Military reference books and manuals (2009-2023, Volume 5) - page 35

 

  Index      Manuals     Military reference books and manuals (2009-2023, Volume 5)

 

Search            copyright infringement  

 

   

 

   

 

Content      ..     33      34      35      36     ..

 

 

 

Military reference books and manuals (2009-2023, Volume 5) - page 35

 

 

Procedure for Lifting Operations
Page 29 of 54
5) Personnel
HAZARD
POSSIBLE CAUSE
CONSEQUENCE
SOLUTION
Human factors
Inadequate training.
Incorrect choice of
Ensure adequate training.
(Knowledge
Lack of competence.
equipment.
Check competency level
based)
Incorrect attachment of
of personnel involved in
lifting accessories.
lifting operation.
Incorrect operation of
Increase supervision.
equipment.
Load swinging.
Load striking person.
Load striking plant.
Equipment damage.
Personnel injury.
Human factors
Slips.
Incorrect choice of
Pre-job safety meetings
(Error based).
Lapse.
equipment.
Realistic time frame to
Mistakes.
Incorrect attachment of
perform job.
lifting accessories.
Increase supervision.
Incorrect operation of
equipment.
Load swinging.
Load striking person.
Load striking plant.
Equipment damage.
Personnel injury.
6) Structural
HAZARD
POSSIBLE CAUSE
CONSEQUENCE
SOLUTION
Structural
Incorrect load applied to
Dropped object
Engineering calculations
collapse
structural component.
Load striking person
Proof load testing
Load striking plant
Equipment fitted or fitted
Lifting equipment not fitted and
Personnel injury
by trained/competent
assembled correctly
personnel
Thorough examination by
competent person prior to
use
Deck collapse
Inadequate surface loading
Mobile crane instability
Engineering calculations
Ground
Capacity for weight of load
Deck failure
Correct anchorage
subsidence
Environmental conditions
Dropped object
Spreader plates placed
Load striking person
under load or mobile
Load striking plant
crane outriggers
Personnel injury
Soil testing
7) Principles to a safe lift
Before the lift:
1. Ensure personnel are competent.
2. Assess the load & identify the risks.
3. Select the correct lifting equipment.
4. Carry out a pre-use check.
5. Ensure lifting equipment is fitted correctly.
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 30 of 54
6. Identify what could go wrong - take appropriate precautions.
7. Control the danger zone during lifting operation.
8. Prevent the load from swinging.
9. Avoid trapping hazards & lifting over personnel.
10. Ensure there is adequate space to land the load.
After Lift:
1. Check equipment after use.
2. Store in correct conditions.
All Lifting Operations must have appropriate Lifting Plan in place.
Important: If you find a problem stop the job and ask!
Work is never so urgent or important that we cannot take time to do it safety.
a) Lift categorization assessment
Routine lifts (part 1)
If the answer to all questions above is “Yes”, proceed with the Routine lift.
Questions
Yes
No
1
Has the lifting operation been performed before?
2
Is there a documented procedure?
3
Are you experienced with all the lifting equipment to be used?
Has the load been checked and made ready for lifting (e.g. sea
4
fastenings released, hold down bolts removed)?
5
Do you have the experience to lift a load of this weight?
6
Is the lifting area free from obstructions and other possible hazards?
Can the lifting operation be carried out without the use of Webbing
7
Slings? Or is a site-specific procedure for the use of webbing slings in
place?
If the answer to any of the above is “No”, go to Part 2 (Simple Lift)
Assessment Part 1 performed by ________________________________
Job title __________________________
Date ____________________________
For Standard Form go to: Baku office on Eubaks5/Operations/Safety & Environment/Checklist
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 31 of 54
Simple lifts (part 2)
Questions
Yes
No
1
Do you know the weight of the load and does the lifting operation
appear to be straightforward?
2
If the load is heavier than you normally handle, do you have the
relevant permission and/or permit?
3
Is there a crane or certified support steelwork (e.g. runway beam or
lifting eye) directly above the load?
4
Does the load have certified lifting points (lifting eyes/collar eyebolts,
etc.) fitted and if not, can slings be wrapped around easily (e.g. no
sharp edges, load not fragile, etc.)?
5
Is there ample headroom for the lifting appliance and slings?
6
Is the lift stable (e.g. centre of gravity below lifting points)?
7
Is the lift balanced (e.g. centre gravity in the middle) or fitted with
special slings to compensate?
8
Is the load free to be lifted (e.g. sea fastenings released, all hold-down
bolts removed, not jammed, etc.)?
9
Is the removal route clear of any obstructions?
10
Can the removal (lift, transfer and landing) be performed without cross
hauling?
11
Is there suitable lay down area and does the load come within the
allowable load bearing capacity of the ground/deck?
12
Are you experienced in using all the lifting equipment and gear
involved?
13
Can the lifting operation be carried out without the use of Webbing
Slings? Or is a site specific procedure for the use of webbing slings in
place?
If the answer to any of the above is “No” go to Part 3 (Complicated Lifts)
If the answer to all questions above is “Yes” proceed with the Simple lift.
Assessment Part 2 performed by _____________________________________________
Job Title ____________________________________________
Date _______________________________________________
NOTE: To the lifting operation nominated person:
If you can give solutions to the negatives in the above questionnaire to allow the lift to
proceed safely, write the instructions in the box. If you cannot supply a solution, seek
guidance from the Lifting Co-Coordinator.
For Standard Form go to: Baku office on Eubaks5/Operations/Safety & Environment/Checklist
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 32 of 54
Complicated Lifts (part 3)
The personnel about to perform the lifting operation shall complete the table below.
Tick against factors, which are applicable and specific to this lifting operation and indicate
whether or not you have the relevant experience to deal with them.
QUESTIONS
Yes
No
1
Is the lift stable? (i.e. centre of gravity below the lifting points and
not offset) .
2
Is the centre of the gravity for the load viewed as balanced and
acceptable?
3
Can the lift be performed without cross-hauling or being
restrained?
4
Does the load have specific lifting attachments?
5
Is the load robust? (not fragile)
6
Does the load have a limited surface area that will not cause
instability in the wind?
7
Does the load require only one crane? E.g: no tandem lifting
8
Can the lift be performed without rotation?
9
Uncertified structural components- can the lift be carried out
safely without the need for MHC engineering calculations
If the answer to any of the above is “No” go to Part 4 (Complex Lifts)
If the answer to all questions above is “Yes” proceed with the Complicated Lifts.
Assessment Part 3 performed by________________________________________
Job title __________________________
Date _____________________________
Approved/Endorsed by__________________________________
Job Title __________________________________
Date ____________________________________
NOTE : To the Lifting Coordinator:
If you have experience and can advise personnel involved in the lifting operation how to deal
with the complication, allow the task to proceed but only under your guidance. However if
you decide that the operation is out with the scope of your competence, indicate the reasons
applicable in the table in Part 4 complex lifts before passing it to the LTA
For Standard Form go to: Baku office on Eubaks5/Operations/Safety & Environment/Checklist
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 33 of 54
Complex Lifts (part 4)
Lifting operations or conditions, which would merit additional engineering input
Tick
REASONS FOR REQUESTING ENGINEERING INPUT
box
The lifting operation involves divers
1
The lifting operation is sub-sea
2
The load will be travelled over unprotected process plant and machinery
3
The load is classified as heavy (as specified by the Site Lifting Coordinator*) and is not being
4
transported in CCU
5
The lift involves a floating crane
6
The load is critical to business
The lift is in a confined space and/or an area with very restricted headroom.
7
Use of non-certified structural components, which require engineering calculations
8
Personnel Transfer / Man-riding activity where no approved site specific procedures exist
9
Lifting Plan/Method Statement and Risk Assessment Part 4 performed by
__________________________________
Job Title____________________________
Date _______________________________
Approved/Endorsed by (delete as applicable)
For Standard Form go to: Baku office on Eubaks5/Operations/Safety & Environment/Checklist
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 34 of 54
Appendix A
Glossary of Terms
Anomaly:
Is a condition which falls outside the present design criteria for the equipment.
Asset
Offshore complex, sub-sea facility, transportation line an onshore terminal and loading
facilities.
Azerbaijan Strategic Performance Unit:
All operations conducted by or on behalf of any Performance Unit or Project in Azerbaijan,
Georgia, or Turkey.
Lifting Equipment Engineering Association (LEEA):
An independent organisation recognised as the technical authority within the industry
responsible for establishing Codes of Practice and training standards.
Non-Statutory examination:
Examination carried out by a person deemed to be competent to determine whether or not a
lifting equipment item is safe to use.
Thorough Examination:
Statutory examination carried out by a competent person for the purpose of certifying that an
item of lifting equipment is free from patent defect and is satisfactory for further use as
specified by the manufacturer.
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 35 of 54
Appendix B
Inspection & Certification of Temporary or New Cranes
Temporary or new cranes to site must have relevant certification and be inspected before
use by a competent person. The certification and inspection should in include as a minimum
the items on this spread sheet.
Crane Certification Details
Make:
Tag / ID No:
Inspection Date :
Serial No:
SWL :
Test Cert No:
Previous Inspection Details
Date of Test:
Company:
Inspector :
Date of Last Visual:
Company:
Inspector :
Visual Cert No:
Company:
Inspector :
Crane Equipment
Main Hoist Rope
Serial No:
Cert No:
Date Fitted:
Boom Hoist Rope ( Luff ) if fitted
Serial No:
Cert No:
Date Fitted:
Whip Line ( If fitted )
Serial No:
Cert No:
Date Fitted:
Headache Ball ( If fitted )
Serial No:
Cert No:
Date Tested:
Crane Block
Serial No:
Cert No:
Date Tested:
Boom Pennant Lines ( If fitted )
Serial No:
Cert No:
Date Fitted:
Wedge Sockets ( if fitted )
Serial No:
Cert No:
Date Fitted:
Load Indicator and load chart
SLI Type:
Model:
Calibration Date:
Load Chart: Yes / No
Load Chart visible Yes / No
Boom Angle indicator: Yes / No
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 36 of 54
Appendix C
References
1. Use of Equipment Directive (95/63/EC)
2. Health and Safety at Work etc. Act 1974
3. Management of Health Safety at Work regulations 1999 (MHSAWR) SI 1999/3242
4. Provision and Use of Work Equipment Regulations 1992 S.I.2306 (PUWER)
5. The Supply of Machinery (Safety) Regulations 1992 S.I.3073
6. Manual Handling Operations Regulations 1992
7. HSE 3268 Lifting Operations & Lifting Equipment Technical Guidance (Relevant to
offshore lifting & handling appliances)
8. NSL: International Rigging and Lifting hand book 2001 Rev2.
9. UKCS-TI- 014.
10. BP North Sea Lifting Rules.
11. BS 7121 “Safe use of Cranes”
12. EN 12079 CCU‟s
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 37 of 54
Appendix D
Examples of Lifting Plans - Routine
AIOC Chirag 1
Lifting Operations Plan
Title
Tie in Dump Line
Area
M2a North
Lifting Plan No.
CH-P-LP 07
Generic / Specific:
Specific
Risk Assessment No.
Category Of Lift
Routine
Date
Revision
Rev-1
Diagrams, Drawings or Sketches
Max Weight of Load :
100kg Calculated
attached.
Actual / Assumed /
Calculated
Brief Description of Lifting Operation.
Remove existing spool and install tie in tee piece.
Certified Lifting Equipment and Accessories to be Used (Specify Type, SWL and Colour Code):
1 X 1te swl chain-blocks, 1 x 1te swl nylon slings, 21x 4.75te wll shackle, 1 x beam clamps. Colour code Green.
Cross Reference Relevant Procedures and Documents: ie DOG, engineering Calcs etc
N/A
All Lifting Operations Require The Following To Be Considered But This List Is Not Exhaustive
Every Lift Every Time
Specify, Yes / No
 Pre-use equipment checks by competent person.
 Working under suspended loads.
Yes
 All lifting equipment should have SWL identified.
 Route adjacent to or over live plant:
Yes
 Weight, size, shape, certification and centre of
 Conflicting tasks in area/adjacent worksites.
Yes
gravity.
 Trial lift required.
Yes
 Proximity hazards, obstructions, path of load,
 Risk of overturning, Cross hauling, tandem lift:
No
laydown area load bearing capacity
 Method of slinging/attaching/detaching the load. Yes
 Environmental conditions including weather / Sea.
 Availability of certified lifting points.
Yes
 Responsibilities clearly defined eg rigger / slinger /
 Lift is in Crane Radius.
N/A
banksman.
 Safe access / Scaffolding.
Yes
 Experience, competence and training of personnel.
 TRA level 2 ? - agree with AA
 All lifts must be checked for loose objects.
N/A
 TRA level 1
 Confirm No of Tag Lines Required:
N/A
 PTW to be raised
 Confirm Number of personnel required for task:
2
 Tool Box Talk - on site
 Check Certification - especially for non-standard
lifts / loads from supply vessel (ie not CCU or
Baskets)
Task Details (step by step)
Position the new spool above and to the North of the existing spool, secured to the 152mm x 300mm “I” beam using a beam
clamp and 1te chain-blocks, this task will be completed prior to shutdown.
Remove the dump line blind flange.
Bolt up the new spool.
Methods of communication to be used :
Radio- / verbal-Yes / hand signals-
Steps to be taken to eliminate danger to personnel: barriers / permit to work procedure/ toolbox talks / lifting plan / no
conflicting tasks in the area. (delete as appropriate) All above
Authorisation:
Level of Operational Control: Area Authority / Permit to Work
Engineering Support Required: No
Competent Person
Signature
Date
Reviewed by
Signature
Date
De-brief and Learning Points
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 38 of 54
Examples of Lifting Plans - Simple
AIOC Chirag 1
Lifting Operations Plan
Title
Shutdown BV/GV Change
Area
Well-bay
out WI Manifold.
Lifting Plan No.
CH-O-LP 008
Generic / Specific:
Specific
Risk Assessment No.
Category of Lift
Simple
Date
Revision
Rev-1
Diagrams, Drawings or Sketches
Max Weight of Load :
100kg Assumed
attached.
Actual / Assumed /
Calculated
Brief Description of Lifting Operation.
Change out Globe Valve No 36656 and Ball Valve 36655 using rigging equipment.
Certified Lifting Equipment and Accessories to be Used (Specify Type, SWL and Colour Code):
2 x 2te swl beam clamps, 3 x 4.75 wll shackles, 4 x 3mtr 1te swl wire slings, 1 x 1te swl chain-block, Colour code Green.
Cross Reference Relevant Procedures and Documents: ie DOG, engineering Calcs etc
N/A
All Lifting Operations Require The Following To Be Considered But This List Is Not Exhaustive
Every Lift Every Time
Specify, Yes / No
 Pre-use equipment checks by competent person.
 Working under suspended loads.
Yes
 All lifting equipment should have SWL identified.
 Route adjacent to or over live plant:
Yes
 Weight, size, shape, certification and centre of
 Conflicting tasks in area/adjacent worksites.
Yes
gravity.
 Trial lift required.
Yes
 Proximity hazards, obstructions, path of load,
 Risk of overturning, Cross hauling, tandem lift:
No
laydown area load bearing capacity
 Method of slinging/attaching/detaching the load. Yes
 Environmental conditions including weather / Sea.
 Availability of certified lifting points.
Yes
