Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 1

 

 

PART 1 

ROADS 

TABLE OF CONTENTS 

General Requirements 

Earthworks 

Pavement 

Concrete Works 

Reinforcing Steel 

Masonry 

Incidental Construction 

Traffic Markings and Signs 

Traffic Control System 

10 

Lighting and Electrical Distribution Works 

11 

Utilities 

12 

Stormwater Drainage 

13 

Landscaping and Irrigation 

 

 

 

 

 

 

STANDARD CONSTRUCTION SPECIFICATIONS 

PART 1 

ROADS 

 

CHAPTER 1 - GENERAL REQUIREMENTS 

 

 

 

 

 

 

 

SECOND

  

EDITION 

SEPTEMBR

 

2020

 

G

ENERAL 

R

 

 

First Edition -January 2018 

 

 

Chapter 1: General Requirements

 

T

ABLE OF 

C

ONTENTS

 

Table of Contents............................................................................................................................. i

 

List of Tables ................................................................................................................................. vii

 

1

 

General Requirements ...................................................................................................... 1-1

 

1.1

 

Introduction to the Standard Construction Specifications ............................................... 1-1

 

1.1.1

 

Purpose and Scope ................................................................................................ 1-1

 

1.1.2

 

Application of This Document ................................................................................. 1-1

 

1.1.3

 

How to Use This Document .................................................................................... 1-2

 

1.1.4

 

Content and Format ................................................................................................ 1-2

 

1.1.4.1

 

Part 1 

– Roads ................................................................................................. 1-2

 

1.1.4.2

 

Part 2 

– Road Structures ................................................................................. 1-3

 

1.2

 

Abbreviations ................................................................................................................. 1-4

 

1.3

 

Codes, Regulations and Referenced Specifications ....................................................... 1-7

 

1.3.1

 

Definitions ............................................................................................................... 1-7

 

1.3.2

 

Reference Standards and Codes .......................................................................... 1-15

 

1.3.2.1

 

General .......................................................................................................... 1-15

 

1.3.2.2

 

Reference Standards and Codes Required in Chapter 1 ............................... 1-17

 

1.3.3

 

Equivalent Standards Acceptable ......................................................................... 1-18

 

1.3.4

 

Builder’s Codes..................................................................................................... 1-18

 

1.3.5

 

Governing Utility Departments and Agencies ........................................................ 1-18

 

1.4

 

Unit Prices ................................................................................................................... 1-19

 

1.4.1

 

Procedures for Unit Prices .................................................................................... 1-19

 

1.5

 

Metric Measurements .................................................................................................. 1-20

 

1.5.1

 

Use of Measurements ........................................................................................... 1-20

 

1.5.2

 

Coordination of Measurements ............................................................................. 1-20

 

1.5.3

 

Relationship of Measurements to Submittals ........................................................ 1-20

 

1.6

 

Work Restrictions ......................................................................................................... 1-20

 

1.6.1

 

Contractor’s Responsibility ................................................................................... 1-21

 

1.6.2

 

Program of Works ................................................................................................. 1-21

 

1.6.3

 

Site Logistics Plan ................................................................................................ 1-22

 

1.6.4

 

Plant, Equipment and Labour ................................................................................ 1-22

 

1.6.5

 

Limits and Access to and Use of Site .................................................................... 1-23

 

1.6.6

 

Land for Contractor’s Use ..................................................................................... 1-23

 

1.6.7

 

Excavated Materials and Debris ........................................................................... 1-24

 

1.7

 

Field Engineering ......................................................................................................... 1-24

 

1.7.1

 

Submittals ............................................................................................................. 1-24

 

1.7.2

 

Quality Assurance ................................................................................................. 1-24

 

1.7.3

 

Examination .......................................................................................................... 1-25

 

1.7.4

 

Laying-out of the Works ........................................................................................ 1-25

 

1.8

 

Project Utility Sources .................................................................................................. 1-26

 

1.8.1

 

Building Codes ..................................................................................................... 1-26

 

1.8.2

 

Government Bodies .............................................................................................. 1-26

 

1.9

 

Project Management and Coordination ........................................................................ 1-27

 

1.9.1

 

Details of Contractor’s Supervisory Staff ............................................................... 1-27

 

1.9.2

 

Use of Site ............................................................................................................ 1-28

 

1.9.3

 

Advertising ............................................................................................................ 1-28

 

1.9.4

 

Working Hours ...................................................................................................... 1-28

 

1.9.5

 

Work Schedule Notifications ................................................................................. 1-28

 

1.9.6

 

Adjoining Plant and Property................................................................................. 1-28

 

1.9.7

 

Temporary Work ................................................................................................... 1-29

 

1.9.8

 

Coordination ......................................................................................................... 1-29

 

1.9.8.1

 

