Erosion Control and Water Pollution Control

If trenching is not feasible due to rocky soils or not advisable due to proximity to a 
downslope sensitive area, a different sediment control device that does not require 
trenching shall be used in place of silt fence.

Backup support is needed for silt fence in areas where extra strength may be required, 
such as the toe of steep cut or fill slopes or areas where equipment may push excessive 
soils toward the fence. When backup support is used, wire shall have a maximum mesh 
spacing of 2 inches, and the plastic mesh shall be as resistant to ultraviolet radiation as 
the geotextile it supports. The strength of the wire or plastic mesh shall be equivalent to 
or greater than as required in 

Section 9-33.2(1)

Table 6, for unsupported geotextile (i.e., 

180 lbs. grab tensile strength in the machine direction). Post spacing and attachments 
shall be as shown in the Standard Plans.

8-01.3(9)A3  High Visibility Silt Fence 

High visibility silt fence (HVSF) shall be orange in color and only be used for the dual 
purpose of demarcating site preservation lines and a sediment control device in a location 
where high visibility mesh fence and black silt fence would otherwise be used together 
at same location. If use of HVSF is allowed the geotextile material shall meet the material 
requirements of 

Section 9-33.2(1)

Table 6. Post spacing and attachments shall be as 

shown in the Standard Plans.

Backup support is needed for high visibility silt fence (HVSF) in areas where extra strength 
may be required, such as the toe of steep cut or fill slopes or areas where equipment may 
push excessive soils toward the sensitive or protected areas. When backup support is 
used, wire shall have a maximum mesh spacing of 2 inches, and the plastic mesh shall be 
as resistant to ultraviolet radiation as the geotextile it supports. The strength of the wire 
or plastic mesh shall be equivalent to or greater than as required in 

Section 9-33.2(1)

Table 6, for unsupported geotextile (i.e., 180 lbs. grab tensile strength in the machine 
direction). Post spacing shall be as shown in the Standard Plans.

When sediment deposits reach approximately ⅓ the height of the silt fence, or 8 inches 
whichever is lower the deposits shall be removed and stabilized in accordance with 

Section 8-01.3(15)

.

8-01.3(9)B 

Gravel Filter, Wood Chip, or Compost Berm

Filter berms shall retain sediment and direct flows. The gravel filter berm shall be a 
minimum of 1 foot in height and shall be maintained at this height for the entire time 
they are in use. Rock material used for filter berms shall meet the grading requirements 
in 

Section 9-03.9(2)

, but shall not include any recycled materials as outlined in 

Section 9-03.21

.

The wood chip berm shall be a minimum of 2 feet in height and shall be maintained at this 
height for the entire time they are in use.

The Compost Berm shall be constructed in accordance with the detail in the Plans. 
Compost shall be Medium Compost.

Erosion Control and Water Pollution Control 

8-01

8-01.3(9)C Vacant
8-01.3(9)D 

Inlet Protection

Inlet protection shall be installed below or above, or as a prefabricated cover at each inlet 
grate, as shown in the Plans. Inlet protection devices shall be installed prior to beginning 
clearing, grubbing, or earthwork activities.

Geotextile fabric in all prefabricated inlet protection devices shall meet or exceed the 
requirements of 

Section 9-33.2

, Table 1, for Moderate Survivability, and the minimum 

filtration properties of Table 2.

When the depth of accumulated sediment and debris reaches approximately ½ the height 
of an internal device or ⅓ the height of the external device (or less when so specified by 
the manufacturers), or as designated by the Engineer, the deposits shall be removed and 
stabilized on-site in accordance with 

Section 8-01.3(16)

.

Below Inlet Grate

Below Inlet Grate devices shall be prefabricated units specifically designed for inlet 
protection and shall remain securely attached to the drainage Structure when fully loaded 
with sediment and debris, or at the maximum level of sediment and debris specified by 
the manufacturer.

Above Inlet Grate

Above Inlet Grate devices may be silt fence, sandbags, or prefabricated units specifically 
designed for inlet protection.

The device shall remain securely in place around the drainage Structure under all 
conditions.

Inlet Grate Cover

Inlet Grate Cover devices shall be prefabricated units specifically designed for inlet 
protection and have the following features:
1.  Be a sewn geotextile fabric unit fitted to the individual grate and completely 

enclosing the grate.