 Responsibilities clearly defined eg rigger / slinger /
 Lift is in Crane Radius.
No
banksman.
 Safe access / Scaffolding.
N/A
 Experience, competence and training of personnel.
 TRA level 2 ? - agree with AA
 All lifts must be checked for loose objects.
 TRA or Baskets)
Task Details (step by step)
Both valves will be installed using the same equipment:
Pre-works
Safely secure 2 x beam clamps to the overhead 152mm x 300mm “I” beams situated directly above and either side of the valve
location, shackle a 3mtr sling to each beam clamp, shackle both lazy eyes together.
Secure a 1te chain-block to the hanging shackle.
Sling both new valves ready for installation.
Change Out.
Methods of communication to be used :
Radio- / verbal-Yes / hand signals-
Steps to be taken to eliminate danger to personnel: barriers / permit to work procedure/ toolbox talks / lifting plan / no
conflicting tasks in the area.
(delete as appropriate) All above
Authorisation:
Level of Operational Control: Area Authority / Permit to Work
Engineering Support Required: No
Competent Person
Signature
Date
Reviewed by
Signature
Date
De-brief and Learning Points
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 39 of 54
Examples of Lifting Plans - Complicated
AIOC Chirag 1
Lifting Operations Plan
Title
Remove Runway Beam
Area
M2A CD
Lifting Plan No.
CH-P-LP-002
Generic / Specific:
Specific
Risk Assessment No.
Category Of Lift
Complicated
Date
Revision Rev 1
Rev 1
Diagra
ings or Sketches attached.
Max Weight of Load :
1.4te Actual.
Actual / Assumed / Calculated
Brief D
n of Lifting Operation / Sketch:
Remove the maintenance runway beam.
Certified Lifting Equipment and Accessories to be Used (Specify Type, SWL and Colour Code):
4 x 2te swl chain-blocks, 8 x 3 et swl wire slings, 6 x 4.75 te swl bow shackles,1 x 3te pull-lift. Colour code green.
Cross Reference Relevant Procedures and Documents: ie DOG, engineering Calcs etc
Ref; EQ KA00-EQ104.
All Lifting Operations Require The Following To Be Considered But This List Is Not Exhaustive
Every Lift Every Time
Specify, Yes / No
Pre-use equipment checks by competent person.
Working under suspended loads.
Yes/No
All lifting equipment should have SWL identified.
Route adjacent to or over live plant:
Yes/No
Weight, size, shape, certification and centre of gravity.
Conflicting tasks in area/adjacent worksites.
Yes/No
Proximity hazards, obstructions, path of load, laydown area load
Trial lift required.
Yes/No
bearing capacity
Risk of overturning, Cross hauling, tandem lift: Yes/No
Environmental conditions including weather / Sea.
Method of slinging/attaching/detaching the load. Yes/No
Responsibilities clearly defined eg rigger / slinger / banksman.
Availability of certified lifting points.
Yes/No
Experience, competence and training of personnel.
Lift is in Crane Radius.
Yes/No
All lifts must be checked for loose objects.
Safe access / Scaffolding.
Yes/No
TRA level 1
TRA level 2 ? - agree with AA
Yes/No
PTW to be raised
Confirm No of Tag Lines Required:
1
Confirm Number of personnel required for task:
4
Task Details (step by step)
Safety.
All rigging equipment being used for this task will have a minimum SWL of 2Te.
A minimum of 2 pieces of rigging equipment will support the beam at all times.
Barriers must be erected to ensure nobody can walk under this load.
A tannoy announcement will be made to stay clear of the area.
Isolate the line of sight gas detectors. Ash 016.
Care must be taken whilst rigging close to Ash 016, hold back rigging must be in place to ensure
the beam does not touch the monitor.
Pre-rigging
Safely secure a 3 Te Swl sling 2.5mtrs from the North end of the runway beam.
Safely secure 2 x 3 Te Swl sling 2.5mtrs from the South end of the runway beam.
Safely secure 4 x 3Te chain blocks to the sub main deck 300mm x 152mm “I” beams.
Safely secure 4 x 2te minimum swl wire slings directly under the chain-block locations , secure the chain blocks to the slings, take
weight.
Methods of communication to be used :
Radio
/
verbal Yes
/
hand signals
Steps to be taken to eliminate danger to personnel: barriers / permit to work procedure / tannoy / toolbox talks / lifting plan / no conflicting tasks
in the area.
(delete as appropriate)
Authorisation:
Level of Operational Control: Area Authority / Permit to Work
Engineering Support Required: No
Competent Person
Signature
Date
Reviewed by
Signature
Date
De-brief and Learning Points
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 40 of 54
Examples of Lifting Plans - Complex
Azfen fabrication yard quayside (Baku)
Lifting Operations Plan
Title
Lifting plan for the purpose of
Area
lifting drilling template and
associated floatation cradle (for
testing and subsequently
transportation).
Lifting Plan No.
CH-P-LP-002
Generic / Specific:
Specific
Risk Assessment No.
Category Of Lift
Complex
Date
Revision Rev 1
Rev 1
Diagrams, Drawings or Sketches attached.
Max Weight of Load :
Cradle- (Design) 50500kg
Actual / Assumed / Calculat. Template- (Design) 41600kg
Task D
ep by step)
Method:
Lift tem
o the cradle using Titan crane barge (interface test as detailed in FAT E687)
 Insuring adequately located access ladders are provided for access to the cradle.
 Attach 4 off 25 tonne safety bow tonne shackles to the lifting points/pad eyes (identified on drawing 3847/01).
 Whilst at ground level, attach 4 off single leg “jumper” slings (Single leg wire rope sling “ 3,5Mx38mm dia, 6x36 IWRC RHOL Galv C/W
soft eye each end, 18.6 tonne SWL template lift sling via 4 off 25 tonne shackles.
 Position the Titan crane hook at an appropriate height and position.
 Crane hook to swivel sling (2 leg wire rope Assy 3 metre x 64 mm dia, 6x36IWRC galv RHOL fitted to HA 70 ML masterlink C/W hard
eyes all round.
 Attach a 55 tonne safety bow shackle to the aforementioned sling master-link.
 Fit 55 tonne swivel to the aforementioned 55 tonne safety bow shackle keeping any manual handling (lifting/bending) to an absolute
minimum.
 Attach the other 55 tonne safety bow shackle to the bottom of the 60 tonne swivel.
 Attach the (2 off-2 leg wire rope sling assy 4.1Mx38mm dia 6Xiwrc GALV RHOL fitted to HA 45 ML masterlink C/W hard eyes) and 4 off
single leg template lifting sling assembly to the 55 tonne shackle via the master link.
 Attach tag lines to the end of the lift assembly.
 Under the supervision of the lift supervisor, slowly lift and position each individual sling assembly leg such as it can be assembled to the
template via the 4 off previously attached 25 tonne shackles on the template.
 Position personnel in appropriate safe positions.
 Then commence when lift supervisor determines it is safe to do so, slowly lift the template and carry out the interface test As specified in
E687.
 When test is determined to be successful, slowly lift the template from the cradle and place in an appropriate location in preparation for
the other aspects of testing as specified in E687.
 Disconnect the lower 55 tonne safety bow shackle, remove template lift sling assembly lay-down in an appropriate position on the
template. Taking care to ensure that all equipment is prevented from „swinging‟ and manual handling is kept to a minimum.
Methods of communication to be used :
Radio
/
verbal Yes
/
hand signals
Steps to be taken to eliminate danger to personnel: barriers / permit to work procedure / tannoy / toolbox talks / lifting plan / no conflicting tasks
in the area.
(delete as appropriate)
Authorisation:
Level of Operational Control: Area Authority / Permit to Work
Engineering Support Required: No
Competent Person
Signature
Date
Reviewed by
Signature
Date
De-brief and Learning Points
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 41 of 54
Appendix E
Check List for Pre-use
Mobile Crane Inspection Form
At the beginning of each shift or working day that the crane is in use, the following
routine as appropriate for the type of crane shall be carried out as a minimum.
NOTE: this list shall be added to (by Site Lifting Coordinator) for specialized
equipment, e.g. vacuum lifting equipment.
To be completed by the Site Competent Person (Deck
Comments
Forman/Site Lifting and Rigging Supervisor)
1
Owner
2
Crane Model
3
Date Of Last Inspection
4
Date Of Last Test
5
Current Cert No.
6
Makers Serial No.
7
Visual Examination of Jib Sections
8
Function test of Limit/Safety Devices
9
Outriggers, functioning properly and can take the full weight
of the Crane/load
10
Daily checks specified in the manufacturer‟s handbook.
11
A check that all ropes are correctly positioned in their
sheaves and that drums are not displaced.
12
A visual check that electrical equipment is not exposed to
contamination by oil, grease, water or dirt.
13
A visual check by inspecting relevant levels and/or
components, that no loss of fluids (e.g. lubricant oil,
coolant) is apparent.
14
A check for correct operation of all limit switches or cut-
outs and the dead man‟s handle or lever, applying caution
during checking in case of malfunction.
15
A check that the automatic safe load indicator is correctly
set and that the manufacturer‟s daily test is carried out.
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 42 of 54
16
A check that the correct air pressure is maintained in any
pneumatic control system (e.g. brakes).
17
A check that lights, windscreen wiper(s) and washers
operate efficiently.
18
A visual check for security of wheels and the condition of
tyres, on wheel-mounted cranes.
A check for correct function of all crane controls without
19
load.
20
A check for correct operation of audible warning devices.
21
A check that the crane is in tidy condition and free from
tins of oil, rags, tools, or materials other that sufficient
access and egress are provided, and that appropriate fire
fighting equipment is available.
22
A check that there are no obstructions in the path of travel
of the crane.
23
Drivers experience to be reviewed.
24
Crane maintenance / certification to be reviewed.
25
Written pre-use check to be carried out prior to crane use.
Extracted from standard BS 7121 - this list does not replace the standard Crane
Driver Check List
Crane accepted/rejected (underline).
Name:
Position:
Date:
For Standard Form go to: Baku office on Eubaks5/Operations/Safety & Environment/Checklist
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 43 of 54
Appendix F
BP North Sea Lifting Rules
The following fundamental rules will be applied to all lifting operations with zero tolerance:
1.
All personnel must keep out of any area where they might be injured by a falling or shifting
load. Do not stand below loads. Never stand between loads and walls/bulkheads etc.
Always ensure an escape route is available.
2.
Immediately a lift deviates from plan or any complication arises the lifting operation must be
stopped and made safe. All personnel should remain in positions clear of the lift until
reassessment/re-planning of the lift is carried out.
3.
Lifting operations will be undertaken by a minimum of three competent people: crane
operator, banksman/flagman and load handler.
4.
The banksman/flagman controls the initial lifting of the load, lay down of the load and lifts
that are out of the line of vision of the crane operator. The crane operator is responsible
while the load is in the air. The banksman must:
a) Ensure that he/she is easily identifiable from other personnel by wearing a hi-vis jacket
or waistcoat, which is clearly marked to indicate that he/she is the authorized crane
banksman.
b)
Not touch the load. He/she must stand back from the load being handled in a
prominent position where he/she has a good view of the lifting activities.
c) Remain in communication with the load handler and crane operator at all times.
d) Keep the load handler in sight during the lifting operation.
5.
The load handler must:
a) Stand clear while a load is lifted clear of the deck and landed, while slack is taken up
with or without a load on the hook and must confirm to the banksman that he is clear.
b) Not touch a load being landed until it is below his/her waist height and never attempt to
manually stop a swinging load.
c) Be easily identifiable, and distinct from the banksman.
6.
For BP operated installations and onshore sites there will be no stacking of containers,
baskets, tanks and half heights.
For designated installations where this is not practicable, stacking requires prior permission of
the relevant Business Unit Leader and:
a) Equipment is specifically designed for that purpose, and clearly marked as suitable for
stacking.
b) Stacking is confined to pre-designated areas.
c) Risk assessment of stacking operations is performed and shows that the risk involved
alternative practicable approaches.
d) Stacked containers must have an additional pennant so that the crane hook can be
attached/detached while the load handler is standing at deck level.
e) Stacking and de-stacking is controlled by permit.
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 44 of 54
The attached notes are an integral part of these rules.
Notes:
These rules were developed for deck lifts or deck/boat lifts using pedestal cranes on offshore
installations. They will also be applicable to similar lifts using mobile cranes, crawler cranes etc
on BP operated onshore sites.
For lifts with other devices (e.g. workshop cranes, winches, hiabs) rules 1 and 2 will always be
applicable. Consider the application of rules 3-6 during job planning and risk assessment.
The rules do not specifically apply to the holding in position of items of equipment during well
servicing/wire line activities. These specialist activities should be covered by job specific
procedures, permit and detailed risk assessment.
1. Rule1: This includes not getting under slung loads, not getting into areas where they could
be trapped between the load and something else. Third parties not involved in the lifting
operation also have a responsibility to keep out of areas where lifting is being conducted.
This rule is now added to the GBC Golden Rules website and will be incorporated into the
Golden Rule booklets at the next revision.
2. Load Handler may also be designated as Slinger, Deck Operator or Hookman.
3. Rule 5b) In some essential lay-down areas it is necessary to manoeuvre containers into
limited landing areas adjacent to handrails, where the handrails are slightly in excess of
waist height. Where it is considered essential to continue using these lay-down areas, and
the lowest practicable risk is provided by touching the load above waist height to orient it,
installations must identify and document steps to be taken to mitigate the risk to the load
handler.
4. i) The intention is to eliminate stacking of containers and other loads as identified in rule 6.
ii) For some installations (particularly some MODU‟s) this may not be practicable due to
limitations on deck space. Exception to the no stacking rule is intended to cater for these
installations and not to provide a general opportunity for all installations to stack as soon as
deck space becomes congested.
iii) BU‟s must be designated on which installations this is not practicable and where stacking
may be undertaken and document why the decision to allow stacking was made.
iv) For those installations where no stacking is not currently practicable, a review should be
undertaken to consider what would be required to be able to operate on a no stacking
basis.
v) However, after appropriate review and documentation, particular equipment (e.g. sphere
racks in SNS) may be authorized as suitable for stacking even though stacking of other
containers is banned on that installation.
vi) Assets should reassess the design of equipment currently designated as suitable for
stacking, to confirm that it is fit for purpose both loaded and empty.
vii) Installations who intend to designate equipment or areas suitable for stacking should
consider using the MOC process to review and document the justification.
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 45 of 54
5. These rules are not exhaustive. They reinforce behavioral aspects of lifting. Procedural and
equipment issues such as risk assessment, lifting equipment specification, lifting plans,
