Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 38

 

  Главная      Manuals     Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     36      37      38      39     ..

 

 

 

Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 38

 

 

Concrete Barrier 

6-10

The barrier shall be precast in sections as the 

Standard Plans

 require. All barrier in the 

same project (except end sections and variable length units needed for closure) shall be 
the same length. All barrier shall be new and unused. It shall be true to Plan dimensions. 
The manufacturer shall be responsible for any damage or distortion that results 
from manufacturing.

Only one section less than 20 feet long for single slope barrier and 10 feet long for all 
other barriers may be used in any single run of precast barrier, and it shall be at least 8 
feet long. It may be precast or cast-in-place. Hardware identical to that used with other 
sections shall interlock such a section with adjacent precast sections.

Barrier connection voids for permanent installations of precast single slope barrier shall 
be filled with grout.

6-10.3(2)  Cast-In-Place Concrete Barrier

Forms for cast-in-place concrete barrier, including traffic barrier, traffic-pedestrian barrier, 
and pedestrian barrier on bridges and related Structures, shall be made of steel or exterior 
plywood coated with plastic. The Contractor may construct the barrier by the slip-form 
method.

The barrier shall be made of Class 4000 concrete that meets the requirements of 

Section 

6-02

, except that the fine aggregate gradation used for slip-form barrier may be either 

Class 1 or 2. The Contractor may use portland cement Type III at no additional expense to 
the Contracting Agency.

In addition to the steel reinforcing bar tying and bracing requirements specified in 

Section 

6-02.3(24) C

, the Contractor may also place small amounts of concrete to aid in holding 

the steel reinforcing bars in place. These small amounts of concrete shall be not more 
than 2-cubic feet in volume, and shall be spaced at a minimum of 10-foot intervals within 
the steel reinforcement cage. These small amounts of concrete shall be consolidated and 
shall provide 2 inches minimum clearance to the steel reinforcing bars on the outside face 
of the barrier. All spattered and excess mortar and concrete shall be removed from the 
steel reinforcing bars prior to slip-form casting.

Barrier expansion joints shall be spaced at 96-foot intervals, and dummy joints shall be 
spaced at 12-foot intervals unless otherwise specified in the Contract.

Immediately after removing the forms, the Contractor shall complete any finishing Work 
needed to produce a uniformly smooth, dense surface. The surface shall have no rock 
pockets and no holes larger than ¼ inch across. The barrier shall be cured and finished in 
accordance with 

Section 6-02.3(11)A

.

The maximum allowable deviation from a 10-foot straightedge held longitudinally on all 
surfaces shall be ¼ inch. For single sloped barrier the maximum allowable deviation from a 
straightedge held along the vertical sloped face of the barrier shall be ¼ inch.

At final acceptance of the project, the barrier shall be free from stains, smears, and any 
discoloration.

Page 6-262 

Concrete Barrier

6-10.3(3)  Removing and Resetting Permanent Concrete Barrier

The Contractor shall reset concrete barrier if the Plans or the Engineer require. If resetting 
is impossible immediately after removal, the Contractor shall store the barrier at Engineer-
approved locations.

6-10.3(4)  Joining Precast Concrete Barrier to Cast-In-Place Barrier

The Contractor may join segments of cast-in-place barrier to precast barrier where 
transitions, split barriers, or gaps shorter than 10 feet require it. At each joint of this 
type, the cast-in-place segment shall include hardware that ties both its ends to abutting 
precast sections.

6-10.3(5)  Temporary Barrier

For temporary barrier, the Contractor may use precast concrete barrier or temporary 
steel barrier. If temporary steel barrier is selected, the Contractor shall verify the 
lateral deflection distance meets or is less than what is shown in the Contract Plans. 
Temporary concrete barrier shall comply with Standard Plan requirements and cross-
sectional dimensions, except that: (1) it may be made in other lengths than those shown 
in the Standard Plan, and (2) it may have permanent lifting holes no larger than 4 inches 
in diameter or lifting loops. Temporary steel barrier shall be certified that it meets 
the requirements of NCHRP 350 or MASH Test Level 3 or 4 and shall be installed in 
accordance with the manufacturer’s recommendations.

If the Contract calls for the removal and resetting of permanent barrier, and the 
permanent barrier is not required to remain in place until reset, the permanent barrier 
may be substituted for temporary concrete barrier. Any of the permanent barrier damaged 
during its use as temporary barrier will become the property of the Contractor and be 
replaced with permanent barrier when the permanent barrier is reset to its permanent 
location.

