Shafts 6-19
6-19.3(7)D
Requirements for Placing Concrete Underwater
When placing concrete underwater, including when water in a shaft excavation exceeds
3 inches in depth, the Contractor shall place the concrete by pressure feed using a
concrete pump, with a watertight tube having a minimum diameter of 4 inches. The
discharge end of the tube on the concrete pump shall include a device to seal out water
while the tube is first filled with concrete. Alternatively, the Contractor may use a plug
that is inserted at the hopper of the concrete pump and travels through the tremie to
keep the concrete separated from the water and slurry. Concrete placement by gravity
feed is not allowed.
Throughout the underwater concrete placement operation, the discharge end of the
tube shall remain submerged in the concrete at least 5 feet and the tube shall always
contain enough concrete to prevent water from entering. The concrete placement shall be
continuous until the work is completed, resulting in a seamless, uniform shaft.
6-19.3(7)E
Testing and Repair of Shaft Concrete Placed Underwater
If the underwater concrete placement operation is interrupted, the Engineer may require
the Contractor to prove by core drilling or other tests that the shaft contains no voids
or horizontal joints. If testing reveals voids or joints, the Contractor shall repair them or
replace the shaft at no expense to the Contracting Agency. Responsibility for coring costs,
and calculation of time extension, shall be in accordance with
Section 6-19.3(9)H
.
6-19.3(7)F
Cleaning and Removal of Previously Placed Shaft Concrete
Before placing any fresh concrete against concrete deposited in water or slurry, the
Contractor shall remove all scum, laitance, loose gravel, and sediment on the upper
surface of the concrete deposited in water or slurry and chip off any high spots on the
upper surface of the existing concrete that would prevent the steel reinforcing bar cage
from being placed in the position required by the Plans.
Prior to performing any of the crosshole sonic log testing operations specified in
Section
6-19.3(9)
, the Contractor shall remove the concrete at the top of the shaft down to
sound concrete.
6-19.3(7)G
Protection of Fresh and Curing Concrete From Vibration
The Contractor’s construction operation in the vicinity of a shaft excavation with freshly
placed concrete and curing concrete shall conform to
Section 6-02.3(6)D
.
6-19.3(7)H
Uniform Yield Form
Except for shafts where the shaft concrete is placed in the dry, the Contractor shall
complete a uniform yield form, consistent with the sample form submitted to the Engineer
as part of the shaft installation narrative as specified in
Section 6-19.3(2)B
, item 6, for
each shaft and shall submit the completed form to the Engineer within 24 hours of
completing the concrete placement in the shaft.