Manholes, Inlets, Catch Basins, and Drywells
7-05
Manholes, catch basins, inlets, and drywells shall be constructed on a compacted or
undisturbed level foundation. If the Contractor elects to use a separate cast-in-place base,
the concrete shall be Class 4000. Upon final acceptance of the Work, all manholes, catch
basins, inlets, drywells, and other drainage Structures shall conform to the requirements
of the
Standard Plans
except as approved by the Engineer.
Any shoring or extra excavation required shall meet the requirements of
Section 2-09.3
.
7-05.3(1) Adjusting Manholes and Catch Basins to Grade
Where shown in the Plans or where directed by the Engineer, the existing manholes,
catch basins, or inlets shall be adjusted to the grade as staked or otherwise designated by
the Engineer.
The existing cast iron ring and cover on manholes and the catch basin and inlet frame and
grate shall first be removed and thoroughly cleaned for reinstalling at the new elevation.
From that point, the existing Structure shall be raised or lowered to the required
elevation. The materials and method of construction shall conform to the requirements
specified above, and the finished Structure shall conform to the requirements of the
Standard Plans
except as approved by the Engineer.
7-05.3(2) Abandon Existing Manholes
Where it is required that an existing manhole be abandoned, the Structure shall be broken
down to a depth of at least 4 feet below the revised surface elevation, all connections
plugged, and the manhole filled with sand and compacted to 90 percent density as
specified in
Section 2-03.3(14)C
. Debris resulting from breaking the upper part of the
manhole may be mixed with the sand subject to the approval of the Engineer. The ring
and cover shall be salvaged and all other surplus material disposed of.
7-05.3(3) Connections to Existing Manholes
The Contractor shall verify invert elevations prior to construction. The crown elevation
of laterals shall be the same as the crown elevation of the incoming pipe unless specified.
The existing base shall be reshaped to provide a channel equivalent to that specified for a
new manhole.
The Contractor shall excavate completely around the manhole to prevent unbalanced
loading. The manhole shall be kept in operation at all times and the necessary precautions
shall be taken to prevent debris or other material from entering the sewer, including a
tight pipeline bypass through the existing channel if required. Water used for flushing and
testing shall not be allowed to enter the sewer.
All damage to the manhole resulting from the Contractor’s operation shall be repaired at
no expense to the Contracting Agency.
7-05.3(4) Drop Manhole Connection
Drop manhole connections shall be constructed in accordance with the Plans. One length
of ductile iron pipe shall be provided outside the manhole.