All barrier shall be in good condition, without cracks, chips, spalls, dirt, or traffic 
marks. If any barrier segment is damaged during or after placement, the Contractor 
shall immediately repair it to the Engineer’s satisfaction or replace it with an 
undamaged section.

Delineators shall be placed on the traffic face of the barrier 6 inches from the top and 
spaced a maximum of 40 feet on tangents and 20 feet through curves. The reflector 
color shall be white on the right side of traffic and yellow on the left side of traffic. 
The Contractor shall maintain, replace and clean the delineators when ordered by 
the Engineer.

As soon as the temporary barrier is no longer needed, the Contractor shall remove it 
from the project. Contracting Agency furnished barrier shall remain Contracting Agency 
property, and the Contractor shall deliver it to a stockpile site noted in the Contract or 
to locations as approved by the Engineer. Contractor furnished barrier shall remain the 
property of the Contractor.

Concrete Barrier 

6-10

6-10.3(6)  Placing Concrete Barrier

Precast concrete barrier Type F, Types 2 and 4, precast single slope barrier, and transitions 
shall rest on a paved foundation shaped to a uniform grade and section. The foundation 
surface for precast concrete barrier Type F, Types 2 and 4, precast single slope barrier, 
and transitions shall meet this test for uniformity: When a 10-foot straightedge is placed 
on the surface parallel to the centerline for the barrier, the surface shall not vary more 
than ¼ inch from the lower edge of the straightedge. If deviations exceed ¼ inch, the 
Contractor shall correct them as required in 

Section 5-04.3(13)

.

The Contractor shall align the joints of all precast segments so that they offset no more 
than ¼ inch transversely and no more than ¾ inch vertically. Grouting is not permitted, 
except as previously stated for single slope barrier. If foundation grade and section are 
acceptable, the Engineer may permit the Contractor to obtain vertical alignment of 
the barrier by shimming. Shimming shall be done with a polystyrene, foam pad (12 by 
24 inches) under the end 12 inches of bearing surface.

Precast barrier shall be handled and placed with equipment that will not damage or 
disfigure it.

6-10.4 Measurement

Precast concrete barrier will be measured by the linear foot along its completed line and 
slope.

Temporary barrier will be measured by the linear foot along the completed line and slope 
of the barrier, one time only for each setup of barrier protected area. Any intermediate 
moving or resetting will not be measured.

Cast-in-place concrete barrier will be measured by the linear foot along its completed 
line unless the Contract specifies that it be measured per cubic yard for concrete Class 
4000 and per pound for steel reinforcing bar (as required in 

Section 6-02.4

).

Cast-in-place concrete barrier light standard section will be measured by the unit for each 
light standard section installed.

Removing and resetting existing permanent barrier will be measured by the linear foot 
and will be measured one time only for removing, storage, and resetting. No measure 
will be made for barrier that has been removed and reset for the convenience of the 
Contractor.

Concrete barrier transition Type 2 to bridge F-shape will be measured by the linear foot 
installed.

Single slope concrete barrier light standard foundation will be measured by the unit for 
each light standard foundation installed.

Traffic barrier, traffic pedestrian barrier, and pedestrian barrier will be measured as 
specified for cast-in-place concrete barrier.

Page 6-264 

Concrete Barrier

6-10.5 Payment

Payment will be made for each of the following Bid items that are included in the Proposal:

“Precast Conc. Barrier Type ____”, per linear foot.
“Cast-In-Place Conc. Barrier”, per linear foot.
“Conc. Class 4000 _____”, per cubic yard.
“St. Reinf. Bar _____”, per pound.
“Removing and Resetting Existing Permanent Barrier”, per linear foot.
The unit Contract price per linear foot for “Cast-In-Place Conc. Barrier” shall be full 
pay for excavation, forms, placement, special construction features, and all other 
materials, tools, equipment, and labor necessary to complete the Work as specified; 
except that when the Contract specifies, the unit Contract price per cubic yard for 
“Conc. Class 4000 _____” and the per pound for “St. Reinf. Bar _____”, shall be full pay 
for excavation, forms, placement, special construction features, and all other materials, 
tools, equipment, and labor necessary to complete the Work as specified.
“Traffic Barrier”, per linear foot.
“Traffic Pedestrian Barrier”, per linear foot.
“Pedestrian Barrier” per linear foot.
The unit Contract price per linear foot for “Traffic Barrier”, “Traffic Pedestrian Barrier”, 
and “Pedestrian Barrier” shall be full pay for constructing the barrier on top of the 
bridge deck, and associated bridge approach slabs, curtain walls and wingwalls, 
excluding the steel reinforcing bars that extend from the bridge deck, bridge approach 
slab, curtain walls, and wingwalls.
“Single Slope Concrete Barrier”, per linear foot.
The unit Contract price per linear foot for “Single Slope Concrete Barrier” shall be full 
pay for either cast-in-place or precast single slope concrete barrier.
“Conc. Barrier Transition Type 2 to Bridge F-Shape”, per linear foot.
The unit Contract price per linear foot for “Conc. Barrier Transition Type 2 to Bridge 
F-Shape” shall be full pay for performing the Work as specified, excluding bridge traffic 
barrier modifications necessary for this installation.
“Single Slope Conc. Barrier Light Standard Foundation”, per each.
“Cast-In-Place Conc. Barrier Light Standard Section”, per each.
“Temporary Barrier”, per linear foot.
The unit Contract price per linear foot for “Temporary Barrier” shall be full pay for all 
costs, including furnishing, installing, connecting, anchoring, maintaining, temporary 
storage, and final removal of the temporary barrier.
Payment for transition sections between different types of barrier shall be made 
at the unit Contract price for the type of barrier indicated in the Plans for each 
transition section.

