Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 17

 

  Главная      Manuals     Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     15      16      17      18     ..

 

 

 

Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 17

 

 

 

G

ENERAL 

R

 

 

 

3.  Samples shall be taken at the place of origin, place of fabrication or from the site, as required 

by the Engineer or as otherwise specified. 

4.  Samples after testing shall remain the property of the Contractor.  

5.  Samples used for testing may only be incorporated into the work with the written approval of 

the Engineer.  

6.  The Contractor shall provide all necessary facilities required for onsite testing of products.  

7.  The Contractor shall ensure that products are made available for testing sufficiently in advance 

of intended use, to allow adequate time for testing and evaluation. 

8.  Delays resulting from the time taken to test a product shall not be acceptable as cause for a 

Claim.  

9.  Before  final  inspection,  all  components,  systems  and  subsystems  shall  be  tested,  to 

demonstrate compliance with the specified performance requirements. 

1.18.6 

Utility Coordinator 

All  submittals  for  mechanical,  electrical  and  other  utility  products  shall  be  approved  by  the  utility 
coordinator before submittal to the Engineer. 

1.18.7 

Operation and Maintenance Data 

Operation and maintenance data and manuals shall be prepared in accordance with Section 1.26. 
All data supplied for the operation and maintenance data or manuals shall be licensed to the Owner.   

1.18.8 

Submittals 

All submittals shall be in compliance with the requirements of Section 1.11. 

1.19 

Product Substitution Procedures 

This  section  includes  administrative  and  procedural  requirements  for  handling  requests  for 
substitutions made after award of the Contract. 

1.19.1 

Definitions 

Term “product” shall mean any material including proprietary goods, equipment, and manufactured 
items. 

1.19.2 

Product Substitution Requirements 

The Contractor shall comply with the following requirements:  

1.  Specifying of manufacturers or their products by name, trade name, catalogue number, etc., 

shall not act to relieve the Contractor either from his responsibility to meet other specification 
requirements, or from his responsibility to make material submittals for approval.  

2.  Substitute  products,  where  permitted  and  approved,  must  conform  to  the  Engineer

’s 

designed space requirements. Any such substitute product that does not meet such space 
requirements, whether approved or not, shall be replaced at the Contractor

’s expense and 

any modification of replaced systems thereby arising shall also be made at his expense.  

3. 

References to “approved equal” of similar terms shall mean that the approval of the Engineer 
is  required  for  any  alternative  product  to  be  considered  for  use  in  the  project  by  the 
Contractor.  

4.  Where products are specified by propriety designation, the Contractor shall not be permitted 

to procure ‘approved equal’ or ‘approved alternative’ products, but must procure the product 
from the selection of manufacturers or suppliers listed.  

 

G

ENERAL 

R

 

 

 

5. 

Substitute products: If the Contractor is unable to obtain the specified product in spite of his 
best endeavours, and if he is unable to find and propose a suitable equal alternative he may 
propose a substitute for the Engineer

’s review and approval, which substitute shall be similar 

to, and as near as possible equal if not better than the quality, durability and performance 
characteristics  of  the  specified  product.  A  substitute  product  will  only  be  considered  if  the 
Contractor has proven to the Engineer

’s reasonable satisfaction that the specified product is 

unobtainable.

 

6.  Identification of Abu Dhabi Emirate produced products:  Tenderer must certify that this tender 

reflects the tenderer’s best, good faith effort to identify and incorporate the Emirate produced 
products  and  manufactured  goods  for  every  component  contained  in  the  tender  documents 
where such Emirate-made components are available and meet the requirements set forth in 
these Specifications. 

1.19.3 

 

Engineer

¶VApproval of Alternatives and Substitutes 

Substitution request submittal: The Engineer will consider requests for substitution as follows:  

a.  Submit 3 copies of each request for substitution for consideration. Submit requests in the form 

and according to procedures required for variation proposals.  

b.  Identify the product or the fabrication or installation method to be replaced in each request. 

Include related specification section and Contract plan numbers.  

c.  Provide complete documentation showing compliance with the requirements for substitutions, 

and the following information, as appropriate:  

1.  Coordination information, including a list of changes or modifications needed to other parts 

of the work and to construction performed by the Owner and separate Contractors that will 
be necessary to accommodate the proposed substitution.  

2.  A detailed comparison of significant qualities of the proposed substitution with those of the 

work  specified. Significant  qualities may include elements, such as performance, weight, 
size, durability, and visual effect.  

3.  Product  data,  including  drawings  and  descriptions  of  products  and  fabrication  and 

installation procedures.  

4.  Samples, where applicable or requested.  

5.  A  statement  indicating  the  substitution's  effect  on  the  Contractor's  construction  schedule 

compared  to  the  schedule  without  approval  of  the  substitution.  Indicate  the  effect  of  the 
proposed substitution on overall Contract time.  

6.  Cost  information,  including  a  proposal  of  the  net  saving,  in  the  Contract  sum.  Additional 

costs  are  not  accepted.  This  should  be  substantiated  by  comparative  quotations  with 
complete rate breakdown for both the proposed alternative/substitute item and the specified 
item.  

7.  The  Contractor's  waiver  of  rights  to  additional  payment  or  time  that  may  subsequently 

become  necessary  because  of  the  failure  of  the  alternative  and  substitution  to  perform 
adequately.  

