Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 65

 

  Главная      Manuals     Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     63      64      65      66     ..

 

 

 

Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 65

 

 

Page 6-124 

Concrete Structures

Prestressing reinforcement not conforming to either Section

 9-07.10

 o

9-07.11

 will 

not be allowed except as otherwise noted. Such reinforcement may be used provided 
it is specifically allowed by the Plans or Special Provisions, it satisfies all material and 
performance criteria specified in the Plans or Special Provisions, and receives the 
Engineer’s acceptance.

From manufacture to encasement in concrete or grout, prestressing strand shall be 
protected against dirt, oil, grease, damage, and all corrosives. Strand shall be stored 
in a dry, covered area and shall be kept in the manufacturer’s original packaging. If 
prestressing strand has been damaged or pitted, it will be rejected. Prestressing strand 
with rust shall be spot-cleaned with a nonmetallic pad to inspect for any sign of pitting or 
section loss. If the prestressing reinforcement will not be stressed and grouted for more 
than 7 calendar days after it is placed in the ducts, the Contractor shall place an accepted 
corrosion inhibitor conforming to Federal Specification MIL-I-22110C in the ducts.

The feeding ends of the strand tendons shall be equipped with a bullet nosing or similar 
apparatus to facilitate strand tendon installation.

Strand tendons may be installed by pulling or pushing. Any equipment capable to 
performing the task may be used, provided it does not damage the strands and conforms 
to the following:
1.  Pulling lines shall have a capacity of at least 2.5 times the dead weight of the 

tendons when used for essentially horizontal tendon installation.

2.  Metal pushing wheels shall not be used.

3.  Bullets for checking duct clearance prior to concreting shall be rigid and be ⅛ inch 

smaller than the inside diameter of the duct. Bullets for checking duct after 
concreting shall be less than ¼ inch smaller than the inside diameter of the duct.

6-02.3(26)G Tensioning

Equipment for tensioning post-tensioning reinforcement shall meet the following 
requirements:
1.  Stressing equipment shall be capable of producing a jacking force of at least 

81 percent of the specified tensile strength of the post-tensioning reinforcement.

2.  Jacking force test capacity shall be at least 95 percent of the specified tensile 

strength of the post-tensioning reinforcement.

3.  Wedge seating methods shall assure uniform seating of wedge segments and 

uniform wedge seating losses on all strand tendons.

4.  Accumulation of differential seating losses during tensioning cycling shall be 

prevented by proper devices.

5.  Jacks used for stressing tendons less than 20 feet long shall have wedge power 

seating capability.

Concrete Structures 

6-02

The Contractor shall not begin to tension the tendons until:
1.  All concrete has reached a compressive strength of at least 4,000 psi or the strength 

specified in the Plans. When tensioning takes place prior to 28-day compressive 
strength testing on concrete sampled in accordance with Section 6-02.3(25)H, 
compressive strength shall be verified on field cured cylinders in accordance with the 
FOP for AASHTO T23.

2.  The Engineer is satisfied that all strands are free in the ducts.

Tendons shall be tensioned to the values shown in the Plans (or processed shop drawings) 
with hydraulic jacks. When stressing from both ends of a tendon is specified, it need not 
be simultaneous unless otherwise specified in the Plans. The jacking sequence shall follow 
the processed shop drawings.

Each jack shall have a pressure gauge that will determine the load applied to the tendon. 
The gauge shall display pressure accurately and readably with a dial at least 6 inches in 
diameter or with a digital display. Each jack and its gauge shall be calibrated as a unit and 
shall be accompanied by a certified calibration chart. The Contractor shall provide one 
copy of this chart to the Engineer for use in monitoring. The cylinder extension during 
calibration shall be in approximately the position it will occupy at final jacking force.

All jacks and gauges must be recalibrated and recertified: (1) at least every 180 days, and 
(2) after any repair or adjustment. The Engineer may use pressure cells to check jacks, 
gauges, and calibration charts before and during tensioning.

These stress limits apply to all tendons (unless the Plans set other limits):
1.  During jacking prior to seating: 90 percent of the yield strength of the steel.
2.  At anchorages after seating: 70 percent of the specified tensile strength of the steel.
3.  At service limit state after losses: 80 percent of the yield strength of the steel.

Tendons shall be anchored at initial stresses that will ultimately maintain service loads at 
least as great as the Plans require.

