical review and risk level 2
approval. - MoC required
MoC with a risk level 2 (OMS Risk Matrix)
Drilling and
Decisions with a potential impact of greater that 2 day of unplanned activities, but
Completions - Risk
level 2 (turquoise)
minimum potential impact on well objectives
(DC&I Tier 3)
Examples set casing off bottom shoe squeeze, side track vs fishing, programme for
dealing with major losses, mud / brine weight properties changes out side the program
guidelines.
Managed within the Operating area but will have independent technical review and risk level 3
approval. - MoC required
MoC with a risk level 3 (OMS Risk Matrix)
Drilling and
Decisions with clear potential impact on SOR well objectives
Completions - Risk
level 3 (blue) (Tier 4)
Examples, changes to the evaluation programme changes that have the potential to
compromise well integrity and / or well productivity / injectivity DHPG failure , completion
integrity failure, policy exceptions, early TD of hole sections.
Managed within the Operating area but will have independent technical review and risk level 4
Drilling and
approval. - MoC required
Completions - Risk
MoC with a risk level 4 (OMS Risk Matrix)
level 4 (Purple)
Note: This risk associated directly with making the change and should not be confused with MoC priority
Note: The VP D&C provides the independent approval
Note: Independent technical review is provided by the Engineering Manager and/or Technical Authority
AzSPU-GEN-PRC-001-A2
Page 74 of 102
17.4 Drilling, Completions & Interventions MoC - Documentation
At the heart of any change is the control of documents and data. Everyone needs to understand the status of these
items at three key stages of change.
Stage
Requirement
Verify (Design)
To ensure verification of operational risk has been considered
Authorisation (pre-start up)
To ensure that all work plans / programmes / work instructions reflect the change.
To ensure that all work plans / programmes / work instructions, basis of design documents, end
Closure (post-start up)
of well reports and well handover documentation is as built and the document data base is
updated
17.5 Drilling, Completions & Interventions MoC - Key Indicators
Number of days to close out an MoC after authorized. This indicates how long it takes to get accurate
documents into the system or to close out the MOC.
Number of MoCs authorized at any one time - A high number indicates increased risk depending on the DC&I
sites ability to manage many simultaneous changes.
Number of MoCs in review and approve stages - This indicates the loading on the DC&I teams.
AzSPU-GEN-PRC-001-A2
Page 75 of 102
17.6 Drilling, Completions & Interventions MoC - Process Flow Diagram
DRILLING, COMPLETIONS & INTERVENTIONS MoC
Use template describe, detail
Identify
scope, justify, cost, attach
the need
supporting documentation assign
for change
(DC&I) ENG (DISCIPLINE)
category, priority and risk level
yes
canel
Confirm that the change is
required and all info is included
no
no
(DC&I) ENG SNR (DISCIPLINE)
Confirm that all the required detail has been
modify
provided and that all effect documents have been
identified assess Hazard and Risk
Confirm priority and risk levels are correct
IDENTIFY WHO IS RESPONSIBLE FOR
SIGNING OFF EACH STAGE OF THE THE MOC
(DC&I) ETL (DISCIPLINE)
Change accepted and meets
NO
standards
(DC&I) H&S TL
(DC&I) WTL
OTHERS AS REQUIRED
YES
NO
(DC&I) WOM
(DC&I) EM
Change accepted and all
RISK LEVEL 3 OR 4
issued addressed
(DC&I) VP & WEA
E&P VP
YES
ANY PRE IMPLEMENTATION ACTIONS ARE COMPLETE
HSE Compliance Advisor
COORDINATOR
(DC&I) WSL SNR
AUTHORISE
CONFIRM THAT THE CHANGE PERFORMANCE HAS BEEN ACCEPTABLE AND IF
APPLICABLE ANY LESSONS LEARNT ARE ISSUED
COORDINATOR
All documents have been upload into the document control system (as applicable
no
All post implment
COORDINATOR
actions complete
close
MOC/EQ TEAM
yes
AzSPU-GEN-PRC-001-A2
Page 76 of 102
18 Specific Guidance - Documentation MoC
Documentation changes cover the review and approval of key documents that are controlled through the Document Management Proc edure, UNIF-OPS-PRC-001 and the HSSE
Document Management Procedure AzSPU-HSSE-DOC-00025-2.