regulation (e.g. LOLER in UK) are also essential to safe lifting. Crane drivers, load handlers
and check operators should comply with contractors‟ procedures, comply with regulatory
requirements, use risk assessments and toolbox talks where appropriate and must be
prepared to stop the job at any stage if the safety of the operation may be compromised.
6. The Deck Operations and Lifting Forum is currently working with crane and deck operations
contractors to identify best practice and establish common procedures for all contractors.
New UK standard operating procedures will be developed from this review. This forum will
be explained to include Norway and Netherlands.
7. These rules are immediately applicable. Although issued under the overall authority of the
Regional Leadership team, for document control purposes they will be maintained as
separate controlled documents within the Management System in UK, Norway and
Netherlands.
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 46 of 54
Appendix G
BP AzSPU reference document for the Selection, Application and Control of Man
Made Fiber Slings for Lifting Operations
Purpose
The purpose of this reference document is to describe the current AzSPU Policy and
Procedures for the safe selection, application and control of man-made fibre slings for lifting
operations, their subsequent inspection requirements and discard process following
completion of the lifting operation.
The use of any type of man made fiber slings in lifting operations will automatically
categorize the lift to at least “Complicated.”
Certification for this type of sling is valid for 6 months only after which time it will be removed
from service and destroyed. NO RECERTIFICATION.
Introduction
All lifting operations on AzSPU sites, including those undertaken by third party contractors,
shall be implemented under the principles of Lifting Operations & Lifting Equipment
Regulations (LOLER 98/SI-2037).
Regulation 8 of LOLER stipulates that all lifting operations using Lifting Appliances and
Accessories should be carried out in a safe manner, under adequate supervision and
following a lifting operation risk assessment and predetermined plan. The degree of planning
is dependent on the lifting equipment to be used, the category of the lifting operation and the
degree of risk involved.
Lifting Sling Selection
When planning the lifting operation consideration should be given to the working load limit,
the mode of use, the nature of the load and the environment in which it is to be used.
Wherever possible, it is recommended that wire rope slings be used for lifting operations.
Never use a man made fiber sling of any type if, during the lifting operation, it can be
subjected to shock or snatch loading and never use this type of sling on boat lifting
operations.
Man made fibre slings are available in five basic formats, the two most commonly used in
lifting operations are the Flat Soft Becketed Eye type webbing sling and the Endless Round
Sling.
The Endless Round sling is the most adaptable for general-purpose use as they are more
flexible, and when choked, provide a more efficient „grip‟ on the load. Flat Soft Becket Eye
type webbing slings are more suitable for use in a “basket type” lifting mode rather than in
„choke‟ mode.
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 47 of 54
Examination and Discard Criteria
Slings constructed in man-made fibers are easily damaged and can be sensitive to chemical
attack.
Strength is lost if there are any cuts, tears, abrasion, fraying and burst stitching, therefore
this sling type requires close examination by a competent person for any signs of damage
prior to every lifting operation.
Endless Round Slings are manufactured with an outer protective sheath, which prevents the
ingress of chemicals and dirt, which can lead to the deterioration of the sling fibers in
service. The protective sheath also makes the examination for defects more difficult and
onerous than that of the Flat Webbing Sling.
Man-Made Fibre Endless Round Slings:
Endless Round slings shall only be used for general purpose lifting duties on the site
providing the sling has a current certificate of conformity and there is an approved lifting plan
and risk assessment for the operation. Site Lifting Coordinator shall inspect slings for
suspected or evident damage prior to use. The sling(s) shall be physically removed and
destroyed if any damage is suspected or evident. Certification for this type of sling is valid for
6 months after which time it will be removed from service and destroyed.
Man-Made Fibre Flat Webbing Slings:
Flat Webbing Slings shall only be used for special lifts where the component to be lifted can
be damaged by the use of conventional wire rope slings. Flat webbing slings shall be used
for lifting duties on the site providing the sling has a current certificate of conformity and
there is an approved lifting plan and risk assessment for the operation. Site Lifting
Coordinator shall inspect slings for suspected or evident damage prior to use. The sling(s)
shall be physically removed and destroyed if any damage is suspected or evident.
Certification for this type of sling is valid for 6 months after which time it will be removed from
service and destroyed.
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 48 of 54
Appendix H
Wind Force Scale
Wind Force in points
Wind Force, mps
Wind Force, knots
0
Calm
0-0.5 (0)
0-0.97 (0)
1
Light air
0.6-1.7 (1)
1.16-3.3 (1.9)
2
Light breeze
1.8-2.3 (2.1)
3.5-4.5 (4.1)
3
Gentle breeze
3.4-5.2 (4.5)
6.6-10.1 (8.7)
4
Moderate breeze
5.3-7.4 (6.5)
10.2-14.4 (12.6)
5
Fresh wind
7.5-9.8 (8.5)
14.5-19.1 (16.5)
6
Strong wind
9.9-12.4 (11)
19.2-24.1 (21.4)
7
High wind
12.5-15.2 (14)
24.2-29.5 (27.2)
8
Very hard wind
15.3-18.2 (17)
29.7-35.4 (33.04)
9
Storm
18.3-21.5 (20)
35.5-41.8 (38.8)
10
Hard storm
21.6-25.1 (23)
41.9-48.8 (44.7)
11
Heavy storm
25.2-29.0 (27)
48.9-56.4 (52.5)
12
Tornado
More than 29.0
More than 56.4
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 48 of 54
Appendix I: Procedure Summary
Banksman
Certification, Examination & Testing
LIFTING OPERATIONS
No lifting operation will take place without an appointed banksman
All lifting equipment shall be inspected and certified. A colour
who will be easily identified by wearing a high visibility vest. The
coding system shall be in place to prove that loose equipment has
Lifting Appliances
banksman must be suitably trained and have adequate experience
been inspected at least once every 6 months. Written records of
Any mechanical devices capable of raising or lowering a load e.g.
for the role.
these inspections are to be maintained.
cranes, fork lift trucks, suspended cradles, powered and manual
hoists, lever and rope hoists, beam trolleys, winches and chain
His primary role is to guide the crane operator, and must never be
The following colour code cycle will be used on portable lifting
blocks
physically involved in the lift.
equipment of categories 1 and 2 to indicate that they have been
examined and fit for use for a six-month period:
Lifting Accessories
Crane Driver / Operator
Any device which is used or designed to be used directly or
Cranes shall only be operated by properly trained and qualified
Green
(April 2007 to October 2007)
indirectly to connect a load to a lifting appliance and which does
personnel who have been authorized by site management. They
Blue
(October 2007 to April 2008)
not form part of the load, e.g. wire, fibre and chain slings, hooks
must not perform other work and must never leave the controls until
Yellow
(April 2008 to October 2008)
and fittings, swivels, shackles, eye bolts and plate clamps.
a load is safely landed.
Then back to Green
BP Golden Rule
Riggers & Slingers
Lifts utilizing cranes, hoists, or other mechanical lifting devices will
All personnel who use rigging equipment must have completed a
NOTE: Colour Code for the 6 month period shall be clearly
not commence unless:
basic rigging training course, approved by BP and appropriate to the
identified and posted in Permit offices and security entrances to
site / installation operational needs.
the site or facility.
¾ An assessment of the lift has been completed and the lift
method and the equipment has been determined by a
The Load
All transit slings will be colour coded as shown below. This will
competent person(s)
The weight of all loads should be known and particular care must be
ensure that all lifting equipment is easily identified and kept
¾ Operators of powered lifting devices are trained and certified
taken when calculating the weight of any plant or equipment prior to
separate from the transit slings. The control and re-certification of
for that equipment
lifting, especially when it may contain a liquid (for example, coiled
unused transit slings shall be the responsibility of the site
¾ Rigging of the load is carried out by a competent person(s)
tubing reels, heat exchangers, etc). The crane operator must be
manager / Site Controller / Offshore Installation Manager.
¾ Lifting devices and equipment have been certified for use
advised of the weight of each load to be lifted.
within the last 12 months (at a minimum)
Brown
(April to October)
¾ Load does not exceed dynamic and/or static capacities of the
Lift Planning & Risk Assessment
Purple
(October to April)
lifting equipment
All lifts must follow a documented procedure and the risks must be
¾ Any safety devices installed on lifting equipment are
assessed.
Cranes are to be formerly inspected and certified every
12
operational
months by a competent 3rd party agreed by BP and contractor.
¾ All lifting devices and equipment have been visually
A complex lift study is required if:
examined before each lift by a competent person(s)
Where possible all lifting equipment should be hard stamped with
¾ The lift involves more than one crane
the safe working load (SWL). Where it is not possible to hard
Personnel in Charge of Lifting Operations
¾ The load has a very high $ value
stamp the SWL directly onto the equipment, the following
Personnel in charge of lifting operations are responsible for
¾ The load is above 90% of the cranes load chart capacity
alternatives are acceptable:
ensuring:
¾ The load is in excess of 20,000 kilograms
¾ The load is being lifted in and out of a confined space
¾ Hard stamp the safe working load on ferrules (for example
¾ The immediate safety of all personnel involved in the lifting
on wire rope slings)
activity
All other lifts which do not fall under the above criteria shall be
¾ Hard stamp the safe working load on a metal plate securely
¾ That all equipment used is suitable for the task and is within
covered by the Project Crane Set-up and Basic Lifting Plan which is
attached to equipment (for example, on chain hoists)
test date
contained in the operator‟s cabin of each crane.
¾ That the lifting operation has been risk assessed and
planned
¾ That the activity is executed in accordance with the plan
¾ That lifting operations are halted if an unsafe situation occurs
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Lifting Operations
Page 49 of 54
¾ The operating limitations shall be clearly displayed in the cab
of the crane.
Lift Categorization Assessments are as follows:
LIFTING OPERATIONS (cont)
Outriggers
Routine Lifts (part 1)
Statistics show that at least 50% of crane incidents occur because
CHECKLIST
YES
NO
Safe Working Load Indicators
the mobile crane or outriggers are not set-up properly. Specific
Has the lifting operation been performed
All cranes must be fitted with a Safe Working Load Indicator. It is
hazards that can cause or contribute to failure or collapse include:
before?
the responsibility of the crane driver/operator to stop lifting a load
Is there a documented procedure?
that causes the Safe Load Indicators to alarm. In particular, crane
¾ Failure to extend the outriggers fully
Are you experienced with all the lifting
drivers/operators must not use the load radius alarms as an
¾ Not extending all outriggers
equipment to be used?
indication of working within safe limits.
¾ Failure to get completely “off-rubber”
Has the load been checked and made ready
¾ Not accounting for poor ground conditions
for lifting
(e.g. sea fastenings released, hold
Safe Working Load Indicators, or any other alarms fitted to lifting
¾ Failure to level the crane
down bolts removed)?
appliances shall not be disconnected or made unserviceable at
any time whilst the equipment is in service. Wherever such
Do you have the experience to lift a load of
Poor conditions reduce the amount of load a crane can safely place
warning devices have been disconnected or made unserviceable,
this weight?
on the outrigger pad. Because of this, all outriggers must have
the lifting equipment shall be taken out of service immediately and
Is the lifting area free from obstructions and
additional
“blocking‟ under them. Blocking will help disperse the
remain so until the devices are reinstated.
other possible hazards?
weight of the crane and its load over more ground area than does
Can the lifting operation be carried out without
the fixed pads.
Lift Area
the use of webbing slings? Or is a site-specific
All lift areas must be barricaded off to keep unauthorized
procedure for the use of webbing slings in
Leveling - If the outrigger pad is set down on unleveled “blocking”,
personnel out. Loads should not be moved over a work area. If
place?
the outrigger pad may slide off when under load, causing the crane
this cannot be done, work should be temporarily halted and the
If the answer to any of the above is “NO”,
go to Part 2
to tip.
area cleared while the lift is taking place. The work area must be
(Simple Lift)
organized so that all trip or slip hazards are removed from the
Excavations - Cranes must be set-up so that no outrigger is closer
travel path before the load is suspended.
Simple Lifts (part 2)
than 1.5 times the depth of the excavation.
CHECKLIST
YES
NO
Wind Speed
Do you know the weight of the load and does
Man-riding Operations
It is the responsibility of the site / installation Lifting Coordinator to
the lifting operation appear to be
Due to specific verification requirements, the suitability of cranes for
ensure that accurate and realistic wind speed readings using an
straightforward?
man-riding shall be assessed by Site Manager‟s / Site Controller‟s /
anemometer set.
If the load is heavier than you normally handle,
Offshore Installation Manager‟s and Site Lifting Coordinator‟s for
do you have the relevant permission and/or
each and every operation.
Lifting operations shall be suspended when average wind speeds
permit?
reach:
Is there a crane or certified support steelwork
Tag Lines
Tag lines shall be used on all lifting operations to control the load
(e.g. runway beam or lifting eye) directly above
¾ Onshore - 25 knots (12.86 m/sec)
the load?
from a safe distance. A tag line is used to enable the load to be
¾ Offshore - 35-40 knots (18 - 20.5 m/sec)
Does the load have certified lifting points (lifting
moved and positioned by allowing the rigger to stay out of harms
way.
eyes/collar eyebolts, etc.) fitted and if not, can
Cranes shall not be operated past this point unless all of the
slings be wrapped around easily (e.g. no sharp
following criteria are met:
edges, load not fragile, etc.)?
The minimum diameter of tag line shall be 16mm. Tag lines should
never be looped around hands, arms or other parts of the body.
Is there ample headroom for the lifting
¾ The lifting equipment (crane) is rated by the manufacturer to
General purpose gloves are to be worn when using tag lines.
appliance and slings?
operate in higher winds
Is the lift stable (e.g. centre of gravity below
¾ All risks have been identified and mitigation measures are in
To prevent slips, trips and falls when guiding a load with a tag line,
lifting points)?
place and documented
the travel path must be clear and safe before the load is suspended.
Is the lift balanced (e.g. centre gravity in the
¾ The responsible Area Authority has reviewed all
middle) or fitted with special slings to
documentation and has signed off
Lift Categories
compensate?
¾ That the operation is immediately stopped if conditions