Reinforced Concrete Walls 

6-11

6-11 

Reinforced Concrete Walls

6-11.1 Description

This Work consists of constructing reinforced concrete retaining walls, including those 
shown in the 

Standard Plans

, L walls, and counterfort walls.

6-11.2 Materials

Materials shall meet the requirements of the following sections:
 Cement 

9-01

 

Aggregates for Concrete 

9-03.1

 

Gravel Backfill 

9-03.12

 

Premolded Joint Filler 

9-04.1(2)

 

Steel Reinforcing Bar 

9-07.2

 

Epoxy-Coated Steel Reinforcing Bar 

9-07.3

 

Concrete Curing Materials and Admixtures 

9-23

 

Fly Ash 

9-23.9

 

Water 

9-25

Other materials required shall be as specified in the Special Provisions. 

6-11.3 

Construction Requirements

6-11.3(1) Submittals

The Contractor shall submit Type 2E Working Drawings consisting of excavation shoring 
plans in accordance with 

Section 2-09.3(3)D

.

The Contractor shall submit Type 2E Working Drawings of falsework and formwork plans 
in accordance with Sections

 6-02.3(16)

 and 

6-02.3(17)

.

If the Contractor elects to fabricate and erect precast concrete wall stem panels, Type 
2E Working Drawings of the following information shall be submitted in accordance with 
Section 

6-02.3(28)A

:

1.  Working drawings for fabrication of the wall stem panels, showing dimensions, steel 

reinforcing bars, joint and joint filler details, surface finish details, lifting devices with 
the manufacturer’s recommended safe working capacity, and material Specifications.

2.  Working drawings and design calculations for the erection of the wall stem panels 

showing dimensions, support points, support footing sizes, erection blockouts, 
member sizes, connections, and material Specifications.

3.  Design calculations for the precast wall stem panels, the connection between the 

precast panels and the cast-in-place footing, and all modifications to the cast-in-
place footing details as shown in the Plans or 

Standard Plans

.

Page 6-266 

Reinforced Concrete Walls

6-11.3(2)  Excavation and Foundation Preparation

Excavation shall conform t

Section 2-09.3(3)

, and to the limits and construction stages 

shown in the Plans. Foundation soils found to be unsuitable shall be removed and 
replaced in accordance with 

Section 2-09.3(1)C

.

6-11.3(3)  Precast Concrete Wall Stem Panels

The Contractor may fabricate precast concrete wall stem panels for construction of 
Standard Plan Retaining Walls. Precast concrete wall stem panels may be used for 
construction of non-Standard Plan retaining walls if allowed by the Plans or Special 
Provisions. Precast concrete wall stem panels shall conform t

Section 6-02.3(28)

and shall be cast with Class 4000 concrete. If Self-Consolidating Concrete is used, 
the concrete shall conform to Sections 

6-02.3(27)B

 and 

6-02.3(27)C

.

The precast concrete wall stem panels shall be designed in accordance with the 
following codes:
1.  For all loads except as otherwise noted – AASHTO LRFD Bridge Design Specifications

latest edition and current interims. The seismic design shall use the acceleration 
coefficient and soil profile type as specified in the Plans.

2.  For all wind loads – AASHTO Guide Specifications for Structural Design of Sound 

Barriers, latest edition and current interims.

The precast concrete wall stem panels shall be fabricated in accordance with the 
dimensions and details shown in the Plans, except as modified in the shop drawings.

The precast concrete wall stem panels shall be fabricated full height, and shall be 
fabricated in widths of 8, 16, and 24 feet.