NOTE: FOR GUIDANCE ON KEY DOCUMENT REFERENCE E&P OMS 4.3
Changes to these documents that are not part of another type of MoC, will be managed through a Documentation MoC. Within other MoC types, documents change will be
managed through the specific MoC type, e.g. Technical MoC.
Note: It is expected that most controlled documents will be developed outside of the e-MoC process, and that the document MoC will capture the final review and approvals instead of wet
signature. Once the document is live, the MoC system shall be used to propose the change, review and approve.
Note: All Asset key documents will have Document Authority and a Document Owner.
Note: Temporary documents, e.g. procedures will follow the same requirements as the temporary technical MoC.
18.1 Documentation MoC - Roles and Responsibilities
THOSE IDENTIFED BY A * ARE A MINIMUM REQUIREMENT FOR RISK LEVEL 1
MoC
Risk
JOB FUNCTION
Responsibility
Stage/Role
To initiate the eMoC providing description and justification and any other information required by the change.
Initiate
1/2/3/4
*ANYONE APPROVED
To identify the MoC verifier typically the Document Owner
Verify
1/2/3/4
*DOCUMENT OWNER
Verify or cancel the change proposed and identify who needs to sign off on each stage of the MoC
To manage the MoC through the process ensuring that correct persons are notified and that comments are answered and the MoC is
Coordinator
1/2/3/4
* ANYONE APPROVED
properly closed out
Content review
1/2/3/4
*Any one as required
State reason for any rejections
Reviewer
2/3/4
(DC&I)TA
Review changes to critical DC&I documentation
2/3/4
TA (Process Safety)
Review changes to HAZOP‟s
2/3/4
TA (Discipline)
Review changes to Engineering or Site Technical Practices. Review Medium and / or High Risk SOP's & Standing Instructions
*DOCUMENT AUTHORITY
Content Approval
1/2/3/4
(TL OR MANAGER)
State reason for any rejections
2/3/4
(DC&I) VP & WEA
Approve changes to critical DC&I documentation
Approve
2/3/4
EA
Approve changes to Engineering or Site Technical Practices. Approve Medium and / or High Risk SOP's & Standing Instructions
4
VP
Approve changes risk level 4
4
E&P VP
Approve changes risk level 4
*DOCUMENT AUTHORITY
Authorize for Use
Authorize
1/2/3/4
(TL OR MANAGER)
Post implement
*DOCUMENT
1/2/3/4
UPDATE THE MASTER DATA BASE/Documentum/DK ENSURE OLD DOCUMENTS ARE VOIDED AND NEW DOCUMENT ARE UPLOADED
Actions
COORDINATOR
1/2/3/4
*COORDNIATOR
To ensure that all post implementation actions have been completed
Close out
1/2/3/4
*MOC/ EQ TEAM
To confirm that all post implementation actions have been completed as identified in this procedure
Note: At any stage reviewers and approvers may be added to the MoC if considered necessary
AzSPU-GEN-PRC-001-A2
Page 77 of 102
18.2 Documentation MoC - Templates
The following will be linked directly to the MoC template to assist with the uniform creation of MoC
Document
Document Title
Applies to
Notes
number
AzSPU Modification Information
Document/
This document identifies the Information
AzSPU
Handover
Maint MoC
deliverables for Documents, data, models etc.
Procedure, This contains the Document
UNIF-OPS-PRC-001
DOCUMENT CONTROL PROCEDURE
Document
Management detail of how to affect change.
