Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 78

 

  Главная      Manuals     Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     76      77      78      79     ..

 

 

 

Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 78

 

 

Page 8-94 

Concrete Slope Protection

Protection of Facilities – During the construction, the Contractor shall protect all 
retaining walls, columns and Structures from concrete splash or overspray. Suitable 
covering shall be provided if such protection is deemed necessary by the Engineer.

Test Cylinders – Two test cylinders shall be made for each full day’s operation. The 
Contractor shall furnish cylinders 6 inches in diameter and 12 inches high made of ¾-inch 
mesh hardware cloth. The test cylinder shall be filled with concrete by utilizing the same 
pneumatic application described above.

The cylinders shall develop a minimum compressive strength of 3,000 psi at the age of 
28 days.

8-16.4 Measurement

Measurement for concrete slope protection will be by the square yard and will include the 
actual area of the slope covered excluding the footings. The area will be computed on the 
basis of slope measurements.

8-16.5 Payment

Payment will be made for the following Bid item when included in the Proposal:

“Conc. Slope Protection”, per square yard.

Impact Attenuator Systems 

8-17

8-17 

Impact Attenuator Systems

8-17.1 Description

This Work consists of furnishing, constructing, repairing, and removing permanent and 
temporary impact attenuator systems selected from the approved list shown in the Plans.

8-17.2 Materials

Materials for inertial sand barrel systems shall be provided and installed in conformance 
with the manufacturer’s instructions and specifications.

Undamaged sand barrel impact attenuators that have been previously utilized may be 
utilized in a temporary impact attenuator array only, if inspected and approved by the 
Engineer prior to use.

8-17.3 

Construction Requirements

The assembly and installation of all attenuator systems, except those utilizing sand 
barrels, shall be supervised at all times by either a manufacturer’s representative or an 
installer who has been trained and certified by the manufacturer of the system within the 
last 5 years and for the specific system(s) being installed. If the supervision is provided by 
a trained installer, a copy of the installer certification shall be provided to the Engineer 
prior to installation.

Assembly and installation shall be in accordance with the manufacturer’s 
recommendations. This Work shall include the connection to a concrete barrier, bridge 
abutment or a transition section identified in the Plans, construction of a steel reinforced 
concrete pad or concrete backup, and anchorage to the pavement, if required by the 
manufacturer’s assembly and installation procedures.

The manufacturer’s representative or certified installer shall complete a manufacturer’s 
attenuator assembly/inspection checklist for each attenuator installed. The original 
completed checklist, signed by the manufacturer’s representative or certified installer, 
shall be provided to the Engineer on the same day that the attenuator installation is 
completed.

The Contractor shall have a complete set of replacement parts on the jobsite for each 
type of temporary impact attenuator in use on the project and shall repair all damaged 
impact attenuators immediately.

When the Engineer determines that a temporary impact attenuator is no longer needed, 
then the Contractor shall remove that attenuator from the project. The removed 
equipment shall remain the property of the Contractor.

Permanent impact attenuators shall meet the crash test and evaluation criteria of the 
Manual for Assessing Safety Hardware (MASH), except as otherwise noted in the Plans or 
Special Provisions.

Page 8-96 

Impact Attenuator Systems

8-17.4 Measurement

Temporary and permanent impact attenuators will be measured per each for each 
installation. Only the maximum number of temporary impact attenuators installed at any 
one time within the project limits will be measured for payment.

Resetting impact attenuators will be measured per each for each installation that is 
adjusted or reset to a new location on the project. The Contracting Agency will not 
measure resetting impact attenuators when it is for the benefit of the Contractor’s 
operations.

