Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 16

 

 

 

G

ENERAL 

R

 

 

 

8.  Pile bearing capacity design calculations and recommendations 

The Contractor shall also provide the following analyses and recommendations, when applicable: 

1.  Lateral pile load analysis 

2.  Pile tip protection 

3.  Pile uplift capacity 

d.  Haul Bridges  

When the Contractor proposes the construction of haul road bridges or other bridges that are not for 
public  use  over  any  right-of-way  that  is  open  to  the  public  or  that  is  over  any  railroad,  they  shall 
submit working drawings that show complete design and details, including the maximum loads to be 
carried,  to  the  Engineer  for  approval.  Such  drawings  shall  be  signed  by a  professional  Engineer. 
Such designs shall conform to AASHTO LRFD Bridge Design Specification, when applicable, or to 
other appropriate standards. 

1.16.12.2  Maintenance for Temporary Bridges 

Maintenance  of  temporary  bridges  for  which  working  drawings  are  required  shall  include  their 
replacement in case of partial or complete failure. In case of the Contractor delays to the project or 
makes inadequate progress on repairs and replacement or fails to furnish such labour, materials, 
and  supervisions  of  the  work  as  may  be  necessary  to  restore  the  structure  to  a  proper  condition 
suitable  for  movement  of  traffic,  the  Owner  will  make  such  repairs  and  the  full  costs  for  such 
restoration and repairs shall be charged back to the Contractor. 

1.17 

Sediment and Pollution Control 

1.17.1 

Description 

Work under this section shall include furnishing, installing, maintaining, removing and disposing of 
temporary sediment and pollution control measures such as wind and rain erosion control silt fences, 
check  dams,  straw  barriers,  and  other  devices  or  methods  as  otherwise  may  be  required  for  the 
Contractors  environmental  sediment  and  pollution  control  plan  as  specified  in  Section  1.15.9,  as 
shown in the Drawings as required in the Particular Specifications as may be required by Abu Dhabi 
EAD or as directed by the Engineer.  

This work also includes the fencing and construction avoidance of areas to be protected as may be 
shown  on  the  Drawings,  included  in  the  Particular  Specifications,  directed  by  the  Engineer  or 
required by Abu Dhabi EAD.  

Design  requirements  on  all  temporary  sediment  and  pollution  control  measures  shall  be  in 
accordance with Chapter 14 of the Abu Dhabi Road Drainage Manual, AD-D-07,

 

and as specified 

herein.  

1.17.2 

Protective Fencing 

Contractor  shall  install  high  visibility  fencing  around  all  areas  to  be  protected  from  construction 
personnel  and  equipment  intrusion  as  shown  on  the  drawings,  included  in  the  particular 
specifications, directed by the Engineer or required by Abu Dhabi EAD, which may include vegetated 
agriculture,  trees  and  landscaping  areas,  environmentally  sensitive  areas,  historic  areas, 
archaeology sites, public access areas, inhabiting species habitats, and protected coral/mangrove 
areas. Contractor shall conduct training for all construction personnel about necessity to protect and 
avoid those protected sites. 

1.17.3 

Sediment Controls 

Sediment  control  involves  both  control  of  sediment  at  a  dewatering  or  temporary  stormwater 
discharge location as well as erosion control caused by wind or rain on open unprotected soils in the 

 

G

ENERAL 

R

 

 

 

construction area. Sediment and erosion controls, both temporary and permanent, shall be installed 
in  accordance  with  Contractor’s  approved  staging  and  phasing  plans  and  coordinated  with  the 
related construction work. 

Control  of  sediment  and  erosion,  caused  by  both  wind  and  precipitation  runoff  and  dewatering 
operations require the Contractor to perform temporary work items including but not  limited to the 
following items: 

1.  Providing  ditches,  berms,  culverts,  temporary  drainage  diversions  and  other  measures  to 

control surface water 

2.  Building berms, settling basins, diversions, and other measures, to control movement of sand 

and sediments to downstream locations carried by the stormwater flows 

3.  Managing dewatering methods to avoid sediment discharge 

4.  Covering  or  otherwise  protecting  soil  slopes  and  stockpiles  until  permanent  erosion  control 

measures can be applied 

5.  Providing  measures  to  control sand  movement  and  dust caused  by  construction  operations 

and wind 

To the degree possible, the Contractor shall coordinate this temporary work with permanent drainage 
and erosion control work the Contract requires. 

Engineer may require additional temporary control measures if it appears pollution or erosion may 
result from weather, the nature of the materials, or progress on the work. 

When natural elements rut or erode the slope, the Contractor shall restore and repair the damage 
with the eroded material where possible, and clean up any remaining material in ditches and culverts.  

If the Engineer anticipates water pollution or erosion, the Contractor shall schedule the work so that 
grading and erosion control immediately follows clearing and grubbing. 

Engineer  may  also  require  erosion  control  work  to  be  done  with  or  immediately  after  grading. 
Clearing,  grubbing,  excavation,  borrow,  or  fill  within  the  project  limits  shall  never  expose  more 
erodible earth than required for the immediate work, without approval by the  Engineer: During the 
winter months of 15 October through 15 April, unprotected soil surfaces in a active work area shall 
be stabilized by either the permanent erosion control measures or temporary measures, as approved 
by the Engineer, prior to opening up another open soil work site. 

Contractor shall be responsible for maintaining all erosion control measures in proper functioning 
condition at all times. 

When deficiencies in the erosion control devices or other elements of work listed herein are noted 
by inspection or other observation, corrections shall be made by the Contractor by the end of the 
day or work shift when directed by the Engineer. 

Work specified herein which is lost, destroyed, or deemed unacceptable by the Engineer as a result 
of  the  Contractor's  operations  shall  be  replaced  by  the  Contractor  at  no  additional  cost  to  the 
Department. 