8.  Warranty shall be equal to or greater than that specified for the original specified item.  

9.  Reimbursement for review and redesign services of the Engineer.  

d.  Engineer's  action:  Approval  of  any  substitute  product  shall  be  solely  at  the  direction  of  the 

Engineer and such approval shall in no way relieve the Contractor of any of his liabilities and 
obligations under the Contract. Burden of proof in satisfying the Engineer as to the suitability 
of any proposed substitute product shall rest with the Contractor. Engineer may request and 
the Contractor shall provide such supporting data, carryout such tests, etc., as the Engineer 
may reasonably require in order to satisfy him as to such suitability. Any extra costs of delay 

 

G

ENERAL 

R

 

 

 

by the Contractor, because of his failure to propose substitutes in a timely manner, so as to 
allow the Engineer reasonable time to review, or because of rejection of substitutes found by 
the Engineer to be unsuitable, shall be the responsibility of the Contractor, and he shall not be 
entitled to additional payment nor to extra time for completion in this respect. 

e.  Cost  effect  in  approving  substitutes:  Should  any  substitute  product  be  approved  by  the 

Engineer, any net increase in cost over and above the specified product shall be borne by the 
Contractor and, any net saving in cost shall be to the benefit of the Owner. 

1.19.4 

Product Storage and Handling Requirements 

a.  Products  shall  be  delivered  according  to  the  construction  schedule,  in  order  to  avoid 

construction delays or undue storage requirements.  

b.  Transport and handle products in a suitable manner at all times to avoid product damage.  

c. 

Deliver  dry  and  in  undamaged  condition  in  the  manufacturer’s  unopened  containers  or 
packaging.  

d.  The Contractor shall inspect shipments upon delivery, to ensure that the products:  

1.  Are properly labelled and identified 

2.  Comply with the requirements of the specifications 

3.  Quantities are correct 

4.  Inspect all products upon delivery and report any damage to the Engineer 

5.  Any products damaged during delivery, storage or installation shall be marked and set aside 

6.  Proposals for repair of any damaged products shall be submitted in writing to the Engineer 

for approval.  

7.  No repairs to damaged products shall be attempted, without the Engineer

’s approval. 

8.  Any damaged products deemed unsuitable for repair by the Engineer shall be removed from 

site and replaced at the Contractors expense.  

e.  Comply  with  specific  transportation  and  handling  requirements  specified  in  individual 

specification sections and as directed by the Engineer. 

1.19.5 

Storage and Protection 

a.  Store products in accordance with manufacturer's instructions, with seals and labels intact and 

legible.  

b.  Store sensitive products in weather-tight enclosures.  

c.  Where  product  manufacturer  recommends  storage  under  controlled  temperatures,  the 

Contractor  must  provide  an  enclosed,  insulated,  cool  store  maintained  at  the  proper 
temperature, 24 hours a day.  

d.  Exterior storage of fabricated products: 

1.  Place on supports above ground 

2.  Cover products subject to deterioration with canvas tarpaulins and provide for air circulation 

to prevent condensation 

e.  Store products so as to allow ready access for inspection 

1.  Date of manufacture and date of expiry shall be clearly visible 

2.  The Contractor shall periodically inspect the products to ensure that they are stored under 

required conditions and are free of damage or deterioration 

 

G

ENERAL 

R

 

 

 

f.  Provide electrical connections to energize heaters or internal climate control units in electrical 

machinery, motors, panels and the like while the unit is in storage and after installation until 
the unit is placed into service.  

g.  The  Contractor  shall  develop  a  method  statement  that  identifies  the  equipment  within  the 

project that will need rotation and operation during storage and after installation to maintain its 
function before the start of the facility and during the warranty period. 

1.20 

Testing of Systems, Start-up and Commissioning 

This section includes the following:  

1.  Requirements for system and facility start-up 

2.  Requirement for operational, field and performance testing  

3.  Exceptions  to  these  requirements  are  in  individual  technical  sections  and  only  modify  the 

individual article and topic   

4.  Other articles and topics in this section remain in force unless specifically deleted by the related 

specification section   

1.20.1 

Definitions 

Definitions of key terms used in this specification are as follows: 

1.  Component: An individual item, piece of equipment, or equipment group as specified in a single 

section of these specifications.  

2.  Start-up Plan: A single and complete plan incorporating all requirements of this section.  

3.  Subsystem: A grouping or assembly of components, all of which operate together to produce 

the specified performance.  

4.  System: An assembly of subsystems and components.  

5.  Validate:  To  support,  substantiate,  and  authenticate  specified  operation  on  a  sound  and 

authoritative basis. 

1.20.2 

Quality Control  

The Contractor shall comply with the following quality control items. 

a.  Utility coordinator: Utility coordinator duties shall continue throughout the testing, start-up and 

commissioning phase until all electrical and mechanical equipment and other installed utilities 
is fully commissioned and accepted by the Engineer. 

b.  Start-up foreman:  

1.  Submit qualifications for approval. 

2.  Minimum experience:  

i. 

Minimum 10 years experience in utility operations and maintenance including water 
and  waste  water  treatment  and  pumping  stations  and  collection  and  distribution 
systems  

ii. 