General .......................................................................................................... 1-29

 

 

G

ENERAL 

R

 

 

 

1.9.8.2

 

Administrative Procedures ............................................................................. 1-29

 

1.9.8.3

 

Drawings ....................................................................................................... 1-30

 

1.9.8.4

 

Specifications ................................................................................................ 1-30

 

1.9.9

 

Work Plan ............................................................................................................. 1-30

 

1.9.10

 

Daily Report .......................................................................................................... 1-30

 

1.9.11

 

Plant Record ......................................................................................................... 1-30

 

1.9.12

 

Defective Work ..................................................................................................... 1-31

 

1.9.13

 

Representatives for Emergencies ......................................................................... 1-31

 

1.9.14

 

Maintaining Existing Facilities in Operation ........................................................... 1-31

 

1.9.15

 

Working Hours and Engineers Supervision ........................................................... 1-31

 

1.10

 

Construction Progress Documentation ......................................................................... 1-31

 

1.10.1

 

Submittals ............................................................................................................. 1-31

 

1.10.2

 

Project Schedule ................................................................................................... 1-32

 

1.10.3

 

Software ............................................................................................................... 1-32

 

1.10.4

 

Basis for Payment ................................................................................................. 1-32

 

1.10.4.1

 

General .......................................................................................................... 1-32

 

1.10.4.2

 

Non-Compliance ............................................................................................ 1-32

 

1.10.4.3

 

Errors and unrealistic and/or unreasonable logic ........................................... 1-32

 

1.10.5

 

Preliminary Critical Path Method ........................................................................... 1-32

 

1.10.6

 

Detailed Progress Schedule.................................................................................. 1-33

 

1.10.7

 

Progress Schedule Bar Chart ............................................................................... 1-33

 

1.10.7.1

 

General .......................................................................................................... 1-33

 

1.10.7.2

 

Format ........................................................................................................... 1-34

 

1.10.7.3

 

Contents ........................................................................................................ 1-34

 

1.10.8

 

Progress Schedule Using Critical Path Method ..................................................... 1-34

 

1.10.8.1

 

General .......................................................................................................... 1-34

 

1.10.8.2

 

Contents ........................................................................................................ 1-34

 

1.10.8.3

 

Network Graphical Display ............................................................................. 1-35

 

1.10.8.4

 

Schedule Report ............................................................................................ 1-35

 

1.10.9

 

Progress Quantity Charts ...................................................................................... 1-36

 

1.10.10

 

Progress of the Work ............................................................................................ 1-36

 

1.10.11

 

Narrative Progress Report .................................................................................... 1-37

 

1.10.11.1

 

Format .......................................................................................................... 1-37

 

1.10.11.2

 

Contents ....................................................................................................... 1-37

 

1.10.12

 

Progress Schedule Acceptance ............................................................................ 1-37

 

1.10.12.1

 

Engineer’s Acceptance ................................................................................. 1-37

 

1.10.12.2

 

Unacceptable Preliminary Progress Schedule ............................................... 1-38

 

1.10.12.3

 

Unacceptable Detailed Progress Schedule ................................................... 1-38

 

1.10.12.4

 

Narrative Report ............................................................................................ 1-38

 

1.10.13

 

Adjustment of Contract Dates ............................................................................... 1-38

 

1.10.13.1

 

Schedule contingency ................................................................................... 1-38

 

1.10.13.2

 

Float .............................................................................................................. 1-38

 

1.10.13.3

 

Claims based on Contract dates ................................................................... 1-38

 

1.10.14

 

Qualifications for Personnel Responsible for Schedules ....................................... 1-39

 

1.11

 

Submittal Procedures ................................................................................................... 1-39

 

1.11.1

 

Definitions ............................................................................................................. 1-39

 

1.11.2

 

Submittal Procedure ............................................................................................. 1-40

 

1.11.3

 

Product Data Submittals ....................................................................................... 1-43

 

1.11.4

 

Shop Drawing Submittals ...................................................................................... 1-43

 

1.11.5

 

Sample Submittals ................................................................................................ 1-44

 

1.11.6

 

Operations and Maintenance Manual Submittals .................................................. 1-44

 

1.11.7

 

Certificates and Affidavits ..................................................................................... 1-44

 

1.11.8

 

Miscellaneous Submissions .................................................................................. 1-45

 

1.11.8.1

 

Manufacturers’ Guarantees and Warranties ................................................... 1-45

 

1.11.8.2

 

Work Plans .................................................................................................... 1-45

 

1.11.8.3

 

Staging and Detour Plans .............................................................................. 1-45

 

1.11.8.4

 

Submittal Schedule ........................................................................................ 1-45

 

 

Purpose of these boreholes shall be to determine the character, thickness and stratification of the 
subsurface material, the relative density and permeability of granular materials, coring of rock and 
such other data as may be required by the Engineer to determine the adequacy of the subsurface 
material. 

a.  Depth of Boreholes

Depth of such boreholes and the depth at which core samples shall be taken shall be as directed by 
the Engineer.  