2.  Have built-in lifting devices to allow manual access of the stormwater system.
3.  Utilize an orange monofilament geotextile fabric.

Check dams or functionally equivalent devices may be used as inlet protection devices 
with the approval of the Engineer.

Page 8-16 

Erosion Control and Water Pollution Control

8-01.3(10) Wattles

Wattles are used as a flow control and sediment control device. Wattles shall be installed 
as soon as construction will allow or when designated by the Engineer. Wattle installation 
and trenching shall begin from the base of the slope and work uphill prior to any topsoil 
or compost placement. Excavated material from trenching shall be spread evenly along 
the uphill slope and be compacted using hand tamping or other method approved by the 
Engineer. On gradually sloped or clay-type soils trenches shall be 2 to 3 inches deep. On 
loose soils, in high rainfall areas, or on steep slopes, trenches shall be 3 to 5 inches deep, 
or half the thickness of the wattle, whichever is greater.

Wattles shall be laid out, spaced, and staked in accordance with the Standard Plans
Live stakes can be used in addition to, but not as a replacement for, wooden stakes. If 
trenching and staking is not possible due to rocky soils, compost socks shall be used 
instead of wattles.

The Contractor shall exercise care when installing wattles to ensure the method of 
installation minimizes the disturbance of waterways and prevents sediment or pollutant 
discharge into water bodies.

8-01.3(11)  Outlet Protection

Outlet protection shall prevent scour at the outlets of ponds, pipes, ditches or other 
conveyances. All quarry spall material used for outlet protection shall be free of 
extraneous material and meet the gradation requirements in 

Section 9-13.1(5)

.

8-01.3(12)  Compost Sock

Compost socks are used to disperse flow and sediment. Compost socks shall be installed 
as soon as construction will allow but before flow conditions create erosive flows or 
discharges from the site. Compost socks shall be installed prior to any mulching or 
compost placement. Compost socks shall be laced together end-to-end with coir rope 
or ends shall be securely overlapped to create a continuous length. Terminal ends of 
the continuous length shall be curved 2 to 4 feet upward into the slope to prevent 
concentrated flows from going around the terminal ends. Finished grades shall be of 
a natural appearance with smooth transitions. Compost for compost socks shall be 
Medium Compost.

Compost socks shall be laid out, spaced and staked in accordance with the Standard Plans
Live stakes can be used in addition to, but not as a replacement for, wooden stakes. If 
staking is not possible or if the compost sock is being used on concrete, heavy blocks or 
an equivalent item shall be used to weigh down and secure the sock.

The Contractor shall exercise care when installing compost socks to ensure that the 
method of installation minimizes disturbance of waterways and prevents sediment 
or pollutant discharge into water bodies. Stakes shall be removed to minimize soil 
disturbance.

Erosion Control and Water Pollution Control 

8-01

8-01.3(13)  Temporary Curb

Temporary curbs shall divert or redirect water around erodible soils.

Temporary curbs shall be installed along pavement edges to prevent runoff from flowing 
onto erodible slopes. Water shall be directed to areas where erosion can be controlled. 
Temporary curbs shall be a minimum of 4 inches in height. Temporary curb shall be 
installed so that ponding does not occur in the adjacent roadway.

8-01.3(14)  Temporary Pipe Slope Drain

Temporary pipe slope drain shall be Corrugated Polyethylene Drain Pipe and shall be 
constructed in accordance with the Plans.

Water interceptor dikes or temporary curbs shall be used to direct water into pipe slope 
drain. The entrance to the drain may consist of a prefabricated funnel device specifically 
designed for application, rock, sand bags, or as approved by the Engineer.

The pipe fittings shall be water tight and the pipe secured to the slope with metal posts, 
wood stakes, or sand bags.

The water shall be discharged to a stabilized conveyance, sediment trap, stormwater 
pond, rock splash pad, or vegetated strip, in a manner to prevent erosion and maintain 
water quality compliance.

8-01.3(15) Maintenance

Erosion and sediment control BMPs shall be maintained or adaptively managed as 
required by the CSWGP until the Engineer determines they are no longer needed. When 
deficiencies in functional performance are identified, the deficiencies shall be rectified 
immediately.

The BMPs shall be inspected on the schedule outlined in 

Section 8-01.3(1)B

 for 

damage and sediment deposits. Damage to or undercutting of BMPs shall be repaired 
immediately.