To assist with the risk Assessment process, lifting operations have
Is the load free to be lifted (e.g. sea fastenings
deteriorate beyond those identified in the risk assessment
been divided into four categories, which are Routine, Simple,
released, all hold-down bolts removed, not
¾ The work is restricted to low level lifts
Complicated and Complex.
jammed, etc.)?
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 50 of 54
Complex Lifts (part 4)
Outriggers are set on “blocks”
LIFTING OPERATIONS (cont)
Crane is level
REASONS FOR REQUESTING
YES
NO
Tag line is connected to load and used to
ENGINEERING INPUT
control load
The lifting operation involves divers
Is the removal route clear of any obstructions?
The lifting operation is sub-sea
Checklist for Suitability of Cranes for Man-riding Operations
Can the removal (lift, transfer and landing) be
The load will be travelled over unprotected
performed without cross hauling?
process plant and machinery
QUESTIONS
YES
NO
Is there suitable lay down area and does the
The load is classified as heavy (as specified by
Has it been established that no other viable
load come within the allowable load bearing
Site Lifting Coordinator*) and is not being
option of carrying out the work is available?
capacity of the ground/deck?
transported in CCU
Are all the necessary certificates for the crane
Are you experienced in using all the lifting
The lift involves a floating crane
wire ropes, slings and other associated
equipment and gear involved?
The load is critical to business
equipment current?
Can the lifting operation be carried out without
The lift is in a confined space and/or an area with
Has the crane and associated equipment been
the use of Webbing Slings? Or is a site specific
very restricted headroom.
thoroughly inspected by a suitably
procedure for the use of webbing slings in
Use of non-certified structural components, which
qualified/competent person within the last 6
place?
require engineering calculations
months?
If the answer to any of the above is “NO”, go to
Part 3
Personnel Transfer / Man-riding activity where no
Is the crane in good condition, regularly
(Complicated Lift)
approved site specific procedures exist
inspected and maintained and are records kept
to substantiate this?
Checklist Prior to Lifting Operation Taking Place
Are all the safety features and systems working
Complicated Lifts (part 3)
properly? e.g. Rated Capacity Indicators
QUESTIONS
YES
NO
(RCIs), overhoist limiters, etc.
CHECKLIST
YES
NO
Lift has been planned and risk assessed and
In the event of a complete power failure, will the
Is the lift stable? (i.e. centre of gravity below the
Crane Set-up booklet has been completed
crane maintain the load in a safe condition (e.g.
lifting points and not offset) .
The weight of the load is known by the crane
do the brakes fail to the applied position)?
Is the centre of the gravity for the load viewed
operator and the person in charge
Are the brakes applied progressively (e.g. to
as balanced and acceptable?
Wind speed is known and within acceptable
avoid shock or snatch loading)?
Can the lift be performed without cross-hauling
limits
In the event of a complete power failure can the
or being restrained?
Crane operator certification is current
personnel be recovered safely? (Is there a
Does the load have specific lifting attachments?
Banksman is easily identifiable “High Viz” jacket
recovery plan in place).
Is the load robust? (not fragile)
Banksman is not physically involved in the lift,
In the event of a primary brake or transmission
Does the load have a limited surface area that
guiding crane operator only
system failure, will the load be prevented from
will not cause instability in the wind?
Adequate means of communication between the
free-falling (e.g. is there a secondary braking
Does the load require only one crane? e.g: no
crane operator and banksman
system or does the transmission system have
tandem lifting
Equipment has been inspected and is painted
hydraulic retardation to prevent this)?
Can the lift be performed without rotation?
the correct colour
Is the crane fitted with an emergency stop,
Uncertified structural components- can the lift
Lift area is barricaded off
which is located for immediate operation by the
be carried out safely without the need for MHC
crane operator?
Lift will not endanger other operations
engineering calculations
Lift area is well organized and slip and trip
Is the crane so designed that inadvertent
If the answer to any of the above is “NO”, go to
Part 4
freefall is prevented when the drive train is in
hazards have been removed
(Complex Lift)
motion or the hook is loaded?
Outriggers are in “full out” position
Outriggers are correct distance from excavations
If the answer to any of the above is “NO”, “DO NOT” carry
out man-riding operations
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 51 of 54
APPENDIX J - Feedback & Improvement Suggestions
Procedure Feedback & Improvement Suggestions
Project Name: ______________________________
Date: ______________________________________
Name:_____________________________________
Badge Number: _____________________________
Procedure Reference: ________________________
Procedure Title: _____________________________
Improvement Suggestions (Write below your improvement suggestions)
Forward your Improvement Suggestion to the HSSE Manager
at the Central HSSE Office, Hyatt Tower 2, 6th Floor
Signature: _____________
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 52 of 54
Revision/Review Log
Revision Date
Authority
Custodian
Revision Details
06 July 2004
Central Engineering
Lifting Technical
Initial issue as controlled document
Senior Authority
Authority
18 June 2007
Steve Grittner
John Thompson
Table of Contents:
(Central Engineering
Eldar Fiahardinov
Section 2 is now Definitions & Abbreviations. All
Senior Authority)
Barry Riddell
other sections moved forward, but remain the
(Lifting Technical
same headings.
Authorities)
General:
Throughout the procedure the document control
numbering for referred procedures has been
changed.
Section 1. Introduction:
1.1 is now Document Purpose. 1.2 is now
Document Scope, with first 4 paragraphs added.
The following are new sub-sections: 1.3 is now
Stopping Unsafe Work. 1.4 is now Deviations. 1.5
Document Review. 1.6 is now SSOW Specific
Cross References. 1.7 is now BP Golden Rules of
Safety 1.8 is now Language Facilitation. 1.9
Procedure Summary.
Section 2. Definitions:
This is a new section
Section 3. Lifting equipment:
First paragraph includes Safe Working Load. 3.1
CATEGORY 1. Now combined with CATEGORY
2. 3.4 CATEGORY 4. 2 additional bullet points.
3.5 CATEGORY 5. This section completely re-
worded. 3.6 CATEGORY 6. Additional paragraph
added. 3.7 Man-riding. This sub-section has been
deleted.
Section 4. Examination Philosophy:
4.1 Examination of Portable Lifting Equipment.
Additional paragraph entered. 4.2 Examination of
Fixed Lifting Equipment. Last paragraph removed.
4.4 Examination of CCU‟s. This sub-section
completely re-worded. 4.5 Examination of Mobile
lifting Equipment. This sub-section completely re-
worded.
Section 5. Reports / Records:
Paragraphs re-worded with bullet point added.
Section 6. Control Processes:
6.1 Rigging Loft (storage area). New sub-section.
6.2 Colour Coding. 3 paragraphs added. 6.3
Control of Portable Lifting Equipment.
Examination and colour code periods updated.
Also “NOTE” added. 6.8 Control of Third Party
Contractor Lifting Equipment. Additional
paragraph added. 6.10 Control of Webbing &
Round Slings. Section added on control of man-
made fibre slings.
Section 7. Competency:
7.1 Competencies and Training of Personnel.
Levels of competency updated on the matrix.
Section 8: Roles and Responsibilities:
2 bullet points added to the generic stakeholders.
8.1 Site Manager/Site Controller/Offshore
Installation Manager. This is a new addition to
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 53 of 54
R&R‟s. 8.2 Area authority. This is a new addition
to R&R‟s. 8.4 Rigger / Slinger. 1 bullet point
added. 8.5 Crane Operator. Additional paragraph
added. 8.8 Lifting Inspector. 5 bullet points added.
Section 9. Communications
New section
Section 10. Risk Assessment and Planning of
Lifting Operations:
10.1 Strategy. Additional paragraph added after
All lifting operations shall be:
Appendices:
3 appendices included to the document as
follows:
 Appendix B: Inspection and Certification of
Temporary or New Cranes
 Appendix I: Procedure Summary
 Appendix J: Feedback & Improvement
Suggestions
Control Tier:
<<2>>
Revision Date: 18 June 2007
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Machine Guards
Page 1 of 6
Procedure for Machine Guards
AZSPU-HSSE-DOC-00057-2
This number supersedes UNIF-HSE-PRO-151-C1
Authority:
AzSPU Central HSE
Custodian:
Safety TL
Manager
Scope:
AzSPU
Document
Administrator:
<< Document Asset Technician Name >>
Issue Date:
05 October 2004
Issuing Dept:
HSE
Revision Date:
05 October 2004
Control Tier:
2
Next Review
20 May 2008
Date:
Control Tier:
<<2>>
Revision Date: <<05 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00057-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Machine Guards
Page 2 of 6
TABLE OF CONTENTS
1
INTRODUCTION
3
1.1
DOCUMENT PURPOSE
3
1.2
DOCUMENT SCOPE
3
2
RESPONSIBILITIES
3
2.1
AREA AUTHORITIES
3
2.2
PERFORMING AUTHORITIES
3
2.3
ALL PERSONNEL
3
3
RISKS FROM UNGUARDED AND POORLY GUARDED EQUIPMENT
4
4
MACHINE GUARD REQUIREMENTS
4
4.1
ALL MACHINERY
4
4.2
AUTOMATIC MACHINERY
4
5
SELECTION AND USE OF GUARDS
5
6
GUARD MATERIALS, CONSTRUCTION AND FITTING
5
6.1
MATERIALS
5
6.2
DESIGN, CONSTRUCTION AND FITTING
5
6.3
RETRO-FITTING OF EMERGENCY STOP CONTROLS
6
7
GUARD REMOVAL
6
Control Tier:
<<2>>
Revision Date: <<05 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00057-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Machine Guards
Page 3 of 6
1 INTRODUCTION
1.1 DOCUMENT PURPOSE
This document contains information on:
 the conditions and situations where machine guards must be in place and
used
 the reasons for installing machine guards and the conditions that must
exist before they may be removed
 the type of guards and protective devices available and the considerations
governing their choice and design.
1.2 DOCUMENT SCOPE
The guidelines contained in this document apply to:
 all BP Azerbaijan / Georgia sites and installations where machinery is
located and operated
 all personnel; both BP employees and contractors.
2 RESPONSIBILITIES
2.1 AREA AUTHORITIES
Area Authorities are responsible for ensuring that:
 all fixed machinery in their area is guarded in accordance with this
procedure
 all machine guards and safety devices in their area are routinely checked
and maintained in working order.
Note: Guards and safety devices shall be checked following any repairs or
modifications.
2.2 PERFORMING AUTHORITIES
Performing Authorities are responsible for ensuring that all portable equipment that is
used by the personnel under their control conforms to this procedure.
2.3 ALL PERSONNEL
All personnel are responsible for:
 ensuring that the machinery and equipment they use or maintain has all the
necessary guards in place and that all guards are properly fitted
 immediately reporting to their supervisor if they believe a machine is in a
Control Tier:
<<2>>
Revision Date: <<05 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00057-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Machine Guards
Page 4 of 6
dangerous condition or if any guards or protective devices are faulty
3 RISKS FROM UNGUARDED AND POORLY GUARDED EQUIPMENT
Moving parts of equipment, if not guarded, are extremely dangerous to operating
personnel and to any other personnel working in the immediate vicinity.
Warning: Any machine part, function or process that may cause injury must be
guarded to prevent contact with personnel.
The risk of accidents involving machinery may be caused by entanglement,
shearing, crushing, trapping, and cutting, etc. These accidents may occur due to:
 a lack of guards or poor guards on machines and equipment
 a failure to keep guards and safety devices properly maintained so that
machines or equipment become unsafe
 provision of inadequate controls or the wrong type of controls so that
equipment cannot be turned off quickly and safely or it may be started
accidentally.
4 MACHINE GUARD REQUIREMENTS
4.1 ALL MACHINERY
Guards must be fitted to those parts of a machine wherever:
 cutting, shaping or boring of any material is performed
 there are components that transmit energy, including:
 flywheels
 pulleys
 belts
 cranks
 gears etc.
 there are moving parts which can be reciprocating or rotating, including feed
mechanisms and other accessories
 debris or products may be emitted / ejected that present a danger to the
operator and /or nearby personnel, e.g., deflectors for relief valves, screens for
bench grinders and lathes, etc.
In addition, where deemed necessary, guardrails or barricades may be placed
around equipment to prevent personnel from getting close to it.
4.2 AUTOMATIC MACHINERY
Guards must be installed on equipment that can start automatically (and / or without
Control Tier:
<<2>>
Revision Date: <<05 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00057-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Machine Guards
Page 5 of 6
warning) such as air compressors, diesel sets, etc.,
In addition, warning signs such as
Caution
- This machine can start
automatically!” shall be posted near all such equipment.
5 SELECTION AND USE OF GUARDS
Fixed guards such as covers and plates are the most common type of guard and
should be used wherever possible. The guards should be properly fastened in place
with screws or nuts and bolts which need tools to remove them.
Interlocks, designed to shut down the machine if protective covers are opened or
removed, should be used where fixed guards are not reasonably practicable and the
equipment user / maintainer needs regular access to parts of the machine. The
interlock should ensure that the machine cannot start before the guard is properly
replaced / closed and must also ensure that the machine will stop if the guard is
opened while the machine is moving.
Two-hand controls are designed to prevent the operator „reaching in‟ while the
machine is running and should therefore be located at a safe distance from the
danger area.
Emergency stop controls should be located within easy reach of the operator,
particularly on larger machines so that they can be operated quickly in an
emergency.
In some cases, presence sensing devices, for example, photoelectric, and
pressure sensing devices may be used instead of fixed guards or interlocks.
However these devices must be regularly checked to ensure their continuing
operation and effectiveness.
6 GUARD MATERIALS, CONSTRUCTION AND FITTING
6.1 MATERIALS
The materials from which the guard is manufactured should be carefully chosen for
suitability. For example:
 plastic is easy to see through but may be easily scratched, damaged or
shattered
 if wire mesh or grating is used, it should not have holes that are large enough
to allow access to the danger area or large enough to allow the passage of
debris
6.2 DESIGN, CONSTRUCTION AND FITTING
All guards shall be designed, constructed and fitted so that they:
 protect the operator and any other personnel from the equipment (especially its
moving parts)
 may not be easily removed or tampered with, e.g., they must be firmly secured
Control Tier:
<<2>>
Revision Date: <<05 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00057-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Machine Guards
Page 6 of 6
to the machine
 can withstand the conditions of normal use
 allow the machine to be cleaned safely
 prevent foreign objects from falling onto moving parts, e.g., small tools, nuts,
bolts, etc
 do not present sharp or jagged edges, i.e., they should be rolled and / or bolted
 do not create interference which would hamper personnel from performing their
assigned tasks quickly and comfortably
 do not obstruct lubrication points and feeds in such a way that the guard must
be removed before these components can be properly accessed.
6.3 RETRO-FITTING OF EMERGENCY STOP CONTROLS