As stated in 

Section 6-02.3(26)A

, the assumed design friction coefficient “

μ

” and wobble 

coefficient “k” shown in the Plans shall be used to calculate the stressing elongation. 
These coefficients may be revised by the post-tensioning supplier by the following 
method provided it is accepted by the Engineer:

Early in the project, the post-tensioning supplier shall test, in place, two 
representative tendons of each size and type shown in the Plans, for the purpose of 
accurately determining the friction loss in a strand and/or bar tendon.
The test procedure shall consist of stressing the tendon at an anchor assembly with 
load cells at the dead end and jacking end. The test specimen shall be tensioned to 
80 percent of the specified tensile strength in 10 increments. For each increment, 
the gauge pressure, elongation, and load cell force shall be recorded and the 
data furnished to the Engineer. The theoretical elongations and post-tensioning 
forces shown on the post-tensioning shop drawings shall be re-evaluated by the 
post-tensioning supplier using the results of the tests and corrected as necessary. 

Page 6-126 

Concrete Structures

Revisions to the theoretical elongations shall be submitted as a Type 2E Working 
Drawing. The apparatus and methods used to perform the tests shall be proposed by 
the post-tensioning supplier and be subject to the Engineer’s acceptance.
All costs associated with testing and evaluating test data shall be included in the unit 
Contract prices for the applicable items of Work involved.

As tensioning proceeds, the Engineer will be recording the applied load, tendon 
elongation, and anchorage seating values.

Elongation measurements shall be made at each stressing location to verify that the 
tendon force has been properly achieved. If proper anchor set has been achieved and 
the measured elongation of each strand tendon is within plus or minus 7 percent of 
the accepted calculated elongation, the stressed tendon represented by the elongation 
measurements is acceptable to the Contracting Agency.

In the event discrepancies greater than 7 percent exist between the measured and 
calculated elongations, the jack calibration shall be checked and stressing records 
reviewed for any evidence of wire or strand breakage. If the jack if properly calibrated 
and there is no evidence of wire or strand breakage, a force verification lift off shall 
be performed to verify the force in the tendon. The post-tensioning supplier force 
verification lift off procedure shall provide access for visual verification of anchor plate 
lift off. The jacking equipment shall be capable of bridging and lifting off the anchor plate. 
The tendon is acceptable if the verification lift off force is not less than 99 percent of the 
accepted calculated force nor more than 70 percent of the specified tensile strength of 
the prestressing steel or as accepted by the Engineer.

Elongation measurements shall be recorded for bar tendons to verify proper tensioning 
only. Acceptance will be by force verification lift off. The bar tendon is acceptable if the 
verification lift off force is not less than 95 percent nor more than 105 percent of the 
accepted calculated force or as accepted by the Engineer.

When removing the jacks, the Contractor shall relieve stresses gradually before cutting 
the prestressing reinforcement. The prestressing strands shall be cut a minimum of 1 inch 
from the face of the anchorage device.

6-02.3(26)H Grouting

Grout for post-tensioning reinforcement shall conform to 

Section 9-20.3(1)

. Prepackaged 

components of the grout mix shall be used within 6 months or less from date of 
manufacture to date of usage. Grout for post-tensioning reinforcement will be accepted 
based on manufacturer’s certificate of compliance in accordance with 

Section 1-06.3

except that the water-cementitious material ratio of 0.45 maximum shall be field verified.

All grout produced for any single structure shall be furnished by one supplier.

All grouting operations shall be conducted by ASBI-certified grout technicians.

Concrete Structures 

6-02

The Contractor shall submit a Type 2 Working Drawing consisting of the grouting 
operation Plan. The grouting operation Plan shall include, but not be limited to, 
the following:
1.  Names of the grout technicians, accompanied by documentation of their ASBI 

certification.

2.  Type, quantity, and brand of materials used in the grouting operations, including all 

manufacturer’s certificates of compliance.

3.  Type of equipment to be used, including meters and measuring devices used to 

positively measure the quantity of materials used to mix the post-tensioning grout, 
the equipment capacity in relation to demand and working conditions, and all back-
up equipment and spare parts.

4.  General grouting procedure.
5.  Duct leak tightness testing and repair procedures as specified in 

Section 6-02.3(26)E

.

6.  Methods used to control the rate of grout flow within the ducts.
7.  Theoretical grout volume calculations, and target flow rates recommended by the 

grout manufacturer as a function of the mixer equipment and the expected range of 
ambient temperatures.

8.  Grout mixing and pumping procedures.
9.  Direction of grouting.
10.  Sequence of use of the grout injection ports, vents, and drains.
11.  Procedures for handling blockages.
12.  Procedures for postgrouting repairs.