Work specified herein which is lost  or  destroyed as a result of  natural events, such as excessive 
rainfall,  which  is  replaced  by  the  Contractor  at  the  direction  of  the  Contractor,  will  be  paid  for  in 
accordance with the requirements of the bills of quantities. 

1.17.4 

Pollution Controls 

Pollution control measures shall be installed in accordance with phasing provisions in the approved 
plans and coordinated with the related construction.  

Controlling pollution requires the Contractor to perform work items including but not limited to the 
following items: 

 

G

ENERAL 

R

 

 

 

1.  Provide for dust and wind born sand and sediment controls to control air pollution 

2.  Implement  spill  and  leak  prevention  procedures  for  paints,  chemicals  and  hazardous 

substances stored on the job site. Have in place a plan for emergency spill containment and 
cleanup,  including  the  providing  and  convenient  access  storage  on-site  of  cleanup  and 
containment materials. 

3.  Provide positive containment and oil/water separation for stormwater runoff from equipment 

maintenance, storage and refuelling yards and depots 

4.  Manage  stormwater  on  a  temporary  basis  to  avoid  movement  of  sediments  and  roadway 

pollutants  to  downstream  locations,  in  particular  where  such  sediment  will  cause  problems 
such as discharge to environmentally sensitive mangrove and coral areas or damaging other 
structures or plugging existing storm drain systems 

5.  Managing dewatering or providing sediment traps or filters prior to discharge to avoid sediment 

discharges to sensitive areas or existing storm drains. 

In cases of serious or wilful disregard for the protection of protected areas by the Contractor, the 
Engineer  will  immediately  notify  the  Contractor  of  such  non-compliance.  If  the  Contractor  fails  to 
remedy the situation within 24 hours after receipt of such notice, the Engineer may immediately place 
the erosion and/or other pollution control elements in proper condition and deduct the cost thereof 
from moneys due the Contractor. 

1.17.5 

Materials 

1.17.5.1 

Submittals 

The  Contractor  shall  provide  an  environmental,  sediment  and  pollution  control  (SPC)  plan  in 
accordance with Sections 1.15.1 and 1.15.9, and per the additional requirements as follows: 

a.  Generally the SPC plan should be submitted at the same time as the Contractors staging and 

detour  plans,  since  the  SPC  plan  must  be  coordinated  with  the  work  staging  location  and 
schedule. 

b.  Contractor shall provide a schedule for SPC plan implementation and incorporate it into the 

Contractor’s construction schedule.  

c. 

Contractor shall obtain the Engineer’s approval of the SPC Plan and schedule before any work 
begins.  

d. 

SPC plan shall cover all areas the Contractor’s work may affect inside and outside the limits 
of the project (including all borrow and disposal sites, and haul roads, and staging areas which 
shall show: 

1.  Location  of  disturbed  soil  areas,  areas  to  be  protected  from  construction,  existing  storm 

drains  and  those  to  be  constructed  as  part  of  that  work  stage,  dewatering  facilities  and 
discharge locations 

2.  Show locations of specific sediment and pollution control measures 

3.  Describe  in  detail the  design,  installation,  maintenance, repair,  and removal  of  proposed 

specific sediment and pollution control measures 

4.  Describe  in  detail  the  design,  installation,  maintenance,  repair  and  removal  of  proposed 

general site sediment and pollution control measures (i.e. for general dust and spill control 
measures) 

 

G

ENERAL 

R

 

 

 

5.  Show  the  locations  and  types  of  specific  temporary  sedimentation  and  pollution  control 

practices that will be used in the work for each construction phase 

6.  Show  the  locations  and  types  of  wind  and  water  pollution  control  practices  that  will  be 

installed permanently under the Contract. 

7.  If dewatering, submit dewatering and discharge work plan. Work plan shall include: 

i. 

Description  of  dewatering  and  discharge  activities  detailing  locations,  quantity  of 
water, equipment, type of dewatering and discharge point 

ii. 

Estimated schedule for dewatering and discharge start and end dates of intermittent 
and continuous activities 

iii. 

Sediment  avoidance  measures  at  discharge,  which  may  include  discharge 
alternatives, such as infiltration, filtration or sediment traps  

iv. 

Visual monitoring procedures with inspection log  

v. 

Obtain approval to discharge into a existing storm drain system  

8.  Items as otherwise required herein. 

Contractor shall amend and resubmit the SCP plan to match any revisions to his program, staging, 
detouring and schedule that effects the proper implementation of the approved SCP plan. 

Contractor  shall  submit  catalogue  c

uts,  manufacturer’s  installation  and  maintenance 

recommendations and specifications and material test results for all materials and items used for 
temporary sediment and pollution control measures. Contractor shall provide samples and specific 
testing of the materials if required by the Engineer. 

1.17.5.2 

Geotextile 

Temporary  geotextile  covering  shall  meet  the  requirements  of  Article  2.7.3.2  of  Chapter  2, 
Earthworks. 

1.17.5.3 

Plastic 

Temporary plastic covering shall meet the requirements of the NIST Voluntary Product Standard, 
PS 17-69, for polyethylene sheeting having a minimum thickness of 6 mils 

1.17.5.4 

Erosion Control Blankets/Mats 

a.  Temporary  erosion  control  blankets  shall  consist  of  temporary,  degradable,  rolled  erosion-

control products composed of natural fibres mechanically or structurally bound together with 
natural or polymer netting to form a continuous matrix. Erosion control blankets are classified 
as to two types, as follows: 

1.  Short 

– term duration  

2.  Extended-term duration 

b.  Short - term duration blankets shall have a minimum one-year degradation period for both the 

netting and fibres, and be composed of 100 % virgin aspen excelsior wood fibres or 100 % 
agricultural straw.  

c.  Extended-term blankets shall have a minimum two-year degradation period for the netting and 

fibres, and be composed of heavy-duty excelsior blankets, or a mix of 70 % straw and 30 % 
coconut fibres, or 100 % coconut fibres. Heavy-duty excelsior blankets used in the extended-
term category shall have a minimum weight of 0.38 kg/m

2

 

G

ENERAL 

R

 

 

 

d.  All other types of blankets, whether for short - term or extended-term use shall have a minimum 

weight of 0.27 kg/m

2

Fibres  for  short-term  erosion  control  blankets  shall  be  encased  top  and  bottom  with 
photodegradable polypropylene or 100-percent biodegradable natural organic fibre netting, as 
specified on the plans. 

e.  Should the plans not specify type of netting for short-term blankets, fibres shall be encased 

with  photodegradable  polypropylene.  Fibres  for  extended-term  blankets  shall  be  encased 
within either a heavy duty UV stabilized top netting (black) and bottom nettings (green), or two 
UV  stabilized  nettings  (black).  All  nettings  for  extended-term  blankets  shall  be 
photodegradable polypropylene. 