In areas where the Contractor’s activities have compromised the erosion control functions 
of the existing grasses, the Contractor shall overseed at no additional cost to the 
Contracting Agency.

The quarry spalls of construction entrances shall be refreshed, replaced, or screened to 
maintain voids between the spalls for collecting mud and dirt.

Unless otherwise specified, when the depth of accumulated sediment and debris 
reaches approximately ⅓ the height of the BMP the deposits shall be removed. Debris or 
contaminated sediment shall be disposed of in accordance with 

Section 2-03.3(7)C

. Clean 

sediments may be stabilized on-site using BMPs as allowed by the Engineer. 

Page 8-18 

Erosion Control and Water Pollution Control

8-01.3(16) Removal

The Contractor shall remove all temporary BMPs, all associated hardware and associated 
accumulated sediment deposition from the project limits prior to Physical Completion 
unless otherwise allowed by the Engineer. When the temporary BMP materials are made 
of natural plant fibers unaltered by synthetic materials the Engineer may allow leaving the 
BMP in place.

The Contractor shall remove BMPs and associated hardware in a way that minimizes soil 
disturbance. The Contractor shall permanently stabilize all bare and disturbed soil after 
removal of BMPs. If the installation and use of the erosion control BMPs have compacted 
or otherwise rendered the soil inhospitable to plant growth, such as construction 
entrances, the Contractor shall take measures to rehabilitate the soil to facilitate 
plant growth. This may include, but is not limited to, ripping the soil, incorporating soil 
amendments, or seeding with the specified seed.

At the request of the Contractor and at the sole discretion of the Engineer the CSWGP 
may be transferred back to the Contracting Agency. Approval of the Transfer of Coverage 
request will require the following:
1.  All other Work required for Contract Completion has been completed.
2.  All Work required for compliance with the CSWGP has been completed to the 

maximum extent possible. This includes removal of BMPs that are no longer needed 
and the site has undergone all Stabilization identified for meeting the requirements 
of Final Stabilization in the CSWGP.

3.  An Equitable Adjustment change order for the cost of Work that has not been 

completed by the Contractor.

4.  Submittal of the Washington State Department of Ecology Transfer of Coverage form 

(Ecology Form ECY 020-87a) to the Engineer.

If the Engineer approves the transfer of coverage back to the Contracting Agency 
the requirement in 

Section 1-07.5(3)

 for the Contractor’s submittal of the Notice of 

Termination form to Ecology will not apply.

8-01.4 Measurement

8-01.4(1)  Lump Sum Bid for Project (No Unit Items) 

When the Bid Proposal contains the item “Erosion Control and Water Pollution 
Prevention” there will be no measurement of unit or force account items for Work defined 
in 

Section 8-01

 except as described in Sections 

8-01.4(3)

 and 

8-01.4(4)

Also, except as 

described in 

Section 8-01.4(3)

all of Sections 

8-01.4(2)

 and 

8-01.5(2) 

are deleted.

Erosion Control and Water Pollution Control 

8-01

8-01.4(2)  Item Bids

When the Proposal does not contain the items “Erosion Control and Water Pollution 
Prevention”, Sections 

8-01.4(1)

 and 

8-01.5(1)

 are deleted and the Bid Proposal will 

contain some or all of the following items measured as noted.

ESC lead will be measured per day for each day that an inspection is made and a report is 
filed.

Erosion control blanket and plastic covering will be measured by the square yard along the 
ground slope line of surface area covered and accepted.

Turbidity curtains will be measured by the linear foot along the ground line of the 
installed curtain.

Check dams will be measured per linear foot one time only along the ground line of the 
completed check dam. No additional measurement will be made for check dams that are 
required to be rehabilitated or replaced due to wear.

Stabilized construction entrances will be measured by the square yard by ground slope 
measurement for each entrance constructed.

Tire wash facilities will be measured per each for each tire wash installed.

Street cleaning will be measured by the hour for the actual time spent cleaning pavement, 
refilling with water, dumping and transport to and from cleaning locations within the 
project limits, as authorized by the Engineer. Time to mobilize the equipment to or from 
the project limits on which street cleaning is required will not be measured.

Inlet protections will be measured per each for each initial installation at a drainage 
structure.