Post-tensioning grout shall be mixed in accordance with the prepackaged grout 
manufacturer’s recommendations using high-shear colloidal mixers. Mechanical paddle 
mixers will not be allowed. The grout produced for filling post-tensioning ducts shall be 
free of lumps and undispersed cement. All equipment used to mix each batch of post-
tensioning grout shall be equipped with appropriate meters and measuring devices to 
positively measure all quantities of all materials used to produce the mixed grout. The 
field test for water-cementitious materials ratio shall be performed prior to beginning 
the grout injection process. Grouting shall not begin until the material properties of each 
batch of grout have been confirmed as acceptable.

After tensioning the tendons, the Contractor shall again blow oil-free, compressed air 
through each duct. All drains shall then be closed and the vents opened. Grout caps shall 
be installed at tendon ends prior to grouting. After completely filling the duct with grout, 
the Contractor shall pump the grout from the low end at a pressure of not more than 
250 psig, except for transverse tendons in deck slabs the grout pressure shall not exceed 
100 psig. Grout shall be continuously wasted through each vent until no more air or water 
pockets show. At this point, all vents shall be closed and grouting pressure at the injector 
held between 100 and 200 psig for at least 10 seconds, except for transverse tendons 
in deck slabs the grouting pressure shall be held between 50 and 75 psig for at least 

Page 6-128 

Concrete Structures

10 seconds. The Contractor shall leave all plugs, caps, and valves in place and closed for at 
least 24 hours after grouting.

Grouting equipment shall:
1.  Include a pressure gauge with an upper end readout of between 275 and 325 psig;
2.  Screen the grout before it enters the pump with an easily reached screen that has 

clear openings of no more than 0.125 inches;

3.  Be gravity fed from an attached, overhead hopper kept partly full during pumping; 

and

4.  Be able to complete the largest tendon on the project in no more than 20 minutes of 

continuous grouting.

In addition, the Contractor shall have standby equipment (with a separate power source) 
available for flushing the grout when the regular equipment cannot maintain a one-way 
flow of grout. This standby equipment shall be able to pump at 250 psig.

The grout mix shall be injected within 30 minutes after the water is added to the cement. 
Temperature of the surrounding concrete shall be at least 35°F from the time the grout 
injecting begins until 2-inch cubes of the grout have a compressive strength of 800 psi. 
Cubes shall be made in accordance with WSDOT 

T 813

 and stored in accordance 

with FOP for AASHTO T 23. If ambient conditions are such that the surrounding 
concrete temperature may fall below 35°F, the Contractor shall provide a heat source 
and protective covering for the Structure to keep the temperature of the surrounding 
concrete above 35°F. Grout temperature shall not exceed 90°F during mixing and 
pumping. If conditions are such that the temperature of the grout mix may exceed 90°F, 
the Contractor will make necessary provisions, such as cooling the mix water and/or dry 
ingredients, to ensure that the temperature of the grout mix does not exceed 90°F.

6-02.3(27)  Concrete for Precast Units

Precast units shall not be removed from forms until the concrete has attained a minimum 
compressive strength of 70 percent of the specified design strength as verified by 
rebound number determined in accordance with FOP for ASTM C805. Type III portland 
cement or blended hydraulic cement is permitted to be used in precast concrete units.

Precast units shall not be shipped until the concrete has reached the specified design 
strength as determined by testing cylinders made from the same concrete as the 
precast units. The cylinders shall be made, handled, and stored in accordance with 
FOP for AASHTO T 23 and compression tested in accordance with AASHTO T 22 and 
AASHTO T 231.

Concrete Structures 

6-02

6-02.3(27)A 

Use of Self-Consolidating Concrete for Precast Units

Self-consolidating concrete (SCC) may be used for the following precast concrete 
structure elements:
1.  Precast roof, wall, and floor panels and retaining wall panels in accordance with 

Section 6-02.3(28)

.

2.  Precast reinforced concrete three-sided structures, box culverts and split box 

culverts in accordance with 

Section 7-02.3(6)

.

3.  Precast concrete barrier in accordance with 

Section 6-10.3(1)

.

4.  Precast concrete wall stem panels in accordance wit

Section 6-11.3(3)

.

5.  Precast concrete noise barrier wall panels in accordance with 

Section 6-12.3(6)

.

6.  Structural earth wall precast concrete facing panels in accordance with 

Section 6-13.3(4)

.

