Legal Relations and Responsibilities to the Public

4.  Retaining Walls
 

Loads above existing and completed retaining walls designed for vehicular loads, 
where any part of the load is located within half the retaining wall height, shall not 
exceed the following load restrictions:
a.  The gross vehicle weight or maximum load on each axle shall not exceed the 

legal load limit.

b.  Construction equipment and material shall not exceed 250 pounds per 

square foot.

 

If necessary and safe to do so, the Engineer may allow higher loads than those 
allowed under these load-limit restrictions. For loads on or over structures designed 
for direct bearing of live load, the Contractor shall submit Type 3E Working Drawings 
consisting of calculations and other supporting information in accordance with 
the requirements of Section 6-01.6. For loads on or over pipes, culverts, buried 
structures, and retaining walls the Contractor shall submit Type 2E Working 
Drawings. All submittals shall contain the following information: a description of 
the loading details; arrangement, movement and position of all vehicles, equipment 
and materials on the Structure, culvert or pipe; and statement that the Contractor 
assumes all risk for damage.

1-07.8 

High-Visibility Apparel

The Contractor shall require all personnel under their control (including service providers, 
Subcontractors, and lower tier subcontractors) that are on foot in the work zone and are 
exposed to vehicle traffic or construction equipment to wear the high-visibility apparel 
described in this section.

The Contractor shall ensure that a competent person as identified in the MUTCD selects 
the appropriate high-visibility apparel suitable for the jobsite conditions. 

High-visibility garments shall always be the outermost garments.

High-visibility garments shall be labeled as, and in a condition compliant with the ANSI/
ISEA 107 (2004 or later version) and shall be used in accordance with manufacturer 
recommendations.

1-07.8(1)  Traffic Control Personnel

All personnel performing the Work described in 

Section 1-10

 (including traffic control 

supervisors, flaggers, spotters, and others performing traffic control labor of any kind) 
shall comply with the following:
1.  During daylight hours with clear visibility, workers shall wear a high-visibility 

ANSI/ISEA 107 Class 2 or 3 vest or jacket, and hardhat meeting the high-visibility 
headwear requirements of 

WAC 296-155-305

; and

Legal Relations and Responsibilities to the Public 

1-07

2.  During hours of darkness (½ hour before sunset to ½ hour after sunrise) or other 

low-visibility conditions (snow, fog, etc.), workers shall wear a high-visibility ANSI/
ISEA 107 Class 2 or 3 vest or jacket, high-visibility lower garment meeting ANSI/
ISEA 107 Class E, and hardhat meeting the high-visibility headwear requirements of 

WAC 296-155-305

.

1-07.8(2)  Non-Traffic Control Personnel

All personnel, except those performing the Work described in 

Section 1-10

, shall wear 

high-visibility apparel meeting the ANSI/ISEA 107 Class 2 or 3 standard.

1-07.9 Wages

1-07.9(1) General

This Contract is subject to the minimum wage requirements of 

RCW 39.12

 and to 

RCW 49.28

 (as amended or supplemented). On Federal-aid projects, Federal wage laws 

and rules also apply. The hourly minimum rates for wages and fringe benefits are listed 
in the Contract Provisions. When Federal wage and fringe benefit rates are listed, the 
rates match those identified by the U.S. Department of Labor’s “Decision Number” shown 
in the Contract Provisions.

The Contractor, any Subcontractor, and all individuals or firms required by 

RCW 39.12

WAC 296-127

, or the Federal Davis-Bacon and Related Acts (DBRA) to pay minimum 

prevailing wages, shall not pay any worker less than the minimum hourly wage rates and 
fringe benefits required by 

RCW 39.12

 or the DBRA. Higher wages and benefits may 

be paid.

By including the hourly minimum rates for wages and fringe benefits in the Contract 
Provisions, the Contracting Agency does not imply that the Contractor will find labor 
available at those rates. The Contractor shall be responsible for any amounts above the 
minimums that will actually have to be paid. The Contractor shall bear the cost of paying 
wages above those shown in the Contract Provisions.

When the project is subject to both State and Federal hourly minimum rates for wages 
and fringe benefits and when the two rates differ for similar kinds of labor, the Contractor 
shall not pay less than the higher rate unless the State rates are specifically preempted by 
Federal law. When the project involves highway Work, heavy Work, and building Work, 
the Contract Provisions may list a Federal wage and fringe benefit rate for the highway 
Work, and a separate Federal wage and fringe benefit rate for both heavy Work and 
building Work. The area in which the worker is physically employed shall determine which 
Federal wage and fringe benefit rate shall be used to compare against the State wage and 
fringe benefit rate.

If employing labor in a class not listed in the Contract Provisions on state funded projects 
only, the Contractor shall request a determination of the correct wage and benefits rate 
for that class and locality from the Industrial Statistician, Washington State Department 
of Labor and Industries (State L&I), and provide a copy of those determinations to 
the Engineer.