Minimum 3 years experience starting up, operating and maintaining equipment  

iii. 

Academic or factory training 

iv. 

Combination of training and experience 

3.  Owner and Engineer reserve the right to reject start-up foremen lacking the experience and 

education necessary to start up, operate and maintain the treatment facility 

 

G

ENERAL 

R

 

 

 

c.  Pre-start-up conference: 

1.  Schedule conference not less than 15 calendar days before beginning start-up of any part 

of the works 

2.  The  Owner,  the  Engineer,  the  Contractor,  start-up  foreman,  utility  coordinator  and  other 

responsible parties (e.g. equipment manufacturers) to attend 

3.  Submit  an  agenda  5  working  days  before  conference.  Include:  Start-up,  testing  and 

equipment demonstration/training schedule 

1.20.3 

Submittals 

All  submittals  shall  be  as  specified  in  Section  1.11.  The  Contractor  shall  submit  the  following  for 
approval:  

a.  Start-up plan  

1.  Submit not less than 30 days before first pre-start-up conference 

2.  Provide step-by-step procedures for starting up each element of each system 

3.  The  Contractor  is  responsible  for  means,  methods,  techniques,  sequences,  procedures, 

coordination, completeness, accuracy, and validity of the plan. 

4.  The Contractor may submit individual sections of the start-up plan as they are developed.  

i. 

Upon approval, incorporate these individual sections into the overall facility  start-up 
plan 

ii. 

Rejection  of  individual  sections  of  the  start-up  plan  by  the  Engineer  shall  not  be 
considered a cause for delay. 

5.  Identify each person and organization participating in the start-up. Identify their duties and 

responsibilities.  

6.  Provide  for  contingencies  if  problems  develop  during  start-up  or  if  a  component  fails  to 

perform as specified. 

b.  Temporary connections to facilitate start-up and testing  

1.  Submit working drawings showing necessary temporary connections.  

2.  Submit written description of how temporary connection will be used.  

3.  Provide  separate  drawings  and  descriptions  for  each  item  or  subsystem  identified  in  the 

start-up plan.  

c.  Start-up validation procedures 

1.  Submit a complete, step-by-step description of each test, simulation, and start-up.  

2.  Submit start-up schedule by system or subsystem as appropriate.  

3.  Identify  individuals  and  organizations  involved  in  the  start  up  as  well  as  their  duties  and 

responsibilities 

4.  Identify test equipment required 

5.  Include accuracy and calibration information 

6.  List  data  requirements  and  identify  proposed methods  of  demonstrating compliance  with 

specified performance requirements. 

d.  Validation report: 

1.  Submit validation report within seven working days of completing performance testing 

2.  Include test procedures, specified performance requirements, performance data, and data 

evaluation. 

 

G

ENERAL 

R

 

 

 

1.20.4 

Sequencing and Scheduling 

Provide  start-up schedule for each system and subsystem. Address each subsystem individually. 
Include required submittals in schedule. Update schedule as necessary. 

1.20.5 

Start-up Requirements 

The Contractors shall comply with the start-up requirements outlined in this section. 

a.  Start-up Prerequisites   

Prerequisites for start-up include the following:  

1.  Building enclosures are complete, weather-tight, and all painting has been completed   

2.  All  system  components  have  been  checked  by  the  manufacturer  (where  required  in  the 

specifications) and are certified as “ready to operate”.  

3.  Electrical and instrumentation components are connected to the permanent power supply. 

b.  Design 

Design requirements include the following: 

1.  Design temporary process and utility connections to meet the specified design requirements 

of the component, subsystem, and system to which they are connected 

2.  Design temporary supports and restraints 

3.  Do not place structural loads on the permanent facility beyond its design capacity 

4.  Provide dielectric unions on temporary connections wherever dissimilar metals connect 

5.  Provide  safety  devices  on  temporary  connections  wherever  they  would  be  required  if  the 

connections were permanent 

c.  Performance 

Performance requirements include the following: 

1.  Tests each system and all of its components 

2.  Demonstrate  compliance  with  the  performance  specified  in  the  individual  sections  of  the 

specifications. This includes operation in all available modes (e.g. manual and automatic) 

3.  Collect operating data for all system components: Refer to Section 1.11.10.  

d.  Maintenance   

Maintenance requirements include the following: 

1.  Maintain all components through completion of start up and testing 

2. 

Follow manufacturer’s recommendations 

3.  Record all maintenance performed 

4.  Submit maintenance records to the Engineer with validation report. 

1.20.6 

Temporary Connections 

Provide  all  materials  necessary  for  temporary  connections.  Materials  shall  be  adequate  for  the 
application. Engineer shall be the sole judge of suitability. 

1.20.7 

Operating Fluids 

Operating fluids shall meet the following requirements: 

 

G

ENERAL 

R

 

 

 

a.  Provide operating fluids required for duration of start-up and performance testing. 

b.  All operating fluids shall be as specified. 

c.  Items provided are in addition to those provided under the specifications.  

d.  The Contractor shall provide all water (treated sewerage effluent or potable as appropriate) 

required  for  all  tests  including  all  trucking  at  no  additional  cost  to  the  Owner.  Availability  of 
water on site for testing purposes is not guaranteed.  