Erosion control blankets shall also conform to the following requirements: 

Table 1-7: Erosion control blanket requirements 

Property 

Test method 

ASTM 

Short-term 

duration 

Extended-term 

duration 

Minimum mass per unit area 

D6475

 

 

271 g/m

2

 

271* g/m

2

 

Minimum thickness** 

D5199

 

 

6.35 mm 

6.35 mm 

Minimum tensile strength (kg/m)*** 

D5035

 

 

111 

148 

*Heavy duty blankets shall have a minimum mass per unit area of 372 g/m

2

 

**Numerical value represents total thickness of blanket, including netting. 

***Numerical value represents minimum average test result in either direction. 

Fibre colour shall be natural unless otherwise specified in the Particular Specifications. 

a.  Fibres shall be free of weed seed, and shall be locked in place to form a mat of consistent 

thickness. Fibres shall remain evenly distributed over the entire area of the blanket after being 
placed on the slope. 

b.  Erosion control blankets shall be furnished in 1.2 to 2.4 m wide rolls, and shall be wrapped 

with suitable material to protect against moisture and extensive ultraviolet exposure prior to 
placement. 

Each roll shall be labelled to provide sufficient identification for quality control purposes. 

a.  All biodegradable ECPs must be anchored using wire staples.  

b.  Contractor  shall  provide  certificates  of  compliance  from  the  manufacturers,  for  all  erosion 

control blankets. 

1.17.5.5 

Anchors 

Staples shall be made of 3.05 mm steel wire and shall be U-shaped with 200 mm legs and 50 mm 
crowns. 

Metal stake pins shall be 5-mm-diameter steel with a 40 mm steel washer at the head of the pin. 

All  anchors  shall  be  a  minimum  of  150  mm  long  and  have  sufficient  penetration  to resist  pullout. 
Longer anchors may be required for loose soils or by the manufacturer’s installation guidelines. 

1.17.5.6 

Pipe Slope Drains 

Pipe materials shall conform to Articles 12.1.3.6 and 12.1.3.7c of Chapter 12, Stormwater Drainage 
for corrugated metal and PVC pipe.  

 

G

ENERAL 

R

 

 

 

Loose riprap rock and bedding shall conform to Section 7.4.3 of Chapter 7, Incidental construction, 
of these standard specifications. 

1.17.5.7 

Fabric Fence 

a.  Fabric 

Fabric or silt fence fabric shall be supplied in accordance with the material requirements of Section 
2.7.2 of Chapter 2, Earthworks. 

b.  Posts 

Posts  for silt fence can be wood or  steel conforming to the requirements of  Article 7.7.2.4. Posts 
shall be a minimum of 1 metre plus the burial depth in length and may be made of either wood or 
steel. Soft wood posts shall be at least 75 mm in diameter, or nominal 50 mm by 100 mm and straight 
enough to provide a fence without noticeable misalignment. If oak posts are used, the size may be 
reduced to 38 mm by 38 mm with a minus tolerance of 3 mm, provided that the cross sectional area 
is  a  minimum  of  1450  mm

2

.  Steel  posts  shall  have  a  minimum  weight  of  1.95  kg/m,  and  have 

projections for fastening the wire and fabric to the fence.  

c.  Wire Supported Fence 

Wire support fence shall be a minimum of 830 mm high composed of 2.8 mm diameter steel wire 
mesh fencing material. 

Wire staples shall be 1.2 mm diameter and shall have a crown at least 19 mm wide and legs at least 
13 mm long. Staples shall be evenly spaced with at least five per post. 

Nails shall be 2 mm in diameter, 25 mm long with 19 mm button heads. Nails shall be evenly spaced 
with at least four per post. 

d.  Fabric Packaging, Handling, and Storage 

Identification, packaging, handling, and storage of the geotextile fabric shall be in accordance with 
ASTM D4873. Fabric rolls shall be furnished with suitable wrapping for protection against moisture 
and extended ultraviolet exposure prior to placement. 

Each  roll  shall  be  labelled  or  tagged  to  provide  product  identification  sufficient  to  determine  the 
product type, manufacturer, quantity, lot number, roll number, date of manufacture, shipping date, 
and the project number and name to which it is assigned. Rolls will be stored on the site or at another 
identified storage location in a manner which protects them from the elements. If stored outdoors, 
they shall be elevated and protected with a waterproof, light colour, opaque cover. 

1.17.5.8 

Rock and Aggregate 

Geotextile  fabric  for  riprap  shall  meet  the  requirements  of  Article  7.4.3.2  of  Chapter  7,  Incidental 
construction. 

Gradation of the loose rock for erosion control shall meet the requirements of Sub-article 7.4.3.2.a 
of Chapter 7, Incidental construction, for hand placed riprap and Sub-article 7.4.3.2.c, for pit run or 
quarry spalls rock. 

Riprap  bedding  aggregate  shall  meet  the  requirements  of  Article  7.4.3.2  of  Chapter  7,  Incidental 
construction. 