7.  Precast drainage structure elements in accordance with 

Section 9-05.50

.

8.  Precast junction boxes, cable vaults, and pull boxes in accordance with 

Section 9-29.2

.

6-02.3(27)B 

Submittals for Self-Consolidating Concrete for Precast Units

With the exception of items 3, 7, and 8 in 

Section 6-02.3(27)A

, the Contractor shall 

submit the mix design for SCC to the Engineer for annual plant approval in accordance 
with 

Section 6-02.3(28)B

. The mix design submittal shall include items specified in 

Sections 6-02.3(2)A

 and 6-02.3(2)C1.

Items 3, 7, and 8 in 

Section 6-02.3(27)A

 require the precast plant to cast one 

representative structure acceptable to the Engineer and have the structure sawn in 
half for examination by the Contracting Agency to determine that segregation has not 
occurred. The Contracting Agency’s acceptance of the sawn structure will constitute 
acceptance of the precast plant’s use of SCC, and a concrete mix design submittal is 
not required.

6-02.3(27)C 

Acceptance Testing of Concrete for Precast Units

Acceptance testing shall be performed by the Contractor and test results shall be 
submitted to the Engineer. Concrete shall conform to the requirements specified in 

Section 6-02.3(2)A

. Unless otherwise noted below, the test methods described in 

Section 

6-02.3(5)D

 shall be followed. Concrete compressive strength shall be in accordance with 

Section 6-02.3(27)

. Compressive strength testing shall be performed a minimum of once 

per day and once for every 20 cubic yards of concrete that is placed.

Page 6-130 

Concrete Structures

Concrete for items 1, 2, 4, 5, and 6 in 

Section 6-02.3(27)A 

that is not self-consolidating 

concrete will be accepted as follows:
1.  Temperature within the allowable temperature band.
2.  Slump below the maximum allowed.
3.  Air content within the required range.

SCC for items 1, 2, 4, 5, and 6 in 

Section 6-02.3(27)A

 will be accepted as follows: 

1.  Temperature within the allowable temperature band.
2.  Slump flow within the target slump flow range.
3.  VSI less than or equal to 1 in accordance with ASTM C1611, Appendix X1, using 

Filling Procedure B.

4.  J ring passing ability less than or equal to 1.5-inches.
5.  Air content within the required range.

SCC for concrete barrier will be accepted in accordance with temperature, air, and 
compressive strength testing listed above.

SCC for precast junction boxes, cable vaults, and pull boxes will be accepted in 
accordance with the temperature and compressive strength testing listed above.

SCC for precast drainage structure elements will be accepted in accordance with the 
requirements of AASHTO M199.

6-02.3(28)  Precast Concrete Panels

The Contractor shall perform quality control inspection. The manufacturing plant for 
precast concrete panels shall be certified by the Precast/Prestressed Concrete Institute’s 
Plant Certification Program for the type of precast member to be produced, or the 
National Precast Concrete Association’s Plant Certification Program or be an International 
Congress Building Officials or International Code Council Evaluation Services recognized 
fabricator of structural precast concrete products, and shall be approved by WSDOT 
as a Certified Precast Concrete Fabricator prior to the start of production. WSDOT 
Certification will be granted at, and renewed during, the annual precast plant review and 
approval process in accordance with WSDOT 

Materials Manual

 M 46-01 Standard Practice 

QC 7. Products that shall conform to this requirement include noise barrier panels, 
wall panels, floor and roof panels, marine pier deck panels, retaining walls, pier caps, 
and bridge deck panels. Precast concrete panels that are prestressed shall meet all the 
requirements of 

Section 6-02.3(25)

.

Prior to the start of production of the precast concrete panels, the Contractor shall advise 
the Engineer of the production schedule. The Contractor shall give the Inspector safe 
and free access to the Work. If the Inspector observes any nonspecification Work or 
unacceptable quality control practices, the Inspector will advise the plant manager. If the 
corrective action is not acceptable to the Engineer, the panel(s) will be rejected.

Concrete Structures 

6-02

6-02.3(28)A 

Shop Drawings

Before casting the structural elements, the Contractor shall submit Type 2E Working 
Drawings of the precast panel shop drawings.

These shop drawings shall show complete details of the methods, materials, and 
equipment the Contractor proposes to use in prestressing/precasting Work. The shop 
drawings shall follow the design conditions shown in the Plans unless the Engineer 
concurs with equally effective variations. 

