12. Brightness adaptor shall be continuous and automatic from 100 % to 10 %
d. Temporary Barriers
The Contractor shall be responsible for furnishing, installing and maintaining all temporary barriers
in areas as determined by the Engineer, where construction operations result in a condition that is
considered to be hazardous to the general public, or to separate the work area from pedestrian
areas. Location and extent of the temporary barriers shall be as directed and approved by the
Engineer. Temporary barriers shall remain the property of the Contractor and shall be removed from
the site of the works as approved by the Engineer when no longer required. Temporary barriers may
be of the following:
1. Temporary concrete barriers
2. Temporary concrete barriers with screens
3. Water filled portable barriers
4. Safety barrier fence system
1. Temporary Concrete Barriers
Temporary concrete barrier shall be new or used precast barrier complying with the
requirements of the Contract plans for precast barrier and meeting the requirements of
Section 7.5 of Chapter 7, Incidental Construction, except for the following:
x
Lengths may differ from those shown in the Contract plans
x
Permanent lifting holes less than 100 mm in diameter may remain
x
Lifting loops are permitted
x
A stamp or stencil reading “temporary” shall be visible on each barrier segment
Permanent barriers that will be removed and reset per the Contract plans or the direction of
the engineer may be used as temporary concrete barrier without being stamped or stencilled
“temporary.” Any permanent barrier damaged during its use as a temporary barrier will
become the property of the Contractor and be replaced with an undamaged permanent
barrier at no expense to the Owner when the permanent barrier is reset to its location.
All barriers shall be in good condition, without cracks, chips, spalls, dirt, or traffic marks. If
any barrier segment becomes damaged during or after placement, the Contractor, at no
expense to the Owner, shall immediately repair it to the engineer’s satisfaction or replace it
with an undamaged section.
As soon as the temporary barrier is no longer needed, the Contractor shall remove it from
the site of the works. Owner-furnished barrier shall remain Owner property, and the
Contractor shall deliver it to a stockpile site noted in the contract or to locations approved by
the engineer. The Contractor-furnished barrier shall remain the property of the Contractor.
2. Temporary Concrete Barriers with Screens
Temporary concrete barriers shall meet the requirements of Paragraph 1 above. The
Contractor shall be required, when directed by the Engineer, to provide warning lights and
reflective painted markings on continuous temporary barriers in areas where detour
pavement is poorly illuminated.
Screen shall be constructed of painted metal and shall be neat in appearance. Screen shall
be fixed over the temporary concrete barriers. Screen shall be solid and continuous, not less
than 1.2 m in height. Supplemental screens shall be connected with the metal screen as
indicated on the Contract plans and as directed by the Engineer. Details of construction shall
be as indicated on the Contract plans and approved by the Engineer. Screen shall be of
substantial construction such that it will not be damaged or displaced by wind or other normal
natural or manmade forces.