Page 1-86
Legal Relations and Responsibilities to the Public
If the Contractor fails to provide the above notification within 60 calendar days, then
the Contractor shall yield to the Contracting Agency sole and exclusive discretion to
allow all or part of the claim on behalf of the Contractor, and the Contractor shall be
deemed to have WAIVED any and all defenses, objections, or other avoidances to the
Contracting Agency’s allowance of the claim, or the amount allowed by the Contracting
Agency, under common law, constitution, statute, or the Contract and these Standard
Specifications. If all or part of a claim is allowed, the Contracting Agency will notify
the Contractor via certified mail that it has allowed all or part of the claim and make
appropriate payments to the claimant(s) with State funds.
Payments of State funds by the Contracting Agency to claimant(s) under this section
will be made on behalf of the Contractor and at the expense of the Contractor, and the
Contractor shall be unconditionally obligated to reimburse the Contracting Agency for the
“total reimbursement amount”, which is the sum of the amount paid to the claimant(s),
plus all costs incurred by the Contracting Agency in evaluating the circumstances
surrounding the claim, the allowance of the claim, the amount due to the claimant, and all
other direct costs for the Contracting Agency’s administration and payment of the claim
on the Contractor’s behalf. The Contracting Agency will be authorized to withhold the
total reimbursement amount from amounts due the Contractor, or, if no further payments
are to be made to the Contractor under the Contract, the Contractor shall directly
reimburse the Contracting Agency for the amounts paid within 30 days of the date notice
that the claim was allowed was sent to the Contractor. In the event reimbursement from
the Contractor is not received by the Contracting Agency within 30 days, interest shall
accrue on the total reimbursement amount owing at the rate of 12 percent per annum
calculated at a daily rate from the date the Contractor was notified that the claim was
allowed. The Contracting Agency’s costs to enforce recovery of these amounts are
additive to the amounts owing.
The Contractor specifically assumes all potential liability for actions brought by employees
of the Contractor and, solely for the purpose of enforcing the defense and indemnification
obligations set forth in
Section 1-07.14
, the Contractor specifically waives any immunity
granted under the State industrial insurance law,
Title 51 RCW
. This waiver has been
mutually negotiated by the parties. The Contractor shall similarly require that each
Subcontractor it retains in connection with the project comply with the terms of this
paragraph, waive any immunity granted under
Title 51 RCW
, and assume all liability for
actions brought by employees of the Subcontractor.
1-07.15
Temporary Water Pollution Prevention
1-07.15(1) Spill Prevention, Control, and Countermeasures Plan
The Contractor shall prepare a Type 2 Working Drawing consisting of a project-specific
spill prevention, control, and countermeasures plan (SPCC Plan), and shall implement the
plan for the duration of the project. No on-site construction activities may commence
until the Contracting Agency accepts an SPCC Plan for the project. An SPCC Plan
template and guidance information is available at
www.wsdot.wa.gov/environment/
technical/disciplines/hazardous-materials/spill-prevent-report
.