8-17.5 Payment

Payment will be made for the following Bid items when they are included in the Proposal:

“Temporary Impact Attenuator”, per each.
The unit Contract price for “Temporary Impact Attenuator” shall be full pay for all 
Work associated with the installation, maintenance, and the final removal of the 
temporary impact attenuator.
“Permanent Impact Attenuator”, per each.
The unit Contract price for “Permanent Impact Attenuator” shall be full pay for all 
Work associated with furnishing, installing and all other costs involved with installing 
the impact attenuator in accordance with the manufacturer’s recommendations.
“Resetting Impact Attenuator”, per each.
The unit Contract price for “Resetting Impact Attenuator” shall be full pay for 
all Work associated with the removing, transporting, and resetting an impact 
attenuator.
If an impact attenuator is damaged by a third party, repairs shall be made in 
accordance with 

Section 1-07.13(4)

 under the Bid item “Reimbursement For Third 

Party Damage”. No payment will be made for repair of impact attenuators damaged 
by the Contractor’s operations.

8-18 

Mailbox Support

8-18.1 Description

This Work consists of removing, maintaining in temporary locations during construction, 
and reinstalling in permanent locations, all mailboxes affected by Construction work in 
accordance with the Plans, these Specifications, and the 

Standard Plans

.

8-18.2 Materials

Materials shall meet the requirements of the following sections:
 

Steel Posts 

9-32.1

 

Bracket, Platform, and Anti-Twist Plate 

9-32.2

 

Type 2 Mailbox Support 

9-32.7

 

Timber Sign Posts 

9-28.14(1)

 

Fasteners 

9-32.5

 

Snow Guard 

9-32.6

 

Concrete Base 

9-32.8

 

Steel Pipe 

9-32.9

 

U-Channel Post 

9-32.10

Mailboxes will be furnished by others.

8-18.3 

Construction Requirements

During construction the mailboxes shall be moved to a temporary location where their 
usefulness will not be impaired. The boxes shall be reinstalled at the original location or at 
locations determined by the Engineer in accordance with the 

Standard Plans

.

The existing mailboxes shall be reinstalled on new mailbox supports, in accordance with 
the 

Standard Plans

within 24 hours of being removed. The existing mailbox posts shall be 

removed and disposed of off the project site.

Excavation for new mailbox supports shall be backfilled with adjacent native material and 
compacted to the satisfaction of the Engineer.

When a newspaper tube is attached to an existing mailbox installation, it shall be removed 
and attached under the mailbox on the new support, to the satisfaction of the Engineer.

8-18.3(1)  Type 3 Mailbox Support

The concrete base shall be constructed using commercial concrete, with the pipe set to 
the dimensions shown in the 

Standard Plans

The base shall be crowned so as to shed 

water. The concrete may be mixed on the jobsite as specified in 

Section 6-02.3(4)B

.

The U-channel post may be driven in place provided the method of driving does not 
damage the post.

Mailbox Support 

8-18

Page 8-98 

Standard Plans

. In which case, the manufacturer’s recommendations concerning 

installation shall be followed; however, the mailbox itself shall be positioned on the 
Roadway according to the dimensions shown in the 

Standard Plans

.

8-18.4 Measurement

Mailbox supports will be measured by the unit for each kind of mailbox support furnished 
and installed in its permanent location.

8-18.5 Payment

Payment will be made for the following Bid item when it is included in the Proposal:

“Mailbox Support, Type ____”, per each.
All costs for the snow guard shall be included in the unit Contract price per mailbox 
support involved.

8-18 

Mailbox Support

8-19 Vacant

Vacant 8-19

Page 8-100 

Illumination, Traffic Signal Systems, Intelligent Transportation Systems, and Electrical

8-20 

Illumination, Traffic Signal Systems, Intelligent 

Transportation Systems, and Electrical

8-20.1 Description

This Work consists of furnishing, installing and field testing all materials and equipment 
necessary to complete in place, fully functional system(s) of any or all of the following 
types including modifications to an existing system all in accordance with approved 
methods, the Plans, the Special Provisions, and these Specifications:
1.  Traffic Signal System
2.  Illumination System
3.  Intelligent Transportation Systems (ITS)

Unless otherwise noted, the location of signals, controllers, standards, and appurtenances 
shown in the Plans are approximate; and the exact location will be established by the 
Engineer in the field.