1.  All testing shall be performed with clean particulate free water acceptable to the Engineer.  

2.  Irrigation and drainage system testing may be with treated sewerage effluent or potable, as 

available. 

3.  All potable water system components shall be tested only with potable water.  

1.20.8 

Spare Parts 

Provide all maintenance and replacement parts required during  start-up and testing. Maintenance 
and  replacement  parts  used  by  the  Contractor  before  the  start  of  the  specified  operations  and 
maintenance period are in addition to those required by the specifications. All spare parts required 
by the specifications shall be catalogued, inventoried and entered into electronic data terms. 

1.20.9 

Component and System Validation 

Component and system validation shall comply with the following: 

a.  Validate each component and each system using one or more of the methods described below:  

1.  Testing to show compliance with the specifications.  

2.  Simulate  actual  operation  using  a  method  certified  as  acceptable  and  valid  by  both  the 

component manufacturer and the Engineer.  

3.  Certification by an independent testing laboratory that the component meets the specified 

industry standard.  

4.  Where  test  procedures  are  specified,  substitute  procedures  will  not  be  accepted  without 

prior written approval from the Engineer.  

b.  Validate components before system start-up and testing. Component validation shall include 

but is not necessarily limited to:  

1.  Operate each component over its full design range 

2.  Demonstrate manual and automatic operation of all components 

3.  Demonstrate all emergency shut down and safety devices 

4.  Demonstrate normal start-up and shut-down procedures 

5. 

Demonstrate “out of parameter” corrections 

6.  Document actions taken and procedures developed which are not covered in the operation 

and maintenance manual. Provide this information as an appendix to the manuals 

c.  Validate  each  system  to  demonstrate  that  components  operate  together  to  produce  the 

specified  system  performance.  Validation  shall  require  the  same  items  as  required  for  the 
individual components. 

1.20.10 

Validation Prerequisites 

Testing shall meet the following validation prerequisites: 

1.  Start-up submittals have been accepted 

2. 

Manufacturer’s have certified component installations wherever required 

 

G

ENERAL 

R

 

 

 

3. 

Specified manufacturer’s field services have been completed 

4.  Auxiliary and support systems are operating properly 

5.  No safety defects exist 

6.  Arrangements for waste disposal (both solid and liquid) have been made.  

7.  All manual and automatic controls are operational 

8.  All equipment has been lubricated and serviced, and it is ready for continuous operation. 

1.20.11 

Validation Preparation 

Implement safeguards and procedures to protect equipment and facilities from damage during start-
up and performance testing.  

Construct  approved  temporary  connections.  Test  all  temporary  connections  using  the  same 
procedures that would be required if the connection were permanent. 

1.20.12 

Preliminary Testing 

Preliminary testing shall meet the following requirements: 

a.  Where appropriate (for example, where doing so will not cause damage), conduct tests using 

either  potable  water,  treated  sewage  effluent,  or  particulate  free  water  acceptable  to  the 
Engineer before performance testing.  

b.  Test components and subsystems before testing the complete system.  

c.  Conduct each test in accordance with the approved testing procedures.  

1.  Engineer shall observe all tests in their entirety 

2.  Schedule testing and coordinate with the Engineer 

3.  Notify Engineer at least 24 hours before re-scheduling a test 

d.  Repair  or  modify  components,  subsystems,  and  systems  which  do  not  meet  specified 

performance criteria.  

1.  Cost of repairs or modifications shall be at the Contractor

’s expense 

2.  Repeat testing until acceptable performance is achieved 

3.  A  maximum  of  two  re-tests  will  be  allowed  (3  tests  total)  unless  the  Engineer  agrees  in 

writing that additional tests are justified 

4.  Equipment which does not meet the specified performance shall be removed and replaced 

with equipment which can meet the criteria 

i. 

All such work shall be at the Contractor

’s expense 

ii. 

Alternatively the Owner may elect to withhold retention money and Claim against the 
Contractor

’s performance security in lieu of replacing the faulty equipment 

e.  Collect operating data as appropriate, for each system component. Include the information as 

specified in Section 1.11. 

f.  At the conclusion of start-up and testing:  

1.  Replace or clean all filters, pipes, structures, etc. 

2.  Remove any temporary supports, plugs or testing equipment used for the testing 

3.  Perform equipment services recommended by the manufacturer 

4. 

Place equipment controls on “automatic” setting as appropriate 

 

G

ENERAL 

R

 

 

 

1.20.13 

Field Quality Control 

Calibrate  test  equipment  used  for  performance  testing  immediately  before  testing.  Confirm 
calibration immediately after testing. Re-testing will be required whenever test equipment is out of 
calibration at the conclusion of performance testing.  

1.20.14 

Performance Testing 

Performance testing shall meet the requirements listed in this section. 

1.20.14.1  Description 

This section includes procedure for performance testing. Following completion of the installation and 
start-up, and after all construction and preliminary testing and validation is complete, the Contractor 
shall test each item to demonstrate compliance with specified performance requirements. 

