- 73 - Remove suspender and note the materials slid. 1. Load hard soil from the bottom to the upper surface 2. Lift the bucket slightly and leave the soil stack. 2.5 Excavation 1. Lay the bucket on the ground and make it have a small excavation angle. 2. Prior to the loader advances, press the bucket downwards, and make the lifting joy stick of the moving arm at the position of holding when the bucket reaches the enough depth. 3 Keep the bucket leveled scraping and excavation by lifting and laying down the bucket. 4 As the bucket is filled, take back the bucket to make it run against the stopper. Drive the loader to the material unloading position when the bucket is away from the ground for 40cm. 2.6 Loading to Bucket 1. Fill the bucket (See “Loading of Stockpile”). When the bucket reaches the lifting limit position, materials may be loaded to the chopper leeward if possible.
|