The shop drawings shall contain as a minimum: 
1.  Panel shapes (elevations and sections) and dimensions. 
2.  Finishes and method of constructing the finish (i.e., forming, rolling). 
3.  Reinforcing, joint, and connection details. 
4.  Lifting, bracing, and erection inserts. 
5.  Locations and details of hardware attached to the Structure.
6.  Relationship to adjacent material. 

The Contractor may deviate from the processed shop drawings only after submitting a 
Type 2E Working Drawing that describes the proposed changes. 

Before completion of the Contract, the Contractor shall provide the Engineer with 
reproducible originals of the shop drawings (and any processed changes). These shall 
be clear, suitable for microfilming, and on permanent sheets that conform with the size 
requirements of 

Section 6-01.9

.

6-02.3(28)B Casting 

Before casting precast concrete panels, the Contractor and Fabrication Inspector shall 
have possession of a processed set of shop drawings.

Concrete shall meet the requirements of 

Section 6-02.3(25)C

 for annual preapproval of 

the concrete mix design and slump. If SCC is used, the concrete shall conform to Sections 

6-02.3(27)B

 and 

6-02.3(27)C

.

Precast panels shall not be removed from forms until the concrete has attained a 
minimum compressive strength of 70 percent of the specified design strength. A minimum 
compressive strength at other than 70 percent may be used for specific precast 
panels if the fabricator requests and receives acceptance as part of the WSDOT plant 
certification process.

Forms may be steel or plywood faced, providing they impart the required finish to 
the concrete.

Page 6-132 

Concrete Structures

6-02.3(28)C Curing 

Concrete in the precast panels shall be cured by either moist or accelerated curing 
methods. The methods to be used shall be preapproved in the WSDOT plant 
certification process.
1.  For moist curing, the surface of the concrete shall be kept covered or moist until 

such time as the compressive strength of the concrete reaches the strength specified 
for stripping. Exposed surfaces shall be kept continually moist by fogging, spraying, 
or covering with moist burlap or cotton mats. Moist curing shall commence as soon 
as possible following completion of surface finishing. 

2.  For accelerated curing, heat shall be applied at a controlled rate following the initial 

set of concrete in combination with an effective method of supplying or retaining 
moisture. Moisture may be applied by a cover of moist burlap, cotton matting, or 
other effective means. Moisture may be retained by covering the panel with an 
impermeable sheet. 

Heat may be radiant, convection, conducted steam or hot air. Heat the concrete to no 
more than 100°F during the first 2 hours after placing the concrete, and then increase 
no more than 25°F per hour to a maximum of 175°F. After curing is complete, cool the 
concrete no more than 25°F per hour to 100°F. Maintain the concrete temperature above 
60°F until the panel reaches stripping strength.

Concrete temperature shall be monitored by means of a thermocouple embedded in the 
concrete (linked with a thermometer accurate to plus or minus 5°F). The recording sensor 
(accurate to plus or minus 5°F) shall be arranged and calibrated to continuously record, 
date, and identify concrete temperature throughout the heating cycle. This temperature 
record shall be made available to the Engineer for inspection and become a part of the 
documentation required.

The Contractor shall never allow dry heat to directly touch exposed panel surfaces at 
any point.

6-02.3(28)D  Contractors Control Strength 

The concrete strength at stripping and the verification of design strength shall be 
determined by testing cylinders made from the same concrete as the precast panels. The 
cylinders shall be made, handled, and stored in accordance with FOP for AASHTO T 23 
and compression tested in accordance with AASHTO T 22 and AASHTO T 231.

For accelerated cured panels, concrete strength shall be measured on test cylinders cast 
from the same concrete as that in the panel. These cylinders shall be cured under time-
temperature relationships and conditions that simulate those of the panel. If the forms 
are heated by steam or hot air, test cylinders will remain in the coolest zone throughout 
curing. If forms are heated another way, the Contractor shall provide a record of the 
curing time-temperature relationship for the cylinders for each panel to the Engineer. 
When two or more panels are cast in a continuous line and in a continuous operation, a 
single set of test cylinders may represent all panels provided the Contractor demonstrates 
uniformity of casting and curing to the satisfaction of the Engineer.

Concrete Structures 

6-02

The Contractor shall mold, cure, and test enough of these cylinders to satisfy 
Specification requirements for measuring concrete strength. The Contractor may use 
4- by 8-inch or 6- by 12-inch cylinders. The Contractor shall let cylinders cool for at least 
½ hour before testing for release strength.