Engineering Critical Documents Listing
This listing will be aligned with the RP SRP 5.0-
MOC-FRM-036
Document
Controlled Document Register
0001 Critical documents 4.3 Table 4L
AZSPU-HSSE-DOC-
Document template to be used for HSE documents
00025-A1
HSE document template
Document
stored in DK
AZSPU-HSSE-DOC-
AzSPU HSE Document Management
00025-2
Document
Procedure
Procedure
Documentum Controlled document
Document template to be used for document
MOC-FRM-026
Document
template
stored in documentum
18.3 Documentation MoC - Risk / Hazard Guidance
Note: This risk associated directly with making the change and should not be confused with MoC priority
Risk Level
Hazard Statement
Documentation-
Managed within the operating area no MoC required
Insignificant Risk
Documentation- Risk
Managed within the Operating area - MoC required
level 1 (white)
MoC with a risk level 1 (OMS Risk Matrix)
Managed within the Operating area but will have independent technical review and risk level 2
approval. - MoC required
MoC with a risk level 2 (OMS Risk Matrix)
Documentation - Risk
To be considered when there is a requirement to site check for HAZOP reasons, and / or
level 2 (turquoise)
multiple high level drawings are being site checked for equipment and correctness.
Critical DC&I Documentation
Managed within the Operating area but will have independent technical review and risk level 3
Documentation - Risk
approval. - MoC required
level 3 (blue)
MoC with a risk level 3 (OMS Risk Matrix)
Managed within the Operating area but will have independent technical review and risk level 4
Documentation - Risk
approval. - MoC required
level 4 (Purple)
MoC with a risk level 4 (OMS Risk Matrix)
Documentation MoC - Documentation
At the heart of any change, is the control of documents and data that personnel use. Everyone needs to understand
the status of these items at three key stages of change.
Stage
Requirement
Verify (Design)
Check out the document to indicate that it is subject to change
Any documents changed that are identified as controlled and / or Engineering Critical must be red-lined, signed and
Authorisation
dated.
Documents have been as-built as per requirements, fully checked by relevant technical discipline and fully loaded into
document database.
Closure
All superseded documents are identified and marked up
To ensure that the document has a document owner and authority so that working issues can be raised and addressed
18.4 Documentation MoC - Key Indicators
Number of days to close out an MoC after Authorization. This indicates how long it takes to get accurate
documents into the system.
Number of MoCs in review and/or approval stage without red-lined drawings in place - This indicates that MoC is
not being correctly reviewed and approved and the change is not fully visible, increasing risk.
AzSPU-GEN-PRC-001-A2
Page 78 of 102
18.5 Documentation MoC - Process Flow Diagram
DOCUMENTATION MoC
Use template describe, detail
Identify
scope, justify, attach supporting
the need
documentation assign category,
for change
anyone
priority and risk level
yes
canel
Confirm that the change is
required and all info is included
no
no
Document owner
modify
Confirm that all the required detail has been
provided - assess Hazard and Risk
Confirm priority and risk levels are correct
IDENTIFY WHO IS RESPONSIBLE FOR
SIGNING OFF EACH STAGE OF THE THE MOC
Change accepted and meets
NO
standards
ANYONE AS REQUIRED
YES
NO
DOCUMENT AUTHORITY (TL OR
MANAGER)
Change accepted and all
RISK LEVEL 3 AND 4
issued addressed
(DC&I) VP & WEA
EA
RISK LEVEL 4
YES
VP, E&P VP
ANY PRE IMPLEMENTATION ACTIONS ARE COMPLETE
COORDINATOR
DOCUMENT AUTHORITY (TL
AUTHORISE
OR MANAGER)
DOCUMENT COORDINATOR
UPDATE THE MASTER DATA BASE ENSURE OLD DOCUMENTS ARE VOIDED AND
NEW DOCUMENTS ARE UPLOADED
no
All post implment
COORDINATOR
actions complete
close
MOC/EQ TEAM
yes
AzSPU-GEN-PRC-001-A2
Page 79 of 102
19 Specific Guidance - Organizational MoC
This process should be used to manage all temporary and permanent changes to organization, personnel, and contractor services to ensure that any business risks arising
from these changes are managed to an acceptable level.
Organizational change falls into two main categories
Personnel change - one in and one out-with job content remaining the same but person changes. In situations where individual discipline professionals or TLs are
handing over a post, the need is to ensure appropriate knowledge of current issues and work in progress is transferred.
Organizational change - changes of structure, business or teams merging, de-merging, down or upsizing, relocating, changes of roles within organization
Company to third party and third party to third party contracted services
19.1 Organizational MoC - Roles and Responsibilities
THOSE IDENTIFED BY A * ARE A MINIMUM REQUIREMENT FOR RISK LEVEL 1
MoC
Risk
Job function
Responsibility
Stage/Role
For Personnel changes identifies who is changing out with who
Initiate
1/2/3/4
*Anyone
For organizational change defines reasons, objective, outcomes, Terms of Reference, should be provided.