The construction tolerances for the precast concrete wall stem panels shall be as follows:
 

Height 

±¼ inch 

Width 

±¼ inch 

Thickness 

+¼ inch 

 

-⅛ inch

 

Concrete cover for steel reinforcing bar 

+⅜ inch

 

 

-⅛ inch

 

Width of precast concrete wall stem panel joints 

±¼ inch 

Offset of precast concrete wall stem panels 

±¼ inch 

(Deviation from a straight line extending 5 feet on each side of the panel joint)

The precast concrete wall stem panels shall be constructed with a mating shear key 
between adjacent panels. The shear key shall have beveled corners and shall be 1½ inches 
in thickness. The width of the shear key shall be 3½ inches minimum and 5½ inches 
maximum. The shear key shall be continuous and shall be of uniform width over the entire 
height of the wall stem.

Reinforced Concrete Walls 

6-11

The Contractor shall provide the specified surface finish as noted, and to the limits 
shown, in the Plans to the exterior concrete surfaces. Special surface finishes achieved 
with form liners shall conform to Sections

 6-02.2

 and 

6-02.3(14)

 as supplemented in the 

Special Provisions. Rolled on textured finished shall not be used. Precast concrete wall 
stem panels shall be cast in a vertical position if the Plans call for a form liner texture on 
both sides of the wall stem panel.

The precast concrete wall stem panel shall be rigidly held in place during placement and 
curing of the footing concrete. 

The precast concrete wall stem panels shall be placed a minimum of 1 inch into the 
footing to provide a shear key. The base of the precast concrete wall stem panel shall be 
sloped ½ inch per foot to facilitate proper concrete placement.

To ensure an even flow of concrete under and against the base of the wall panel, a form 
shall be placed parallel to the precast concrete wall stem panel, above the footing, to 
allow a minimum 1-foot head to develop in the concrete during concrete placement.

The steel reinforcing bars shall be shifted to clear the erection blockouts in the precast 
concrete wall stem panel by 1½ inches minimum.

All precast concrete wall stem panel joints shall be constructed with joint filler installed 
on the rear (backfill) side of the wall. The joint filler material shall extend from 2 feet 
below the final ground level in front of the wall to the top of the wall. The joint filler shall 
be a nonorganic flexible material and shall be installed to create a waterproof seal at 
panel joints.

The soil bearing pressure beneath the falsework supports for the precast concrete wall 
stem panels shall not exceed the maximum design soil pressure shown in the Plans for 
the retaining wall.

6-11.3(4)  Cast-In-Place Concrete Construction

Cast-in-place concrete for concrete retaining walls shall be formed, reinforced, cast, 
cured, and finished in accordance with 

Section 6-02

, and the details shown in the Plans 

and 

Standard Plans

All cast-in-place concrete shall be Class 4000. Cast-in-place footings 

shall have a longitudinal slope no steeper than 1V: 6H, unless otherwise shown in the 
Plans or Standard Plans.

The Contractor shall provide the specified surface finish as noted, and to the limits 
shown, in the Plans to the exterior concrete surfaces. Special surface finishes achieved 
with formliners shall conform to Sections

 6-02.2

 and 

6-02.3(14)

 as supplemented in the 

Special Provisions.

Cast-in-place concrete for adjacent wall stem sections (between vertical expansion joints) 
shall be formed and placed separately, with a minimum 12-hour time period between 
concrete placement operations.

Premolded joint filler, ½ inch thick, shall be placed full height of all vertical wall stem 
expansion joints in accordance with 

Section 6-01.14

.

Page 6-268 

Reinforced Concrete Walls

6-11.3(5)  Backfill, Weepholes, and Gutters

Unless the Plans specify otherwise, backfill and weepholes shall be placed in accordance 
with the 

Standard Plans

 and 

Section 6-02.3(22)

. Gravel backfill for drain shall be 

compacted in accordance with 

Section 2-09.3(1)E

. Backfill within the zone defined as 

Bridge Approach Embankment in 

Section 1-01.3

 shall be compacted in accordance with 

Method C of 

Section 2-03.3(14)C

. All other backfill shall be compacted in accordance with 

Method B of 

Section 2-03.3(14)C

, unless otherwise specified.

Cement concrete gutter shall be constructed as shown in the 

Standard Plans

.

6-11.3(6)  Traffic Barrier and Pedestrian Barrier

When shown in the Plans, traffic barrier and pedestrian barrier shall be constructed in 
accordance with Sections

 6-02.3(11)A

 and 

6-10.3(2)

, and the details shown in the Plans 

and 

Standard Plans

.