Crushed rock or gravel for temporary or permanent ground surface coverings shall consist of hard, 
durable rock, with at least two fractured faces of size ranging from 6 to 50 mm nominal diameter. 

 

G

ENERAL 

R

 

 

 

1.17.5.9 

Gravel Bags  

Gravel bags consist of a heavyweight fabric (synthetic or canvas materials), sewn sack filled with 
gravel and the opening closed with a wrap of twine or wire. Weight of the filled sack shall not exceed 
50 kg, so that it can be handled by two people, one on each end. 

Bags, when filled shall measure approximately 600 mm long by 400 mm wide by 100 mm thick. Bag 
dimensions are nominal and may vary locally but shall not be significantly different. Alternate bag 
sizes shall be submitted to Engineer for approval.  

Gravel shall be between 10 mm and 20 mm in diameter.  

Gravel shall be clean and free from clay balls, organic matter and deleterious material.  

Bags shall be manufactured from polypropylene, polyethylene, or polyamide woven fabric with the 
following characteristics: 

 

Table 1-8: Gravel bag requirements 

Unit weight, minimum 

135 g/m

2

 

Mullen burst strength, as per ASTM D3786, exceeding 

2 mPa 

Ultraviolet stability, as per ASTM D4355, exceeding, % 

70 % 

1.17.5.10  Fibre Rolls  

Erosion control blankets used to construct fibreroll shall meet the requirements of Article 1.17.5.4. 

Wooden stakes shall be made from wood of type and density to withstand the driving process, as 
approved by the Engineer. Stakes shall be 19 mm by 19 mm and maximum 1.2 m long. 

Erosion  control  blankets  used  to  construct  fibre  rolls  shall  be  between  2  m  and  2.4  m  wide  by 
approximately 15 m long. Wood excelsior blankets shall have 80 % of its fibres equal to or greater 
than  150  mm.  Blankets  used  to  construct  the  fibre  rolls  shall  have  photodegradable  plastic  or 
biodegradable natural netting, with a maximum 25 mm by 25 mm grid, on at least one side. 

Contractor shall produce fibre rolls by rolling the blankets along their width to produce 15 m lengths, 
and securing the rolls with jute twine spaced at 2 m intervals along the roll for the full length and at 
150 mm from each end. If shown on the plans or directed by the Engineer, the Contractor may cut 
the  blankets  before  rolling  to  produce  completed  fibre  roll  lengths  of  between  4  and  15  m  as 
applicable for the location. Nominal diameter of the finished rolls shall be 220, 300, or 450 mm, as 
shown  on  the  plans.  Overlapping  of  more  than  one  blanket  may  be  required  to  achieve  larger 
diameters. When overlapping is required, the end of one blanket shall overlap 150 mm onto the end 
of the next blanket prior to rolling. 

1.17.5.11  Temporary Fence 

High  visibility  fence  shall  be  used  by  Contractor  as  temporary  fencing  to  mark  protected  area 
boundaries as shown in plans such as for demarcating areas of vegetation protection.  

High visibility fence shall be at least 1.2 m tall UV stabilized, construction orange colour, high-density 
polyethylene or polypropylene mesh with mesh openings approximately 50 mm by 50 mm. Colour 
shall be construction orange. Fence posts shall be wood or steel and shall meet the requirements of 
Sub-article b of Article 1.17.5.7 

High visibility fence fabric shall have a minimum tensile strength of 145 kg per ASTM D5735. 

 

G

ENERAL 

R

 

 

 

1.17.6 

Construction Requirements 

1.17.6.1 

Preservation of Existing Vegetation and Topsoil 

Contractor shall comply with the following requirements: 

1.  Contractor shall preserve existing vegetation, topsoil and other existing soil covering materials 

at areas on a site where no construction activity is planned or will occur at a later date. 

2.  Temporary  fencing  shall  be  provided  around  areas  designated  for  being  maintained  from 

inadvertent disturbance by the Contractor’s operations. 

3.  Clearing and grubbing operations should be staged, with the area limited to the area that will 

be  immediately  under  construction.  Final  surface  covering  (paving,  decorative  pavers, 
landscaping, gravel, etc.) should be provided prior to moving to the next stage of the work. 

4.  Minimise  the  disturbed  areas  by  locating  temporary  roadways  to  avoid  stands  of  trees  and 

shrubs and to follow existing contours to reduce cutting and filling. 

5.  Consider the impact of grade changes to existing vegetation and the root zone. 

6.  Keep equipment away from trees and shrubs to be retained, to prevent trunk and root damage. 

7.  Maintain existing irrigation systems. 

8.  Employees and subcontractors shall be instructed to honour protective fences. 

9.  No heavy equipment, vehicular traffic, or storage piles of any construction materials shall be 

permitted within the drip line of any tree to be retained. 

10.  Removed trees shall not be felled, pushed, or pulled into any retained trees. 

11.  Prior to excavation and trenching, remove topsoil to a depth of 200 to 300 mm, and stockpile 

it for later re-application per requirements of Article 2.2.2.5 of Chapter 2, Earthworks. 

12.  Trenching shall be as far away from tree trunks as possible, usually outside of the tree drip 

line or canopy. Curve trenches around trees to avoid large roots or root concentrations. If roots 
are encountered, consider tunnelling under them. 

13.  When trenching and/or tunnelling near or under trees to be retained, tunnels shall be at least 

450 mm below the ground surface, and not below the tree centre, to minimise impacts to the 
roots. 

14.  Tree roots shall not be left exposed to air. They shall be covered with soil as soon as possible, 

protected, and kept moistened with wet burlap or peat moss until the tunnel and/or trench can 
be completed. 

15.  Smoothly cut off the ends of damaged or cut roots. 

16.  Trenches  and  tunnels  shall  be  filled  as  soon  as  possible.  Careful  filling  and  tamping  will 

eliminate air spaces in the soil that can damage roots. 