Note: Before fitting emergency stop controls to machines that have not previously
had such controls fitted, it is essential to check that the emergency stop
controls do not in themselves present new risks. For example, some
machines require the power supply to be on in order to operate the brakes.
This power might be lost if the machine is stopped using the emergency stop
control.
7 GUARD REMOVAL
Machine guards shall only be removed by competent and experienced personnel for
maintenance and repair purposes.
Whenever guards are removed for maintenance or repair:
 the removal shall be carried out under a Permit to Work
 the energy source to the machine must be isolated and the switch, button,
lever etc., must be locked out and tagged before the guard can be
removed
 all guards must be in place before the lock and tags can be removed.
Revision/Review Log
Revision Date
Authority
Custodian
Revision Details
05 October 2004
Alan McNulty
Esmira Akhundova
Initial Issue
Control Tier:
<<2>>
Revision Date: <<05 October 2004>>
Document Number: << AZSPU-HSSE-DOC-00057-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 1 of 34
Procedure for:
Management of Radioactive Materials and
Radiation Generators
AZSPU-HSSE-DOC-00058-2
This number substitutes UNIF-HSE-PRO-205-C1
Authority:
AzSPU Central HSE Manger
Custodian:
Safety TL
Scope:
AZSPU
Document
Administrator:
<< Document Asset Technician Name >>
Issue Date:
20 October 2004
Issuing Dept:
HSE
Revision Date:
20 October 2004
Control Tier:
2
Next Review
20 May 2008
Date:
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 2 of 34
TABLE OF CONTENTS
1
INTRODUCTION
3
1.1
Document Purpose
3
1.2
Document Scope
3
2
RESPONSIBILITIES
4
2.1
Site Manager/OIM
4
2.2
Radiation Protection Supervisor (RPS)
4
2.3
Radiation Protection Adviser (RPA)
4
3
CONDITIONS FOR WORK WITH IONISING RADIATION
7
3.1
Work with Ionising Radiation
7
3.2
General Conditions for Work with Ionising Radiation
7
3.3
Risk Assessment
7
3.4
Designated Areas
8
3.5
Controlled Areas
8
3.6
Supervised Areas
9
4
LOCAL RULES FOR WORK WITH IONISING RADIATION
11
4.1
Storing Radioactive Sources
11
4.2
Outside Contractors Using Sealed Sources
11
4.3
Radiography
12
4.4
Radioactive Sources Used in Well Logging Operations
13
4.5
Use of Other Mobile Sources
14
4.6
Use of Installed Sealed Radioactive Sources in Nucleonic Interface Gauges
15
4.7
Contingency Plans for Incidents Involving Sealed Radioactive Sources
16
4.8
Removal of Equipment Contaminated with Naturally Occurring Radioactive
Material
17
4.9
Entry into Vessels Contaminated with Naturally Occurring Radioactive
Material
18
4.10
Contingency Plans for Incidents Involving Naturally Occurring Radioactive
Material
20
4.11
Transport of Radioactive Material
20
5
MONITORING FOR RADIATION AND CONTAMINATION
22
Appendix A
23
Appendix B
26
Appendix C
29
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 3 of 34
Appendix D
30
Appendix E
32
Appendix F
33
1
INTRODUCTION
1.1 Document Purpose
Radiation Protection is based on three principles recommended by the International
Commission on Radiological Protection (ICRP) and is described below.
Justification: Every practice resulting in exposure to Ionising Radiation shall be
justified by the advantages it produces.
Optimisation: All exposures shall be kept as low as reasonably achievable (ALARA),
economic and social factors being taken into consideration.
Dose Limits: The sum of all doses received shall not exceed certain limits.
This Safe System of Work employs these principles and, if correctly applied, will
ensure that all exposures to Ionising Radiation and therefore all associated risks are
kept as low as reasonably achievable.
1.2 Document Scope
This Safe System of Work applies to all work with ionising radiation carried out on BP
installations and sites in Azerbaijan and Georgia. Contractors working on BP owned
or operated sites/installations are also responsible for alignment with this SSOW.
Responsibilities are detailed with written instructions that will ensure radiation doses
are as low as reasonably practicable.
This SSOW contributes to compliance with the “HSE expectations” contained in
“getting HSE right”.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 4 of 34
2 RESPONSIBILITIES
2.1 Site Manager/OIM
The manager of any BP Facility or Site either onshore or offshore has overall
responsibility for the implementation of this SSOW.
2.2 Radiation Protection Supervisor (RPS)
A Radiation Protection Supervisors
(RPS) shall be appointed where any work
involving ionising radiation is to be carried out. At BP operating sites the Safety
Advisors/Officers should be trained to RPS certification. They will exercise
supervision to the extent that any work with ionising radiation is carried out in
accordance with this SSOW. The RPS will review the local rules of any third party
that intends to work with radioactive substances or radiation generators.
To enable them to carry out this role, appointed persons should receive appropriate
training, including a written assessment, at an approved course prior to appointment.
They will also receive suitable refresher training at a period of not more than three
years.
The appointment describing areas of responsibility shall be in writing by the Site
Manager/OIM.
The RPS is responsible for:
 Ensuring all work involving ionising radiation is carried out in accordance with
this Safe System of Work
 Ensuring all hazards related to work with ionising radiation are identified and
suitable precautions are taken to minimize the risks associated with these
hazards
 Maintaining a full and up-to-date record of all radioactive sources that are
under his control and held on the site/installation.
The RPS will make use of the checklist contained in Appendix 3 when a contracting
company brings sources of ionising radiation to the site/installation or when specialist
companies arrive on the site/installation to carry out activities with naturally occurring
radioactive material.
Copies of letters of appointment for RPSs shall be retained at the facility.
2.3 Radiation Protection Adviser (RPA)
The RPA is responsible for providing advice on all aspects of work with ionising
radiation and for evaluating and approving the plans, organisation and arrangements
of specialist contractors. The RPA is also responsible for carrying out an annual
review of work with ionising radiation to ensure doses received by workers, visitors
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 5 of 34
and members of the public are as low as reasonably achievable. This review will
ensure the accounting system used to record the location and quantity of radioactive
material provides a true record.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 6 of 34
has appointed TRACERCO Protection Adviser.
They can be contacted at the following address:
PRIMARY CONTACT:
Graham Wales
Chattan Mews Offices
Suites 1&2
Chattan Place
Aberdeen AB11 6RD
United Kingdom
Tel: +44 (0) 1224 592527
Fax: +44 (0) 1224 212641
Mobile: +44 (0) 7764 836669
Home: +44(0) 1224 732908
E-mail: graham.wales@matthey.com
SECONDARY CONTACT:
Bill Good at the above address
John Lambley, Paul Warren and Andrew Smith
Tracerco
PO BOX 1
G Building
Billingham
Cleveland
United Kingdom
TS23 1LB
Tel: +44(0) 01642 522350 / 375500
Fax: +44(0) 01642 522991
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 7 of 34
3 CONDITIONS FOR WORK WITH IONISING RADIATION
3.1 Work with Ionising Radiation
The following work with ionising radiation may be carried out on BP
sites/installations:
 The use of installed nucleonic gauges
 Accumulation and disposal of naturally occurring radioactive material
 Work with equipment contaminated with naturally occurring radioactive
material
 Use of radiography sources
 Use of sealed and unsealed radioactive sources for process investigation and
measurement
 Use of well logging sources
 The use of casing depth markers
 Use and storage of instrument test sources
Use and storage of smoke detectors incorporating radioactive sources.
3.2 General Conditions for Work with Ionising Radiation
Any use of sources of ionising radiation must be justified and measures must be
taken to ensure radiation doses are as low as reasonably practicable. In general this
can be achieved by following basic rules when working with sealed sources and
radiation generators:
Most importantly, radioactive sources must never be handled directly:
 Use appropriate shielding to reduce the intensity of the radiation.
 Maximize the distance between radiation sources and personnel.
 Minimize the time spent in the vicinity of radiation sources.
The risks associated with unsealed radioactive material can be minimized by:
 Keeping the material contained within vessels or pipe work
 Observing good standards of hygiene and housekeeping
 Carrying out operations in such a way that material does not become
airborne.
3.3 Risk Assessment
Supervisors will ensure that a suitable and sufficient written risk assessment is
carried out prior to any new applications involving the use of ionising radiation. Risk
Assessment is required in order to identify the measures to restrict the exposure of
employees, contractors or members of the public to ionising radiation. Generic Risk
Assessments for nucleonics and NORM have been provided by the RPA.
The RPS should be consulted if there is any doubt about the requirement for, or the
content of, a risk assessment.
Changes in work activities may result in the requirement for a review of the
assessment.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 8 of 34
3.4 Designated Areas
To assist in managing the work with ionising radiation, the RPS will decide if the area
should be designated as a Supervised Area or Controlled Area. Dose criteria for
Designation of Areas are given in the following Tables 1 and 2 (reference to Tracerco
Training manual fro Radiation Protection section 3, “Ionising Radiations Regulations
1999” ACOP and Guidance):
Table 1 Dose Criteria for Designation of Areas
Annual Dose Criteria (greater than)
PART OF BODY
CONTROLLED AREAS
SUPERVISED AREAS
Whole body
6 mSv
1 mSv
Lens of eye
45 mSv
15 mSv
Skin and extremities
150 mSv
50 mSv
Table 2 Annual Dose Limits
CATEGORIES OF
PART OF BODY
DOSE LIMITS
PERSONNEL
Effective Dose
20 mSv (annual)
Employees* of 18 years of
Equivalent Dose - Lens of Eye
150 mSv (annual)
age or above
Equivalent Dose - Skin
500 mSv (annual)
Equivalent Dose - Extremities
500 mSv (annual)
Effective Dose
6 mSv (annual)
Trainees aged under 18
Equivalent Dose - Lens of Eye
50 mSv (annual)
years
Equivalent Dose - Skin
150 mSv (annual)
Equivalent Dose - Extremities
150 mSv (annual)
Women of reproductive
Without prejudice to Limits for
13 mSv in any
capacity
both Categories above,
consecutive period of 3
Equivalent Dose for the
months (for abdomen)
abdomen, averaged
Other Persons**
Effective Dose
1 mSv
Notes:
Employee* - is a competent person, certified and authorised to work with radioactive
sources.
Other Persons** - other than Employee or Trainee, including any person aged under
16 years.
3.5 Controlled Areas
Sealed Sources
An area will be designated as a controlled area when one or more of the following is
applicable
 i) A prior risk assessment indicates that the person is likely to exceed 3/10 of
any dose limit (whole body 6 mSv/y: single organ 150 mSv/y)
 ii) The instantaneous radiation dose rate is greater than 7.5 Sv/h
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 9 of 34
 iii) A control measure is put in place to ensure the dose to an individual does
not exceed 1 mSv/y
Note1 If the dose rate is less than 7.5Sv/h the risk assessment will still need to
prove that
6 mS/y will not be exceeded otherwise a controlled area will be
designated.
Note 2 The closing of a shutter mechanism is seen as a control measure. Therefore
the first person into a vessel with nucleonics attached will do so under controlled area
conditions. He will carry out radiation dose rate measurements, proving the shutter is
closed and then de-designate the area. If NORM is present the area will remain a
controlled area.
Unsealed Material
An area will be designated as a controlled area when one or more of the following is
applicable
 A prior risk assessment indicates that the person is likely to exceed 3/10 of
any dose limit (whole body 6 mSv/y: single organ 150 mSv/y)
 A control measure is put in place to ensure the dose to an individual does not
exceed 1 mSv/y.
Note1 Any vessel containing NORM will be designated a Controlled area due to the
potential activities and volumes of material.
Note2 Any major containment break will be done under controlled area conditions,
due to the potential activities and volumes of material
Note3 Small containment breaks may, following the risk assessment, be carried out
under Supervised area conditions
Note4 The wearing of respiratory protection could be seen as a control measure
unless the RPS is confident that the risk assessment shows the wearing of RPE is
not to reduce the possible dose below 1 mSv/y.
All Controlled areas must be barriered and a suitable number of notices placed at the
barrier displaying the Trefoil symbol, the legend “Radiation Controlled Area” the
nature of the radiation i.e. Gamma radiography and the hazard - External.
3.6 Supervised Areas
Sealed and Unsealed material
A Supervised area will be designated, following a risk assessment,
 where any person is likely to exceed 1/10 of any dose limit. (Whole body 1
mSv/y : single organ 50 mSv/y)
 where an area is required to be kept under supervision for purposes of
contamination or possible increased radiation dose rates.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 10 of 34
Supervised areas do not require being barriered but must have a suitable
number of warning signs to delineate the area. The signs must display the
Trefoil symbol, the legend “Radiation Supervised Area” the nature of radiation
i.e. NORM and the hazard - Internal.
Note: There is no acceptable level of contamination. Any contamination must
be removed as soon as possible after it is detected.
These conditions are summarized in the Diagram 1 below:
Diagram 1 Procedure for Designated, Supervised and Controlled Areas
Is Dose Rate greater
YES
Stop Work
than 30Sv/hour?
Contact HSE Dept.
Seek Advice from RPA
NO
Measure Dose Rate and Surface Contamination Levels and Designate Area as
appropriate:
Less than 2.5Sv/hour
2.5-7.5Sv/hour and
>7.5Sv/hour
and free of
low volumes and
or high volumes or
contamination
activity of
activity of
contamination
contamination
UNDESIGNATED
SUPERVISED
CONTROLLED
AREA
AREA
AREA
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 11 of 34
4 LOCAL RULES FOR WORK WITH IONISING RADIATION
4.1 Storing Radioactive Sources
Storage When Not in Use
When not in use, radioactive sources must be stored in an appropriate container
locked in a secure store. The following conditions apply to the storage of radioactive
sources:
 The store must be used exclusively for this purpose.
 The store should be in a low occupancy area away from accommodation and
not near explosives.
 The store must not restrict access to the emergency services.
 A sign marked with a trefoil and the word
“RADIOACTIVE” must be
prominently displayed at all access points.
 Regular surveys must be carried out to ensure the external radiation dose
rate is below 7.5 Sv/h.
 The RPS must maintain a full and up-to-date register for all sources held in
the store.
 All movements of sources must be logged in and out of the store by the RPS.
 All packages containing radioactive substances must be suitably labelled.
Source Security
The keys for stores containing radioactive material will be kept under the control of
the RPS.
Source Accountancy
The RPS will keep an up to date record of all radioactive sources on the installation.
The quantity and location of all radioactive sources will be recorded as follows:
INSTALLED SOURCES
Once per calendar month
(i.e. nucleonic gauges)
MOBILE SOURCES
Once per day
(e.g. radiography sources)
(Unless in storage when Once per week)
Contractors bringing radioactive material onto BP sites/installations will carry out
checks according to this frequency.