Identify the Verifier
Verifies the personnel change,
1/2/3/4
*TL
Ensures appropriate contract and call-off is in place through PSCM to cover 3rd party services change
To identify who needs to be involved for each of the stages of the MoC as per this procedure
AOM / VP, or
For organizational change
Verify
Facility Manager,
To review the MoC and verify the organization change can proceed
or Maintenance
To identify who is responsible for MoC coordination
3/4
& Reliability
To verify High Risk MoC
Manger, or Head
To confirm the Terms of Reference
of Department
To identifies the Change Review Team,
To manage the MoC through the process ensuring that correct persons are notified. That comments are answered. That risks have
*Anyone
been assessed mitigation in place if required, that all pre-implementation and post implementation actions have been identified and the
Coordinator
1/2/3/4
Authorized
MoC is properly closed out
2/3/4
PSCM specialist
To confirm that appropriate contract is in place and necessary elements are covered for 3rd party services change
Reviewer
3/4
HSEA
To ensure that any HSE issues associated with the Organizational change have been correctly identified and addressed.
3/4
HR specialist
Independent review of Organizational Change identifying any risks
*Department
1/2/3/4
manager
Approve the personnel change
Approve
2/3/4
PSCM manager
Approve 3rd party contract changes
Approve Organizational Change
/3/4
AOM / VP
To ensure that all appropriate funding is in place
Approve Organizational Change
4
E&P VP
To ensure that all pre-implementation actions have been identified and completed, and any announcements made. Authorizing the
Authorize
1/2/3/4
*TL
change for implementation on site
AzSPU-GEN-PRC-001-A2
Page 80 of 102
3/4
AOM / VP
To ensure that all pre-implementation actions have been identified and completed, and any announcements made
*Coordinator
To ensure that all post implementation actions have been completed and any organigrams & non HR data bases have been updated
1/2/3/4
and responsibilities have been handed over
Post Implement
To confirm organigrams have been updated, that all check list as required have been completed and all HR data bases have been
1/2/3/4
*HR MANAGER
updated
Close out
1/2/3/4
*MOC/ EQ TEAM To confirm that all post implementation actions have been completed as identified in this procedure
AzSPU-GEN-PRC-001-A2
Page 81 of 102
Note: At any stage reviewers and approvers may be added to the MoC if considered necessary
Note: If the change is confidential then all attachments etc should be stored in a secure area
19.2 Organisational MoC - Template Attachments
The following will be linked directly to the MoC template to assist with the uniform creation of MoC
Document number
Document Title
Applies to
Notes
MOC PRIORITIZATION TOOL
ALL MoC TYPES
This tool is the same as the one used for EQ and is used to
MOC-FRM-008
IFP
ensure that all MoC are consistently categorized and
prioritized
ORGANIZATION MoC
ORGANISATIONAL
To be complete for personnel change over to ensure all
MOC-FRM-019
HANDOVER FORM
responsibilities and accountabilities have been transferred
ORGANIZATION MoC RISK AND
ORGANISATIONAL
To be used for major organizational change affecting the
MOC-FRM-020
MITIGATION
structure of the organization
ORGANIZATION MoC RISK
ORGANISATIONAL
To be used for major organizational change affecting the
MOC-FRM-021
MATRIX
structure of the organization
ORGANIZATION MoC CLOSE
ORGANISATIONAL
To be used for major organizational change affecting the
MOC-FRM-022
OUT REVIEW
structure of the organization
19.3 Organisational MoC - Risk / Hazard Guidance
Note: This risk associated directly with making the change and should not be confused with MoC priority
Risk Level
Hazard Statement
Organisational -
Managed within the operating area no MoC required
insignificant Risk (
Managed within the Operating area - MoC required
Organisational - Risk
level 1 (white)
MoC with a risk level 1 (OMS Risk Matrix)
Personnel change which does not change the organisational structure
Managed within the Operating area but will have independent technical review and risk level 2
Organisational - Risk
approval. - MoC required
level 2 (turquoise)
MoC with a risk level 2 (OMS Risk Matrix)
Company to third party and third party to third party contracted services
Managed within the Operating area but will have independent technical review and risk level 3
approval. - MoC required
Organisational - Risk
level 3 (blue)
MoC with a risk level 3 (OMS Risk Matrix)
Organisational change affecting the structure of the organisation
Managed within the Operating area but will have independent technical review and risk level 4
Organisational - Risk
approval. - MoC required
level 4 (Purple)
MoC with a risk level 4 (OMS Risk Matrix)
19.4 Organizational MoC - Documentation
At the heart of any change, is the control of documents and data. Everyone needs to understand the status of these
items at three key stages of change.