17.  Remove any trees intended for retention if they are damaged seriously enough to affect their 

survival. Such trees shall be replaced as directed by the Engineer at the Contractors expense. 

18.  After all other work is complete, temporary fences shall be removed last, because protected 

trees  may  be  destroyed  by  equipment  operator  carelessness  during  the  final  cleanup  and 
landscaping. 

 

G

ENERAL 

R

 

 

 

1.17.6.2 

Soil Surface Coverings 

This measure involves the placement of geotextile, plastic covers, erosion control blankets or gravel 
to stabilise disturbed areas and protect soils from erosion by wind or water. 

These measures are used as a temporary surface covering for the following situations: 

1.  Steep slopes, generally steeper than 1:3 velocity to height (V:H) in areas to be landscaped to 

hold the soil until the plant root zone is established. 

2.  Slopes of cuts and compacted embankments to be protected during the rainy season until the 

permanent slope protection measures can be installed. 

3.  Stockpiles  of  topsoil  or  other fine-grained  construction  materials  to  avoid  erosion  by  rain  or 

wind. 

4.  Temporary channels with flow velocities exceeding 1 m per second. 

5.  Slopes adjacent to environmentally sensitive areas. 

a.  Geotextile, Plastic and Blanket Installation 

Prior to laying of the covering, Contractor shall: 

1.  Grade and shape the area of installation. 

2.  Remove all rocks, clods, vegetation, or other obstructions so that the installed blankets or mats 

will have complete, direct contact with the soil. 

3.  When using a fabric or mat that is designed to be used in conjunction with seed or vegetation, 

follow the manufacturer’s guidelines for proper installation. Prepare the planting bed by either 
loosening the existing 50 to 75 mm of topsoil or placing new 150 to 200 mm thick topsoil per 
requirements of Article 13.1.3.10 of Chapter 13, Landscaping and irrigation. 

Installation  should  be  in accordance  with  the  manufacturer's recommendations.  In  general, these 
shall be as follows: 

1.  Begin at the top of the slope and anchor the blanket in a 150 mm deep by 150 mmwide trench. 

Backfill the trench and tamp the earth firmly. 

2.  Unroll the blanket down slope in the direction of water flow. 

3.  Overlap the edges of adjacent parallel rolls 50 mm to 75 mm and staple every 1.0 m. 

4.  When  blankets  must  be  spliced,  place  blankets  end  over  end  (shingle  style)  with  150  mm 

overlap. Staple through overlapped area, approximately 300 mm apart. 

5.  Lay blankets loosely and maintain direct contact with the soil. Do not stretch. 

6.  U-shaped wire staples, metal stake pins, or triangular wooden stakes can be used to anchor 

mats and blankets to the ground surface 

7.  Staple blankets sufficiently to anchor the blanket and maintain contact with the soil. Staples 

shall be placed down the centre and staggered with the staples placed along the edges. Steep 
slopes, 1:1 to 2:1 require a minimum of two staples per square meter. Moderate slopes, 2:1 to 
3:1,  require  a  minimum  of  one-and-a-half  staples  per  square  meter,  placing  one  staple  per 
meter on centres. Gentle slopes require a minimum of one staple per square meter. 

8.  Seed (if specified); fill turf reinforcement matting with soil; and insert plantings. 

9.  Do not drive tracked or heavy equipment over matting.  

10.  Avoid any traffic over matting if loose or wet soil conditions exist. 

 

G

ENERAL 

R

 

 

 

11.  Use shovels, rakes, or brooms for fine grading and touch up.  

12.  Smooth out soil filling, just exposing the top netting of the mat. 

When  no  longer  required,  Contractor  shall  remove  and  dispose  of  all  non-degradable  temporary 
coverings in a manner approved by the Engineer. 

b.  Aggregate Installation 

Crushed aggregate shall be spread over the sand to increase the surface roughness and prevent 
sand  movement  and  erosion.  It  may  be  applied  as  a  temporary  wind  and  water  erosion  control 
measure or as shown on the Drawings as the permanent soil covering method. Unless otherwise 
shown on the Drawings or approved by the Engineer, crushed aggregate shall be installed as follows: 

1.  Prepare ground surfaces as described in Sub-article a above. Take care to avoid compaction 

of  the  final  ground  surface  to  maintain  as  much  surface  soil  permeability  as  possible  for 
precipitation infiltration. 

2.  Minimum gravel thickness should be 150 mm . Where shown on the drawings for permanent 

gravel coverings, provide and install a geotextile filter fabric under the gravel surfacing. 

3.  Do not use crushed rock or gravel in areas of pedestrian or vehicle traffic, which will disperse 

the rock. Provide temporary paved walkways and paved driveways through the gravel area. 

4.  Rock or gravel should be clean, free of weeds, debris, and trash. 

5.  Slopes  on  which  gravel  covering  is  placed  shall  not  be  steeper  than  3:1  slopes,  unless 

otherwise approved by the Engineer. Provide an blanket type covering for steeper slopes. 

1.17.6.3 

Concentrated flow diversions 

This  measure  consists  of  temporary  ditches,  swales,  and  dikes  that  intercept,  divert,  and  convey 
surface runoff to provide protection from flooding and sedimentation of the Contractors works and 
provide for the public safety in the case of rainfall. These temporary measures shall be constructed 
and maintained for the winter season of 15 October through 15 April of configurations as appropriate 
for the Contractor’s staging and detour plans during that time period. The Contractor shall design 
and construct concentrated flow diversions in accordance with Chapter 14 of the Abu Dhabi Road 
Drainage Manual, AD-D-07, and as follows: 

a.  Care shall be applied to correctly size and locate earth dikes, swales, and ditches. Excessively 

steep, unlined dikes and swales are subject to erosion and gully formation 

b.  Refer to Chapter 4 of the Abu Dhabi Road Drainage Manual, AD-D-07, for the hydraulic design 

of ditches and swales 

c.  Conveyances shall be stabilised 

d.  Use a lined ditch for high-flow velocities 

e.  Select flow velocity based on a careful evaluation of the risks due to the erosion of the measure, 

soil types, over-topping, flow backups, washout, and drainage flow patterns for each project 
site 

f.  Compact any temporary dike fills to prevent unequal settlement 

g.  When  possible,  install  and  use  permanent  stormwater  facilities  early  in  the  construction 

process for the collection and conveyance of construction site runoff and dewatering flows 

h.  Provide stabilised outlets. 