Page 1-72 

Legal Relations and Responsibilities to the Public

If employing labor in a class not listed in the Contract Provisions on federally funded 
projects, the Contractor shall request a determination of the correct wage and benefit for 
that class and locality from the U.S. Secretary of Labor through the Engineer. Generally, 
the Contractor initiates the request by preparing standard form 1444 Request for 
Authorization of Additional Classification and Rate, available at www.gsa.gov/reference/
forms,
 and submitting it to the Engineer for further action.

The Contractor shall ensure that any firm (Supplier, Manufacturer, or Fabricator) that 
falls under the provisions of 

RCW 39.12

 because of the definition “Contractor” in 

WAC 

296-127-010

, complies with all the requirements of 

RCW 39.12

.

The Contractor shall be responsible for compliance with the requirements of the DBRA 
and 

RCW 39.12

 by all firms (Subcontractors, lower tier subcontractors, Suppliers, 

Manufacturers, or Fabricators) engaged in any part of the Work necessary to complete 
this Contract. Therefore, should a violation of this Subsection occur by any firm that 
is providing Work or materials for completion of this Contract whether directly or 
indirectly responsible to the Contractor, the Contracting Agency will take action against 
the Contractor, as provided by the provisions of the Contract, to achieve compliance, 
including but not limited to, withholding payment on the Contract until compliance 
is achieved.

In the event the Contracting Agency has an error (omissions are not errors) in the listing 
of the hourly minimum rates for wages and fringe benefits in the Contract Provisions, 
the Contractor, any Subcontractor, any lower tier subcontractor, or any other firm that 
is required to pay prevailing wages, shall be required to pay the rates as determined 
to be correct by State L&I (or by the U.S. Department of Labor when that agency sets 
the rates). A change order will be prepared to ensure that this occurs. The Contracting 
Agency will reimburse the Contractor for the actual cost to pay the difference between 
the correct rates and the rates included in the Contract Provisions, subject to the 
following conditions:
1.  The affected firm relied upon the rates included in the Contract Provisions to 

prepare its Bid and certifies that it did so; 

2.  The allowable amount of reimbursement will be the difference between the rates 

listed and rates later determined to be correct plus only appropriate payroll markup 
the employer must pay, such as, social security and other payments the employer 
must make to the Federal or State Government;

3.  The allowable amount of reimbursement may also include some overhead cost, such 

as, the cost for bond, insurance, and making supplemental payrolls and new checks 
to the employees because of underpayment for previously performed Work; and

4.  Profit will not be an allowable markup.

Firms that anticipated, when they prepared their Bids, paying a rate equal to, or higher 
than, the correct rate as finally determined will not be eligible for reimbursement.

Listing Recovery Act (and other) new hire opportunities with the Employment Security 
Department.

Legal Relations and Responsibilities to the Public 

1-07

There are many talented people currently unemployed. As the signs on the Contracting 
Agency’s projects advertise, the Recovery Act is about creating jobs and putting people 
back to work. As a companion effort, the Employment Security Department has been 
charged with giving people the opportunity to compete for these jobs. Their tool for doing 
so is WorkSource. WorkSource is a free service located across the State that screens, 
shortlists, and refers qualified candidates.

WorkSource employees are aware that the Contractor has other commitments as part of 
your business practices and as part of the Contract. Contractors may be subject to hiring 
commitments such as Equal Employment Opportunity or union commitments. However, 
utilizing WorkSource can be an essential effort as part of their various good faith efforts.

WorkSource is a resource that is available across the State. Contractors who have been 
awarded WSDOT Contracts shall be prepared to discuss their recruitment plans and 
how WorkSource will be incorporated into that effort at the preconstruction conference. 
WorkSource has a simple process for requesting and reporting new hires. 

The Contractor may contact the ARRA Business Unit at 877-453-5906 (toll free) or  

ARRA@esd.wa.gov

. There is additional information available on the website at  

https://fortress.wa.gov/esd/worksource

.

1-07.9(2)  Posting Notices

Notices and posters shall be placed in areas readily accessible to read by employees. The 
Contractor shall ensure the most current edition of the following are posted:
1.  EEOC - P/E-1  – Equal Employment Opportunity IS THE LAW published by US 

Department of Labor. Post for projects with federal-aid funding.

2.  Mandatory Supplement to EEOC P/E-1 published by US Department of Labor. Post 

for projects with federal-aid funding.

3.  Pay Transparency Nondiscrimination Provision published by US Department of 

Labor. Post for projects with federal-aid funding.

4.  FHWA 1022 – NOTICE Federal-Aid Project published by Federal Highway 

Administration (FHWA). Post for projects with federal-aid funding.

5.  WH 1321 – Employee Rights Under the Davis-Bacon Act published by US 

Department of Labor. Post for projects with federal-aid funding.

6.  WHD 1088 – Employee Rights Under the Fair Labor Standards Act published by US 

Department of Labor. Post on all projects.

7.  WHD 1420 – Employee Rights and Responsibilities Under The Family And Medical 

Leave Act published by US Department of Labor. Post on all projects.