8-20.1(1)  Regulations and Code

All electrical equipment shall conform to the standards of the National Electrical 
Manufacturers Association (NEMA), Electric Utility Service Equipment Requirements 
Committee (EUSERC), and California Department of Transportation document entitled 
Transportation Electrical Equipment Specifications (TEES). Traffic signal control equipment 
shall conform to the Contract and these Standard Specifications: EIA Electronic Industries 
Alliance, IEEE Institute of Electrical and Electronics Engineers, the American Society 
for Testing and Materials (ASTM), the American Association of State Highway and 
Transportation Officials (AASHTO), the American National Standards Institute (ANSI), 
whichever is applicable, and to other codes listed herein. In addition to the requirements 
of these Specifications, the Plans, and the Special Provisions, all material and Work shall 
conform to the requirements of the National Electrical Code, hereinafter referred to as 
the Code, and any WACs and local ordinances, which may apply.

Wherever reference is made in these Specifications or in the Special Provisions to the 
Code, the rules, or the standards mentioned above, the reference shall be construed to 
mean the code, rule, or standard that is in effect on the Bid advertisement date.

In accordance with 

RCW 39.06.010

, the Contractor need not be registered or licensed if 

the Contractor has been prequalified as required by 

RCW 47.28.070

.

Safe wiring labels normally required by the Department of Labor and Industries will not be 
required on electrical Work within the Rights-of-Way of Contracting Agency Highways as 
allowed in 

RCW 19.28.141

.

Persons performing electrical Work shall be certified in accordance with and supervised 
as required by 

RCW 19.28.161

. Proof of certification shall be worn at all times in 

accordance with 

WAC 296-46B-942

Persons failing to meet these certification 

requirements may not perform any electrical work, and shall stop any active electrical 
work, until their certification is provided and worn in accordance with this section.

Illumination, Traffic Signal Systems, Intelligent Transportation Systems, and Electrical 

8-20

8-20.1(2)  Industry Codes and Standards

The following electrical industry codes and standard procedures are listed for reference 
purposes:

Air Movement and Control Association (AMCA), 30 West University Drive, Arlington 
Heights, IL 60004.
American Association of State Highway and Transportation Officials (AASHTO), 
444 North Capitol Street NW, Suite 225, Washington, D.C. 20001.
American National Standards Institute (ANSI), 70 East 45th Street, New York, NY. 
American Society for Testing and Materials (ASTM), 1916 Race Street, 
Philadelphia, PA.
American Wood Protection Association (AWPA), 836 Seventeenth Street, 
Washington, D.C.
Bell Company Research and Evaluation (Bellcore) 31220 La Baya DR, Westlake 
Village, CA 91362.
Edison Electric Institute (EEI), 420 Lexington Avenue, New York, NY. 
Electronics Industries Alliance (EIA), 101 Pennsylvania Avenue, Washington, D.C. 
Electric Utility Service Equipment Requirements Committee (EUSERC).
Federal Communications Commission (FCC), 445 12th SW, Washington, D.C. 20554.
International Municipal Signal Association (IMSA), PO Box 539, 1115 North Main 
Street, Newark, NY 14513.
Institute of Electrical and Electronics Engineers (IEEE), 17th Floor, New York, 
NY 10016
International Telephony Communications Union (ITU) Place des Nations CH 
1211 Geneva 20 Switzerland.
Institute of Transportation Engineers (ITE), 2029 K Street, Washington, D.C. 20005.
Insulated Power Cable Engineers’ Association (IPCEA), 283 Valley Road, 
Montclair, NJ.
National Electrical Manufacturers’ Association (NEMA), 155 East 44th Street, New 
York, NY.
National Fire Protection Association – National Electrical Code (NEC), 470 Atlantic 
Avenue, Boston, MA.
National Television Standards Committee (NTSC), 445 12th SW, Washington, 
D.C. 20554.
National Transportation Communications for ITS Protocol (NTCIP). 
Rural Utilities Service (RUS), 1400 Independence Avenue, Washington, D.C.
Underwriters’ Laboratories (UL), 207 East Ohio Street, Chicago, IL.