Stage
Requirement
Verify (Design)
To ensure change is announced
Authorisation (pre-start up)
Ensure third party services providing contract and appropriate call-off are signed
To ensure that all organigrams have been updated and posted and all responsibilities have
Closure (post-start up)
been transferred
19.5 Organizational MoC - Key Indicators
Number of days to close out an MoC after authorization. This indicates how long it takes to get accurate
documents into the system.
Number of MoCs authorized to start up at any one time - A high number indicates increased risk depending on
the sites ability to manage many simultaneous changes.
AzSPU-GEN-PRC-001-A2
Page 82 of 102
Number of MoCs in review and approve stages - This indicates the loading on the facility teams.
19.6 Organizational MoC - Process flow diagram
Organizational MoC
Use template describe, detail
Identify
scope, justify, attach supporting
the need
documentation assign category,
for change
anyone
priority and risk level
yes
canel
Confirm that the change is
TL
required and all info is included
no
no
Risk level 3 or 4
AOM/ VP OR FACILITY
MANAGER OR MAINTENANCE
modify
Confirm that all the required detail has been
RELIABILITY MANAGER OR
provided - assess Hazard and Risk
HEAD OF DEPARTMENT
Confirm priority and risk levels are correct
IDENTIFY WHO IS RESPONSIBLE FOR
SIGNING OFF EACH STAGE OF THE THE MOC
Change accepted and meets
NO
TL
RISK LEVEL 3 AND 4
standards
HSSE ADVISOR
HR SPECIALIST
YES
NO
TL
Change accepted and all
RISK LEVEL 3 AND 4
issued addressed
HR MANAGER, AOM ,VP
RISK LEVEL 4
E&P VP
YES
ANY PRE IMPLEMENTATION ACTIONS ARE COMPLETE
COORDINATOR
DOCUMENT AUTHORITY (TL
AUTHORISE
OR MANAGER)
COORDINATOR
ENSURE THAT ALL POST IMPLEMENTATION ACTIONS HAVE BEEN IDENTIFIED AND
DOCUMENT COORDINATOR
ANY ORGANIGRAMS HAVE BEEN UPDATED, THAT ALL CHECK LIST AS REQUIRED
HR MANAGER
HAVE BEEN COMPLETED AND ALL DATA BASES HAVE BEEN UPDATED
no
All post implment
COORDINATOR
actions complete
close
MOC/EQ TEAM
yes
AzSPU-GEN-PRC-001-A2
Page 83 of 102
20 Specific Guidance - IT&S MoC
IT&S have a global change management process and GSMS (Global Service Management System link: http://gsms.bpweb.bp.com) system for managing each change. IT&S
will use GSMS process as required by the function.
Scheduled system outages related to maintenance activities are not considered as change and normal IT&S GSMS procedure will be followed. All users will be notified 7 days
in advance of any system outage required for planned maintenance, allowing business users and stakeholders to raise any concerns that they may have.
Emergency maintenance notifications will be sent to business users within 24hrs.
IT&S GSMS will be used together with IT&S eMOC in order to implement any change that require business technical endorsement and impacts safety critical equipment or
requires modification to approved infrastructure design based on criteria below:
For any project related activities or system enhancements originated by IT&S and which will affect business processes or infrastructure IT&S Project Manager or his
delegate will raise GSMS change request
(if required) and IT&S eMOC. Business stakeholders will ensure that affected business processes are
managed/changed/approved appropriately in eMOC.