6-11.4 Measurement

Concrete Class 4000 for retaining wall will be measured as specified in 

Section 

6-02.4

. Steel reinforcing bar for retaining wall and epoxy-coated steel reinforcing bar for 

retaining wall will be measured as specified in 

Section 6-02.4

.

Traffic barrier and pedestrian barrier will be measured as specified in 

Section 6-10.4

 for 

cast-in-place concrete barrier.

6-11.5 Payment

Payment will be made for each of the following Bid items when they are included in the 
Proposal:

“Conc. Class 4000 For Retaining Wall”, per cubic yard.
All costs in connection with furnishing and installing weep holes and premolded 
joint filler shall be included in the unit Contract price per cubic yard for “Conc. Class 
4000 for Retaining Wall”.
“St. Reinf. Bar For Retaining Wall”, per pound.
“Epoxy-Coated St. Reinf. Bar For Retaining Wall”, per pound.
“Traffic Barrier”, per linear foot.
“Pedestrian Barrier”, per linear foot.
The unit Contract price per linear foot for “___ Barrier” shall be full pay for 
constructing the barrier on top of the retaining wall, except that when these Bid 
items are not included in the Proposal, all costs in connection with performing the 
Work as specified shall be included in the unit Contract price per cubic yard for 
“Conc. Class 4000 For Retaining Wall”, and the unit Contract price per pound for “___ 
Bar For Retaining Wall”.

Noise Barrier Walls 

6-12

6-12 

Noise Barrier Walls

6-12.1 Description

This Work consists of constructing cast-in-place concrete, precast concrete, masonry, and 
timber noise barrier walls, including those shown in the 

Standard Plans

.

6-12.2 Materials

Materials shall meet the requirements of the following sections:
 Cement 

9-01

 

Aggregates for Concrete 

9-03.1

 

Gravel Backfill 

9-03.12 

Premolded Joint Filler 

9-04.1(2)

 

Bolts, Nuts, and Washers 

9-06.5(1)

 

Noise Barrier Wall Access Door 

9-06.17 

Steel Reinforcing Bar 

9-07.2

 

Epoxy-Coated Steel Reinforcing Bar 

9-07.3

 

Paints 

9-08

 

Grout 

9-20.3

 

Concrete Curing Materials and Admixtures 

9-23

 

Fly Ash 

9-23.9

 

Water 

9-25

Other materials required shall be as specified in the Special Provisions.

6-12.3 

Construction Requirements

6-12.3(1) Submittals

All noise barrier walls not constructed immediately adjacent to the Roadway, and that 
require construction of access for Work activities, shall have a noise barrier wall access 
plan. The Contractor shall submit a Type 2 Working Drawing consisting of the noise 
barrier wall access plan. The noise barrier wall access plan shall include, but not be limited 
to, the locations of access to the noise barrier wall construction sites, and the method, 
materials, and equipment used to construct the access, remove the access, and recontour 
and reseed the disturbed ground.

For construction of all noise barrier walls with shafts, the Contractor shall submit a Type 
2 Working Drawing consisting of the shaft construction plan, including at a minimum the 
following information:
1.  List and description of equipment to be used to excavate and construct the shafts, 

including description of how the equipment is appropriate for use in the expected 
subsurface conditions.

2.  The construction sequence and order of shaft construction.

Page 6-270 

Noise Barrier Walls

3.  Details of shaft excavation methods, including methods to clean the shaft 

excavation.

4.  Details and dimensions of the shaft, and casing if used.
5.  The method used to prevent ground caving (temporary casing, slurry, or 

other means).

6.  Details of concrete placement including procedures for deposit through a conduit, 

tremie, or pump.

7.  Method and equipment used to install and support the steel reinforcing bar cage.

For construction of precast concrete noise barrier walls, the Contractor shall submit 
Type 2 Working Drawings consisting of shop drawings for the precast concrete panels 
in accordance with 

Section 6-02.3(28)A

. In addition to the items listed in 

Section 

6-02.3(28)A

, the precast concrete panel shop drawings shall include the following:

1.  Construction sequence and method of forming the panels.
2.  Details of additional reinforcement provided at lifting and support locations.
3.  Method and equipment used to support the panels during storage, transporting, and 

erection.

4.  Erection sequence, including the method of lifting the panels, placing and adjusting 

the panels to proper alignment and grade, and supporting the panels during bolting, 
grouting, and backfilling operations.

The Contractor shall not begin noise barrier wall construction activities, including access 
construction and precast concrete panel fabrication, until receiving the Engineer’s 
approval of all appropriate and applicable submittals.

