Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 61

 

  Главная      Manuals     Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     59      60      61      62     ..

 

 

 

Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 61

 

 

Hot Mix Asphalt 

5-04

5-04.3(10)B 

HMA Compaction – Cyclic Density

Low cyclic density areas are defined as spots or streaks in the pavement that are less 
than 90 percent of the theoretical maximum density. At the Engineer’s discretion, the 
Engineer may evaluate the HMA pavement for low cyclic density, and when doing so will 
follow 

WSDOT SOP 733

A $500 Cyclic Density Price Adjustment will be assessed for any 

500-foot section with two or more density readings below 90 percent of the theoretical 
maximum density.

5-04.3(10)C 

HMA Compaction Acceptance – Statistical Evaluation

HMA compaction which is accepted by Statistical Evaluation will be based on acceptance 
testing performed by the Contracting Agency, and statistical analysis of those acceptance 
tests results. This will result in a Compaction Price Adjustment.

5-04.3(10)C1  HMA Compaction Statistical Evaluation – Lots and Sublots

HMA compaction which is accepted by Statistical Evaluation will be evaluated by the 
Contracting Agency dividing the project into compaction lots, and each compaction lot 
will be evaluated using stratified random sampling by the Contracting Agency sub-dividing 
each compaction lot into compaction sublots. All mixture in any individual compaction lot 
shall be of the same mix design. The compaction sublots will be numbered in the order in 
which the mixture (of a particular mix design) is paved.

Each compaction lot comprises a maximum of 15 compaction sublots, except for the 
final compaction lot of each mix design on the Contract, which comprises a maximum of 
25 sublots.

Each compaction sublot shall be uniform in size as shown in 

Table 15

, except that the 

last compaction sublot of each day may be increased to a maximum of two times the 
compaction sublot quantity calculated. Minor variations in the size of any sublot shall not 
be cause to invalidate the associated test result.

Table 15 

HMA Compaction Sublot Size

HMA Original Plan Quantity (tons)

1

Compaction Sublot Size (tons)

<20,000

100

20,000 to 30,000

150

>30,000

200

1

In determining the plan quantity tonnage, do not include any tons accepted by test 

point evaluation.

Page 5-50 

Hot Mix Asphalt

The following will cause one compaction lot to end prematurely and a new compaction lot 
to begin:

• 

For a compaction lot in progress with a compaction CPF less than 0.75 using an LSL 

= 91.5, a new compaction lot will begin at the Contractor’s request after the Engineer 

is satisfied that material conforming to the Specifications can be produced. See also 

Section 5-04.3(11)F

.

All HMA which is paved on a bridge and accepted for compaction by Statistical Evaluation 
will compose a bridge compaction lot. If the contract includes such HMA on more than 
one bridge, compaction will be evaluated on each bridge individually, as separate bridge 
compaction lots.

Bridge compaction sublots will be determined by the Engineer subject to the following:

• 

All sublots on a given bridge will be approximately the same size.

• 

Sublots will be stratified from the lot.

• 

In no case will there be less than 3 sublots in each bridge compaction lot.

• 

No sublot will exceed 50 tons.

• 

Compaction test locations will be determined by the Engineer in accordance with 

WSDOT Test Method 

T 716

.

5-04.3(10)C2  HMA Compaction Statistical Evaluation – Acceptance 

Testing

Comply with 

Section 1-06.2(1)

.

The location of HMA compaction acceptance tests will be randomly selected by the 
Contracting Agency from within each sublot, with one test per sublot. The Contracting 
Agency will determine the random sample location using WSDOT Test Method 

T 716

.

Use 

Table 16

 to determine compaction acceptance test procedures and to allocate 

compaction acceptance sampling and testing responsibilities between the Contractor and 
the Contracting Agency. HMA cores shall be taken or nuclear density testing shall occur 
after completion of the finish rolling, prior to opening to traffic, and on the same day that 
the mix is placed.

Hot Mix Asphalt 

5-04

Table 16 

HMA Compaction Acceptance Testing Procedures and Responsibilities

When Contract Includes 

Bid Item “HMA Core – 

Roadway” or “HMA Core 

– Bridge”

4

When Contract Does Not Include Bid Item “HMA 

Core – Roadway” or “HMA Core – Bridge”

4

Basis for Test:

Cores

Cores

3

Nuclear Density Gauge

3

In-Place 

Density 

Determined by:

Contractor shall take 

cores

1

 using WSDOT 

SOP 

734

2

 

Contracting Agency will 

determine core density 

using FOP for AASHTO 

T 166

Contracting Agency will 

take cores

1

 using WSDOT 

SOP 734

 

Contracting Agency will 

determine core density 

using FOP for AASHTO 

T 166

Contracting Agency, using 

FOP for AASHTO T 355

Theoretical 

Maximum 

Density 

Determined by:

Contracting Agency, using FOP for AASHTO T 209

Rolling Average 

of Theoretical 

Maximum 

Densities 

Determined by:

Contracting Agency, using WSDOT 

SOP 729

Percent 

Compaction 

in Each Sublot 

Determined by:

Contracting Agency, 

using WSDOT 

SOP 736

Contracting Agency, 

using WSDOT 

SOP 736

Contracting Agency, 

using FOP for AASHTO 

T 355

The core diameter shall be 4-inches unless otherwise approved by the Engineer.