Test cylinders may be cured in a moist room or water tank in accordance with FOP for 
AASHTO T 23 after the panel concrete has obtained the required release strength. If, 
however, the Contractor intends to ship the panel prior to standard 28-day strength test, 
the design strength for shipping shall be determined from cylinders placed with the panel 
and cured under the same conditions as the panel. These cylinders may be placed in a 
noninsulated, moisture-proof envelope.

To measure concrete strength in the precast panel, the Contractor shall randomly select 
two test cylinders and average their compressive strengths. The compressive strength in 
either cylinder shall not fall more than 5 percent below the specified strength. If these 
two cylinders do not pass the test, two other cylinders shall be selected and tested.

6-02.3(28)E Finishing

The Contractor shall provide a finish on all relevant concrete surfaces as defined in 

Section 6-02.3(14)

, unless the Plans or Special Provisions require otherwise.

The Contractor may repair defects in precast panels in accordance with Section 6-01.16.

6-02.3(28)F Tolerances

The panels shall be fabricated as shown in the Plans, and shall meet the dimensional 
tolerances listed in the latest edition of PCI-MNL-116, unless otherwise required by the 
Plans or Special Provisions.

6-02.3(28)G  Handling and Storage

The Contractor shall lift all panels only by adequate devices at locations designated 
on the shop drawings. When these devices and locations are not shown in the Plans, 

Section 6-02.3(25)L

 shall apply.

Precast panels shall be stored off the ground on foundations suitable to prevent 
differential settlement or twisting of the panels. Stacked panels shall be separated and 
supported by dunnage of uniform thickness capable of supporting the panels. Dunnage 
shall be arranged in vertical planes. The upper panels of a stacked tier shall not be used 
as storage areas for shorter panels unless substantiated by engineering analysis and 
accepted by the Engineer.

Page 6-134 

Concrete Structures

6-02.3(28)H Shipping

Precast panels shall not be shipped until the concrete has reached the specified design 
strength, and the Engineer has reviewed the fabrication documentation for Contract 
compliance and stamped the precast concrete panels “Approved for Shipment”. The 
panels shall be supported in such a manner that they will not be damaged by anticipated 
impact on their dead load. Sufficient padding material shall be provided between tie 
chains and cables to prevent chipping or spalling of the concrete.

6-02.3(28)I Erection

When the precast panels arrive on the project, the Engineer will confirm that they are 
stamped “Approved for Shipment”. The Engineer will evaluate the present panels for 
damage before accepting them.

The Contractor shall lift all panels by suitable devices at locations designated on the shop 
drawings. Temporary shoring or bracing shall be provided, if necessary. Panels shall be 
properly aligned and leveled as required by the Plans. Variations between adjacent panels 
shall be leveled out by a method accepted by the Engineer.

6-02.4 Measurement

Except as noted below, all classes of concrete shall be measured in place by the cubic yard 
to the neat lines of the Structure as shown in the Plans.

Exception: concrete in cofferdam seals. Payment for Class 4000W concrete used in these 
seals will be based on the volume calculated using the neatline dimensions for the seal 
as shown in the Contract Plans. For calculated purposes, the horizontal dimension will 
be increased by 1 foot outside the seal neatline perimeter. The vertical dimension is the 
distance between the top and bottom neatline elevations. No payment will be made for 
any concrete that lies outside of these limits to accommodate the Contractor’s cofferdam 
configuration. If the Engineer eliminates the seal in its entirety a Contract change order 
will be issued.

Exception: concrete in a separate lump-sum, Superstructure Bid item. Any concrete 
quantities noted under this item in the Special Provisions will not be measured. Although 
the Special Provisions list approximate quantities for the Contractor’s convenience, 
the Contracting Agency does not guarantee the accuracy of these estimates. Before 
submitting a Bid, the Contractor shall have verified the quantities. Even though actual 
quantities used may vary from those listed in the Special Provisions, the Contracting 
Agency will not adjust the lump sum Contract price for Superstructure (except for 
processed changes).

The Contracting Agency will pay for no concrete placed below the established elevation 
of the bottom of any footing or seal.

Concrete Structures 

6-02

Lean concrete will be measured by the cubic yard for the quantity of material placed 
in accordance with the producer’s invoice, except that lean concrete included in other 
Contract items will not be measured.

No deduction will be made for pile heads, reinforcing steel, structural steel, bolts, weep 
holes, rustications, chamfers, edgers, joint filler, junction boxes, miscellaneous hardware, 
ducts or less than 6-inch diameter drain pipes when computing concrete quantities for 
payment.