8.  WHD 1462 – Employee Polygraph Protection Act published by US Department of 

Labor. Post on all projects.

9.  F416-081-909 – Job Safety and Health Law published by Washington State 

Department of Labor and Industries. Post on all projects.

10.  F242-191-909 – Notice To Employees published by Washington State Department 

of Labor and Industries. Post on all projects.

Page 1-74 

Legal Relations and Responsibilities to the Public

11.  F700-074-909 – Your Rights as a Worker in Washington State by Washington State 

Department of Labor and Industries (L&I). Post on all projects.

12.  EMS 9874 – Unemployment Benefits published by Washington State Employment 

Security Department. Post on all projects.

13.  Post one copy of the approved “Statement of Intent to Pay Prevailing Wages” for the 

Contractor, each Subcontractor, each lower tier subcontractor, and any other firm 
(Supplier, Manufacturer, or Fabricator) that falls under the provisions of 

RCW 39.12

 

because of the definition of “Contractor” in 

WAC 296-127-010

.

14.  Post one copy of the prevailing wage rates for the project.

1-07.9(3) Apprentices

If employing apprentices, the Contractor shall submit to the Engineer written evidence 
showing:
1.  Each apprentice is enrolled in a program approved by the Washington State 

Apprenticeship and Training Council;

2.  The progression schedule for each apprentice; and
3.  The established apprentice-journey level ratios and wage rates in the project locality 

upon which the Contractor will base such ratios and rates under the Contract. 
Any worker for whom an apprenticeship agreement has not been registered and 
approved by the Washington State Apprenticeship and Training Council shall be paid 
at the prevailing hourly journey level rate as provided in 

RCW 39.12.021

.

1-07.9(4) Disputes

If labor and management cannot agree in a dispute over the proper prevailing wage rates, 
the Contractor shall refer the matter to the Director of State L&I (or to the U.S. Secretary 
of Labor when that agency sets the rates). The Director’s (or Secretary’s) decision shall be 
final, conclusive, and binding on all parties.

1-07.9(5)  Required Documents

On forms provided by the Industrial Statistician of State L&I, the Contractor shall submit 
to the Engineer the following for itself and for each firm covered under 

RCW 39.12

 tha

provided Work and materials for the Contract:
1.  A copy of an approved “Statement of Intent to Pay Prevailing Wages” State L&I’s 

form number F700-029-000. The Contracting Agency will make no payment under 
this Contract for the Work performed until this statement has been approved by 
State L&I and a copy of the approved form has been submitted to the Engineer.

2.  A copy of an approved “Affidavit of Prevailing Wages Paid”, State L&I’s form number 

F700-007-000

The Contracting Agency will not grant Completion until all approved 

Affidavit of Wages paid for Contractor and all Subcontractors have been received by 
the Engineer. The Contracting Agency will not release to the Contractor any funds 
retained under 

RCW 60.28.011

 until all of the “Affidavit of Prevailing Wages Paid” 

Legal Relations and Responsibilities to the Public 

1-07

forms have been approved by State L&I and a copy of all the approved forms have 
been submitted to the Engineer.

The Contractor shall be responsible for requesting these forms from State L&I and for 
paying any approval fees required by State L&I.

Certified payrolls are required to be submitted by the Contractor to the Engineer, for the 
Contractor and all Subcontractors or lower tier subcontractors, on all Federal-aid projects 
and, when requested in writing by the Engineer, on projects funded with only Contracting 
Agency funds. If these payrolls are not supplied within 10 calendar days of the end of 
the preceding weekly payroll period for Federal-aid projects or within 10 calendar days 
from the date of the written request on projects with only Contracting Agency funds, 
any or all payments may be withheld until compliance is achieved. Also, failure to provide 
these payrolls could result in other sanctions as provided by State laws (

RCW 39.12.050

and/or Federal regulations (29 CFR 5.12). All certified payrolls shall be complete and 
explicit. Employee labor descriptions used on certified payrolls shall coincide exactly with 
the labor descriptions listed on the minimum wage schedule in the Contract unless the 
Engineer approves an alternate method to identify the labor used by the Contractor to 
compare with the labor listed in the Contract Provisions. When an apprentice is shown 
on the certified payroll at a rate less than the minimum prevailing journey wage rate, the 
apprenticeship registration number for that employee from the State Apprenticeship and 
Training Council shall be shown along with the correct employee classification code.

1-07.9(6) Audits

The Contracting Agency may inspect or audit the Contractor’s wage and payroll records as 
provided in 

Section 1-09.12

.

1-07.10 

Worker’s Benefits

The Contractor shall make all payments required for unemployment compensation under 

Title 50 RCW

 and for industrial insurance and medical aid required under 

Title 51 RCW

If any payment required by Title 50 or Title 51 is not made when due, the Contracting 
Agency may retain such payments from any money due the Contractor and pay the same 
into the appropriate fund. Such payment will be made only after giving the Contractor 15 
days prior written notice of the Contracting Agency’s intent to disburse the funds to the 
Washington State Department of Labor and Industries or Washington State Employment 
Security Department as applicable. The payment will be made upon expiration of the 
15 calendar day period if no legal action has been commenced to resolve the validity 
of the claim. If legal action is instituted to determine the validity of the claim prior to 
the expiration of the 15-day period, the Contracting Agency will hold the funds until 
determination of the action or written settlement agreement of the appropriate parties.