4.2 Outside Contractors Using Sealed Sources
Before contractors bring radioactive sources or radiation generators onto BP facilities
the following information must be exchanged:
 A detailed description of the work to be done
 An estimate of the total radiation dose likely to arise
 The arrangements that will be in place to restrict exposure
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 12 of 34
 The name of the contractor’s representative who will be responsible for the
work
 Arrangements in place for receipt, storage and transport of the radioactive
source
 Details of the contingency plan that will be invoked in the event of an incident.
Where considered appropriate, the RPS will liase with the RPA over any aspects of
the work to be done.
Details relating to the source(s) must be supplied to the Site Manager/OIM, RPS and
the sponsoring department representative, at least 24 hours before the despatch to
the installation.
These shall include:
 Isotope name
 Source strength at a particular date
 Source identification number
 Container number
 Transport index
 Transport category
 Name of Radiation Protection Supervisor
 Appropriate transport details, e.g. date, ETD, ETA including Contractors.
Sources must not be left on the site/installation premises unless prior agreement has
been reached with the Site Manager/OIM.
4.3 Radiography
The following instructions must be adhered to in conjunction with all previously
mentioned responsibilities and instructions:
 All work involving the use of a radioactive source or radiation generator shall
only be undertaken in accordance with detailed procedures agreed with the
installation RPS under the Permit to Work System.
The contractor shall be responsible for preparing procedures, agreed with the
RPA, which shall include:
o Arrangements for excluding non-classified personnel from the work
site
o A detailed description of the work to be done
o A description of agreed pre-exposure and exposure warnings
o Detailed contingency plans for dealing with any emergency likely to
arise in the course of the work and actions to be taken in the event of
a site/installation alarm.
 Descriptions of individual operations must be specific to the work to be
undertaken.
 At least two contractor’s personnel will be present while radiography is
undertaken. Both will be classified workers and one will be the nominated
RPS.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 13 of 34
The contractor shall be responsible for supplying a minimum of two radiation
dose rate monitors and for checking that these monitors are functioning
correctly. A valid certificate of test must be available for each instrument.
The contractor shall be responsible for ensuring that all equipment required in
the case of an emergency is available as agreed with the RPA. The
emergency equipment will include 2 bags of lead shot, remote handling tongs,
a hacksaw or wire cutters, barriers and warning lamps, an audible radiation
monitor, emergency pot and suitable hand tools.
The contractor will be responsible for maintaining appropriate records and for
supplying copies of these to the installation RPS on request.
Where appropriate, sealed radioactive sources shall have a current certificate
of test for leakage of radioactive material and sources should be re-tested
within 24 months of the date of the last test. This requirement does not apply
to sources that are replaced within 24 months period because of decay (e.g.
Iridium 192 sources with 74 day half life).
These are three conditions upon which the Site Manager/OIM and RPS must
be informed immediately:
o A sealed source or container is damaged, lost or mislaid.
o The immediate container or the bonding of a sealed source is broken.
o The radiation level from the immediate container or the bonding of a
sealed source increases significantly above its previous level.
4.4 Radioactive Sources Used in Well Logging Operations
In addition to the instructions detailed above the following instructions must be
adhered to:
 All work involving the use of radioactive sources shall only be undertaken in
accordance with detailed procedures agreed with the RPS under the Permit
to Work System.
 The contractor shall be responsible for preparing procedures, agreed with the
RPA, which shall include:
o Arrangements for excluding non-classified personnel from the work
site
o A detailed description of the work to be done
o Detailed contingency plans for dealing with any emergency likely to
arise in the course of the work and actions to be taken in the event of
an installation alarm.
 The contractor’s local rules should specify any more stringent requirements
and identify specified controlled areas when logging tools are in use.
 If a neutron source or generator is being used, the contractor must make a
neutron detector available.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 14 of 34
 Only the contractor’s RPS or other classified persons are allowed to transport
the source to the rig floor.
 The rig floor must be cleared of all non-essential personnel until the source
has been loaded into the tool by the contractor’s RPS.
 After the tool has been loaded personnel may re-enter the rig floor.
 When the log has been completed the rig floor must be cleared prior to the
tool being pulled clear of the riser and the source being unloaded.
 On completion of the operation, the source must be returned and logged back
into the radioactive source store.
4.5 Use of Other Mobile Sources
Specialist contractors may use mobile radioactive sources for purposes such as non-
invasive process investigations. The following conditions will apply to the use of
these sources:
All work involving the use of a radioactive source shall only be undertaken in
accordance with detailed procedures agreed with the RPS under the Permit
to Work System.
The contractor shall be responsible for preparing procedures, agreed with the
RPA, which shall include:
o Arrangements for excluding non-classified personnel from the
work site
o A detailed description of the work to be done
o Detailed contingency plans for dealing with any emergency likely to
arise in the course of the work and actions to be taken in the event of
an installation alarm.
Descriptions of individual operations must be specific to the work to be
undertaken.
The contractor shall be responsible for supplying appropriate radiation dose
rate monitors and for checking that these monitors are functioning correctly. A
valid certificate of test must be available for each instrument.
The contractor shall be responsible for ensuring that all equipment required in
the case of an emergency is available as agreed with the RPA.
The contractor will be responsible for maintaining appropriate records and for
supplying copies of these to the installation RPS on request.
Where appropriate, sealed radioactive sources shall have a current certificate
of test for leakage of radioactive material and sources should be re-tested
within 24 months of the date of the last test. This requirement does not apply
to sources that are replaced within 24 months period because of decay (e.g.
Iridium 192 sources with 74 day half life).
These are three conditions upon which the Facilities and RPS must be
informed immediately:
o A sealed source or container is damaged, lost or mislaid.
o The immediate container or the bonding of a sealed source is broken.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 15 of 34
o The radiation level from the immediate container or the bonding of a
sealed source increases significantly above its previous level.
4.6 Use of Installed Sealed Radioactive Sources in Nucleonic Interface
Gauges
Radioactive sources may be installed at various locations for level and interface
detection and density measurement. These sources emit penetrating gamma rays
and are housed in lead containers. The gauges are designed, manufactured and
installed to standards that ensure any risks associated with their use are insignificant.
Specific safety information on each of the gauges is contained in the hand over
documentation supplied at the time of installation.
Accounting for Sealed Sources
The installation RPS is responsible for maintaining an up to date record of all sealed
sources on the installation. This record must contain the following information:
 Name of isotope
 Serial number of each source (or other unique identification mark)
 Date of receipt
 Activity of source at date of receipt
 Current location of each source
 Date and manner of disposal (when appropriate)
This record must be updated every time the source is moved to a new location or, for
installed sources once per calendar month and, for mobile sources once per day (if in
storage once per week will suffice)
Copies of these records must be maintained for two years, or longer if required by
the certificate of registration.
Leakage Tests
Sealed sources must be tested for leakage at least once in every 24 months.
Normally this will be carried out by the RPA during the annual audit. The
site/installation RPS must retain copies of the test results for two years from the date
of test.
Routine Checks
Once each calendar month, the site/installation RPS will carry out basic checks to
ensure the continued radiological safety of the installed gauges. These checks will
include:
 Measure radiation dose rate and check it does not exceed 7.5 Sv/h at
accessible points.
 Check the source container is securely bolted to the mounting brackets.
 Ensure all warning notices are in place and are legible.
 Check the source is secured in the container with a padlock.
Check that the state of the shutter mechanism is clear and that the shutter
has not been padlocked in the “OPEN” position.
General Precautions for Work in Vessels on Which Nucleonic Interface Gauges are
installed
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 16 of 34
Warning notices must be displayed on all man ways on vessels on which nucleonic
gauges are installed. Sources must be withdrawn and shutters locked in the “SHUT”
position before man ways are opened. The installation RPS will confirm this has been
done before anyone is permitted to enter the vessel.
Precautions for Vessels Incorporating Nucleonic Interface Gauges
During normal operations, the source is retained in a dip pipe inside the vessel. The
fluids inside the vessel provide adequate shielding. If the liquid level inside the vessel
falls it is possible that radiation dose rates outside the vessel will increase. In this
event, the sources must be withdrawn into their shielded container and the shutter
must be locked in the “SHUT” position. The RPS will retain the key and will ensure
that the source is not exposed until the fluid level has increased to the normal level.
For operational reasons it may, exceptionally, be necessary to operate the gauge
with the source exposed above the liquid level. In these circumstances the RPS must
measure the radiation dose rate outside the vessel and designate the area as
appropriate. As a rule of thumb, if the source is to be exposed for more than one hour
the source will be retracted into the housing.
Source Removal
Under no circumstances may a radioactive source be removed from its shielded
container. If it is necessary to remove the container from the vessel, either
temporarily or permanently, the RPS must ensure by measurement that the source is
shielded within the container and that the shutter mechanism is padlocked in the
“SHUT” position. The container may then be moved to an appropriate storage
location.
4.7 Contingency Plans for Incidents Involving Sealed Radioactive
Sources
The hazards associated with any job involving the use of sealed sources must be
assessed before the work begins and precautions implemented to minimise risks. In
the unlikely event of an incident, which could result in the conditions for a controlled
area applying or any person being overexposed to ionising radiation, the following
actions must be taken.
Loss of or Damage to Shielding
The following actions must be taken in event of loss or damage to shielding:
 The person discovering the damage will evacuate the immediate area and
warn others to do the same.
 Contact the Site Manager/OIM, Control Room and the RPS.
 The RPS will attend the scene and ensure all personnel have withdrawn to a
safe area i.e. dose rate less than 7.5 Sv/h.
 Erect barriers to prevent access bearing in mind that access may need to be
restricted on the levels above and below the incident.
Prepare a recovery plan with the aim of ensuring that no individual involved in
the recovery receives a radiation dose greater than 1 millisievert.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 17 of 34
Advice can be obtained from the Radiation Protection Adviser on how radiation
doses can be restricted. In general:
 Keep as far from the unshielded source as possible.
 Make use of available shielding materials (lead sheet etc.).
 Limit the amount of time spent in the area.
 Never handle the unshielded source directly.
 In the case of fire, no attempt should be made to withdraw the sources into
their housings or to close shutters if this involves personnel entering
hazardous areas.
 In the event of a significant emergency that threatens the lives of personnel or
the continuing integrity of the installation, the potential presence of radioactive
sources should not be regarded as sufficient reason to prevent entry of any
incident team to the affected area.
 When the situation has been made safe the RPA will make assessments of
the radiation doses received by those involved in the incident and advise on
notifications to be made to regulatory authorities.
Loss of a Radioactive Source
In the event that a sealed source is lost or otherwise unaccounted for the RPS shall
immediately notify the Site Manager/OIM and the RPA. The RPS shall initiate a
search of all likely areas using available dose rate meters. When the source is found
the RPS shall implement a retrieval plan incorporating information from the RPA on
dose limitation and, if necessary, temporary source storage.
All packages leaving the installation/site must be surveyed using a radiation dose
rate meter until the source is found.
If the source cannot be readily found, the RPS shall prepare a detailed report of the
incident and hand over responsibility for further action to the Site Manager/OIM. The
RPA will advise on statutory notifications that must be made to regulatory bodies.
Sources Owned and Used by Third Parties
If the radioactive source belongs to a contracting company, the contractor’s RPS will
immediately implement the appropriate contingency plan. The RPS and other
personnel will provide any assistance necessary to make the situation safe.
4.8 Removal of Equipment Contaminated with Naturally Occurring
Radioactive Material
The removal of equipment including pumps, meters, spool pieces etc. that are
suspected, either by measurement or location, of being contaminated must be done
as follows:
 Written authorisation must be obtained from the area authority before work
can proceed.
 Persons carrying out the work must use the recommended protective
equipment and a suitable floor covering must be used to limit the spread of
contamination.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 18 of 34
 When containment has been breached, contamination measurements must
be made and the area will be designated as Controlled, Supervised or
released as free for normal work.
 Any contaminated item removed from the area must be securely capped at all
open ends using blank flanges, end caps or by wrapping with heavy-duty
polythene and the ends labelled with LSA / NORM tape.
 Equipment that requires maintenance in a workshop must be decontaminated
to backg2round level if the work could result in radioactive material becoming
airborne.
 Prior to equipment being released from the installation for refurbishment,
disposal or movement it must be cleaned to backg2round level or sent to an
authorised decontamination facility.
 Any tools or equipment used must be monitored for contamination at the end
of the operation. If contaminated they should be washed until backg2round
levels are achieved.