For any project related activities or system enhancements not originated by IT&S the business will initiate appropriate eMOC and will ensure that affected business
processes are managed/changed/approved appropriately. If a change will consequently affect any IT&S systems/processes then corresponding GSMS change request
will be raised by IT&S project manager or his delegate.
20.1 IT&S MoC - Roles and Responsibilities
MoC Stage
Risk
Job function
Responsibility
To initiate the eMoC providing description and justification and any other information required by the change.
Initiate
2/3/4
Anyone
Identify the eMoC verifiers.
Verify
2/3/4
TL- IT&S
To verify that the request is supported by the Az SPU IT&S and assign persons to each stage o f MoC
To manage the MoC through the IT&S GSMS process ensuring that correct persons are notified and that comments are answered
IT&S Change Owner
Coordinator
2/3/4
and the MoC is properly closed out.
(same as per GSMS)
IF a physical change is required on site then a technical moc will be raised
To review the change and state reason for any rejections
2/3/4
TL- IT&S BIMs
To verify that the request is supported by the operations
Reviewer
2/3/4
Service Delivery Manager
To verify that the request is supported by the operations
2/3/4
IT&S Technical Authority
Facility Manger or
To approve the change and state reason for any rejections
2/3/4
Department manager
Approve
2/3/4
Application Business Owner
To approve the change if applicable to a specific application
3 / 4
VP
To approve the risk level 3 & 4
4
E&P VP
To approve the risk level 4
IT&S Change Owner
Pre implement
2/3/4
To raise Technical MOC if physical change is required on site
(same as per GSMS)
AzSPU-GEN-PRC-001-A2
Page 84 of 102
To authorize for implementation once all necessary approvals are in place
2/3/4
TL-IT&S
Authorize
To ensure that any pre implementation actions have been identified and completed.
2/3/4
TL or Facility Managers
To authorize for implementation on site
IT&S Change Owner
2/3/4
To ensure that all post-implement actions have been completed and lessons learnt issued
(same as per GSMS)
Close out
1/2/3/4
MOC/ EQ TEAM
To confirm that all post implementation actions have been completed as identified in this procedure
Note: The roles in black bold font are the minimum required for a low risk MoC with others to be added in line with risk level as indicated in the risk column or as required.
Note: At any stage reviewers and approvers may be added to the MoC if considered necessary
AzSPU-GEN-PRC-001-A2
Page 85 of 102
20.2 IT&S MoC - Templates
The following will be linked directly to the MoC template to assist with the uniform creation of MoC
Document
Document Title
Applies to
Notes
number
AZSPU SOFTWARE
Used to identify who needs to be consulted for IT&S
UNIF-ITS- REG-001
IT&S
APPLICATIONS REGISTER
application changes
20.3 IT&S MoC - Risk / Hazard Guidance
Note: This risk associated directly with making the change and should not be confused with MoC priority
Risk Level
Hazard Statement
Managed within the operating area no MoC required
Scheduled system outages related to maintenance activities are not considered as change and
IT&S - Insignificant
normal IT&S GSMS procedure will be followed. All users will be notified 7 days in advance of any
Risk (
system outage required for planned maintenance, allowing business users and stakeholders to
raise any concerns that they may have.
IT&S - Risk level 1 (
Managed within the Operating area - MoC required
white)
MoC with a risk level 1 (OMS Risk Matrix)
Managed within the Operating area but will have independent technical review and risk level 2
approval. - MoC required
IT&S l - Risk level 2
MoC with a risk level 2 (OMS Risk Matrix)
(turquoise)
IT&S GSMS will be used together with IT&S eMOC in order to implement any change that
require business technical endorsement and impacts safety critical equipment or requires
modification to approved infrastructure design.
Managed within the Operating area but will have independent technical review and risk level 3
IT&S - Risk level 3
approval. - MoC required
(blue)
MoC with a risk level 3 (OMS Risk Matrix)
Managed within the Operating area but will have independent technical review and risk level 4
IT&S - Risk level 4
approval. - MoC required
(Purple)
MoC with a risk level 4 (OMS Risk Matrix)
20.4 IT&S MoC - Documentation
At the heart of any change, is the control of documents and data. Everyone needs to understand the status of these
items at three key stages of change.