For Work on or adjacent to water, the Contractor shall make the determination as to 
whether workers are to be covered under the Longshoremen’s and Harbor Worker’s 
Compensation Act administered by the U.S. Department of Labor, or the State Industrial 
Insurance coverage administered by the Washington State Department of Labor 
and Industries.

Page 1-76 

Legal Relations and Responsibilities to the Public

The Contractor shall include in the various items in the Bid Proposal all costs for payment 
of unemployment compensation and for providing either or both of the insurance 
coverages. The Contractor will not be entitled to any additional payment for: (1) failure 
to include such costs, or (2) determinations made by the U.S. Department of Labor or the 
Washington State Department of Labor and Industries regarding the insurance coverage.

The Public Works Contract Division of the Washington State Department of Labor and 
Industries will provide the Contractor with applicable industrial insurance and medical aid 
classification and premium rates. After receipt of a Revenue Release from the Washington 
State Department of Revenue, the Contracting Agency will verify through the Department 
of Labor and Industries that the Contractor is current with respect to the payments of 
industrial insurance and medical aid premiums.

1-07.11 

Requirements for Nondiscrimination

1-07.11(1)  General Application

Discrimination in all phases of contracted employment, contracting activities and 
training is prohibited by Title VI of the Civil Rights Act of 1964, Section 162(a) of the 
Federal-Aid Highway Act of 1973, Section 504 of the Rehabilitation Act of 1973, the 
Age Discrimination Act of 1975, the Justice System Improvement Act of 1979, the 
American with Disabilities Act of 1990, the Civil Rights Restoration Act of 1987, 49 CFR 
Part 21, 

RCW 49.60

 and other related laws and statutes. The referenced legal citations 

establish the minimum requirements for affirmative action efforts and define the basic 
nondiscrimination provisions as required by this section of these Standard Specifications

1-07.11(2)  Contractual Requirements

1.  The Contractor shall maintain a Work site that is free of harassment, humiliation, 

fear, hostility and intimidation at all times. Behaviors that violate this requirement 
include but are not limited to:
a.  Persistent conduct that is offensive and unwelcome.
b.  Conduct that is considered to be hazing.
c.  Jokes about race, gender, or sexuality that are offensive.
d.  Unwelcome, unwanted, rude or offensive conduct or advances of a sexual 

nature which interferes with a person’s ability to perform their job or creates an 
intimidating, hostile, or offensive work environment.

e.  Language or conduct that is offensive, threatening, intimidating or hostile based 

on race, gender, or sexual orientation.

f. 

Repeating rumors about individuals in the Work Site that are considered to be 
harassing or harmful to the individual’s reputation.

2.  The Contractor shall not discriminate against any employee or applicant for 

contracted employment because of race, religion, color, national origin, sex, age, 
marital status, or the presence of any physical, sensory or mental disability.

Legal Relations and Responsibilities to the Public 

1-07

3.  The Contractor shall, in all solicitations or advertisements for employees, state 

that all qualified applicants will be considered for employment, without regard to 
race, religion, color, national origin, sex, age, marital status, or the presence of any 
physical, sensory, or mental disability.

4.  The Contractor shall insert the following notification in all solicitations for bids for 

Work or material subject to federal laws and regulations and made in connection 
with all program and activities and, in adapted form in all proposals for negotiated 
agreements:

 

The Contractor in accordance to Title VI of the Civil Rights Act of 1964, 78 Stat.252, 
42 U.S. Code 2000d to 2000d-4, and Title 49 Code of Federal Regulations, Part 
21, hereby notifies all bidders that it will affirmatively ensure that in any contract 
entered into pursuant to this advertisement, minority business enterprises will be 
afforded full opportunity to submit bids in response to this invitation and will not 
be discriminated against on the grounds of race, color national origin and sex in 
consideration for an award.

5.  The Contractor shall make decisions with regard to selection and retention of 

subcontractors, procurement of materials and equipment and similar actions related 
to the Contract without regard to race, religion, color, national origin, sex, age, 
marital status, or the presence of any physical, sensory, or mental disability. 

6.  The Contractor shall send to each labor union, employment agency, or representative 

of workers with which the Contractor has a collective bargaining agreement or other 
contract or understanding, a notice advising the labor union, employment agency or 
worker’s representative, of the Contractor’s commitments under this Contract with 
regard to nondiscrimination.

7.  The Contractor shall permit access to its books, records and accounts by the 

Contracting Agency for the purpose of investigating to ascertain compliance with 
these Specifications. In the event that information required of a Contractor is in the 
possession of another who fails or refuses to furnish this information, the Contractor 
shall describe, in writing, what efforts were made to obtain the information.