Silt fence, gravel filter, compost berms, and wood chip berms will be measured by the 
linear foot along the ground line of the completed barrier.

Wattles and compost socks will be measured by the linear foot.

Temporary curbs will be measured by the linear foot along the ground line of the 
completed installation.

Temporary pipe slope drains will be measured by the linear foot along the flow line of the 
pipe.

Coir logs will be measured by the linear foot along the ground line of the completed 
installation.

Outlet protections will be measured per each initial installation at an outlet location.

Temporary seeding, temporary mulching, and tackifiers will be measured by the acre by 
ground slope measurement. 

Compost blanket will be measured by the square yard by ground slope surface area 
covered and accepted.

Page 8-20 

Erosion Control and Water Pollution Control

8-01.4(3)  Reinstating Unit Items with Lump Sum Erosion Control and 

Water Pollution Prevention

The Contract Provisions may establish the project as lump sum, in accordance with 

Section 8-01.4(1)

 and also include one or more of the items included above in 

Section 

8-01.4(2)

When that occurs, the corresponding measurement provision in 

Section 

8-01.4(2)

 is not deleted and the Work under that item will be measured as specified.

8-01.4(4) 

Items not included with Lump Sum Erosion Control and Water 

Pollution Prevention

Compost blanket will be measured by the square yard by ground slope surface area 
covered and accepted.

Temporary mulch will be measured by the acre by ground slope surface area covered and 
accepted.

High visibility fence will be measured by the linear foot along the ground line of the 
completed fence.

8-01.5 Payment

8-01.5(1)  Lump Sum Bid for Project (No Unit Items)

Payment will be made for the following Bid item when it is included in the Proposal:

“Erosion Control and Water Pollution Prevention”, lump sum.

The lump sum Contract price for “Erosion Control and Water Pollution Prevention” 
shall be full pay to perform the Work as described in 

Section 8-01

 except for costs 

compensated by Bid Proposal items inserted through Contract Provisions as described in 

Section 8-01.4(2)

. Progress payments for the lump sum item “Erosion Control and Water 

Pollution Prevention” will be made as follows:
1.  The Contracting Agency will pay 15 percent of the bid amount for the initial set up 

for the item. Initial set up includes the following:
a.  Acceptance of the TESC Plan provided by the Contracting Agency or submittal 

of a new TESC Plan,

b.  Submittal of a schedule for the installation of the BMPs,
c.  Identifying water quality sampling locations, and

2.  Seventy percent of the bid amount will be paid in accordance with 

Section 1-09.9

.

3.  Once the project is physically complete and copies of the all reports submitted to 

Ecology have been submitted to the Engineer, and, if applicable, transference of the 
CSWGP back to the Contracting Agency is complete, the remaining 15 percent of 
the bid amount shall be paid in accordance with 

Section 1-09.9

.

Erosion Control and Water Pollution Control 

8-01

8-01.5(2)  Item Bids

“ESC Lead”, per day.

“Turbidity Curtain”, per linear foot.

“Erosion Control Blanket”, per square yard.

“Plastic Covering”, per square yard.

“Check Dam”, per linear foot.

“Inlet Protection”, per each.

“Gravel Filter Berm”, per linear foot.

“Stabilized Construction Entrance”, per square yard.

“Street Cleaning”, per hour.

“Silt Fence”, per linear foot.

“Wood Chip Berm”, per linear foot.

“Compost Berm”, per linear foot.

“Wattle”, per linear foot.

“Compost Sock”, per linear foot.

“Coir Log”, per linear foot.

“Temporary Curb”, per linear foot.

“Temporary Pipe Slope Drain”, per linear foot.

“Temporary Seeding”, per acre.

“Temporary Mulching”, per acre.

“Compost Blanket”, per square yard.

“Outlet Protection”, per each.

“Tackifier”, per acre.

“Erosion/Water Pollution Control”, by force account as provided in Section 1-09.6.

Maintenance and removal of erosion and water pollution control devices including 
removal and disposal of sediment, stabilization and rehabilitation of soil disturbed 
by these activities, and any additional Work deemed necessary by the Engineer to 
control erosion and water pollution will be paid by force account in accordance with 
Section 1-09.6.

To provide a common Proposal for all Bidders, the Contracting Agency has entered an 
amount in the Proposal to become a part of the Contractor’s total Bid.