Page 8-102 

Illumination, Traffic Signal Systems, Intelligent Transportation Systems, and Electrical

8-20.1(3)  Permitting and Inspections

Electrical installations are subject to electrical inspection in accordance with 

RCW 

19.28.101

. Electrical inspections may only be performed by an electrical inspector 

meeting the requirements of RCW 19.28.321. Electrical installations will not be accepted 
until they have been inspected and approved by an electrical inspector as required by 
this Section. This inspection is required even if there is no new electrical service or new 
electrical meter being installed in the Contract.

Installations within WSDOT right of way are subject to a minimum of a final inspection 
by a WSDOT certified electrical inspector as allowed by 

RCW 19.28.141

. A separate 

permit is not required for electrical installations within WSDOT right of way. Additional 
inspections may be required at the discretion of the Engineer.

Installations outside of WSDOT right of way are subject to permitting and inspection by 
the Washington State Department of Labor and Industries (L&I) or a local jurisdiction 
approved for that location by L&I. Approved local jurisdictions and their contacts can be 
found on the L&I website a

www.lni.wa.gov/TradesLicensing/Electrical/FeePermInsp/

CityInspectors

.

8-20.2 Materials

Materials shall meet the requirements of 

Section 9-29

. Unless otherwise indicated in the 

Plans or specified in the Special Provisions, all materials shall be new.

Where existing systems are to be modified, the existing material shall be incorporated in 
the revised system, salvaged, or abandoned as specified in the Contract documents, or as 
ordered by the Engineer.

8-20.2(1)  Equipment List and Drawings

Within 20 days following execution of the Contract, the Contractor shall submit to the 
Engineer a completed “Request for Approval of Material” that describes the material 
proposed for use to fulfill the Plans and Specifications.

If required to do so, the Contractor shall submit Type 2 Working Drawings consisting 
of supplemental data, sample articles, or both, of the material proposed for use. 
Supplemental data includes such items as catalog cuts, product Specifications, shop 
drawings, wiring diagrams, etc.

If the luminaires are not listed in the Qualified Products List, the Contractor shall submit 
Type 2 Working Drawings consisting of the following information for each different type 
of luminaire required on the Contract:
1.  Isocandela diagrams showing vertical light distribution, vertical control limits, and 

lateral light distribution classification.

2.  Details showing the lamp socket positions with respect to lamp and refractor for 

each light distribution type. This requires that the Contracting Agency know what 
the light pattern available are and the light distribution.

Illumination, Traffic Signal Systems, Intelligent Transportation Systems, and Electrical 

8-20

The Contractor shall submit for approval Type 3E Working Drawings in accordance with 

Section 1-05.3

 for each of the following types of standards called for on this project:

1.  Light standards without preapproved plans.
2.  Signal standards with or without preapproved plans.

The Contractor will not be required to submit shop drawings for approval for light 
standards and traffic signal standards conforming to the preapproved plans listed in the 
Special Provisions. The Contractor may use preapproved plans posted on the WSDOT 
website with a more current revision date than stamped in the Special Provisions.

The Engineer’s acceptance of any submitted documentation shall in no way relieve the 
Contractor from compliance with the safety and performance requirements as specified 
herein.

Submittals required shall include but not be limited to the following:
1.  A Type 2 Working Drawing consisting of a material staging plan, should the 

Contractor propose Contracting Agency-owned property for staging areas.

2.  A Type 2 Working Drawing consisting of a cable vault installation plan showing the 

exact proposed installation location by Roadway station, offset and the scheduled 
sequence for each cable vault installation.

3.  A Type 2E Working Drawing consisting of a pit plan, for each boring pit, depicting the 

protection of traffic and pedestrians, pit dimensions, shoring, bracing, struts, walers, 
sheet piles, conduit skids, and means of attachment, casing type, and casing size.

4.  A Type 2E Working Drawing consisting of a boring plan depicting the boring system 

and entire support system.

8-20.3 

Construction Requirements

8-20.3(1) General

All workmanship shall be complete and in accordance with the latest accepted standards 
of the industry.