1.20.14.2  General 

After all construction and preliminary testing and validation is complete and before taking-over of any 
part of the works, the Contractor shall perform performance tests as called for in the specifications.  

a.  The  Contractor shall  demonstrate  operation  of  the  facilities to  the  Engineer  showing  proper 

sequence  of  operation  as  well  as  satisfactory  performance  of  the  system  and  individual 
components.  

b.  Any improper operation of the system or any improper, neglected or faulty construction shall 

be repaired or corrected to the satisfaction of the Engineer.  

c.  The Contractor shall make such changes, adjustments or replacement of equipment as may 

be  required to  make same comply  with  the  specifications,  or replace  any  defective  parts  or 
material.  

1.20.14.3  Performance 

a.  At the time of testing, failure of the system or unit process to perform at the specified level will 

be the responsibility of the Contractor.  

b.  In the event of failure of equipment to meet the specified performance, the Owner reserves the 

right to:  

1.  Not accept such equipment or system  

2.  Withhold retention money  

3.  Make Claims on the performance security/bond  

c.  Test schedule: 

1.  Prepare and submit a consolidated schedule of performance tests not later than 90 calendar 

days before the scheduled start of the first test.  

2.  Submit updates at monthly intervals.  

3.  Prepare and submit weekly a schedule of tests to be carried out during the following week.  

4.  Inform  the  Engineer  not  later  than  twenty-four  hours  in  advance  of  changes  in  the 

scheduling of a test.  

d.  Submittals: For all specified performance tests, prepare and submit:  

1.  Draft test  procedure:  Submit  not  later  than two months  in  advance  of  the  scheduled  test 

date 

2.  Final  test  procedure:  Submit  not  later  than two months  in  advance  of  the  scheduled  test 

date.  

 

G

ENERAL 

R

 

 

 

3.  Test report: Submit within fourteen days of the successful completion of the test. 

1.20.14.4  Performance Test Execution  

a.  Prerequisites for performance test:  

1.  Component and system preliminary test acceptance 

2.  Snag list rectified 

3.  Commissioning plan approved 

4.  Notification of the Engineer issued at least 14 calendar days before scheduled date of test 

5.  Equipment manufacturer representative appointed to supervise the test. 

6.  Performance testing shall not commence until equipment has been approved by Engineer 

as having met all specified requirements.  

b.  Plant and process control systems and all associated electrical equipment shall be tested to 

demonstrate that the facility operates as specified, and that all protection devices are working 
correctly.  

c.  No  test  shall  commence  until  all  related  structures,  piping,  electrical,  instrumentation  and 

controls has been installed, tested, connected and approved by the  Engineer in compliance 
with  the  specification  and  manufacturer’s  requirements.  Satisfactory  operation  shall  mean 
operating  safely  at  the  guaranteed  duty  and  efficiency  without  adversely  overheating, 
overloading, vibrating or exceeding specified noise level. 

d.  Unless  otherwise  agreed  with  the  Engineer

,  each  manufacturer’s  representative  shall  be 

present  at  the  start  of  the  operational  demonstration  to  examine  their  equipment  at  the 
beginning  and  end  of  the  test,  and  will  supervise  the  start-up,  calibration  and  adjustment 
procedures and other services necessary for the correct operation.  

e.  Any component test failure or improper operation of a system or any improper, neglected or 

faulty construction shall be repaired or corrected to the satisfaction of the Engineer.  

f.  The Contractor shall make such changes, adjustments or replacement of equipment as may 

be required to comply with the specifications, or replace any defective parts or material.  

g.  At the time of testing, failure of a component or system to perform at the specified level will be 

the responsibility of the Contractor. In the event of failure of equipment to meet the specified 
performance, the Engineer reserves the right to:  

1.  Not accept such equipment or system 

2.  Withhold retention money  

3.  Make Claims on the performance bond 

h.  Acceptance of plant and equipment may be dependent on the completion of other Contracts, 

operation  of  existing  works  or  a  planned  commissioning  schedule  for  complex  works  as 
determined by the Engineer. 

i.  Under performance tests, each component facility or item shall meet the acceptance testing 

as otherwise specified for that item. Separate performance testing may not be required where 
components and items have successfully passed other field and operational tests as specified, 
as determined by the Engineer. 

j.  Unless otherwise indicated, furnish all labour, materials, and supplies for conducting the test 

and taking all samples and performance measurements.  

k.  Prepare performance test report summarizing test method and results.  

l.  When,  in  Engineer's  opinion,  equipment  meets  performance  requirements  specified,  such 

equipment will be accepted as to conforming to Contract requirements. Such acceptance will 
be evidenced by Engineer's signature on equipment test report. 

 

G

ENERAL 

R

 

 

 

m. During the course of initial operation, the  Contractor shall instruct the Owner

’s personnel in 

proper operation and maintenance of the equipment, as specified herein.  

n.  The Contractor shall make necessary power connection to conduct an integrated site test. In 

the absence of permanent power supply, the Contractor shall supply a mobile generator to be 
used for the duration of the test.  

o.  The Contractor shall employ services of an approved independent certified testing laboratory 

to perform sample testing and provide on-site laboratory as required. Owner reserves the right 
to directly employ services of an independent testing agency or laboratory to perform special 
testing. Employment of the testing agency in no way relives the Contractor of his obligations 
to perform the work in accordance with the specifications. 

p.  Laboratory shall be accredited to a recognized international standard and shall submit a valid 

accreditation  certificate  to  be  approved  by  the  Engineer  before  the  testing  program  is 
approved.  

q.  Testing  equipment  shall  be  calibrated  at  reasonable  intervals  in  accordance  with  the 

manufacturer’s requirements 

r.  Tests to verify compliance with the specifications shall conform to the testing procedure and 

undertaken by the qualified personnel specified. Substitutes to the specified personnel shall 
be  submitted  to  the  Engineer  for  approval  and  shall  be  at  least  equal  in  experience  and 
qualifications to those specified 

s.  The Contractor shall perform additional tests at no extra cost as required by the Engineer to 

prove full compliance of the performance of the completed works 

t.  After each test, the Contractor shall promptly submit six copies of a test report to the Engineer. 