 

G

ENERAL 

R

 

 

 

1.17.6.4 

 Pipe slope drain 

Slope drains are pipes used to intercept and direct surface runoff or groundwater into a stabilised 
watercourse, trapping  device,  or  stabilised  area.  Slope  drains  are  used with  ditches,  swales,  and 
dikes to intercept and direct surface flow away from slope areas to protect cut or fill slopes. Slope 
drains may also be used at construction sites where slopes may be eroded by surface runoff. Slope 
drains  shall  be  hydraulically  design  in  accordance  with  the requirements of  Chapter  4  of  the  Abu 
Dhabi Road Drainage Manual, AD-D-07, and as follows: 

a.  When using slope drains, limit the drainage area to 4 ha per pipe. 

b.  Direct surface runoff to the entrance of a slope drain with interceptor dikes, swales, or ditches. 

c.  Slope drains may be placed on or buried underneath the slope surface.  

d.  When installing slope drains: 

1.  Install slope drains perpendicular to slope contours. 

2.  Compact the soil around and under the entrance, outlet, and along the length of pipe.  

3.  Securely anchor and stabilise pipe and appurtenances into soil.  

4.  Check to ensure that pipe connections are watertight.  

5.  Protect the area around the inlet with geotextile fabric or erosion control blanket. Protect the 

outlet with riprap. Ensure that high velocities/energy are dissipated at the outlet.  

6.  Protect the inlet and outlet of slope drains with a standard flared-end section at the entrance 

for pipe slope drains 300 mm and larger. 

1.17.6.5 

Sediment trapping 

Sediment trapping measures function by slowing water velocities thereby allowing soil particles to 
settle out or by attenuating the peak flow by detaining flow and releasing water at a slower rate. 

a.  Fabric fence 

Fabric  fence  or  silt  fence  is  a  temporary  linear  sediment  barrier  of  permeable  fabric  designed  to 
intercept sediment laden runoff. Silt fences may consist of a wire supported geotextile silt fence or a 
self supporting geotextile silt fence. 

Contractor shall place fabric fences at the following general locations, or as otherwise shown on the 
Drawings or required by the Engineer: 

1.  Between the perimeter of a project and an environmentally sensitive area 

2.  Below the toe of exposed and erodible slopes 

3.  Along slope contours for longer slope lengths 

4.  Downslope of exposed soil areas 

5.  Around temporary stockpiles 

Installation shall meet the following requirements: 

1.  At  the  time  of  installation,  the  fabric  will  be  rejected  if  it  has  defects,  rips,  holes,  flaws, 

deterioration, or damage incurred during manufacture, transportation, storage or installation 

2.  Fence height shall not exceed 900 mm above ground surface. 

3.  Geotextile fabric shall be attached on the upstream side of the posts by wire, cord, button head 

nails, pockets, staples, or other acceptable means 

 

G

ENERAL 

R

 

 

 

4.  Geotextile fabric shall be installed in such a manner that 200 to 250 mm of fabric is left at the 

bottom to be buried. The fabric shall be installed in the trench such that 150 mm of fabric is 
against the side of the trench and 50 to 100 mm of fabric is across the bottom of the trench in 
the upstream direction. The trench shall then be backfilled and compacted so that no flow can 
pass under the barrier 

5.  A minimum overlap of 450 mm shall be provided at all splice joints with posts at the ends of 

each fabric roll.  

6.  Contractor shall be responsible to maintain the integrity of silt fences as long as necessary to 

contain sediment runoff or as directed by the Engineer 

7.  Sediment deposits shall be removed when the deposit reaches approximately one-half of the 

height of the silt fence.  

8.  Silt  fence  shall  remain  in  place  during  the  duration  of  the  Contractors  work  and  that  winter 

season or  until the Engineer  directs that it be removed. Upon removal, the Contractor shall 
remove  and  dispose  of  any  excess  silt  accumulations,  grade  the  area  to  leave  a  generally 
smooth appearance. 

b.  Sediment traps 

A sediment trap is a temporary basin formed by excavating and/or constructing an embankment so 
that sediment-laden runoff is temporarily detained under quiescent conditions, allowing sediment to 
settle  out  before  the  runoff  is  discharged.  Contractor  shall  design  and  install  sediment  traps  as 
needed  for  control  of  downstream  sedimentation,  as  may  be  shown  on  the  drawings  or  where 
directed by the Engineer. Design shall meet the applicable requirements of Chapter 14 of the Abu 
Dhabi Road Drainage Manual, AD-D-07, and as follows: 

1.  Limit the contributing area to the sediment trap basin to only the runoff from the disturbed soil 

areas. Use temporary concentrated flow conveyance controls to divert runoff from undisturbed 
areas away from the sediment trap basin. 

2.  Provide the minimum surface area required for the sediment basin as per the formulas and 

procedure in Chapters 6 and 14 of the Abu Dhabi Road Drainage Manual, AD-D-07. 