6-12.3(2)  Work Access and Site Preparation

The Contractor shall construct Work access in accordance with the Work access plan. The 
construction access roads shall minimize disturbance to the existing vegetation, especially 
trees. Only trees and shrubs in direct conflict with the approved construction access road 
alignment shall be removed. Only one access road into the noise barrier wall from the 
main Roadway and one access road from the noise barrier wall to the main Roadway shall 
be constructed at each noise barrier wall.

Existing vegetation that has been identified by the Engineer shall be protected in 
accordance with Sections

 1-07.16

 and 

2-01

, and the Special Provisions.

6-12.3(3)  Shaft Construction

The Contractor shall excavate and construct the shafts in accordance with the shaft 
construction plan.

The shafts shall be excavated to the required depth as shown in the Plans. The excavation 
shall be completed in a continuous operation using equipment capable of excavating 
through the type of material expected to be encountered.

Noise Barrier Walls 

6-12

If the shaft excavation is stopped, the Contractor shall secure the shaft by installing a 
safety cover over the opening. The Contractor shall ensure the safety of the shaft and 
surrounding soil and the stability of the side walls. A temporary casing, slurry, or other 
methods acceptable to the Engineer shall be used as necessary to ensure such safety 
and stability.

When caving conditions are encountered, the Contractor shall stop further excavation 
until implementing the method to prevent ground caving as specified in the shaft 
construction plan.

When obstructions are encountered, the Contractor shall notify the Engineer promptly. 
An obstruction is defined as a specific object (including, but not limited to, boulders, 
logs, and man made objects) encountered during the shaft excavation operation, which 
prevents or hinders the advance of the shaft excavation. When efforts to advance past 
the obstruction to the design shaft tip elevation result in the rate of advance of the 
shaft drilling equipment being significantly reduced relative to the rate of advance for 
the rest of the shaft excavation, then the Contractor shall remove the obstruction under 
the provisions of 

Section 6-12.5

The method of removal of such obstructions, and the 

continuation of excavation shall be as proposed by the Contractor and accepted by 
the Engineer.

The Contractor shall use appropriate means to clean the bottom of the excavation of 
all shafts. No more than 2 inches of loose or disturbed material shall be present at the 
bottom of the shaft just prior to beginning concrete placement.

The Contractor shall not begin placing steel reinforcing bars and concrete in the shaft 
until receiving the Engineer’s acceptance of the shaft excavation.

The steel reinforcing bar cage shall be rigidly braced to retain its configuration during 
handling and construction. The Contractor shall not place individual or loose bars. The 
Contractor shall install the steel reinforcing bar cage as specified in the shaft construction 
plan. The Contractor shall maintain the minimum concrete cover shown in the Plans.

If casings are used, the Contractor shall remove the casing during concrete placement. A 
minimum 5-feet head of concrete shall be maintained to balance soil and water pressure 
at the bottom of the casing. The casing shall be smooth. Where the top of the shaft is 
above the existing ground, the Contractor shall case the top of the hole prior to placing 
the concrete.

Concrete for shafts shall conform to Class 4000P. The Contractor shall place concrete in 
the shaft immediately after completing the shaft excavation and receiving the Engineer’s 
acceptance of the excavation. The Contractor shall place the concrete in one continuous 
operation to the elevation shown in the Plans, using a method to prevent segregation of 
aggregates. The Contractor shall place the concrete as specified in the shaft construction 
plan. If water is present, concrete shall be placed in accordance with 

Section 6-02.3(6)B

.

Page 6-272 

Noise Barrier Walls

6-12.3(4)  Trench, Grade Beam, or Spread Footing Construction

Where the noise barrier wall foundations exist below the existing ground line, excavation 
shall conform to 

Section 2-09.3(4)

, and to the limits and construction stages shown in 

the Plans. Foundation soils found to be unsuitable shall be removed and replaced in 
accordance with 

Section 2-09.3(1)C

.

Where the noise barrier wall foundations exist above the existing ground line, 
the Contractor shall place and compact backfill material in accordance with 

Section 2-03.3(14)C

.

Concrete for trench, grade beam, or spread footing foundations shall conform to 
Class 4000.

Cast-in-place concrete shall be formed, placed, and cured in accordance with 

Section 6-02

, except that concrete for trench foundations shall be placed against 

undisturbed soil. Cast-in-place footings shall have a longitudinal slope no steeper than 
1V: 6H, unless otherwise shown in the Plans or Standard Plans.

The excavation shall be backfilled in accordance with item 1 of the Compaction 
Subsection of 

Section 2-09.3(1)E

.