Page 8-22 

Erosion Control and Water Pollution Control

8-01.5(3)  Reinstating Unit Items with Lump Sum Erosion Control and 

Water Pollution Prevention

The Contract may establish the project as lump sum, in accordance with 

Section 8-01.4(1)

 

and also reinstate the measurement of one or more of the items described in 

Section 

8-01.4(2)

except for Erosion/Water Pollution Control, by force account. When that 

occurs, the corresponding payment provision in 

Section 8-01.5(2)

 is not deleted and the 

Work under that item will be paid as specified.

8-01.5(4)  Items not included with Lump Sum Erosion Control and 

Water Pollution Prevention

Payment will be made for the following Bid item when it is included in the Proposal:

“High Visibility Fence”, per linear foot.

Roadside Restoration 

8-02

8-02 

Roadside Restoration

8-02.1 Description

This Work consists of preserving, maintaining, establishing and augmenting vegetation 
on the roadsides and within mitigation or sundry site areas. It includes vegetation 
preservation, weed and pest control, furnishing and placing topsoil, compost, and soil 
amendments, and furnishing and planting seed, sod and plants of all forms and container 
types. It includes performing plant establishment activities and soil bioengineering. Work 
shall be performed in accordance with these Specifications and as shown in the Plans or 
as designated by the Engineer.

Trees, whips, shrubs, ground covers, cuttings, live stakes, live poles, live branches, 
rhizomes, tubers, rootstock, and seedlings will hereinafter be referred to collectively as 
“plants” or “plant material”. Grass, wildflowers, and other plant materials installed in seed 
form will hereinafter be referred to collectively as “seed”.

8-02.2 Materials

Materials shall meet the requirements of the following sections:
 

Topsoil 

9-14.2

 

Fertilizer 

9-14.4 

Mulch and Amendments 

9-14.5

 

Erosion Control Devices 

9-14.6

 

Plant Materials 

9-14.7

 

Stakes, Guys, and Wrapping 

9-14.8

 

Water 

9-25.2

Botanical identification and nomenclature of plant materials shall be based on 
descriptions by Hitchcock and Cronquist in “Flora of the Pacific Northwest”. Botanical 
identification and nomenclature of plant material not found in "Flora" shall be based on 
Bailey in “Hortus Third” or superseding editions and amendments or as referenced in the 
Plans.

8-02.3 

Construction Requirements

8-02.3(1)  Responsibility During Construction

The Contractor shall prepare, install, and ensure adequate and proper care of all roadside 
seeded, planted, and lawn areas on the project until all plant establishment periods 
required by the Contract are complete or until Physical Completion of the project, 
whichever is last.

Adequate and proper care shall include, but is not limited to, keeping all plant material in a 
healthy, growing condition by watering, pruning, and other actions deemed necessary for 
plant health. This Work shall include keeping the project area free from insect infestation, 
weeds or unwanted vegetation, litter, and other debris along with retaining the finished 
grades and mulch in a neat uniform condition.

Page 8-24 

Roadside Restoration

Existing desirable vegetation shall be saved and protected unless removal is required by 
the Contract or allowed by the Engineer.

The Contractor shall have sole responsibility for the maintenance and appearance of the 
roadside restoration.

8-02.3(2)  Work Plans

Three Work Plan submittals exist under this Section:
1.  Roadside Work Plan: This plan is required when Work will disturb the roadside 

beyond 20 feet from the pavement or where trees or native vegetation will be 
removed, the Contractor shall submit a Type 2 Working Drawing.

2.  Weed and Pest Control Plan: This plan is required when the proposal contains the 

item “Weed and Pest Control,” and prior to application of any chemicals or weed 
control activities, the Contractor shall submit a Type 2 Working Drawing.

3.  Plant Establishment Plan: This plan is required when the proposal contains the item 

“PSIPE__”, and prior to completion of Initial Planting, the Contractor shall submit a 
Type 2 Working Drawing.

8-02.3(2)A 

Roadside Work Plan

The Roadside Work Plan shall define the expected impacts to the roadside and 
restoration resulting from Work necessary to meet all Contract requirements. The 
Contractor shall define how the roadside restoration Work included in the Contract 
will be phased and coordinated with project Work such as earthwork, staging, access, 
erosion and water pollution control, irrigation, etc. The Roadside Work Plan shall include 
the following:
1.  Limiting impacts to roadsides:

a.  Limits of Work including locations of staging or parking.
b.  Means and methods for vegetation protection (in accordance with 

Section 1-07.16(2)).

c.  Locations outside of clearing limits where vegetation shall be removed to 

provide access routes or other needs to accomplish the Work.

d.  Plans for removal, preservation and stockpile of topsoil or other native 

materials, if outside of clearing and grubbing limits and within the project limits.