 The work area should be kept as free from contamination as possible.
Measurements of contamination in the area should be made at regular
intervals. Following completion of the work the area should be monitored
using a contamination monitor and monitoring records should be kept.
4.9 Entry into Vessels Contaminated with Naturally Occurring
Radioactive Material
Specialist contractors who carry out this work shall be responsible for preparing
procedures, agreed with the RPA, which shall include:
o Arrangements for excluding non-classified personnel from controlled
areas
o A detailed description of the work to be done
o Detailed contingency plans for dealing with any emergency likely to
arise in the course of the work and actions to be taken in the event of
an installation alarm.
Clearance
Written permission (Permit To Work System) is required for opening up or for entry
into vessels, etc. The clearance must give consideration to the use of air tools that
will cause a volume of air to be discharged inside the vessel and hence affect
extraction flows.
Protective Equipment and General Safety
All persons entering the vessel must wear suitable impervious overalls, boots and
gloves.
If any dust (or spray containing dust) is likely to arise from the cleaning operation,
breathing apparatus must be worn. Any inhalation of radioactive dust is to be
avoided.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 19 of 34
Ideally, surfaces should be kept damp to prevent the production of dust and its
dispersal into the atmosphere. If the only practical last resort is sand-blasting,
burning, grinding or similar to complete a particular task the RPS should, in
consultation with the RPA, assess the best method for radiation protection on a case
by case basis.
Preparatory Work Prior to Vessel Entry
Pre-Entry precautions include the following:
A polythene or PVC tent should be erected where required around the vessel
entry point to create a decontamination area. The structure should be such
that any contamination, which is released during entry and cleaning
operations can be contained. The tent should be of sufficient size to allow
capping, cleaning or containment operations to be carried out on
contaminated items. Washing facilities in the form of a water supply,
detergent and scrubbing brush should be provided within the tented area, as
well as storage facilities for personal protective clothing and receptacles for
contaminated clothing.
The tented area shall be designated as necessary. Only classified workers
and personnel working under the written system of work are allowed into a
Controlled Area. A control point must be set up at the entrance of any
controlled area.
Prior to opening any vessel, rigorous attempts must be made to flush away or
remove as much debris, sludge and scale as possible by jet washing, water
washing or steam injections, etc.
All monitoring for contamination should be carried out under the general
supervision of an RPS.
Any tools or equipment used must be monitored for contamination at the end
of the operation. If contaminated, they should be washed until backg2round
levels are achieved. If this is not possible, they should be sealed in strong
plastic bags marked “Radioactive” and retained for future similar use or sent
for decontamination in accordance with local regulations.
The work area should be kept as free from contamination as possible.
Measurements of contamination in the area should be made at regular
intervals.
Following completion of work the area should be monitored using a
contamination monitor. Records of monitoring must be kept.
Disposal of Radioactive Material
All loose material with an activity greater than backg2round as measured with a
suitable contamination monitor must be disposed of as required by local regulations.
Records of the date of disposal of such waste including its weight and specific activity
should be retained by the RPS in a clear and legible form. Representative samples of
material disposed of must be sent for radiochemical analysis in order to assess the
total activity of the material.
Handling Contaminated Items
Any item removed from the decontamination area must be securely capped at all
open ends using blank flanges, protective end caps, or by wrapping with heavy duty
polythene to prevent the spread of contamination during subsequent handling.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 20 of 34
Similarly, drums of scale removed during the cleaning operation must be securely
fastened to prevent dispersal of radioactive materials. The outside surfaces of the
drums should be washed to reduce the contamination level on the surface as far as
possible.
Items of contaminated equipment if they should be returned to the vessel should be
capped or plastic wrapped to prevent the spread of contamination prior to their
refitting.
Access to Vessel After Decontamination
Once decontaminated to backg2round, radiological restrictions can be removed, good
hygiene practices should still be applied.
4.10
Contingency Plans for Incidents Involving Naturally Occurring
Radioactive Material
Ensuring the material is contained within vessels or pipe work can normally control
the hazards associated with radioactive material. When this is not possible operation,
which could lead to the material becoming airborne or released in an uncontrolled
manner should, as far as is practicable, be avoided.
In the unlikely event of an incident involving naturally occurring radioactive material,
the following actions must be taken.
Spill of Radioactive Material in an Uncontrolled Area
In event of spill of radioactive material in an Uncontrolled Area the following actions
must be taken:
 The person who discovers the incident must evacuate the area and warn
others to do the same.
 Notify the Site Manager/OIM, Control Room and the RPS.
 The RPS will attend the scene and establish barriers around the incident.
Personnel who may have been contaminated as a result of the incident will be
monitored for contamination. Remove any contaminated clothing and seal it in
a plastic bag. Any contamination on the skin should be washed away taking
care to ensure material is not ingested.
The material shall then be collected and disposed of under the direction of the
RPS.
4.11 Transport of Radioactive Material
Radioactive material must be transported in appropriate containers packaged and
labelled in accordance with appropriate national and international legislation. The
following specific conditions apply to the transport of radioactive material to and from
the site/installation:
 The Site Manager/OIM must be notified at least
24 hours before a
radioactive source is transported to the site/installation.
 The supplier of the radioactive material must ensure he has an RPS on
the installation to receive the material. The supplier’s RPS shall liase with
the site/installation RPS regarding the storage arrangements for the
material.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 21 of 34
 In exceptional circumstances it may not be possible for the supplier’s RPS
to be present on the installation/site when the material is received. The
Site Manager/OIM may allow the material to be received provided the
supplier has provided detailed written instructions regarding how the
material should be handled.
 The site/installation RPS will inspect packages or containers containing
radioactive material and ensure they are correctly labelled and provide
adequate shielding. If packages are incorrectly labelled or if dose rates
are greater than 7.5 Sv/h, they will be placed in a barriered area until
dealt with by the supplier.
The owner of the radioactive material will be responsible for ensuring the
transport of radioactive material from the facility complies with all
legislative requirements. Radioactive material must be packed inside the
appropriate, labelled containers.
Transport of Naturally Occurring Radioactive Material
Samples of naturally occurring radioactive material or equipment contaminated with
naturally occurring radioactive material are transported as “Excepted Packages”. The
following conditions will apply:
 The material must be suitably contained so that it cannot escape from the
package during transport.
 The RPS must confirm that the dose rate at the surface of the package
does not exceed 5 Sv/h.
The package must be free of surface contamination.
Note: loose scale other than samples must not be transported onshore.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 22 of 34
5 MONITORING FOR RADIATION AND CONTAMINATION
Calibrated radiation dose rate monitors, appropriate to the radiation being used, must
be available wherever radioactive sources are likely to be used.
These monitors must be thoroughly examined and tested at least once in every
period of 12 months. A qualified and certified Contractor company shall undertake
the examination and test of radiation dose rate monitors.
The certificate resulting from such a test must be retained for two years from the date
of the test.
If a radiation-monitoring instrument is damaged such that the accuracy of the
calibration may have been affected, then the instrument must be repaired and re-
calibrated.
Only individuals who have been trained in their safe use may use these monitors.
Under normal operating conditions, dose rates around sites/installations, which
incorporate a radioactive source shall be monitored monthly or following any work
which has been carried out which could affect the adequacy of the shielding.
The Radiation Protection Supervisor or his delegate will carry out this activity. The
results of such monitoring shall be recorded and retained on the facility for 2 years.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 23 of 34
Appendix A
Glossary of terms
DEFINITION
TERM
Absorbed Dose
Quantity of energy imparted by ionising radiation to unit mass
of matter such as tissue. Unit gray, Symbol Gy. Gy = 1 joule
per kilogram.
Activity
Measure of an amount of a radionuclide. Describes the rate at
which transformations occur in it. Unit becquerel. Symbol Bq. 1
Bq = 1 transformation per second.
Classified Person
Classified person is a person who is likely to receive an
effective dose in excess of 6 mSv per year or an equivalent
dose that exceeds three-tenths of any relevant dose limit.
Classified person should be informed if he/she is so
designated. Classified person should be over 18 years old and
has a health record certified by doctor confirming he/she is fit
for this job.
Contamination
Loose unsealed radioactive material/substance.
Contingency Plan
Document the purpose of which is to restrict any exposure that
arises from an accident both to the employees themselves and
to others, including emergency services personnel, who may
be affected by it.
Controlled Area
Controlled Area is the area where:
1.
It is necessary for any person who enters or works in
the area to follow special procedures designated to
restrict significant exposure to ionising radiation in that
area or prevent or limit the probability and magnitude of
radiation accidents or their effects; or
2.
Any person working in the area is likely to receive an
effective dose greater that
6 mSv a year or an
equivalent dose greater than three-tenths of any
relevant dose limit in respect of an employee aged 18
years or above.
Decay
The process of spontaneous transformation of a radionuclide.
The decrease in activity of a radioactive substance.
Designated Area
Designated Areas include Controlled and Supervised Areas.
Disposal
In relation to radioactive waste, dispersal or emplacement in
any medium without the intention of retrieval.
Dose
General term for quantity of radiation. See absorbed dose,
equivalent dose, and effective dose.
Dose Limit
Dose Limit in relation to persons of a specified class is the limit
on effective dose or equivalent dose in relation to a person of
that class.
Dose Rate
Dose Rate, in relation to a place, is the rate at which a person
or part of a person would receive a dose of ionising radiation
from external radiation if he were at that place being a dose
rate at that place averaged over one minute.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 24 of 34
Effective Dose
The quantity obtained by multiplying the dose equivalents to
various tissues and organs by the tissue weighting factor
appropriate to each and summing the products. Unit sievert,
symbol Sv. Frequently abbreviated to dose.
Equivalent Dose
The quantity obtained by multiplying the absorbed dose by a
weighting factor to allow for the different effectiveness of the
various ionising radiations in causing harm to tissue. Unit
sievert, symbol Sv. Usually the factor for gamma rays, X-rays
and beta particles is 1 but for alpha particles is 20.
External Radiation
External radiation, in relation to a person, is the ionising
radiation coming from outside the body of that person.
Internal Radiation
Internal radiation, in relation to a person, is the ionising
radiation coming from inside the body of that person.
Ionising Radiation
Gamma rays, x-rays or corpuscular radiations such as alpha
and beta, which are capable of producing ions either directly or
indirectly.
Local Rules
Set of working procedures written in accordance with the
Ionising Radiations Regulations, 1999, to enable work with
ionising radiations to proceed safely, and in accordance with
the Health and Safety at Work Act, 1974. Incorporating
Contingency Plans.
LSA Scale
Inorganic based chemical scale produced in conjunction with
oil and gas production and containing low levels of naturally
occurring radioactive material.
Non-ionising radiation
Radiation that does not produce ionisation in matter. Examples
are ultraviolet radiation, light, infrared radiation, and radio
frequency radiation.
NORM
Naturally Occurring Radioactive Material produced with oil and
gas deposits within process equipment.
Overexposure
Any exposure of a person to ionising radiation to the extent
that the dose received by that person causes a dose limit
relevant to that person to be exceeded or causes a proportion
of a dose limit relevant to any employee to be exceeded.
Practice
Practice means work involving:
1. The production, processing, handling, use, holding,
storage, transport or disposal of radioactive substances;
or
2. The operation of any electrical equipment emitting
ionising radiation and containing components operating
at a potential difference of more than 5Kv,
that can increase the exposure of individuals to radiation from
an artificial source, or from a radioactive substance containing
naturally occurring radionuclides that are processed for their
radioactive, fissile or fertile properties.
Radiation
The process of emitting energy as waves or particles.
Radiation accident
Accident where immediate action would be required to prevent
or reduce the exposure to ionising radiation of employees or
any other persons.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 25 of 34
Radiation control
Obtaining information about radiation state in the organisation,
in the environment and of the level of exposure to radiation
(includes dosimetric and radiometric control)
Radiation Protection
Person or body consulted in accordance with the Ionising
Adviser
Radiations Regulations, 1999, to give advice on radiation
protection.
Radiation Protection
Person appointed in accordance with the Ionising Radiations
Supervisor
Regulations, 1999 who is responsible for day-to-day
supervision of work with ionising radiation.
Radioactive Material
Substance in any aggregated state containing active
radionuclids
Radioactive Waste
Waste material containing radionuclides. Frequently
categorised, in the nuclear power industry, according to
activity content and other criteria, as low level, intermediate
level, and high-level waste.
Radioactivity
The property of radionuclides of spontaneously emitting
ionising radiation.
Radionuclid source
Source of ionising radiation containing radionuclid or a mixture
of radionuclids
Risk Assessment
Assessment that must be carried out in accordance with the
Ionising Radiations Regulations, 1999. Forms basis of
Contingency Plans. See Local Rules.
Source of ionising