The report shall include as a minimum:  

1.  Project identification 

2.  Date issued 

3.  Name of inspector 

4.  Date and time of sampling and testing 

5.  Identification of product and specification reference 

6.  Type and test method 

7.  Test results and interpretation  

u.  Remotely controlled plant and equipment shall demonstrate suitable operation both from local 

controls and remote controls. As a minimum this procedure shall include full open and full close 
positioning and shall demonstrate the ability of each valve to hold the set  position under all 
operational conditions.  

v.  Variable speed equipment shall demonstrate accurate response to speed controlling devices 

within  the  specified  operating  range.  During  such  tests,  actual  output  shaft  speed  shall  be 
validated by mechanical measurement of shaft speed to compare actual speed with equipment 
instruments. 

w. Response  of  automatic  control  system  shall  be  tested  to  prove  the  manual  and  automatic 

controls,  and  combination  of  both  is  correct  and accurate.  Where  a component  of  a  control 
system performs more than one function, each function shall be validated. Under automatic 
control  plant  shall  respond  accurately  and  reliably  to  its  controlling  signals.  Automatic 
alternation and backup functions shall also be validated during the test. 

x.  Instruments,  gauges  and  other  sensors  and  display  devices  forming  part  of  the  completed 

installation shall be properly calibrated before the test begin, and may be used to measure and 
record the test data. Any other test equipment required shall be provided by the Contractor for 
the duration of the test.  

 

G

ENERAL 

R

 

 

 

y.  All the works shall be examined at the conclusion of the performance test to establish that all 

the  plant  and  equipment  is  free  from  damage  and  undue  wear.  This  inspection  shall  be 
considered as part of the performance test. Plant shall be considered to have failed such test 
if there is any detectable damage or undue wear.  

z.  The  Contractor  shall  correct  all  defects  and  malfunctions  disclosed  by  test  using  approved 

methods and new materials for repairs as required and within the time of test specified in the 
schedule and at his expense. 

aa.  Pump  stations:  In  addition  to  the  component  testing  as  otherwise  specified  the  following 

procedures shall be followed: 

1.  A record of bearing and coupling clearances and alignments shall be tabulated to show the 

"as-built" condition of each pump.  

2.  A record of all overload, timing relay and oil pressure relays shall be tabulated to show the 

"as-built" condition of each motor starter.  

3.  All  cables  shall  be  "megger"  tested  to  confirm  the  integrity  of  the  insulation.  A  tabulated 

record of results shall be made.  

4.  Control  panel  shall  be  statically  tested  with  motors  disconnected  to  confirm  the  correct 

sequence of operation.  

5.  Each  pump  shall  be  operated  individually  over the  range  from  closed  valve  to maximum 

emergency top water level on a recirculation basis using the Contractor water supply and 
for a minimum of four hours continuously. During this test the following parameters will be 
recorded: 

i. 

Motor current 

ii. 

Pump output 

iii. 

Bearing temperature (shall be determined by a contact type thermometer, or lubricant 
temperature may be measured).  

iv. 

Vibration: Full speed vibration of all pumps shall be equal to or less than the amplitude 
limits  recommended  in  the  Hydraulic  Institute  Standards  and/or  the  manufacturer's 
recommendation, whichever is more stringent.  

v. 

Test trials shall extend until each pump unit has run 'continuously' for at least 3 days 
under  all  operating  conditions.  Term  'continuously'  shall  include  running  at  various 
speeds or on a start/stop basis as determined by the control system. 

6. 

Document each unit’s performance by obtaining concurrent readings showing motor voltage 
and amperage, suction head and discharge head.  

i. 

Readings  shall  be  documented  for  at  least  three  conditions  to  ascertain  the  actual 
performance curve 

ii. 

One test shall be at shutoff conditions 

iii. 

Each power lead to the motor shall be checked for proper current balance 

7.  Determine bearing temperatures using a contact type thermometer. Alternatively lubricant 

temperature may be measured.  

i. 

Operate the equipment at least two hours at the maximum specified pressure.  

ii. 

Bearing  temperature  shall  not  exceed  the  limits  recommended  in  the  Hydraulic 
Institute  Standards  and/or  the  manufacturer’s  recommendation,  whichever  is  more 
stringent. 

8.  In the event any equipment fails to meet the above test requirements, it shall be modified 

and retested in accordance with the requirements of these specifications.  

 

G

ENERAL 

R

 

 

 

i. 

Test  results  shall  be  recorded  for  each  pump  for  each  test  and  full  report  shall  be 
submitted  to  the  Engineer.  Cost  of  re-resting  and  reporting  shall  be  borne  by  the 
Contractor.  