Existing electrical systems, traffic signal or illumination, or approved temporary 
replacements, shall be kept in effective operation during the progress of the Work, except 
when shutdown is permitted to allow for alterations or final removal of the system.

If a portion of an existing communication conduit system is damaged due to the 
Contractor’s activities, the affected system shall be restored to original condition. Conduit 
shall be repaired. Communication cables shall be replaced and the communication system 
shall be made fully operational within 24 hours of being damaged.

Damaged communication cable shall be replaced between existing termination or splice 
points. No additional termination or splice points will be allowed. An existing termination 
or splice point is defined as a location where all existing fiber strands or twisted pair 
wires are terminated or spliced at one point. Communication cable shall be defined as 
either copper twisted pair or fiber optic cables. The Contractor may use temporary splices 

Page 8-104 

Illumination, Traffic Signal Systems, Intelligent Transportation Systems, and Electrical

to restore WSDOT communication systems until the permanent communication cable 
system is restored.

When damage to an existing communication system has occurred, the Contractor shall 
perform the following in addition to other restoration requirements:
1.  Inspect the communication raceway system including locate wire or tape to 

determine the extent of damage.

2.  Contact the Engineer for Fiber Optic Cable and Twisted Pair (TWP) Copper 

Cable acceptance testing requirements and communication system restoration 
requirements.

3.  Initially perform the acceptance tests to determine the extent of damage and 

also perform the acceptance tests after repairs are completed. Provide written 
certification that the communication cable system, including the locate wire or tape, 
is restored to test standard requirements.

Communication cables shall be restored by Contractor personnel that are WSDOT 
prequalified for communication installation work. Restoration shall be considered 
electrical work when the path of the communication system interfaces with electrical 
systems. Electrical work of this nature shall be performed by Contractor personnel that 
are WSDOT prequalified for work on both electrical and communication systems.

If the Contractor or Subcontractors are unable or unqualified to complete the restoration 
work, the Engineer may have the communication or electrical systems restored by other 
means and subtract the cost from the money that will be or is due the Contractor.

When field repair of existing conduit, innerduct or outerduct is required, the repair kits 
shall be installed per manufacturer’s recommendations. Repair kits and each connection 
point between the repair kit and the existing raceway system shall be sealed to prevent 
air leakage during future cable installation.

Illumination system shutdowns shall not interfere with the regular lighting schedule, 
unless permitted by the Engineer. The Contractor shall notify the Engineer prior to 
performing any Work on existing systems.

Work shall be so scheduled that each electrical system is operational prior to opening the 
corresponding section of Roadway to traffic.

Traffic signals shall not be placed in operation for use by the public until all required 
channelization, pavement markings, illumination, signs, and sign lights are substantially 
complete and operational unless otherwise allowed by the Engineer.

The embedded anchors attaching existing electrical, illumination, and traffic signal 
systems specified for removal to existing concrete Structures shall be removed a 
minimum of 1 inch beneath the existing concrete surface. The void left by removal of 
the embedded anchors shall be coated with epoxy bonding agent and filled with mortar 
conforming t

Section 9-20.4(2)

The epoxy bonding agent shall be Type II, conforming 

to 

Section 9-26.1

with the grade and class as recommended by the epoxy bonding 

agent manufacturer and as approved by the Engineer. The mortar shall consist of cement 

Illumination, Traffic Signal Systems, Intelligent Transportation Systems, and Electrical 

8-20

and fine aggregate mixed in the proportions to match the color of the existing concrete 
surface as near as practicable.

All costs incurred by the Contractor for providing effective operation of existing electrical 
systems shall be included in the associated electrical Bid items.

8-20.3(2)  Excavating and Backfilling

The excavations required for the installation of conduit, foundations, poles and other-
accessories shall be performed in a manner that prevents damage to the streets, 
sidewalks, and other improvements. The trenches shall not be excavated wider than 
necessary for the proper installation of the electrical accessories and foundations. 
Excavating shall not be performed until immediately before installation of conduit and 
other accessories. The material from the excavation shall be placed where the least 
interference to vehicular and pedestrian traffic, and to surface drainage, will occur.