3.  Basin length shall be more than twice the dimension as the width 

4.  For  safety  purposes,  the  maximum  depth  shall  be  no  greater  than  1.5  m  unless  otherwise 

protected from public access 

5.  Outlet structures shall be placed on a firm, smooth foundation, with the base securely anchored 

with concrete, or by another means, to prevent floatation 

6.  Discharge from the basin shall be accomplished through a corrugated metal or a high-density 

polyethylene riser pipe. A riser is sized so that the top opening acts as an overflow weir of total 
circumference  to  accommodate  the  design  storm  frequency  flows.  A  riser  should  also  be 
perforated  and  wrapped  with  a  geotextile  filter  fabric  around  the  base  to  allow  for  low-flow 
dewatering 

7.  Perforated sections should be designed to drain the basin within 72 hours after a storm 

8.  Attach  the  riser  pipe  with  a  watertight  connection,  to  a  horizontal  pipe  which  outlets  to  a 

stabilised outfall or to a storm drain system 

9.  Cleanout level shall be clearly marked on the riser pipe 

 

G

ENERAL 

R

 

 

 

10.  Remove accumulated sediments when the depth reaches one-third the depth of the sediment 

storage in the basin. 

c.  Check dams 

Check dams shall be used where applicable to reduce scour and channel erosion by reducing flow 
velocity and encouraging sediment settlement. Check dams are small devices constructed of rock, 
gravel bags, sandbags, fibre rolls, or other proprietary products, placed across small open channels, 
in  steep  channels  where  stormwater  runoff  exceed  1.5  m  per  second  and  in  temporary  ditches. 
Contractor shall place check dams per the following guidelines: 

1.  Check dams shall be placed at a distance and height to allow small pools to form behind them. 

Install the first check dam approximately 5 m from the outfall device and at regular  intervals 
based on slope gradient and soil type. 

2.  For multiple check dam installation, spacing shall be such that backwater from the downstream 

check dam shall reach the toe of the upstream dam. 

3.  High flows (typically a two-year storm or larger) shall safely flow over the check dam without 

an increase in upstream flooding or damage to the check dam, channel, or bank. 

4.  Rock should be placed individually by hand or by mechanical methods (no dumping). 

5.  Fibre rolls may be used as check dams (more temporary than rock) 

6.  Gravel bags may be used as check dams 

7.  Install check dams along a level contour, placed approximately perpendicular to the centreline 

of the ditch or drainage line 

8.  Tightly abut and stack rock, gravel bags or fibre rolls using a pyramid approach 

9.  Check  dams  shall  not  be  any  higher  than  1  m.  Midpoint  of  the  rock  check  dam  shall  be  a 

minimum of 150 mm lower than the sides in order to direct across the centre and away from 
the channel sides. Base of the check dam shall be entrenched approximately 150 mm 

10.  Where the check dam is constructed of rock, the rock shall be placed so that it completely 

covers  the  width  of  the  channel.  Stone  placement  shall  be  performed  either  by  hand  or 
mechanically as long as the center of check dam is lower than the sides and extends across 
entire channel. Side slopes of the check dam shall be no steeper than 2:1. 

11.  Where gravel bags are used, upper rows of gravel bags shall overlap joints in lower rows 

12.  If a temporary check dam is to be placed in the same area as an erosion control blanket, 

install the blanket before placing the dam. 

13.  Check  dams  shall  remain  in  service  until  the  permanent  stabilization  work  commences  or 

until  they  are  no  longer  needed,  as  approved  by  the  Engineer.  When  a  rock  check  dam  is 
discontinued, the materials shall be removed and disposed of as approved by the Engineer 

d.  Fibre rolls 

Fibre rolls are placed on the toe and face of slopes to intercept runoff, reduce its flow velocity, release 
the runoff as sheet flow, and provide a removal of sediment from the runoff. Fibre rolls may also be 
used for inlet protection and as check dams. Fibre rolls shall be installed at the following general 
locations 

1.  Located  along  the  toe,  top,  face,  and  at-grade  breaks  of  exposed  and  erodible  slopes  to 

shorten slope length and spread runoff as sheet flow 

 

G

ENERAL 

R

 

 

 

2.  Place below the toe of exposed and erodible slopes 

3.  Place around storm drain inlets to trap sediment before entering the inlet 

4.  Use downslope of exposed soil areas 

5.  Place around temporary stockpiles and along the perimeter of a project 

6.  Installation shall meet the following guidelines: 

i. 

Slope inclination of 1:4 or flatter: fibre rolls shall be placed on slopes 6 m apart 

ii. 

Slope inclination of 1:4 to 1:2: fibre rolls shall be placed on slopes 4.5 m apart 

iii. 

Slope inclination 1:2 or greater: fibre rolls shall be placed on slopes 3 m apart 

iv. 

Stake fibre rolls into a 50 to 100 mm deep trench 

v. 

Drive stakes at the end of each fibre roll 

vi. 

Use wood stakes 19 mm by 19 mm and a minimum length of 600 mm 

vii. 

If more than one fibre roll is placed in a row, the rolls shall be overlapped, not abutted 

7.  Removal: 

viii. 

Fibre  rolls  are  typically  left  in  place  and  will  degrade  and  compost  in  areas  used  for 
landscaping or other agricultural plantings 

ix. 

If  fibre  rolls  are  removed,  collect  and  dispose  of  sediment  accumulation,  and  fill  and 
compact holes, depressions, or any disturbance to blend with adjacent ground. 

e.  Gravel bag berms 

A gravel bag berm consists of a single row of gravel bags that are installed end-to-end to form a 
barrier across a slope to intercept runoff, reduce its flow velocity, release the runoff as sheet flow, 
and provide some sediment removal. Contractor shall use gravel berms at the following locations: 

1.  Where flows are moderately concentrated, such as ditches, swales, and storm drain inlets 

2.  Where  control  or  redirect  runoff  on  detour  pavement  is  needed  to  avoid  concentrated  flow 

across adjacent traffic lanes 

3.  When site conditions or construction sequencing requires adjustments or a relocation of the 

barrier to meet changing field conditions and needs during construction 

4.  At grade breaks of exposed and erodible slopes to shorten slope length 

5.  As check dams using stacked bags 

When used as a linear control for sediment remova, berms shall be installed as followsl: 