8.  The Contractor shall maintain records with the name and address of each minority/

female worker referred to the Contractor and what action was taken with respect to 
the referred worker. 

9.  The Contractor shall notify the Contracting Agency whenever the union with 

which the Contractor has a collective bargaining agreement has impeded the 
Contractor’s efforts to effect minority/female workforce utilization. This being the 
case, the Contractor shall show what relief they have sought under such collective 
bargaining agreements.

10.  The Contractor is encouraged to participate in Contracting Agency and Washington 

State Human Rights Commission approved program(s) designed to train craft-
workers for the construction trades.

Page 1-78 

Legal Relations and Responsibilities to the Public

1-07.11(2)A 

Equal Employment Opportunity (EEO) Responsibilities

Title VI Responsibilities

During the performance of this Contract, the Contractor, for itself, its assignees and 
successors in interest (hereinafter referred to as the “Contractor”) agrees as follows:
1.  Compliance With Regulations – The Contractor shall comply with the Regulations 

relative to nondiscrimination in federally assisted programs of the Department of 
Transportation (hereinafter DOT), Title 49, Code of Federal Regulations, part 21, as 
they may be amended from time to time, (hereinafter referred to as the Regulations), 
which are herein incorporated by reference and made a part of this Contract.

2.  Nondiscrimination – The Contractor, with regard to the Work performed by it during 

the Contract, shall not discriminate on the grounds of race, color, sex, or national 
origin in the selection and retention of Subcontractors, including procurement 
of materials and leases of equipment. The Contractor shall not participate either 
directly or indirectly in the discrimination prohibited by Section 21.5 of the 
Regulations, including employment practices when the Contract covers a program 
set forth in Appendix B of the Regulations.

3.  Solicitations for Subcontracts, Including Procurement of Materials and Equipment 

– In all solicitations either by competitive bidding or negotiations made by the 
Contractor for Work to be performed under a subcontract, including procurement of 
materials or leases of equipment, each potential Subcontractor or supplier shall be 
notified by the Contractor of the Contractor’s obligations under this Contract and 
the Regulations relative to nondiscrimination on the ground of race, color, sex, or 
national origin.

4.  Information and Reports – The Contractor shall provide all information and reports 

required by the Regulations or directives issued pursuant thereto, and shall permit 
access to its books, records, accounts, other sources of information, and its facilities 
as may be determined by the Washington State Department of Transportation or 
the Federal Highway Administration to be pertinent to ascertain compliance with 
such Regulations, orders and instructions. Where any information required of a 
Contractor is in the exclusive possession of another who fails or refuses to furnish 
this information, the Contractor shall so certify to the Washington State Department 
of Transportation, or the Federal Highway Administration as appropriate, and shall 
set forth what efforts it has made to obtain the information.

5.  Sanctions for Noncompliance – In the event of the Contractor’s noncompliance with 

the nondiscrimination provisions of this Contract, the Washington State Department 
of Transportation shall impose such Contract sanctions as it or the Federal Highway 
Administration may determine to be appropriate, including, but not limited to:
a.  Withholding of payments to the Contractor under the Contract until the 

Contractor complies, and/or;

b.  Cancellation, termination, or suspension of the Contract, in whole or in part.

Legal Relations and Responsibilities to the Public 

1-07

6.  Incorporation of Provisions – The Contractor shall include the provisions of 

paragraphs (1) through (5) in every subcontract, including procurement of materials 
and leases of equipment, unless exempt by the Regulations, or directives issued 
pursuant thereto. The Contractor shall take such action with respect to any 
Subcontractor or procurement as the Washington State Department of Transportation 
or the Federal Highway Administration may direct as a means of enforcing such 
provisions including sanctions for noncompliance.

 

Provided, however, that in the event a Contractor becomes involved in, or is 
threatened with, litigation with a Subcontractor or supplier as a result of such 
direction, the Contractor may request the Washington State Department of 
Transportation enter into such litigation to protect the interests of the state and, 
in addition, the Contractor may request the United States to enter into such litigation 
to protect the interests of the United States.

1-07.11(3)  Equal Employment Opportunity Officer

The Contractor shall officially designate and make known to the Engineer during the 
preconstruction conference and discussions the firm’s Equal Employment Opportunity 
Officer (hereinafter referred to as the EEO Officer). The EEO Officer will also be 
responsible for making him/herself known to each of the Contractor’s employees. The 
EEO Officer must possess the responsibility, authority, and capability for administering and 
promoting an active and effective Contractor program of equal employment opportunity.

1-07.11(4)  Dissemination of Policy

1-07.11(4)A 

Supervisory Personnel

All members of the Contractor’s staff who are authorized to hire, supervise, promote, and 
discharge employees, or who recommend such action, or who are substantially involved 
in such action, shall be made fully cognizant of, and shall implement the Contractor’s 
equal employment opportunity policy and contractual responsibilities to provide equal 
employment opportunity in each grade and classification of employment. To ensure that 
the above agreement will be met, the following actions shall be taken as a minimum:
1.  EEO Meetings – Periodic meetings of supervisory and personnel office employees 

shall be conducted before the start of Work and then not less often than once every 
6 months, at which time the Contractor’s equal employment opportunity policy and 
its implementation shall be reviewed and explained. The meetings shall be conducted 
by the EEO Officer or other knowledgeable company official.