All surplus excavated material shall be removed and disposed of by the Contractor 
in accordance with 

Section 2-03

, or as ordered by the Engineer in accordance with 

Section 1-04.4

.

The excavations shall be backfilled in conformance with the requirements of 

Section 2-09.3(1)E

, Structure Excavation.

At the end of each day’s Work and at all other times when construction operations are 
suspended, all equipment and other obstructions shall be removed from that portion of 
the Roadway open for use by public traffic.

Excavations in the street or Highway shall be performed in such a manner that not more 
than one traffic lane is restricted in either direction at any time unless otherwise approved 
by the Engineer.

8-20.3(3)  Removing and Replacing Improvements

Improvements such as sidewalks, curbs, gutters, Portland cement concrete and hot mix 
asphalt pavement, bituminous surfacing, base material, and any other improvements 
removed, broken, or damaged by the Contractor, shall be replaced or reconstructed with 
the same kind of materials as found on the Work or with other materials satisfactory to 
the Engineer.

Whenever a part of a square, slab, or section of existing concrete sidewalk, curb, gutter or 
driveway is broken or damaged, the entire square, slab or section, curb, gutter, driveway 
shall be removed and the concrete reconstructed as specified above.

The outline of all areas to be removed in Portland cement concrete sidewalks and 
pavements and hot mix asphalt pavements shall be cut to a minimum depth of 3 inches 
with a saw prior to removing the sidewalk, driveway, slabs and pavement material. The 
cut for the remainder of the required depth may be made by a method satisfactory to the 
Engineer. Cuts shall be neat and true with no shatter outside the removal area.

Page 8-106 

Illumination, Traffic Signal Systems, Intelligent Transportation Systems, and Electrical

8-20.3(4) Foundations

Foundation concrete shall conform to the requirements for the specified class, be cast-
in-place concrete and be constructed in accordance with 

Sections 6-02.2

 and 

6-02.3

Concrete for Type II, III, IV, V, and CCTV signal standards and light standard foundations 
shall be Class 4000P and does not require air entrainment. Concrete for pedestals and 
cabinets, Type PPB, PS, I, FB, and RM signal standards and other foundations shall be 
Class 3000. Concrete placed into an excavation where water is present shall be placed 
using an approved tremie. If water is not present, the concrete shall be placed such that 
the free-fall is vertical down the center of the shaft without hitting the sides, the steel 
reinforcing bars, or the steel reinforcing bar cage bracing. The 

Section 6-02.3(6)

 restriction 

for 5-feet maximum free-fall shall not apply to placement of Class 4000P concrete into a 
shaft. Steel reinforcing bars for foundations shall conform to 

Section 9-07

.

The bottom of concrete foundations shall rest on firm ground. If the portion of the 
foundation beneath the existing ground line is formed or cased instead of being cast 
against the existing soil forming the sides of the excavation, then all gaps between 
the existing soil and the completed foundation shall be backfilled and compacted in 
accordance with 

Section 2-09.3(1)E

.

Foundations shall be cast in one operation where practicable. The exposed portions shall 
be formed to present a neat appearance.

The top edges of the luminaire foundation, traffic signal standard foundations, electrical 
service foundations, traffic signal controller cabinets, Transformer cabinets, ITS Standards, 
and ITS cabinets shall have a ¾-inch chamfer on the top edge of the foundation. Where 
one or more of the above foundations directly abut each other, no chamfer shall be 
permitted.

Where soil conditions are poor, the Engineer may order the Contractor to extend the 
foundations shown in the Plans to provide additional depth. Such additional Work will be 
paid for according to 

Section 1-04.4

.

When slip bases are installed the conduit, anchor bolts, and other obstructions shall 
terminate at a height below the elevation of the top of the bottom slip plate. The 
galvanized surfaces of the slip plates, the keeper plate and the luminaire base plate 
shall be smooth, without irregularities, to reduce friction and to prevent slacking of bolt 
tension due to flattening of the irregularities. Slip base luminaire foundations shall have a 
maximum conduit size of 1-inch.