1.  Install along a level contour 

2.  Install with ends tightly abutting each other to eliminate gaps 

3.  Turn the ends of the gravel bag row upslope to prevent flow around the ends 

4.  Install with a setback of at least 1 m from the toe of a slope 

5.  Bags  in  the  vicinity  of  curbs  and  inlets  shall  be  installed  to  50  mm  below  the  height  of  the 

adjacent curb to allow drainage into the inlet. When sediment depth behind the bags reaches 
75 mm the sediment shall be removed 

When used for concentrated flows, such as for a check dam, berms shall be installed as follows: 

 

G

ENERAL 

R

 

 

 

1.  Stack gravel bags to the required height using a pyramid approach 

2.  The upper rows of gravel bags shall overlap joints in the lower rows 

Sand or gravel bag features shall remain in service until disturbed areas have been stabilized, as 
directed by the Engineer. During removal, all sediment shall be disposed of, and the area restored 
to a finished condition as shown on the plans, or as directed by the Engineer. 

f.  Storm drain inlet protection 

Storm drain inlet protection measures are used at storm drain inlets that are subject to runoff from 
construction  activities.  These  devices  are  used  to  detain  and/or  to  filter  sediment-laden  runoff  in 
order  to  allow  sediment  to  settle  and/or  to  filter  sediment  prior  to  discharge  into  storm  drainage 
systems. Installed protection shall not be used where ponding may encroach into highway traffic. 
Storm drain inlet protection shall be installed and maintained during the winter season of 15 October 
through 15 April for the following conditions: 

1.  Sediment-laden surface runoff may enter an inlet. 

2.  Disturbed drainage areas have not yet been permanently stabilised. 

Inlet protection shall consist of one of the following types: 

1.  Inlet protection Type 1 

– fabric fence: Filter fabric fence protection is similar to constructing a 

fabric fence. Do not place filter fabric underneath the inlet grate because the collected sediment 
may fall into the drain inlet when the fabric is removed or replaced. 

2.  Inlet  protection Type 2  - excavated drop inlet sediment trap: Applicable for  existing inlets  in 

open areas, where a sediment trap can be excavated adjacent to the inlet, using the inlet as 
the open top overflow structure. Refer to the requirements for sediment traps, in the subsection 
above.  

3.  Inlet protection Type 3 

– gravel bag: Install gravel bags in accordance with the requirements 

for gravel bag berm described in the subsection above, around the inlet opening. Gravel bags 
are generally used due to their high permeability. 

4.  Inlet protection Type 4 

– fibre rolls: Fibre roll is placed around the inlet and keyed and anchored 

to the surface. Fibre rolls are intended for use as inlet protection where the area around the 
inlet is unpaved and the fibre roll can be secured to the surface by staking. 

1.18 

Basic Product Requirements, Product Options 

This  Section  specifies  general  requirements  for materials  and  equipment  and  includes,  but  is  not 
limited to, the following:  

1.  Products 

2.  Transportation, delivery, receiving, and handling 

3.  Storage and protection 

4.  Products list 

5.  Substitutions 

6.  Product acceptance 

1.18.1 

Products 

Term “product” shall mean any material, including proprietary goods, equipment or services that are 
incorporated into the final works.  

Products  do  not  include  materials,  machinery,  or  equipment  that  is  used  for  the  preparation, 
fabrication, conveyance, or erection of works. 

 

G

ENERAL 

R

 

 

 

If possible, products of a similar nature shall be standardized, interchangeable and supplied by the 
same manufacturer.  

All  products  shall  comply  with  the  specifications  and  referenced  standards,  unless  otherwise 
approved by the Engineer. 

1.18.2 

Transportation and Handling 

All products shall be transported, stored and handled at all times in accordance with the requirements 
of Sections 1.18.5 and 1.18.6.  

1.18.3 

Products List 

Products  shall  be  delivered  according to  the  construction  schedule  in  order  to  avoid  construction 
delays or undue storage requirements. Submit four copies of a list of all products which are proposed 
for installation, not later than 30 calendar days after the start of the Contract. The list shall include 
the following items: 

1.  Include the name of manufacturer and supplier, the trade name, and the model number of 

each product.  

2.  List shall identify products that are specifically listed by manufacturer or product model, those 

which  are  not  referenced  and  those  that  are  proposed  as  a  substitute  to  a  listed  product 
model or manufacturer.  

3.  The  Contractor  shall  ensure  that  the  listed  products  comply  with  the  requirements  of  the 

Contract documents. 

4.  Product list shall be arranged according to specification section number.  

5.  Include the specification title and the paragraph number.  

Engineer will notify the Contractor in writing of any product deemed to be unacceptable. Notification 
shall be made no later than 30 days after submission of the products list.  Engineer

’s objection or 

failure  to  object  to  a  listed  item  shall  not  constitute  a  waiver  of  the  requirements  of  the  Contract 
documents. 

1.18.4 

Product Substitutions 

Substitution  requests  shall  be  in  conformance  with  the  requirements  of  Section  1.19  and  the 
requirements in this section.  

The Contractor must submit requests for substitution within 60 days of starting the  Contract. After 
that date, substitutions will only be considered when a product becomes unavailable, due to no fault 
of the Contractor.  

Document each request with complete date substantiating that the proposed substitution complies 
with the Contract documents. Substitutions will not be considered in either of the following situations: 

1.  Substitution  is  indicated  or  implied  on  shop  drawings  or  product  data  submittals  without 

separate written request complying with the above requirements.  

2.  When acceptance will require substantial revisions to the Contract documents. 

1.18.5 

Product Acceptance 

All products shall be tested as required by the specification, as follows: 

1.  Product testing shall be by an approved site laboratory, independent laboratory or a recognized 

testing organization  

2.  The  Contractor  shall  be  responsible  for  all  costs  associated  with  product  testing  including 

labour,  transportation  and  the  cost  of  the  test  itself,  except  as  specified  elsewhere  in  the 
specifications. 

 

 

 

 

 

 

 