9.  Equipment  manufacturer  or  his  authorized  representative  shall  submit  a  certified  written 

report with respect to his equipment stating that:  

i. 

Equipment has been properly installed, wired and connected under his supervision 

ii. 

Equipment is in accurate alignment and free from stress imposed by connecting piping 
or anchor bolts 

iii. 

He was present when the equipment was placed in operation 

iv. 

He has checked, inspected and adjusted the equipment as necessary  

v. 

Equipment has been operated under full load conditions and operated satisfactorily 

vi. 

Equipment is fully covered under the terms of the guarantee 

vii. 

Is ready for continuous operation under specified operating conditions 

viii. 

Is per approved drawings, data and material 

bb.  Other plant, pipes and facilities: Testing in accordance with the applicable specifications 

1.21 

Execution  

This section includes general procedural requirements governing execution of the work including, 
but not limited to, the following:  

1.  Construction layout 

2.  Field Engineering and surveying 

3.  General installation of products 

4.  Coordination of Owner-installed products 

5.  Progress cleaning 

6.  Starting and adjusting 

7.  Protection of installed construction 

1.21.1 

General Requirements 

The  Contractor  shall  provide  and  install  materials  and  equipment  necessary  for  a  complete  and 
functioning project as shown on the Contract plans and required in the Contract documents. 

The Contractor is responsibility for site safety and quality of all materials and work. 

1.21.2 

Submittals  

The Contractor shall comply with the following submittal requirements: 

a.  Qualification data: Land surveyor and professional Engineer 

1.  Construction layout and survey work shall be performed by a qualified land surveyor and / 

or professional Engineer.  

2.  Land surveyor qualifications: A professional land surveyor who is legally qualified to practice 

in  Abu  Dhabi  and  who  is  experienced  in  providing  land-surveying  services  of  the  kind 
indicated. 

3.  Field Engineer shall be performed by a qualified professional Engineer. 

b.  Certificates: Submit certificate signed by land surveyor or a professional  Engineer certifying 

that the location and elevation of improvements comply with requirements.  

 

G

ENERAL 

R

 

 

 

c.  Landfill  receipts:  Submit  copy  of  receipts  issued  by  a  landfill  facility,  licensed  to  accept 

hazardous materials, for hazardous waste disposal 

d.  Certified surveys: Submit two copies signed by land surveyor or professional Engineer 

e.  Final property survey: Submit 10 copies showing the work performed and record survey data. 

1.21.3 

Delivery, Storage, and Handling  

General  requirements  for  delivery,  storage  and  handling  of  products  and  materials  shall  be  as 
specified in Section 1.18.1 and Section 1.18.3. 

Specific  requirements  shall  be  as  specified  in  the  relevant  specification  section  governing  the 
material or product. Additional requirements may be added by the Engineer. 

1.21.4 

Examination  

The Contractor shall be aware of the following conditions: 

a.  Existing  conditions:  Existence  and  location  of  site  improvements,  utilities,  and  other 

construction indicated as existing are not guaranteed. Before beginning work, investigate and 
verify the existence and location of mechanical and electrical systems and other construction 
affecting the work. Before construction, verify the location and points of connection of utility 
services.  

b.  Existing  utilities:  Existence  and  location  of  underground  and  other  utilities  and  construction 

indicated as existing are not guaranteed. Before beginning site work, investigate and verify the 
existence and location of underground utilities and other construction affecting the work.  

1.  Before  construction,  verify  the  location  and  invert  elevation  at  points  of  connection  of 

sanitary  all  utilities  including  sewer,  storm  sewer,  and  water-service  piping;  and 
underground electrical services.  

2.  Furnish location data for work related to project that must be performed by public utilities 

serving project site.  

c.  Acceptance  of  conditions:  Examine  substrates,  areas,  and  conditions,  for  compliance  with 

requirements  for  installation  tolerances  and  other  conditions  affecting  performance.  Record 
observations.  

1.  Written report: Where a written report listing conditions detrimental to performance of the 

work is required by other sections, include the following:  

i. 

Description of the Work 

ii. 

List of detrimental conditions, including substrates 

iii. 

List of unacceptable installation tolerances 

iv. 

Recommended corrections 

2.  Verify  compatibility  with  and  suitability  of  substrates,  including  compatibility  with  existing 

finishes or primers 

3.  Examine  roughing-in  for  mechanical  and  electrical  systems  to  verify  actual  locations  of 

connections before equipment and fixture installation 

4.  Examine walls, floors, and roofs for suitable conditions where products and systems are to 

be installed 

5.  Proceed with installation only after unsatisfactory conditions have been corrected 

d.  Proceeding with the Work indicates acceptance of surfaces and conditions. 

1.21.5 

Preparation  

Prior to starting the work, the Contractor shall comply with the following: 

 

G

ENERAL 

R

 

 

 

1.  Existing  utility  information:  Furnish  information  to  local  utility  that  is  necessary  to  adjust, 

move,  or  relocate  existing  utility  structures,  utility  poles,  lines,  services,  or  other  utility 
appurtenances  located  in  or  affected  by  construction.  Coordinate  with  authorities  having 
jurisdiction.  