Forms shall be true to line and grade. Tops of foundations for posts and standards, except 
special foundations, shall be finished to ground line or sidewalk grade, unless otherwise 
noted in the Plans.

Forms shall be rigid and securely braced in place. Conduit ends and anchor bolts shall 
be plumbed and rigidly placed in proper position and to proper height prior to placing 
concrete and shall be held in place by means of a template until the forms are removed.

Illumination, Traffic Signal Systems, Intelligent Transportation Systems, and Electrical 

8-20

Anchor bolts shall be installed so that two full threads extend above the top of the top 
heavy-hex nut, except that slip base anchor bolt extensions shall conform to the specified 
slip base clearance requirements. Anchor bolts shall be installed plumb, plus or minus 
1 degree.

See 

Section 8-20.3(9)

 for additional grounding requirements.

Plumbing of standards shall be accomplished by adjusting leveling nuts. Shims or other 
similar devices for plumbing or raking will not be permitted except on power installed hot 
dipped galvanized steel luminaire foundations.

The top heavy-hex nuts of light standards and signal standards shall be tightened in 
accordance with 

Section 6-03.3(33)

, and as follows:

1.  The top heavy-hex nuts for all clamping bolts of slip base light standards and Type 

RM and FB signal standards, shall be tightened using a torque wrench to the torque 
specified in Sections

 8-20.3(13)A

 and 

8-20.3(14)E

, respectively.

2.  The top heavy-hex nuts for type ASTM F1554 grade 105 anchor bolts shall be 

tightened by the Turn-of-Nut Tightening Method to a minimum rotation of ¼ turn 
(90 degrees) and a maximum rotation of ⅓ turn (120 degrees) past snug tight. 
Permanent marks shall be set on the base plate and nuts to indicate nut rotation past 
snug tight.

3.  The top hex nuts for type ASTM F1554 grade 55 anchor bolts shall be tightened by 

the Turn-of-Nut Tightening Method to a minimum rotation of ⅛ turn (45 degrees) 
and a maximum rotation of 1/6 turn (60 degrees) past snug tight. Permanent marks 
shall be set on the base plate and nuts to indicate nut rotation past snug tight.

Both forms and ground which will be in contact with the concrete shall be thoroughly 
moistened before placing concrete; however, excess water in the foundation excavation 
will not be permitted. Foundations shall have set at least 72 hours prior to the removal 
of the forms. All forms shall be removed, except when the Plans or Special Provisions 
specifically allow or require the forms or casing to remain.

Class 2 surface finish shall be applied to exposed surfaces of concrete in accordance with 
the requirements of 

Section 6-02.3(14)B

.

Where obstructions prevent construction of planned foundations, the Contractor shall 
construct an effective foundation satisfactory to the Engineer.

The combined height of the light standard concrete foundation plus the anchor bolt stub 
height shall not exceed 4-inches above the ground line.

Page 8-108 

Illumination, Traffic Signal Systems, Intelligent Transportation Systems, and Electrical

8-20.3(5) Conduit

8-20.3(5)A General

The ends of all conduit, metallic and nonmetallic, shall be reamed to remove burrs and 
rough edges. Field cuts shall be made square and true. The ends of unused conduits shall 
be capped. When conduit caps are removed, the threaded ends of metal conduit shall be 
provided with approved conduit bushings and non-metal conduit shall be provided with 
end bells.

Reducing couplings will not be permitted.

Existing conduit in place scheduled for installation of new conductor(s) shall first have 
any existing conductor(s) removed and a cleaning mandrel shall be pulled through. The 
existing conduit shall then be prepared subject to the same requirements outlined in 
this paragraph, for new conduit and innerduct, unless otherwise indicated in the Plans. 
All new conduit and all innerduct shall be blown clean with compressed air. Then in the 
presence of the Engineer, an 80 percent sizing mandrel, correctly sized for the raceway, 
shall be pulled through to ensure that the raceway has not been deformed. This shall be 
done prior to pulling wire or fiber optic cable and after final assembly is in place. Existing 
conductor(s) shall be reinstalled unless otherwise indicated in the Plans.