Stage
Requirement
Verify (Design)
Not applicable
Authorisation (pre-start up)
Not applicable
Closure (post-start up)
Documents and user manual has been updated
IT&S MoC - Key Indicators
Number of days to close out an MoC after authorization. This indicates how long it takes to get accurate
documents into the system.
Number of MoCs authorized to start up at any one time - A high number indicates increased risk depending on
the sites ability to manage many simultaneous changes.
Number of MoCs in review and approve stages - This indicates the loading on the facility teams.
AzSPU-GEN-PRC-001-A2
Page 86 of 102
20.5 IT&S MoC - Process Flow Diagram
IT&S MoC
Use template describe, detail
Identify
scope, justify, attach supporting
the need
documentation assign category,
for change
anyone
priority and risk level
yes
canel
Confirm that the change is
required and all info is included
no
no
Tl-IT&S
modify
Verify that the request is supported by IT&S
Confirm priority and risk levels are correct
IDENTIFY WHO IS RESPONSIBLE FOR
SIGNING OFF EACH STAGE OF THE THE MOC
NO
TL-IT&S BIMS
Change accepted and meets
IT&S Technical Authority
standards
OTHERS AS REQUIRED
NO
YES
FACILITY MANAGER OF
DEPARTMENT MANAGER
Change accepted and all
OTHERS AS REQUIRED
issued addressed
RISK LEVEL 3 4
VP
RISK LEVEL 4
YES
E&P VP
GSMS PROCESS LINKED TO MOC
If a physical change on site is required an technical MoC will be raised
COORDINATOR
TL&ITS
AUTHORISE
OTHERS AS REQUIRED
COORDINATOR
ANY IDENTIFIED POST IMPLEMENTATION ACTIONS
no
All post implment
COORDINATOR
actions complete
close
MOC/EQ TEAM
yes
AzSPU-GEN-PRC-001-A2
Page 87 of 102
20.6 Specific Guidance - Marine MoC
Marine Change is a permanent, temporary or emergency physical change that affects everything owned or operated or contracted by AzSPU that floats excluding Mission
systems as long as there is no impact on marine systems.
A Marine Contractor operates his own MoC system. Where the Contractor MoC addresses a situation which would attract a "risk level 3 or 4" ranking in an AzSPU eMOC, the BP
Contract Technical Specialist shall inform the BP Marine Authority (MA). The MA in such situation will request the Operations Marine Authority (OMA) to initiate an AzSPU eMOC
for the purpose of corroborating the particulars contained in the Contractor MOC.
Note: Definition of Mission System, Special purpose equipment installed on a marine unit for executing non-marine activities. For example, related to diving, ROV, seismic,
drilling, coring, hydrography, pipelay, subsea installation, heavy lift offshore
Note: An eMOC is also required in the situation where a new vessel is permanently introduced into the fleet or when there is a change in the role of an existing marine unit, for
example a supply vessel being adapted for the purpose to undertake seismic or subsea installation work, or to conduct offshore crew changes.
20.7 Marine MoC - Roles and Responsibilities
THOSE IDENTIFED BY A * ARE A MINIMUM REQUIREMENT FOR RISK LEVEL 1
MoC
Risk
JOB FUNCTION
Responsibility
Stage/Role
To create the eMOC choosing the affected Area and Facility and will choose the Marine template (the use of a template is a mandatory
requirement).
To identify the scope of work (identifies the change which identifies and describes all work necessary to produce the change. The scope
establishes the tone for the remainder of the planning efforts and therefore should be sufficiently detailed.).
To provide a justification for the work (this section details why the change is required)
To provide details of other options considered.
Initiate
1/2/3/4
*ANYONE
Where the change is required due to some other business process, Engineering Query, incident report etc, the initiator shall reference this
process.
To initiator is required to identify the Key Change Verifier as OMA.
To suggest priority
The EQ system is used by the operating area operations teams to formally raise technical questions and should be linked if available. Operating
areas may cancel an MoC that has not been agreed using the EQ or other operating area system.
AzSPU-GEN-PRC-001-A2
Page 88 of 102
|
||
|
|
|