2.  Field Measurements: Take field measurements as required to fit the work properly. Recheck 

measurements before installing each product. Where portions of the work are indicated to fit 
to other construction, verify dimensions of other construction by field measurements before 
fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the 
work.  Space  requirements:  Verify  space  requirements  and  dimensions  of  items  shown 
diagrammatically on the Contract plans.  

3.  Review of Contract documents and field conditions: Immediately on discovery of the need for 

clarification  of  the  Contract  documents,  submit  a  request  for  information  to  the  Engineer. 
Include a detailed description of problem encountered, together with recommendations for 
changing the Contract documents.  

1.21.6 

Construction Layout 

The Contractor shall comply with the following requirements: 

a.  Verification:  Before  proceeding  to  lay  out  the  work,  verify  layout  information  shown  on  the 

Contract plans, in relation to the property survey and existing benchmarks. If discrepancies 
are discovered, notify the Engineer promptly. 

b.  General:  Engage  a  land  surveyor  and/  or  professional  Engineer  to  lay  out  the  work  using 

accepted surveying practices 

1.  Establish benchmarks and control points to set lines and levels at each stage of construction 

and elsewhere as needed to locate each element of the project 

2.  Establish dimensions within tolerances indicated. Do not scale the Contract plans to obtain 

required dimensions 

3.  Inform installers of lines and levels to which they must comply 

4.  Check the location, level, and plumb, of every major element as the Work progresses 

5.  Notify  the  Engineer  when  deviations  from  required  lines  and  levels  exceed  allowable 

tolerances 

6.  Close site surveys with an error of closure equal to or less than the standard established by 

authorities having jurisdiction 

c.  Site improvements: Locate and lay out site improvements, including pavements, grading, fill 

and topsoil placement, utility slopes, and invert elevations.  

d.  Building  lines  and  levels:  Locate  and  lay  out  control  lines  and  levels for structures,  building 

foundations,  column  grids,  and  floor  levels,  including  those  required  for  mechanical  and 
electrical work. Transfer survey markings and elevations for use with control lines and levels. 
Level foundations and piers from two or more locations. 

e.  Record log: Maintain a log of layout control work. Record deviations from required lines and 

levels. Include beginning and ending dates and times of surveys, weather conditions, name 
and duty of each survey party member, and types of instruments and tapes used. Make the 
log available for reference by the Engineer. 

1.21.7 

Field Engineering 

The Contractor

’s field Engineering shall include the following: 

a.  Identification: Owner will identify existing benchmarks, control points, and property corners 

 

G

ENERAL 

R

 

 

 

b.  Reference  points:  Locate  existing  permanent  benchmarks,  control  points,  and  similar 

reference points before beginning the work. Preserve and protect permanent benchmarks and 
control points during construction operations. 

1.  Do  not  change  or  relocate  existing  benchmarks  or  control  points  without  prior  written 

approval of the Engineer.  

2.  Report lost or destroyed permanent benchmarks or control points promptly.  

3.  Report the need to relocate permanent benchmarks or control points to the Engineer before 

proceeding 

4.  Replace  lost  or  destroyed  permanent  benchmarks  and  control  points  promptly.  Base 

replacements on the original survey control points.  

c.  Benchmarks: Establish and maintain a minimum of three permanent benchmarks on project 

site, referenced to data established by survey control points. Comply with authorities having 
jurisdiction for type and size of benchmark.  

1.  Record benchmark locations, with horizontal and vertical data, on project record documents 

2.  Where the actual location or elevation of layout points cannot be marked, provide temporary 

reference points sufficient to locate the work 

3.  Remove temporary reference points when no longer needed. Restore marked construction 

to its original condition 

d.  Certified survey: On completion of foundation walls, major site improvements, and other work 

requiring field-Engineering services, prepare a certified survey showing dimensions, locations, 
angles, and elevations of construction and site work 

e.  Final  property  survey:  Prepare  a  final  property  survey  showing  significant  features  (real 

property)  for  project.  Include  on  the  survey  a  certification,  signed  by  land  surveyor  or 
professional Engineer, that principal metes, bounds, lines, and levels of project are accurately 
positioned as shown on the survey 

1.  Show  boundary  lines,  monuments,  streets,  site  improvements  and  utilities,  existing 

improvements  and  significant  vegetation,  adjoining  properties,  acreage,  grade  contours, 
and the distance and bearing from a site corner to a legal point 

2.  Recording:  At  substantial  completion,  have  the  final  property  survey  recorded  by  or  with 

authorities having jurisdiction as the official property survey. 

1.21.8 

Installation 

The Contractor

’s installation of work shall comply with the following items: 

a.  General: Locate the work and components of the work  accurately, in correct alignment and 

elevation, as indicated 

1.  Make vertical work plumb and make horizontal work level 

2.  Where space is limited, install components to maximize space available for maintenance 

and ease of removal for replacement 

3.  Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated 

4.  Maintain minimum headroom clearance of 2.4 m in spaces without a suspended ceiling 

b.  Comply with manufacturer's written instructions and recommendations for installing products 

in applications indicated 

c.  Install  products  at  the  time  and  under  conditions  that  will  ensure  the  best  possible  results. 

Maintain conditions required for product performance until substantial completion 

d.  Conduct construction operations so no part of the work is subjected to damaging operations 

or loading in excess of that expected during normal conditions of occupancy 

 

 

 

 

 

 

 