Immediately after the sizing mandrel has been pulled through, install an equipment 
grounding conductor if applicable (see 

Section 8-20.3(9)

) and any new or existing wire or 

cable as specified in the Plans.

All conduits shall include a pull tape with the equipment grounding conductor. The pull 
tape shall be attached to the conduit near the end bell or grounded end bushing, or to 
duct plugs or caps if present, at both ends of the conduit.

8-20.3(5)A1  Fiber Optic Conduit

Where conduit to contain fiber optic cable or conduit identified to contain future fiber 
optic cable is installed by open trenching, Detectable Underground Warning Tape shall be 
placed 12-inches above the conduit unless otherwise detailed in the Plans. Detectable 
Underground Warning Tape shall extend 2-feet into boxes or vaults. Splicing of the tape 
shall be per the tape manufacturer’s recommended materials and procedures.

8-20.3(5)A2  ITS and Cabinet Outer and Inner Duct Conduit

ITS conduit and both ends of conduit runs entering cabinets, with the exception of 
the ½-inch grounding conduit, shall be sealed with self expanding water proof foam or 
mechanical plugs; unless otherwise required. At other locations conduit shall be sealed 
with Duct Seal.

Outer-duct conduit with non factory assembled innerduct shall be sealed around 
the innerduct with self-expanding waterproof foam. Outer-duct conduit with factory 
assembled innerduct shall be sealed around the innerduct with a multiplex expansion 
plug. Innerduct containing one cable shall be plugged using an expandable split plug. 
Innerduct with multiple cables shall be sealed with self-expanding waterproof foam. 

Illumination, Traffic Signal Systems, Intelligent Transportation Systems, and Electrical 

8-20

Duct plugs shall be installed in all unused inner-ducts (those that are specified as empty) 
at the time of conduit installation. Duct plugs shall be installed in all used inner-ducts 
(as specified in the Plans), at the time of conduit installation, unless cable pulling for 
those inner-ducts will commence within 48-hours. Installation shall conform to the 
manufacturer’s recommendations.

Foam sealant shall be installed with the following additional requirements:
1.  Penetration of the sealant into the conduit or duct shall be limited using a high 

temperature backer rod material or rag.

2.  Penetration of the sealant into the conduit shall be limited to 1-inch.
3.  The foam sealant shall not project outside the end of the conduit or duct.

Where open trenching is allowed and conduit with innerduct is installed, a maximum of 
1000-feet of continuous open trench will be allowed unless otherwise approved by the 
Engineer.

8-20.3(5)B 

Conduit Type

Conduit shall be rigid polyvinyl chloride (PVC), high density polyethylene (HDPE), rigid 
metal or flexible metal depending on the application.

Rigid metal conduit shall be installed at the following locations:
1.  Within railroad right of way.
2.  All surface-mounted conduit, with the exception of pole risers.
3.  All runs within slip form placed concrete.

Unless otherwise required by the owning utility:
1.  Service lateral runs shall be Schedule 80 PVC or Schedule 80 HDPE.
2.  Pole risers shall be Schedule 80 PVC.

PVC and HDPE conduits shall be Schedule 80 unless installed as innerduct.

Flexible metal conduit is allowed only at locations called for in the Plans.

Except as described under Non-Metallic Conduit, unless otherwise indicated in the Plans 
or Standard Plans, the same type of conduit shall be used for the entire length of the run, 
from outlet to outlet.

Innerduct shall have a smooth wall non ribbed interior surface, with factory pre-lubricated 
coating.

Innerduct within the Traveled Way or Shoulders and innerduct which is not factory 
installed shall be Schedule 40 HDPE. The innerduct shall be continuous with no splices. 
Innerduct which is pulled into the outer duct in the field shall be installed with an extra 
2 feet of conduit beyond each end of the outer-duct and shall be allowed to finish 
contracting for 21 calendar days before it is terminated. Innerduct shall be terminated 
with end bells flush to ¼-inch out of the outer-duct and the space between the outer-

 

 

 

 

 

 

 

Content      ..     76      77      78      79     ..