2.  EEO Indoctrination – All new supervisory or personnel office employees shall be 

given a thorough indoctrination by the EEO Officer or other knowledgeable company 
official covering all major aspects of the Contractor’s equal employment opportunity 
obligations within 30 days following their reporting for duty with the Contractor.

3.  Internal EEO Procedures – All personnel who are engaged in direct recruitment 

for the project shall be instructed by the EEO Officer or appropriate company 
official in the Contractor’s procedures for locating and hiring minority group and 
female employees.

Page 1-80 

Legal Relations and Responsibilities to the Public

1-07.11(4)B 

Employees, Applicants, and Potential Employees

In order to make the Contractor’s equal employment opportunity policy known to all 
employees, prospective employees, and potential sources of employees, e.g., schools, 
employment agencies, labor unions (where appropriate), college placement officers, and 
community organizations, the Contractor shall take the following actions:
1.  Notices and Posters – Notices and posters setting forth the Contractor’s equal 

employment opportunity policy shall be placed in areas readily accessible to 
employees, applicants for employment, and potential employees.

2.  EEO Indoctrination – The Contractor’s equal employment opportunity policy and the 

procedures to implement such policy shall be brought to the attention of employees 
by means of meetings, employee handbooks, or other appropriate means.

1-07.11(5) Sanctions

In the event of the Contractor is found in noncompliance with the provisions of 

Section 

1-07.11

, the Contracting Agency may impose such Contract sanctions as it or the Federal 

Highway Administration may determine necessary to gain compliance including, but not 
limited to: 
1.  Progress payment requests may not be honored until the noncompliance is remedied 

to the satisfaction of the Contracting Agency.

2.  The Contract may be suspended, in whole or in part, until such time as the 

Contractor is determined to be in compliance by the Contracting Agency.

3.  The Contractor’s pre-qualification may be suspended or revoked pursuant to 

WAC 468-16

. The Contracting Agency may refer the matter to the Federal Highway 

Administration (FHWA) for possible federal sanctions.

4.  The Contract may be terminated.

Immediately upon the Engineer’s request, the Contractor shall remove from the Work 
site any employee engaging in behaviors that promote harassment, humiliation, fear or 
intimidation including but not limited to those described in these specifications.

1-07.11(6)  Incorporation of Provisions

The Contractor shall include the provisions of 

Section 1-07.11(2)

 Contractual 

Requirements (1) through (5) and the 

Section 1-07.11(5)

 Sanctions in every subcontract 

including procurement of materials and leases of equipment. The Contractor shall take 
such action or enforce sanctions with respect to a Subcontractor or supplier as the 
Contracting Agency or the FHWA may direct as a means of enforcing such provisions. In 
the event a Contractor becomes involved in litigation with a Subcontractor or supplier 
as a result of such direction, the Contractor may request the Contracting Agency enter 
into such litigation to protect their interests and the Contracting Agency may request 
the federal government to enter into such litigation to protect the interests of the 
United States.

Legal Relations and Responsibilities to the Public 

1-07

1-07.11(7) Vacant

1-07.11(8) Vacant

1-07.11(9)  Subcontracting, Procurement of Materials, and Leasing of Equipment

Nondiscrimination – The Contractor shall not discriminate on the grounds of race, 
color, religion, sex, national origin, age, or disability in the selection and retention of 
Subcontractors, including procurement of materials and leases of equipment.

Solicitation and Utilization – The Contractor shall use their best effort to solicit bids from, 
and to utilize, disadvantaged, minority, and women Subcontractors, or Subcontractors 
with meaningful minority and women representation among their employees.

Subcontractor EEO Obligations – The Contractor shall notify all potential Subcontractors 
and suppliers of the EEO obligations required by the Contract. The Contractor shall 
use their efforts to ensure Subcontractors compliance with their equal employment 
opportunity obligations.

1-07.11(10) Records and Reports

1-07.11(10)A General

The Contractor shall keep such records as are necessary to determine compliance with 
the Contractor’s equal employment opportunity obligations. The records kept by the 
Contractor shall be designated to indicate:
1.  Work Force Data – The number of minority and nonminority group members and 

women employed in each work classification on the project.

2.  Good Faith Efforts – Unions – The progress and efforts being made in cooperation 

with unions to increase employment opportunities for minorities and women 
(applicable only to contractors who rely in whole or in part on unions as a source of 
their work force).

3.  Good Faith Efforts – Recruitment – The progress and efforts being made in locating, 

hiring, training, qualifying, and upgrading minority and female employees.

4.  Subcontracting – The progress and efforts being made in securing the services 

of disadvantaged, minority, and women Subcontractors or Subcontractors with 
meaningful minority and female representation among their employees.