All reinforcing steel will be measured by the computed weight of all steel required by 
the Plans. The weight of mechanical splices will be based on the weight specified in the 
manufacturer’s existing catalog cut for the specific item. Splices noted as optional in 
the plans but installed by the Contractor will be included in the measurement. Epoxy-
coated bars will be measured before coating. The Contractor shall furnish (without extra 
allowance):
1.  Bracing, spreaders, form blocks, wire clips, and other fasteners.
2.  Extra steel in splices not shown in the Plans or specified in the Plans as optional.
3.  Extra shear steel at construction joints not shown in the Plans when the Engineer 

permits such joints for the Contractor’s convenience.

The following table shall be used to compute weight of reinforcing steel:

Steel Reinforcing Bar

Deformed Bar 

Designation Number

Nominal Diameter inches

Unit Weight 

Pounds per Foot

3

0.375

0.376

4

0.500

0.668

5

0.625

1.043

6

0.750

1.502

7

0.875

2.044

8

1.000

2.670

9

1.128

3.400

10

1.270

4.303

11

1.410

5.313

14

1.690

7.650

18

2.260

13.600

Gravel backfill will be measured as specified in 

Section 2-09.4

.

Expansion joint system___seal - superstr. will be measured by the linear foot along its 
completed line and slope.

Expansion joint modification will be measured by the linear foot of expansion joint 
modified along its completed line and slope.

Page 6-136 

Concrete Structures

Prestressed concrete girder will be measured by the linear foot of girder specified in the 
Proposal.

Bridge approach slab will be measured by the square yard.

Permeon treatment will be measured by the square yard of concrete surface area 
receiving the treatment.

6-02.5 Payment

Payment will be made for each of the following Bid items that are included in the 
Proposal:

“Conc. Class ____”, per cubic yard.
“Commercial Concrete”, per cubic yard.
All concrete, except in Superstructure when this is covered by a separate Bid item, 
will be paid for at the unit Contract price per cubic yard in place for the various 
classes of concrete. All costs in connection with concrete curing, producing concrete 
surface finish, and furnishing and applying sealer to concrete surfaces as specified, 
shall be included in the unit contract price per cubic yard for “Conc. Class ____”. If 
the concrete is to be paid for other than by class of concrete, then the costs shall be 
included in the associated item of work.
“Superstructure (name bridge)”, lump sum.
All costs in connection with constructing, finishing and removing the bridge deck test 
slab as specified in 

Section 6-02.3(10)D1

 shall be included in the lump sum Contract 

price for “Superstructure___” or “Bridge Deck___” for one bridge in each project, as 
applicable.
All costs in connection with providing holes for vents, for furnishing and installing 
cell drainage pipes for box girder Structures, and furnishing and placing grout and 
shims under steel shoes shall be included in the unit Contract prices for the various 
Bid items involved.
All costs in connection with the construction of weep holes, including the gravel 
backfill for drains surrounding the weep holes except as provided in 

Section 2-09.4

shall be included by the Contractor in the unit Contract price per cubic yard for 
“Conc. Class ____”.
“Lean Concrete”, per cubic yard.
Lean concrete, except when included in another Bid item, will be paid for at the unit 
Contract price per cubic yard.
“St. Reinf. Bar ____”, per pound.

Concrete Structures 

6-02

“Epoxy-Coated St. Reinf. Bar ____”, per pound.
Payment for reinforcing steel shall include the cost of drilling holes in concrete for, 
and setting, steel reinforcing bar dowels with epoxy bonding agent, and furnishing, 
fabricating, placing, and splicing the reinforcement. In Structures of reinforced 
concrete where there are no structural steel Bid items, such minor metal parts as 
expansion joints, bearing assemblies, and bolts will be paid for at the unit Contract 
price for “St. Reinf. Bar ____” unless otherwise specified.
“Gravel Backfill for Foundation Class A”, per cubic yard.
“Gravel Backfill for Foundation Class B”, per cubic yard.
“Gravel Backfill for Wall”, per cubic yard.
“Deficient Strength Conc. Price Adjustment”, by calculation.
“Deficient Strength Conc. Price Adjustment” shall be calculated and paid for as 
described in 