The steel reinforcing bar cage and the noise barrier wall anchor bolts shall be installed 
and rigidly braced prior to grade beam and spread footing concrete placement to retain 
their configuration during concrete placement. The Contractor shall not place individual 
or loose steel reinforcing bars and anchor bolts, and shall not install anchor bolts during or 
after concrete placement.

6-12.3(5)  Cast-In-Place Concrete Panel Construction

Construction of cast-in-place concrete panels for noise barrier walls shall conform to 

Section 6-11.3(4)

. For noise barrier walls with traffic barrier, the construction of the traffic 

barrier shall also conform to 

Section 6-10.3(2)

.

The top of the cast-in-place concrete panels shall conform to the top of wall profile 
shown in the Plans. Where a vertical step is constructed to provide elevation change 
between adjacent panels, the dimension of the step shall be 2 feet. Each horizontal run 
between steps shall be a minimum of 48 feet.

6-12.3(6)  Precast Concrete Panel Fabrication and Erection

The Contractor shall fabricate and erect the precast concrete panels in accordance with 

Section 6-02.3(28)

, and the following requirements:

1.  Concrete shall conform to Class 4000. If Self-Consolidating Concrete is used, the 

concrete shall conform to Sections 

6-02.3(27)B

 and 

6-02.3(27)C

.

2.  Except as otherwise noted in the Plans and Special Provisions, all concrete surfaces 

shall receive a Class 2 finish in accordance with 

Section 6-02.3(14)B

.

Noise Barrier Walls 

6-12

3.  The precast concrete panels shall be cast in accordance with 

Section 6-02.3(28)B

The Contractor shall fully support the precast concrete panel to avoid bowing and 
sagging surfaces.

 

After receiving the Engineer’s review of the shop drawings, the Contractor shall cast 
one precast concrete panel to be used as the sample panel. The Contractor shall 
construct the sample panel in accordance with the procedure and details specified 
in the shop drawings. The Contractor shall make the sample panel available to the 
Engineer for acceptance.

 

Upon receiving the Engineer’s acceptance of the sample panel, the Contractor 
shall continue production of precast concrete panels for the noise barrier wall. All 
precast concrete panels will be evaluated against the sample panel for the quality 
of workmanship exhibited. The sample panel shall be retained at the fabrication site 
until all precast concrete panels have been fabricated and accepted. After completing 
precast concrete panel fabrication, the Contractor may utilize the sample panel as a 
production noise barrier wall panel.

4.  In addition to the fabrication tolerance requirements of 

Section 6-02.3(28)F

, the 

precast concrete panels for noise barrier walls shall not exceed the following scalar 
tolerances:

 

Length and Width: ± ⅛ inch per 5 feet, not to exceed ¼ inch total.

 

Thickness: ± ¼ inch.

 

The difference obtained by comparing the measurement of the diagonal of the face 
of the panels shall not be greater than ½ inch.

 

Dimension tolerances for the traffic barrier portion of precast concrete panels 
formed with traffic barrier shapes shall conform to 

Section 6-10.3(2)

.

5.  Precast concrete panels shall not be erected until the foundations for the panels 

have attained a minimum compressive strength of 3,400 psi.

6.  The bolts connecting the precast concrete panels to their foundation shall be 

tightened to “snug tight” as defined in 

Section 6-03.3(32)

.

7.  After erection, the precast concrete panels shall not exceed the joint space 

tolerances shown in the Plans. The panels shall not exceed ⅜ inch out of plumb in 

any direction.

 

The Contractor shall seal the joints between precast concrete panels with a backer 
rod and sealant system as specified. The Contractor shall seal both sides of the joint 
full length.

The top of precast concrete panels shall conform to the top of wall profile shown in the 
Plans. Where a vertical step is constructed to provide elevation change between adjacent 
panels, the dimension of the step shall be 2 feet. Each horizontal run between steps shall 
be a minimum of 48 feet.

Page 6-274 

Noise Barrier Walls

6-12.3(7)  Masonry Wall Construction

Construction requirements for masonry noise barrier wall panels shall be as specified in 
the Special Provisions.

6-12.3(8)  Fabricating and Erecting Timber Noise Barrier Wall Panels

Construction requirements for timber noise barrier wall panels shall be as specified in the 
Special Provisions.

6-12.3(9)  Access Doors and Concrete Landing Pads

The Contractor shall install access doors and door frames as shown in the Plans and 

Standard Plans

The Contractor shall install the access doors to open toward the Roadway 

side. The door frames shall be set in place with grout conforming to either 

Section 

9-20.3(2)

 or 

9-20.3(4)

 and placed in accordance with 

Section 6-02.3(20)

with the grout 

completely filling the void between the door frame and the noise barrier wall panel.