Page 1-82 

Legal Relations and Responsibilities to the Public

1-07.11(10)B  Required Records and Retention

All records must be retained by the Contractor for a period of three years following 
acceptance of the Contract Work. All records shall be available at reasonable times 
and places for inspection by authorized representatives of either the Washington State 
Department of Transportation or the Federal Highway Administration.

Federal-Aid Highway Construction Contractors Annual EEO Report

FHWA #1391 – This form is required for all federally assisted projects provided the 
Contract is equal to or greater than $10,000 and for every associated subcontract 
equal to or greater than $10,000. Each Contract requires separate reports filed for the 
Contractor and each Subcontractor (subject to the above noted criteria). These forms 
are due by August 25

th

 in every year during which Work was performed in July. The 

payroll period to be reflected in the report is the last payroll period in July in which Work 
was performed. This report is required of each Contractor and Subcontractor for each 
federally assisted Contract on which the Contractor or Subcontractor performs Work 
during the month of July.

Monthly Employment Utilization Reports

WSDOT Form 820-010 – This form (or substitute form as approved by the Contracting 
Agency) is required for all federally assisted projects if the Contract is equal to or 
greater then $10,000 and for every associated subcontract equal to or greater than 
$10,000. These monthly reports are to be maintained in the respective Contractor or 
Subcontractor’s records.

1-07.12 

Federal Agency Inspection

Federal laws, rules, and regulations shall be observed by the Contractor on Federal-
aid projects. This Work is subject to inspection by the appropriate Federal agency. 
The Contractor shall cooperate with the Federal agencies in these inspections. These 
inspections shall not make the Federal Government a party to the Contract and shall not 
constitute an interference with the rights of the Contracting Agency or the Contractor.

1-07.13 

Contractor’s Responsibility for Work

1-07.13(1) General

All Work and material for the Contract, including any change order Work, shall be at 
the sole risk of the Contractor until the entire improvement has been completed as 
determined by the Engineer, except as provided in this section.

The Contractor shall rebuild, repair, restore, and make good all damages to any portion of 
the permanent or temporary Work occurring before the Physical Completion Date and 
shall bear all the expense to do so, except damage to the permanent Work caused by: (a) 
acts of God, such as earthquake, floods, or other cataclysmic phenomenon of nature, or 
(b) acts of the public enemy or of governmental authorities; or (c) slides in cases where 

Section 2-03.3(11)

 is applicable; Provided, however, that these exceptions shall not apply 

Legal Relations and Responsibilities to the Public 

1-07

should damages result from the Contractor’s failure to take reasonable precautions or to 
exercise sound engineering and construction practices in conducting the Work.

If the performance of the Work is delayed as a result of damage by others, an extension of 
time will be evaluated in accordance with 

Section 1-08.8

.

Nothing contained in this section shall be construed as relieving the Contractor of 
responsibility for, or damage resulting from, the Contractor’s operations or negligence, 
nor shall the Contractor be relieved from full responsibility for making good any defective 
Work or materials as provided for under 

Section 1-05

.

1-07.13(2)  Relief of Responsibility for Completed Work

Upon written request, the Contractor may be relieved of the duty of maintaining and 
protecting certain portions of the Work, as described below, which have been completed 
in all respects in accordance with the requirements of the Contract. If the Engineer 
provides written approval, the Contractor will be relieved of the responsibility for damage 
to said completed portions of the Work resulting from use by public traffic or from the 
action of the elements or from any other cause, but not from damage resulting from the 
Contractor’s operations or negligence.

Portions of the Work for which the Contractor may be relieved of the duty of 
maintenance and protection as provided in the above paragraph include but are not 
limited to the following:
1.  The completion of ¼ mile of Roadway or ¼ mile of one Roadway of a divided 

Highway or a frontage road including the Traveled Way, Shoulders, drainage control 
facilities, planned Roadway protection Work, lighting, and any required traffic control 
and access facilities.

2.  A bridge or other Structure of major importance.
3.  A complete unit of a traffic control signal system or of a Highway lighting system.
4.  A complete unit of permanent Highway protection Work.
5.  A building that is functionally complete and open to the public.
6.  Any Contract Proposal item.

1-07.13(3)  Relief of Responsibility for Damage by Public Traffic

When it is necessary for public traffic to utilize a Highway facility during construction, the 
Contractor will be relieved of responsibility for damages to permanent Work by public 
traffic under the following circumstances:
1.  The Work is in accordance with the Contract Plans or approved stage construction 

plans,

2.  The Work is on a section of Roadway required by the Contract to be opened to 

public traffic, and

3.  The traffic control is in accordance with the approved traffic control plans.

Page 1-84 

Legal Relations and Responsibilities to the Public

If traffic is relocated to another section of Roadway, the Contractor shall resume 
responsibility for the Work until such time as the section of Roadway is again open 
to public traffic or the Contractor submits a written request for Work that is completed 
to a point where relief can be granted in accordance with 

Section 1-07.13(2)

.