Section 6-02.3(5)L

. For the purpose of providing a common Proposal for 

all Bidders, the Contracting Agency has entered an amount for the item “Deficient 
Strength Conc. Price Adjustment” in the Bid Proposal to become a part of the total 
Bid by the Contractor. The item “Deficient Strength Conc. Price Adjustment” covers 
all applicable classes of concrete.
“Expansion Joint System _____ - Superstr.”, per linear foot.
“Expansion Joint Modification - ___”, per linear foot.
“Prestressed Conc. Girder ___”, per linear foot.
“Bridge Approach Slab”, per square yard.
The unit Contract price per square yard for “Bridge Approach Slab” shall be full pay 
for providing, placing, and compacting the crushed surfacing base course, furnishing 
and placing Class 4000A concrete, and furnishing and installing compression seal, 
anchors, and reinforcing steel.
“Permeon Treatment”, per square yard. 
The unit contract price per square yard for “Permeon Treatment” shall be full pay for 
performing the work as specified.

Page 6-138 

Steel Structures

6-03 

Steel Structures

6-03.1 Description

This Work consists of furnishing, fabricating, erecting, cleaning, and painting steel 
Structures and the structural steel parts of nonsteel Structures

6-03.2 Materials

Materials shall meet the requirements of the following sections:
 

Structural Steel and Related Materials 

9-06

 

Paints and Related Materials 

9-08

 

Grout 

9-20.3

Structural steel shall be classified as:
1.  Structural carbon steel (to be used whenever the Plans do not specify another 

classification),

2.  Structural low alloy steel, and
3.  Structural high-strength steel.

Unless the Plans or Special Provisions state otherwise, the following shall be classified as 
structural carbon steel: shims; ladders; stairways; anchor bolts and sleeves; pipe, fittings, 
and fastenings used in handrails; and other metal parts, even if made of other materials, 
for which payment is not specified.

All AASHTO M270 material used in what the Plans show as main load-carrying tension 
members or as tension components of flexural members shall meet the Charpy V-notch 
requirements of AASHTO M270 temperature zone 2. All AASHTO M270 material used 
in what the Plans show as fracture critical members shall meet the Charpy V-notch 
requirements of AASHTO M270, Fracture Critical Impact Test Requirements, temperature 
zone 2. Charpy V-notch requirements for other steel materials shall be as specified in the 
Plans and Special Provisions.

The Contractor shall submit Type 1 Working Drawings describing the methods for visibly 
marking the material so that it can be traced. These marks shall remain visible at least 
through the fit-up of the main load-carrying tension members. The marking method shall 
permit the Engineer to verify: (1) material Specification designation, (2) heat number, and 
(3) material test reports to meet any special requirements.

For steel in main load-carrying tension members and in tension components of flexural 
members, the Contractor shall include the heat numbers on the reproducible copies of 
the as-built shop plans.

Steel Structures 

6-03

6-03.3 

Construction Requirements

Structural steel fabricators of plate and box girders, floorbeams, truss members, stringers, 
cross frames, diaphragms, and laterals shall be certified under the AISC Certification 
Program for Steel Bridge Fabricators, Advanced Bridges Category. When fracture critical 
members are specified in the Contract, structural steel fabricators shall also meet the 
supplemental requirements F, Fracture Critical, under the AISC Quality Certification 
Program for Steel Bridge Fabricators.

6-03.3(1) Vacant

6-03.3(2)  Facilities for Inspection

The Contractor shall provide all facilities the Inspector requires to inspect material and 
workmanship. Inspectors shall be given safe and free access to all areas in the mill and 
shop.

6-03.3(3)  Inspector’s Authority

The Inspector may reject materials or workmanship that does not comply with these 
Specifications. In any dispute, the Contractor may appeal to the Engineer whose decision 
shall be final.

By its inspection at the mill and shop, the Contracting Agency intends only to facilitate 
the Work and prevent errors. This inspection shall not relieve the Contractor of any 
responsibility for identifying and replacing defective material or workmanship.

6-03.3(4) Rejections

Even if the Inspector accepts materials or finished members, the Contracting Agency may 
later reject them if defective. The Contractor shall promptly replace or make good any 
rejected materials or workmanship.

6-03.3(5)  Mill Orders and Shipping Statements

The Contractor shall furnish as many copies of mill orders and shipping statements as the 
Engineer requires.

6-03.3(6) Weighing

Structural steel need not be weighed unless the Plans or Special Provisions require 
it. When a weight is required, it may either be calculated or obtained by scales. The 
Contractor shall furnish as many copies of the calculations or weight slips as the Engineer 
requires. If scale weights are used, the Contractor shall record separately the weights of 
all tools, erection material, and dunnage.

 

 

 

 

 

 

 

Content      ..     63      64      65      66     ..