2.  Roadside Restoration:

a.  Plan for propagation and procurement of plants, ground preparation for 

planting, and installation of plants.

b.  Means and methods to limit soil compaction where seeding and planting are to 

occur, such as steel plates, hog fuel access roads, wood mats for sensitive areas 
(including removal) and decompaction for unavoidable impacts.

c.  Plan and timing to incorporate or remove erosion control items.

Roadside Restoration 

8-02

3.  Lawn Installation:

a.  Schedule for lawn installation work.
b.  Establishment and maintenance of lawns.

8-02.3(2)B 

Weed and Pest Control Plan

The Weed and Pest Control Plan shall describe all weed and pest control needs for the 
project.

The plan shall be prepared and signed by a licensed Commercial Pest Control Operator or 
Consultant. The plan for control of weeds and pests on the Contract in accordance with 
Section 8-02.3(3) shall include the following:
1.  Names of plan preparer and pesticide operators, including contact information. The 

Contractor shall furnish the Engineer evidence that all operators are licensed with 
appropriate endorsements, and that the pesticide used is registered for use by the 
Washington State Department of Agriculture.

2.  Means and methods of weed control, including mechanical and/or chemical.
3.  Schedule for weed control including re-entry times for pesticide application by 

pesticide type.

4.  Proposed pesticide use in accordance with Section 8-02.3(3)A: name, application 

rate, and Safety Data Sheets of all proposed pesticides. Include a copy of the current 
product label for each pesticide to be used.

5.  Plan to ensure worker safety until pesticide re-entry periods are met.

8-02.3(2)C 

Plant Establishment Plan

The Plant Establishment Plan shall describe activities necessary to ensure continued 
health and vigor of planted and seeded areas in accordance with the requirements of 
Sections 8-02.3(12) and 8-02.3(13). Should the plan become unworkable at any time 
during the first-year plant establishment, the Contractor shall submit a revised plan prior 
to proceeding with further Work. The Plant Establishment Plan shall include:
1.  Proposed scheduling of joint inspection meetings, activities, materials, equipment to 

be utilized for the first-year plant establishment.

2.  Proposed adaptive management activities to ensure successful establishment of 

seeded, sodded, and planted areas.

3.  A contact person.
4.  Management of the irrigation system, when applicable.

Page 8-26 

Roadside Restoration

8-02.3(3)  Weed and Pest Control

The Contractor shall control weed and pest species within the project area using 
integrated pest management principles consisting of mechanical, biological, and 
chemical controls that are outlined in the Weed and Pest Control Plan or as designated 
by the Engineer. Controlling weeds consists of killing and removing weeds by chemical, 
mechanical, and hand methods.

8-02.3(3)A 

Chemical Pesticides

Chemical pesticides include, but are not restricted to, any substance or mixture of 
substances intended for preventing, destroying, repelling or mitigating any pest, including 
but not limited to, insecticides, herbicides, fungicides, adjuvants, and additives, including 
plant regulators, defoliants and desiccants. The Contractor shall apply chemical pesticides 
in accordance with the label recommendations, the Washington State Department of 
Ecology, local sensitive area ordinances, and Washington State Department of Agriculture 
laws and regulations. Only those pesticides listed in the table Herbicides Approved 
for Use on WSDOT Rights of Way and accepted as part of the Weed and Pest Control 
Plan or by written authorization from the Engineer may be used (www.wsdot.wa.gov/
maintenance/roadside/herbicide_use.htm).

The applicator shall be licensed by the State of Washington as a Commercial Applicator or 
Commercial Operator, with additional endorsements as required by the Special Provisions 
or the proposed weed control plan. All chemical pesticides shall be delivered to the job 
site in the original containers, or if pre-mixed off-site, a certification of the components 
and formulation from the supplier is required. The licensed applicator or operator shall 
complete WSDOT Form 540-509, Commercial Pesticide Application Record, each day the 
pesticide is applied and furnish a copy to the Engineer by the following business day.