1-07.13(4)  Repair of Damage

The Contractor shall promptly repair all damage to either temporary or permanent Work 
as ordered by the Engineer. For damage qualifying for relief under Sections 

1-07.13(1)

1-07.13(2)

1-07.13(3)

, or 

8-17.5

, payment will be made in accordance with 

Section 

1-09.4

, using the estimated Bid item “Reimbursement for Third Party Damage”.

In the event the Contracting Agency pays for damage to the Contractor’s Work or for 
damage to the Contractor’s equipment caused by third parties, any claim the Contractor 
had or may have had against the third party shall be deemed assigned to the Contracting 
Agency, to the extent of the Contracting Agency’s payment for such damage.

Payment will be limited to repair of damaged Work only. No payment will be made for 
delay or disruption of Work.

For the purpose of providing a common Proposal for all Bidders, the Contracting Agency 
has entered an amount for “Reimbursement for Third Party Damage” in the Proposal to 
become a part of the total Bid by the Contractor.

1-07.14 

Responsibility for Damage

The State, Governor, Commission, Secretary, and all officers and employees of the State, 
including but not limited to those of the Department, will not be responsible in any 
manner: for any loss or damage that may happen to the Work or any part; for any loss 
of material or damage to any of the materials or other things used or employed in the 
performance of Work; for injury to or death of any persons, either workers or the public; 
or for damage to the public for any cause which might have been prevented by the 
Contractor, or the workers, or anyone employed by the Contractor.

The Contractor shall be responsible for any liability imposed by law for injuries to, or the 
death of, any persons or damages to property resulting from any cause whatsoever during 
the performance of the Work, or before final acceptance.

Subject to the limitations in this section, and 

RCW 4.24.115

, the Contractor shall 

indemnify, defend, and save harmless the State, Governor, Commission, Secretary, and all 
officers and employees of the State from all claims, suits, or actions brought for injuries 
to, or death of, any persons or damages resulting from construction of the Work or in 
consequence of any negligence or breach of Contract regarding the Work, the use of any 
improper materials in the Work, caused in whole or in part by any act or omission by the 
Contractor or the agents or employees of the Contractor during performance or at any 
time before final acceptance. In addition to any remedy authorized by law, the State may 
retain so much of the money due the Contractor as deemed necessary by the Engineer 
to ensure the defense and indemnification obligations of this section until disposition has 
been made of such suits or claims.

Legal Relations and Responsibilities to the Public 

1-07

Subject to the limitations in this section and 

RCW 4.24.115

, the Contractor shall 

indemnify, defend, and save harmless any county, city, or region, its officers, and 
employees connected with the Work, within the limits of which county, city, or region 
the Work is being performed, all in the same manner and to the same extent as provided 
above for the protection of the State, its officers and employees, provided that no 
retention of money due the Contractor be made by the State except as provided in 

RCW 60.28

, pending disposition of suits or claims for damages brought against the 

county, city, or district.

Pursuant t

RCW 4.24.115

, if such claims, suits, or actions result from the concurrent 

negligence of (a) the indemnitee or the indemnitee’s agents or employees and (b) the 
Contractor or the Contractor’s agent or employees, the indemnity provisions provided in 
the preceding paragraphs of this section shall be valid and enforceable only to the extent 
of the Contractor’s negligence or the negligence of its agents and employees.

The Contractor shall bear sole responsibility for damage to completed portions of the 
project and to property located off the project caused by erosion, siltation, runoff, or 
other related items during the construction of the project. The Contractor shall also bear 
sole responsibility for any pollution of rivers, streams, ground water, or other waters that 
may occur as a result of construction operations.

The Contractor shall exercise all necessary precautions throughout the life of the Project 
to prevent pollution, erosion, siltation, and damage to property.

The Contracting Agency will forward to the Contractor all claims filed against the State 
according t

RCW 4.92.100

 that are deemed to have arisen in relation to the Contractor’s 

Work or activities under this Contract, and, in the opinion of the Contracting Agency, 
are subject to the defense, indemnity, and insurance provisions of these Standard 
Specifications
. Claims will be deemed tendered to the Contractor and insurer, who 
has named the State as a named insured or an additional insured under the Contract’s 
insurance provisions, once the claim has been forwarded via certified mail to the 
Contractor. The Contractor shall be responsible to provide a copy of the claim to the 
Contractor’s designated insurance agent who has obtained/met the Contract’s insurance 
provision requirements.

Within 60 calendar days following the date a claim is sent by the Contracting Agency to 
the Contractor, the Contractor shall notify the Claimant and WSDOT (Risk Management 
Office, PO Box 47418, Olympia, WA 98504-7418) of the following:
a.  Whether the claim is allowed or is denied in whole or in part, and, if so, the specific 

reasons for the denial of the individual claim, and if not denied in full, when payment 
has been or will be made to the claimant(s) for the portion of the claim that is 
allowed, or

b.  If resolution negotiations are continuing. In this event, status updates will be 

reported no longer than every 60 calendar days until the claim is resolved or a 
lawsuit is filed.

 

 

 

 

 

 

 

Content      ..     17      18      19      20     ..