Radioactive substance or device emitting or capable of
radiation
emitting ionising radiation
Sealed Source
Radiation source containing a radioactive material and
constructed to certain standards to prevent loss of that
material.
Unsealed Radioactive
Radioactive material not in the form of a sealed source, e.g.
Materials
gas, liquids or solid powder.
Waste Management
The control of radioactive waste from creation to disposal.
Written System of Work
A written method of work that permits non-classified workers
who to enter a controlled area.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 26 of 34
Appendix B
Written System of Work
1.
This written system of work applies to all non-classified workers who are
required to enter controlled areas.
2.
Before work begins in a controlled area, each individual worker must be given
a copy of the written system of work form attached below. The RPS is
responsible for ensuring the details of the form are completed.
3.
No non-classified person may enter a controlled area where the external dose
rate is more than 30 microsieverts per hour without reference to the radiation
protection adviser.
4.
No non-classified person may work in controlled areas for more than 200
hours in any calendar year.
5.
No person will remain in a controlled area for longer than is necessary.
6.
No person will enter a controlled area unless a Permit to Work has been
issued. This Permit to Work shall include the following details:
 A description of the work to be done
 The precautions to be used to minimise the effects of any hazard
 A copy of the relevant local rule
 The period of time for which the permit is valid.
7.
The Permit to Work will be signed by the Area Authority and countersigned by
the RPS.
8.
The following conditions will apply when the controlled area has been
established because of the presence of uncontained radioactive material:
 All persons entering the controlled area will use the appropriate personal
protective equipment.
 Washing, changing and monitoring facilities will be provided as close as
reasonably practicable to the exit from the controlled area.
 Eating, drinking, smoking and chewing gum are prohibited in the
controlled area.
 Minor cuts, grazes etc. must be covered with a suitable waterproof
dressing before entry to the controlled area. Any cuts received in the
controlled area must be reported to the RPS and appropriate first aid
treatment obtained.
 All reasonably practicable steps will be taken to eliminate the production
of airborne radioactive material and to control surface contamination to
prevent the spread of contamination outside the controlled area.
9.
The RPS will frequently carry out radiation dose rate and contamination
measurements in and around the controlled area to ensure the precautions in
place are effective.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 27 of 34
Written System of Work
Name of Worker_______________________________________
Radiation dose for year to date _____________ mSv
(confirmed by RPS)
Time spent in controlled areas this year____________ hours (confirmed by RPS)
Description of Work Area:
____________________________________________
Brief Description of Work:
____________________________________________
___________________________________________
Permit to Work Reference
____________________________________________
This area has been designated as a Controlled Area. The radiation protection
supervisor for this area is _______________________________.
The maximum radiation dose rate in this area is _________________ microsieverts
per hour.
The average level of surface contamination in this area is _________________
Becquerels per cm2.
While in this area you must use the protective equipment selected by the radiation
protection supervisor. You will be instructed in the use of any equipment with which
you are not familiar. You must not eat, drink or smoke in the controlled area. Any cuts
must be covered.
Any contaminated clothing must be left inside the controlled area. You will be
monitored for contamination when you leave the controlled area. You should then go
to the locker room and wash before eating. The radiation protection supervisor must
monitor any tools or equipment before being removed from the controlled area.
Contaminated equipment must be suitably bagged or wrapped and labelled before
being removed from the controlled area.
The log sheet on the other side of this form will be kept to record each time you enter
and leave the controlled area. You must make sure this is completed every time you
enter and leave the area.
Issued by __________________________________ (RPS)
Date __________
I understand and will comply with the conditions contained in this written system of
work:
Signed __________________________ Print
_________________
Date
__________________________
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 28 of 34
Record of Entries into Controlled Areas
Date
Time of Entry
Time of Exit
Time Spent in
Free of
Initialled
Controlled
Contamination
by RPS
Area
(1)
(3)
Yes/No (2)
Total Time in
Area (hours)
(1) Rounded up to nearest half hour.
(2) All contamination MUST be removed before worker can leave the area.
(3) RPS or appointed deputy.
On completion of the work one copy of this form is sent to the worker’s
employer and one is retained on the installation for two years.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Management of Radioactive Materials and Radiation Generators
Page 29 of 34
Appendix C
Contractors Checklist
Details of contractor using radioactive material
Contractor’s Name and Address
Contract Company’s RPA:
Contract Company’s RPS on site
Nature of work:
Has hazard assessment been seen and accepted?
Yes No N/A
Valid Registration Seen
Yes No N/A
Valid Authorisation Seen
Yes No N/A
Local Rules Seen and Acceptable
Yes No N/A
Notification Given to HSE
Yes No N/A
Are Workers classified?
Yes No
Is Personal Dosimeter Available?
Yes No
Is Functioning Dose rate Meter Available?
Yes No N/A
Test certificate seen?
Yes No
Is Functioning Contamination Meter Available?
Yes No N/A
Test certificate seen?
Yes No
Is Neutron Monitor Available?
Yes No N/A
Test certificate seen?
Yes No
Source Movement Notification Details
Container/Packing Adequate?
Yes No
Are Source Leakage Tests Available?
Yes No N/A
Intended Source Storage Location on site
Responsible Person when Contractor
not on site
Details of Emergency Equipment/
Warning Notices
Special Precautions
........................................................…
Comments:
Signed
Facilities RPS…
Contractor
......................................………
Print
…….. Print
………
Date
……. Date
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Title: Management of Radioactive
Doc No: UNIF-HSE-PRO-205-C1
Materials and Radiation
Rev No: 01
Page 30 of 34
Generators Procedure
Dated: October, 2004
Originating Dept: HSE
Appendix D
Sealed Radioactive Source Management & Accountancy Register
Local I.D. No.
(if applicable)
Distinguishing
Nature of
Radioactive
Date
Date of
Element
Strength
Measured
Receipt
Mark No
Address of Normal Location of Source
Initial Date Source Accounted For.
Year:
Location
Date
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
Date
Dept/Area
Site
Used for
Source Movements/Inspection Comments
Date and
New Location of Source
Mover.
Time
(Inspector:
Signature)
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Title: Management of Radioactive
Doc No: UNIF-HSE-PRO-205-C1
Materials and Radiation
Rev No: 01
Page 31 of 34
Generators Procedure
Dated: October, 2004
Originating Dept: HSE
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Title: Management of Radioactive
Doc No: UNIF-HSE-PRO-205-C1
Materials and Radiation
Rev No: 01
Page 32 of 34
Generators Procedure
Dated: October, 2004
Originating Dept: HSE
Appendix E
References
The Ionising Radiations Regulations 1999 SI 1999/3232 Stationery Office
1999.
Work with Ionising Radiation. Ionising Radiations Regulations
1999.
Approved Code of Practice and Guidance HSE Books (L121) 2000.
Health and Safety at Work etc. Act 1974 HMSO 1974.
”Council Directive 96/29 Euratom of 13 May 1996 laying down basic safety
standards for the protection of health of workers and the general public
against the dangers arising from ionising radiation” Official Journal of the
European Communities 1996 39(L159) 1-114.
“Council Directive 97/43 Euratom of 30 June 1997 on health protection of
individuals against the dangers of ionising radiation in relation to medical
exposure” Official Journal of the European Communities 1997 40 (L180).
Radioactive Substances Act 1993 HMSO 1993.
Radiation doses - assessment and recording IRIS (rev) HSE Books 2000.
Radiation protection - sealed radioactive sources - leakage test methods ISO
9978: 1992.
Atomic Energy and Radioactive Substances: Radioactive Material (Road
Transport) (Great Britain) Regulations 1996 HMSO 1996.
Packaging, Labelling and Carriage of Radioactive Material by Rail
Regulations 1996 SI 1996/2090 HMSO 1996.
Reporting of Injuries, Diseases and Dangerous Occurrences Regulations
1995 SI 1995/3163 HMSO 1995.
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Title: Management of Radioactive
Doc No: UNIF-HSE-PRO-205-C1
Materials and Radiation
Rev No: 01
Page 33 of 34
Generators Procedure
Dated: October, 2004
Originating Dept: HSE
Appendix F
Correlation
Between SI system of units and Off-system Units of Activity and
Radiation Field Features
Value and its
Name and symbol of units
Relation between the units
symbol
SI unit
Off-system unit
Activity (А)
Becquerel (Bq)
Curie (Ci)
1 Ci = 3.700 *1010 Bq;
equals to one
1 Bq = 1 dec../s;
disintegration per
1 Bq = 1 dec../s = 2.703 * 10-11
second (dec./s)
Ci
Absorbed Doze
Gray (Gy) equals to
Rad (rad)
1 rad = 100 erg/g = 1*10-2 J/kg
(D)
one joule per
=
kilogram (J/kg)
= 1*10-2 Gy;
1 Gy = 1 J/kg;
1 Gy = 1 J/kg = 104 egr/g = 100
rad.
Equivalent Doze
Sievert (Sv) equals to
Rem (Rem)
1 Rem = 1 rad/Q = 1*10-2 J/kg /
(H)
one gray per Quality
Q =
coefficient
= 1* 10-2 Gy/Q = 1*10-2 Sv;
[1 Gy/Q = 1 (J/kg)/Q]
1 Sv = 1 Gy/Q = 1 J/kg/Q =
100 rad/Q=
= 100 Rem.
Equivalent Doze
Sievert per second
Rem per
1 Rem/s = 1 *10-2 Sv/s;
rating(Н)
(Sv/s)
second (Rem/s)
1 Sv/s = 100 Rem/s
Exposure Doze
Coulomb per
Roentgen (R)
1 R = 2.58*10-4 C/kg (exact);
(Х)
kilogram (C/kg)
1 C/kg = 3.88 103 R
(approximately)
Kerma (К)
Gray (Gy) equals to
Rad (rad)
1 rad = 100 erg/g = 1*10-2 J/kg
one joule per
=
kilogram (J/kg)
= 1*10-2 Gy;
1 Gy = 1 J/kg;
1 Gy = 1 J/kg = 104 egr/g = 100
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Title: Management of Radioactive
Doc No: UNIF-HSE-PRO-205-C1
Materials and Radiation
Rev No: 01
Page 34 of 34
Generators Procedure
Dated: October, 2004
Originating Dept: HSE
rad.
Revision/Review Log
Revision Date
Authority
Custodian
Revision Details
20 October 2004
Alan McNulty
Esmira Akhundova
Initial Issue
Control Tier:
<<2>>
Revision Date: <<20 October 2004e>>
Document Number: << AZSPU-HSSE-DOC-00058-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Man Riding Operations
Page 1 of 29
Procedure for Man Riding Operations
AZSPU-HSSE-DOC-00059-2
This number supersedes UNIF-HSE-PRO-117-C1
Authority:
CHSSE Manager
Custodian:
Man Riding Operations Technical Authority
Scope:
AzSPU
Document
Administrator:
Document Asset Technician Name
Issue Date:
05 October 2004
Issuing Dept:
CHSSE
Revision Date:
14 September 2007
Control Tier:
2
Next Review
14 September 2008
Date:
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00059-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Man Riding Operations
Page 2 of 29
TABLE OF CONTENTS
1
INTRODUCTION
4
1.1 PURPOSE
4
1.2 SCOPE
4
1.3 LEGISLATION & STANDARDS
4
1.4 COMPANY REQUIREMENTS
5
1.5 STOPPING UNSAFE WORK
5
1.6 DEVIATIONS
5
1.7 DOCUMENT REVIEW
5
1.8 SSOW SPECIFIC CROSS REFERENCE
5
1.9 LANGUAGE FACILITATION
6
1.10 PROCEDURE SUMMARY
6
2
DEFINITIONS
6
3
RESPONSIBILITIES
6
3.1 SITE MANAGER (SM)/SITE CONTROLLER (SC)/OFFSHORE INSTALLATION MANAGER (OIM) 6
3.2 PERSONNEL SUPERVISING MAN RIDING OPERATIONS
7
3.3 CRANE / FORKLIFTOPERATORS
7
3.4 BANKS-MAN
7
3.5 BASKET PASSENGERS
8
4
MAN BASKET CONSTRUCTION
8
4.1 CONSTRUCTION
8
4.2 FROG / BILLY PUGH
9
4.3 RIDING BELTS
10
4.4 FORKLIFT CAGES / INTEGRATED WORKING PLATFORMS
10
5
INSPECTION AND MAINTENANCE
11
6
CRANE / WINCH SPECIFICATIONS FOR MANRIDING
12
6.1 INSPECTION, EXAMINATIONS AND CERTIFICATION
12
6.2 CRANE OPERATING REQUIREMENTS
12
6.3 WINCH REQUIREMENTS
13
6.4 FORKLIFT REQUIREMENTS
13
7
COMMUNICATIONS
14
7.1 HAND SIGNALS FROM RIDING BELTS
15
7.2 FORKLIFT / INTEGRATED WORKING PLATFORM COMMUNICATIONS
15
8
RISK ASSESSMENT AND PLANNING
15
8.1 RISK ASSESSMENT
15
8.2 PLANNING
15
9
HARNESSES & SAFETY EQUIPMENT
16
9.1 HARD HATS
16
10 RESCUE PLANS
16
11 MAN BASKET TRANSFER OPERATING GUIDELINES
17
11.1
OPERATING REQUIREMENTS
17
11.2
SUITABILITY OF VESSELS FOR TRANSFER OPERATIONS
19
11.3
WEATHER CONDITIONS
19
11.4
COMMUNICATIONS
19
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00059-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Man Riding Operations
Page 3 of 29
11.5
SAFETY EQUIPMENT AND RESCUE PROCEDURES
19
11.6
TRAINING
19
11.7
PRE-TRANSFER OPERATIONS
19
11.8
TRANSFER OPERATIONS
20
11.9
POST-TRANSFER OPERATIONS
20
12 APPENDICES
20
12.1
APPENDIX A: PRE START CHECKLIST
21
12.2
APPENDIX B: PROCEDURE SUMMARY
22
12.3
APPENDIX C: FEEDBACK & IMPROVEMENT SUGGESTIONS
27
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00059-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT
Procedure for Man Riding Operations
Page 4 of 29
1 INTRODUCTION
Man-riding operations should only take place if no other means can be found to carry
out the task.
Man-riding operations shall be conducted under a Permit to Work, with a Level 2 Risk
Assessment conducted and in line with a site
/ installation specific procedure
containing a rescue plan.
1.1 PURPOSE
The purpose of this Safe System of Work is to provide information and guidance on
the safe use of man-riding operations and baskets for transferring personnel between
vessels and structures.
Information is provided on individual responsibilities, planning and risk assessment,
basket transfer use, and the maintenance and inspection of associated equipment.
1.2 SCOPE
The contents of this procedure are applicable to all BP owned and managed sites /
installations in Azerbaijan and Georgia. Contractors working on BP owned or
managed sites / installations are also responsible for alignment with this procedure.
This document does not replace the procedures prepared and adopted by specialist
contractors. Neither does it supersede any national and local regulatory
requirements.
This procedure contributes to compliance with the “HSE expectations” contained in
“getting HSE right”, the „Golden Rules of Safety‟ and the Control of Work (CoW)
standard that the Hazards associated with BP activities are identified and that the
risks are assessed and managed.
All guidelines contained shall be regarded as the minimum requirements for BP
owned or managed sites / installations in Azerbaijan and Georgia.
1.3 LEGISLATION & STANDARDS
The aim of this Safe System of Work is to achieve ”no accidents”, “no harm to
people” and “no damage to the environment”. To achieve this aim, this SSOW
complies with National Legislation, the terms of the Production Sharing Agreement
(PSA) and mandatory BP Standards.
The best International Oil Industry practice and relevant goal setting legislation have
been adopted to reduce the level of risk to as low as reasonably practicable and
therefore well below that mandated by applicable statutory laws and regulations.
In the absence of local regulations, BP Group Standards will apply. In addition,
appropriate UK and US regulations and industry best practice have been considered
in setting suitable goals and targets.
The equipment to which this document applies includes, but is not necessarily limited
to:
 Man Baskets / Work Baskets / FROG / Billy Pugh
Control Tier:
<<2>>
Revision Date: 14 Sept 2007
Document Number: << AZSPU-HSSE-DOC-00059-2>>
Print Date: 7/24/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE
CONTROLLED VERSION OF THIS DOCUMENT CAN BE FOUND AT

 

 

 

 

 

 

 

Content      ..     33      34      35      36     ..