The  depth  of  the  boreholes  shall  be  determined  according  to  the  type  and  characteristics  of  the 
subsurface  soil.  If  no  rock  is  encountered,  boreholes  shall  be  driven  to  a  depth  of  20  metres  in 
predominantly gravelly-sandy-silty soils and to 30 metres in soft clay soils or soils with a low bearing 
capacity where piling may be required, all in accordance with the directions and to the satisfaction 
of  the  Engineer.  If  rock  is  encountered  before  reaching  the  above  depths,  the  borehole  shall 
penetrate  at  least  10  metres  in  the  rock.  If  the  thickness  of  the  rock  is  less  than  10  metres,  the 
borehole shall be continued as specified above and/or as directed by the Engineer. 

b.  Drilling of Boreholes

Boreholes or test borings shall be advanced between sampling intervals by driving a steel casing to 
such depth below the ground surface. Casing diameter shall be as required to facilitate removal of 
the soil sampling or rock coring that is required. 

Boreholes  shall  be  augered  or  core  drilled  as  directed  by  the  Engineer.  Augered  boreholes  shall 
comply with the requirements of ASTM D1452 and as specified herein. Core drilled boreholes shall 
comply  with  ASTM  D2113  with  double  tube,  swivel-type,  M-design  core  barrels  and  as  specified 
herein.  Casing at boreholes shall be NX size, with outside diameter of 89 mm and inside diameter 
of 76.2 mm. 

The boring shall be performed with continuous coring and the cores extracted shall be carefully kept 
in proper core boxes so that the lithology can be recorded as accurately as possible. A preliminary 
description of the core shall be made when it is extracted. Then these descriptions, together with 
technical operational details shall be entered in the daily log which shall be available for inspection 
by the Engineer at all times. 

c.  Borehole Equipment and Methods

Method  and  the  equipment  to  be  used  for  advancing  the  borehole  shall  be  submitted  by  the 
Contractor to the Engineer for approval. Casing shall be driven without the use of wash water unless 
the Engineer specifically approves simultaneous washing and driving.  Washing, spudding or drilling 
ahead of the casing will not be permitted. 

Between  the  depth  intervals  at  which  sampling  is  accomplished  as  hereinafter  specified,  loose 
material within the casing shall be removed by the usual wash pipe method or other suitable means. 
No  downward  directed  jets  will  be  permitted.    Casing  shall  remain  in  the  hole  until  the  Engineer 
authorizes its removal. 

To prevent caving and mixing strata, casing or drilling mud material (bentonite) shall be used when 
boring through any stratus which is not sufficiently cohesive to stand firmly without it. 

Use  of  drilling  mud  to  stabilize  a  borehole  will  be  permitted  only  if  the  Engineer  deems  it  is  not 
detrimental to pumping tests or groundwater observations. 

d.  In-Situ Testing and Sampling

Standard  Penetration  Tests  (S.P.T.)  is  to  be  performed  during  the  course  of  the  boring  at  1.0m 
intervals or at every change of stratum.  

Pocket penetrometer and/or vane test measurements shall be performed on all suitable cohesive 
samples immediately after their sampling and before waxing. 

Disturbed samples shall be taken from the top of each stratum from the material contained within 
the standard penetration tool after the S.P.T. has been carried out, and from the cutting shoe of the 

 

undisturbed sampler after the undisturbed samples have been taken. Each soil samples shall be 
stores in a container of glass, plastic or other approved material, fitted with an airtight cover and 
waxed immediately being taken from the boreholes. Each container shall be numbered and labelled 
in such a way that the sample can be easily be identified with the boreholes, the soil stratum, the 
depth from which it was taken and the date on which it was taken  

Undisturbed samples should be taken in cohesive soils including mixed soils. Undisturbed samples 
shall be taken from the most significant beds using appropriate means. The internal diameter of the 
sampler shall be about 10cm and the useful length at least 50cm. The samplers shall be in good 
condition and therefore shall be no signs of oxidation on the inner walls or damage to the base.  

After the samples have been taken the ends shall be coated with wax, after having removed the 
loose material. The containers shall then be sealed and clearly marked as specified for the disturbed 
samples.  A careful description shall be made of the undisturbed samples in the laboratory when 
they are extracted from the container and before starting the required laboratory testing. 

Samples and rock cores, immediately upon recovery, shall be placed in containers as approved by 
the  Engineer,  identified  as  specified  herein  and  delivered  to  the  Site  Laboratory  included  under 
Section 1.19.7 of Chapter 1, General Requirement, of these Standard Specifications. 