The Contractor shall ensure confinement of the chemicals within the designated areas. 
The use of spray chemical pesticides shall require the use of anti-drift and activating 
agents and a spray pattern indicator unless otherwise allowed by the Engineer.

The Contractor shall assume all responsibility for rendering any area unsatisfactory for 
planting by reason of chemical application. Damage to adjacent areas, either on or off 
the Highway Right of Way, shall be repaired to the satisfaction of the Engineer or the 
property owner at no additional cost to the Contracting Agency.

8-02.3(3)B 

Planting and Lawn Area Weed Control

Planting and lawn area weed control consists of controlling weeds and pests in planted 
and lawn areas shown in the Plans. This Work is included in the bid items for planting and 
lawn installation.

All planting and lawn areas shall be prepared so that they are weed and debris free at the 
time of planting and until completion of the project. The planting areas shall include the 
entire ground surface, regardless of cover, areas around plants, and those areas shown in 
the Plans.

Roadside Restoration 

8-02

Within planting or lawn areas, all species that are not shown in the Plans are unwanted 
and shall be controlled unless specifically allowed by the Engineer to remain.

Grass growing within the mulch ring of a plant, including grass applied in accordance with 
Sections 8-01.3(2)A1, 8-02.3(9) or 8-02.3(10), shall be considered a weed and shall be 
controlled on the project in accordance with the weed and pest control plan.

All applications of post-emergent herbicides shall be made while green and growing tissue 
is present. Residual herbicides shall not be used where rhizomatous species or perennial 
species are indicated.

Should unwanted vegetation reach the flowering and seed stage in violation of these 
Specifications, the Contractor shall physically remove and bag the seed heads prior to 
seed dispersion. All physically removed vegetation and seed heads shall be disposed of 
off-site at no cost to the Contracting Agency.

8-02.3(3)C 

Project Area Weed and Pest Control

The Contractor shall control weeds not otherwise covered in accordance with Section 
8-02.3(3)B, in all areas within the project limits, including erosion control seeding areas 
and vegetation preservation areas, as designated by the Engineer.

When the Bid Item “Project Area Weed and Pest Control” is included in the Contract, 
the Contractor shall also control all weeds specified as noxious by the Washington State 
Department of Agriculture, the local Weed District, or the County Noxious Weed Control 
Board outside of planting areas within the project limits.

8-02.3(4) Topsoil

Topsoil shall not be worked or placed when the ground or topsoil is frozen, or 
excessively wet.

The Contractor shall protect topsoil stockpiled for project use to prevent erosion and 
weed growth. Weed growth on topsoil stockpile sites shall be immediately eliminated in 
accordance with the accepted Weed and Pest Control Plan and Section 8-02.3(3)C.

The subsoil where topsoil is to be placed shall be tilled to a depth of 1 foot or as specified 
in the Special Provisions or the Plans. Topsoil of the type specified shall be evenly spread 
over the specified areas to the depth shown in the Plans or as otherwise ordered by 
the Engineer. Topsoil depths greater than 6 inches shall be placed in lifts no more than 
6 inches in depth. The first lift of topsoil shall be incorporated with sub-soil to a depth of 
8 inches and subsequent lifts placed and lightly tamped between lifts. After the topsoil 
has been spread, all large clods, hard lumps, and rocks 2 inches in diameter and larger, and 
litter shall be raked up, removed, and disposed.

8-02.3(4)A 

Topsoil Type A

Topsoil Type A shall be as specified in the Special Provisions. The Contractor shall submit 
a certification by the supplier that the contents of the Topsoil meet the requirements in 
the Special Provisions.

Page 8-28 

Roadside Restoration

8-02.3(4)B 

Topsoil Type B

Topsoil Type B shall be taken from within the project limits. Topsoil Type B shall be taken 
from areas shown in the Plans to the designated depth and stockpiled at locations that 
will not interfere with the construction of the project, and outside of sensitive areas, as 
allowed by the Engineer. The general limits of the material to be utilized for topsoil will 
be indicated in the Plans or in the Special Provisions. The Engineer will make the final 
determination of the areas where the most suitable material exists within these general 
limits. Material for Topsoil Type B shall not be taken from a depth greater than 1 foot 
from the existing ground unless otherwise designated by the Engineer. Prior to topsoil 
removal, the Contractor shall reduce the native vegetation to a height not exceeding 
1 foot. A minimum of two weeks prior to excavation of Topsoil Type B, the Contractor 
shall pre-treat the vegetation on the designated Topsoil Type B areas according to the 
Weed and Pest Control Plan. Areas beyond the slope stakes shall be disturbed as little 
as possible in the above operations and under no circumstances shall Topsoil Type B be 
stockpiled within 10 feet of any existing tree or vegetation area designated to be saved 
and protected. The Contractor shall protect topsoil stockpile from weed infestation.

