Cement 9-01
9-01.4
Storage on the Work Site
At the request of the Engineer, the Contractor shall provide test data to show that cement
stored on site for longer than 60 days meets the requirements of
Section 9-01
. Tests shall
be conducted on samples taken from the site in the presence of the Engineer. Test results
that meet the requirements of
Section 9-01
shall be valid for 60 days from the date of
sampling, after which the Engineer may require further testing.