Each sample or rock core shall be identified and include the following information: 

1.  Location of borehole.

2.  Date when sample was taken.

3.  Boring number.

4.  Surface elevation.

5.  Name of driller.

6.  Description and length of casing, if any.

7.  Depth of bottom of boring.

8.  Depth from which the sample or rock core was taken.

Testing of all samples and rock cores will be performed by the Engineer in the Site Laboratories. 
Contractor shall furnish the Engineer with all pertinent data as may be required relative to the sample 
so as to aid the Engineer in his testing program. 

e.  Water Levels

All water levels encountered in the boreholes shall be recorded and a check shall be made of the 
static level after boring has been completed. 

f.  Borehole Logs

Boreholes logs shall be supplied to the Engineer as soon as possible after the borings have been 
completed. They shall be in such a form as to indicate the location relative to any of the reference 
points,  the  description  and  thickness  of  each  type  of  soil,  the  level  of  the  lower  contact  of  each 
stratum  relative  to  the  said  level,  the  level  of  the  water  table  if  any,  and  the  position  and  record 
number of every sample taken. The records are to be written in English and the descriptions of the 
layers have to be in accordance with the International Standards. Furthermore, the records shall 
include the results of standard penetration tests and of pocket penetrometer and/or vane tests and 
rock core descriptions (total core recovery, solid core recovery and rock quality designation).  

The site investigation works shall not be regarded as complete until all boreholes logs have been 
submitted to the Engineer and approved by him. 

g.  Laboratory Tests

As a minimum, the following laboratory tests are to be carried out: 

i. 

For disturbed samples:

 

  Grading  and  Atterberg  Limits  (LL  and  PL)  on  representative  samples  from  each

borehole as requested by the Engineer. 

ii. 

For undisturbed samples:

  Grading by sieves and or by sedimentation,  Atterberg Limits (LL and PL), Natural

Moisture Content and Bulk Density on all samples. 

  Consolidated undrained triaxial test (3 tests at different confining pressures on three

1-1/2" diameter specimens from each sample) on samples selected by the Engineer.

  Oedometer consolidation tests on samples selected by the Engineer.

iii. 

Unconfined compression tests on rock samples.

iv. 

Corrosion effect on concrete of water and soils.

The results of the tests shall be given to the Engineer on approved forms. All measurements shall 
be expressed in the decimal system.  

The  above  laboratory  tests  provide  a  general  guideline.  Additional  testing  or  elimination  of  some 
tests may be requested by the Engineer 

h.  Final Reports

On completion of all laboratory testing a final report in triplicate shall be submitted to the Engineer. 

This final report shall include a generalized subsoil profile and all borehole logs, soil identification, 
in-situ and laboratory testing, observations and recommendations on the type of foundation and on 
safe bearing capacity of the foundation soils and where piles are advised recommendations on their 
safe bearing capacity. 

2.2 

Clearing and Grubbing 

2.2.1 

Description 

This  section  describes  clearing  of  the  site,  grubbing,  and  removal  of  topsoil  necessary  for 
construction of the work covered by the Contract, in accordance with these specifications. 

2.2.2 

Construction Requirements 

No clearing and grubbing shall be performed unless approved by the Engineer. Contractor shall take 
all necessary precautions to prevent damage to structures and other private or public property. 

Any unauthorised damage to, or interference with, private or public property, including trees, shall 
be repaired to the satisfaction of the Engineer and the owner, at the Contractor’s sole expense. 

2.2.2.1 

Areas to be Cleared, Grubbed, and Removed of Topsoil 

Areas  to  be  cleared,  grubbed,  and  removed  of  topsoil  shall  be  in  accordance  with  the  particular 
specifications and Contract plans, or as directed by the Engineer. In general, clearing and grubbing 
shall be performed to 3 m outside the top of the fill slope and 3 m outside the top of the cut slope, to 
include the following areas: 

1.  To be excavated, including areas staked for slope treatment

2.  Where  utility,  drainage,  and  subdrainage  trenches  shall  be  dug,  unsuitable  material

removed, or structures built 

3.  Upon which embankments shall be placed

4.  Wherever road, parking, and pedestrian pavement is to be placed

No trees that fall between the worksite and the limits of clearing and grubbing shall be removed or 
damaged without the written authorisation of the concerned authority. Contractor shall submit shop 
drawings,  depicting  the  existing  trees  within  the  limits  of  the  woks,  clearly  indicating  those  to  be 
removed  and  those  to  be  retained,  for  the  Engineer’s  approval  and  as  per  the  tree  removal 
management plan as may be contained in the Contract Documents. Individual trees designated by 
the Engineer shall be left standing and uninjured. 

 

 

 

 

 

 

 

 