The Contractor shall set aside sufficient material to satisfy the needs of the project.

Upon completion of topsoil placement, the Contractor shall dispose of remaining 
stockpiled Topsoil Type B not required for use on the project at no additional expense to 
the Contracting Agency in accordance with Section 2-03.3(7)C.

Should a shortage of Topsoil Type B occur, and the Contractor has wasted or otherwise 
disposed of topsoil material, the Contractor shall furnish Topsoil Type A or C at no 
additional expense to the Contracting Agency.

8-02.3(4)C 

Topsoil Type C

Topsoil Type C shall be naturally occurring topsoil obtained from a source provided by 
the Contractor outside of the Contracting Agency-owned Right of Way. Topsoil Type C 
shall meet the requirements of Sections 8-02.3(4) and 8-02.3(4)B. The Contractor shall 
not begin removal of Topsoil Type C from the proposed source until the material has been 
allowed for use by the Engineer.

8-02.3(5)  Roadside Seeding, Lawn and Planting Area Preparation

This Work includes preparing worked areas for the installation of all types of permanent 
erosion control planting. Work shall be conducted so the flow lines in drainage channels 
are maintained. Material displaced by the Contractor’s operations that interferes with 
drainage shall be removed from the channel and disposed of as allowed by the Engineer.

8-02.3(5)A 

Seeding Area Preparation

The Contractor shall prepare roadside seeding areas as follows:
1.  Remove all excess material, debris, stumps, and rocks greater than 3 inches in 

diameter from areas to be seeded. Dispose of removed materials offsite.

2.  Prepare roadside seeding area to a weed free and bare condition.

Roadside Restoration 

8-02

3.  Bring area to uniform grade and install topsoil, soil amendments, or compost 

as specified. Any slopes 3(H) to 1(V) or steeper shall not be tilled unless 
otherwise specified.

4.  Compact to provide a reasonably firm but friable seedbed; tractor walk to uniformly 

cover the surface with longitudinal depressions at least 2 inches deep formed 
perpendicular to the natural flow of water on the slope. Condition the soil with 
sufficient water so the longitudinal depressions remain in the soil surface until 
completion of the seeding.

5.  Seed and mulch within 2 days of preparation.

8-02.3(5)B 

Lawn Area Preparation

The Contractor shall prepare lawn areas as follows:
1.  Prepare lawn area to a weed free and bare condition in accordance with 

Section 8-02.3(3)B.

2.  Remove excess material, stumps, wood or rocks over 3 inches in diameter and 

remove from site.

3.  Bring area to uniform grade and install topsoil or soil amendments in accordance 

with Section 8-02.3(4) and 8-02.3(6).

4.  Till to an 8-inch depth, rake to a smooth even grade without low areas that trap 

water, and compact with a 50-pound roller. The finished grade of the soil shall be 
1 inch below the top of all curbs, junction and valve boxes, walks, driveways, and 
other Structures.

5.  Seed or sod the area within two days of preparation.

8-02.3(5)C 

Planting Area Preparation

The Contractor shall prepare planting areas as follows:
1.  Prepare planting area to a weed free and bare condition in accordance with 

Section 8-02.3(3)B.

2.  Decompact soil to a depth of 18 inches where construction activities have taken 

place or where native soils are compacted.

3.  Return soil to uniform grade even with surrounding areas, leaving no holes or 

mounds over 3 inches in depth or height.

4.  Remove excess material, stumps, wood or rocks over 3 inches in diameter and 

remove from site.

5.  Apply compost or other amendments as indicated in the plans and in accordance 

with Section 8-02.3(6).

6.  Cultivate amendments to a depth of 12 inches to provide a reasonably firm but 

friable planting area. Do not till any slopes 3(H) to 1(V) or steeper.

 

 

 

 

 

 

 