Structure Excavation
2-09
Controlled Density Fill (CDF) or Controlled Low-Strength Material (CLSM) – CDF is a
self compacting, cementitious, flowable material requiring no subsequent vibration or
tamping to achieve consolidation. The Contractor shall provide a mix design in writing
to the Engineer on WSDOT
Form 350-040
and utilize ACI 229 as a guide to develop the
CDF mix design. No CDF shall be placed until the Engineer has reviewed the mix design.
CDF shall be designed to have a minimum 28-day strength of 50 psi and a maximum 28-
day strength not to exceed 300 psi. The CDF consistency shall be flowable (approximate
slump 3 to 10 inches).
The following testing methods shall be used by the Contractor to develop the CDF
mix design:
28-day compressive strength – ASTM D4832;
Unit weight, yield, and air content – ASTM D6023;
Slump – FOP for AASHTO T 119.
The water/cement ratio shall be calculated on the total weight of cementitious material.
Cementitious materials are those listed in
Section 5-05.2
.
Admixtures used in CDF shall meet the requirements of
Section 9-23.6
, Admixtures
for Concrete, and foaming agents, if used, shall meet the requirements of ASTM C869.
Admixtures shall be used in accordance with the manufacturer’s recommendations and
non-chloride accelerating admixtures may be used to accelerate the hardening of CDF.
CDF shall meet the requirement of
Section 6-02.3(5)C
and shall be accepted based on a
Certificate of Compliance. The producer shall provide a Certificate of Compliance for each
truckload of CDF in accordance with
Section 6-02.3(5)B
.
Stockpiling – The Engineer may require the Contractor to selectively remove and
stockpile any usable material excavated for a Structure. If this material meets the
requirements for gravel backfill for walls it may replace gravel as wall or abutment backfill.
If the Contractor stockpiles excavated material for use as backfill, it shall be protected
with plastic sheeting or by some other method from contamination and weather damage.
If the material becomes too wet or contaminated in the stockpile, the Contractor shall
dispose of and replace it with an equal amount of suitable material, all at no expense
to the Contracting Agency. All costs for storing, protecting, rehandling, and placing
stockpiled material shall be included in the unit Contract price for Structure excavation,
Class A or B.
Compaction – Backfill from Structure excavation shall be placed and compacted in
keeping with the following requirements:
1. Backfill supporting Roadbed, Roadway embankments, or Structures, including backfill
providing lateral support for noise barrier wall foundations, luminaire poles, traffic
signal standards, and roadside and overhead sign Structure foundations shall be
placed in horizontal layers no more than 6 inches thick with each layer compacted
to 95 percent of the maximum density determined by the Compaction Control Test
according to
Section 2-03.3(14)D
.