All frame and door surfaces, except stainless steel surfaces, shall be painted in accordance 
with 

Section 6-07.3(9)

. Primer shall be applied to all non-stainless steel surfaces. 

All primer coated exposed metal surfaces shall be field painted with the remaining 

Section 6-07.3(9)A

 paint system coats. The top coat, when dry, shall match the color 

specified in the Plans or Special Provisions.

The Contractor shall construct concrete landing pads for each access door location as 
shown in the Plans. The concrete shall conform to

 Section 6-02.3(2)B

.

Access door deadbolt locks shall be capable of accepting a Best CX series core. The 
Contractor shall furnish and install a spring-loaded construction core lock with each lock. 
The Engineer will furnish the permanent Best CX series core for the Contractor to install 
at the conclusion of the project.

6-12.3(10)  Finish Ground Line Dressing

The Contractor shall contour and dress the ground line on both sides of the noise barrier 
wall, providing the minimum cover over the foundation as shown in the Plans. The 
Contractor shall contour the ground adjacent to the barrier to ensure good drainage away 
from the barrier.

After the access roads are no longer needed for noise barrier wall construction activities, 
the Contractor shall restore the area to the original condition. The Contractor shall 
recontour the access roads to match into the surrounding ground and shall reseed all 
disturbed areas in accordance with the 

Section 8-01

 and the Special Provisions, and the 

noise barrier wall access plan. 

Noise Barrier Walls 

6-12

6-12.4 Measurement

Noise barrier wall will be measured by the square foot area of one face of the completed 
wall panel in place. Except as otherwise noted, the bottom limit for measurement will be 
the top of the trench footing, spread footing, or shaft cap. For Noise Barrier Type 5, the 
bottom measurement limit will be the optional construction joint at the base of the traffic 
barrier. For Noise Barrier Type 7, the bottom measurement limit will be base of the traffic 
barrier. For Noise Barrier Types 8, 11, 12, 14, 15, and 20, the bottom measurement limit 
will be the base of the wall panel.

Noise barrier wall access door will be measured once for each access door assembly with 
concrete landing pad furnished and installed.

6-12.5 Payment

Payment will be made for each of the following Bid items when they are included in the 
Proposal:

“Noise Barrier Wall Type __”, per square foot. 
The unit Contract price per square foot for “Noise Barrier Wall Type __” shall be 
full pay for constructing the noise barrier walls as specified, including constructing 
and removing access roads, excavating and constructing foundations and grade 
beams, constructing cast-in-place concrete, and masonry wall panels, fabricating and 
erecting precast concrete, and timber wall panels, applying sealer, and contouring 
the finish ground line adjacent to the noise barrier walls.
“Noise Barrier Wall Access Door”, per each. 
The unit Contract price per each for “Noise Barrier Wall Access Door” shall be full 
pay for furnishing and installing the access door assembly as specified, including 
painting the installed access door assembly and constructing the concrete landing 
pads.
“Removing Noise Barrier Wall Shaft Obstructions”, estimated.
Payment for removing obstructions, as defined in 

Section 6-12.3(3)

, will be made 

for the changes in shaft construction methods necessary to remove the obstruction. 
The Contractor and the Engineer shall evaluate the effort made and reach agreement 
on the equipment and employees utilized, and the number of hours involved 
for each. Once these cost items and their duration have been agreed upon, the 
payment amount will be determined using the rate and markup methods specified 
in 

Section 1-09.6

. For the purpose of providing a common proposal for all bidders, 

the Contracting Agency has entered an amount for the item “Removing Noise Barrier 
Wall Shaft Obstructions” in the bid proposal to become a part of the total bid by 
the Contractor.

Page 6-276 

Noise Barrier Walls

If the shaft construction equipment is idled as a result of the obstruction removal work 
and cannot be reasonably reassigned within the project, then standby payment for 
the idled equipment will be added to the payment calculations. If labor is idled as a 
result of the obstruction removal work and cannot be reasonably reassigned within the 
project, then all labor costs resulting from Contractor labor agreements and established 
Contractor policies will be added to the payment calculations.

The Contractor shall perform the amount of obstruction work estimated by the 
Contracting Agency within the original time of the contract. The Engineer will consider a 
time adjustment and additional compensation for costs related to the extended duration 
of the shaft construction operations, provided:
1.  The dollar amount estimated by the Contracting Agency has been exceeded, and;
2.  The Contractor shows that the obstruction removal work represents a delay to 

the completion of the project based on the current progress schedule provided in 
accordance with 

Section 1-08.3

.

 

 

 

 

 

 

 