The Contractor shall take the core samples in the presence of the Engineer, at locations designated by the 

Engineer, and deliver the core samples to the Contracting Agency.

The Contracting Agency will determine, in its sole discretion, whether it will take cores or use the nuclear 

density gauge to determine in-place density. Exclusive reliance on cores for density acceptance is generally 
intended for small paving projects and is not intended as a replacement for nuclear gauge density testing on 
typical projects.

The basis for test of all compaction sublots in a bridge compaction lot shall be cores. These cores shall be 

taken by the Contractor when the Proposal includes the bid item “HMA Cores – Bridge”. When there is no 
bid item for “HMA Cores – Bridge”, the Engineer will be responsible for taking HMA cores for all compaction 
sublots in a bridge compaction lot. In either case, the Engineer will determine core location, in-place density 
of the core, theoretical maximum density, rolling average of theoretical maximum density, and percent 
compaction using the procedure called for in this section.

When using the nuclear density gauge for acceptance testing of pavement density, the 
Engineer will follow WSDOT 

SOP 730

 for correlating the nuclear gauge with HMA cores. 

When cores are required for the correlation, coring and testing will be by the Contracting 
Agency. When a core is taken for gauge correlation at the location of a sublot, the relative 
density of the core will be used for the sublot test result and is exempt from retesting.

Page 5-52 

Hot Mix Asphalt

5-04.3(10)C3  HMA Statistical Compaction – Price Adjustments

For each HMA compaction lot (that is accepted by Statistical Evaluation) which has 
less than three compaction sublots, for which all compaction sublots attain a minimum 
of 91 percent compaction determined in accordance with FOP for AASHTO T 355 (or 
WSDOT 

SOP 736

 when provided by the Contract), the HMA will be accepted at the unit 

Contract price with no further evaluation.

For each HMA compaction lot (that is accepted by Statistical Evaluation) which does 
not meet the criteria in the preceding paragraph, the compaction lot shall be evaluated 
in accordance with 

Section 1-06.2(2)D5

 to determine the appropriate Composite Pay 

Factor (CPF). All of the test results obtained from the acceptance samples from a given 
compaction lot shall be evaluated collectively. Additional testing by either a nuclear 
density gauge or cores will be completed as required to provide a minimum of three tests 
for evaluation.

Determine the Compaction Price Adjustment (CPA) from the table below, selecting the 
equation for CPA that corresponds to the value of CPF determined above.

Calculating HMA Compaction Price Adjustment (CPA)

Value of CPF

Equation for Calculating CPA

When CPF > 1.00

CPA = [1.00 × (CPF – 1.00)] × Q × UP

When CPF = 1.00

CPA = $0

When CPF < 1.0

CPA = [0.60 × (CPF – 1.00)] × Q × UP

Where

CPA  =  Compaction Price Adjustment for the compaction lot ($)

CPF  =  Composite Pay Factor for the compaction lot (maximum is 1.05)

=  Quantity in the compaction lot (tons)

UP 

=  Unit price of the HMA in the compaction lot ($/ton)

5-04.3(10)C4  HMA Statistical Compaction – Requests for Retesting

For a compaction sublot that has been tested with a nuclear density gauge that did not 
meet the minimum of 91.5 percent of the theoretical maximum density in a compaction 
lot with a CPF below 1.00 and thus subject to a price reduction or rejection, the 
Contractor may request that a core, taken at the same location as the nuclear density 
test, be used for determination of the relative density of the compaction sublot. The 
relative density of the core will replace the relative density determined by the nuclear 
density gauge for the compaction sublot and will be used for calculation of the CPF and 
acceptance of HMA compaction lot. When cores are taken by the Contracting Agency 
at the request of the Contractor, they shall be requested by noon of the next workday 
after the test results for the compaction sublot have been provided or made available to 
the Contractor. Traffic control shall be provided by the Contractor as requested by the 
Engineer. Failure by the Contractor to provide the requested traffic control will result in 
forfeiture of the request for retesting. When the CPF for the compaction lot based on the 
results of the cores is less than 1.00, the Contracting Agency will deduct the cost for the 
coring from any monies due or that may become due the Contractor under the Contract 
at the rate of $200 per core and the Contractor shall pay for the cost of the traffic control.

Hot Mix Asphalt 

5-04

5-04.3(10)D  HMA Compaction – Visual Evaluation

Visual Evaluation will be the basis of acceptance for compaction of the Bid items “HMA 
for Pavement Repair Cl. ___ PG ___” and “HMA for Prelevelling Class___ PG___”. This HMA 
shall be thoroughly compacted to the satisfaction of the Engineer. HMA that is used to 
prelevel wheel ruts shall be compacted with a pneumatic tire roller.

5-04.3(10)E 

HMA Compaction – Test Point Evaluation

When compaction acceptance is by Test Point Evaluation, compact HMA based on 
a test point evaluation of the compaction train. Perform the test point evaluation in 
accordance with instructions from the Engineer. The number of passes with an approved 
compaction train, required to attain the maximum test point density, shall be used on all 
subsequent paving.

5-04.3(10)F 

HMA Compaction Acceptance – Notification of Acceptance 

Test Results

The obligations and responsibilities for notifying the Contractor of compaction 
acceptance test results are the same as for mixture acceptance test results. See 

Section 5-04.3(9)E

.

5-04.3(11)  Reject Work

This section applies to HMA and all requirements related to HMA (except aggregates prior 
to being incorporated into HMA). For rejection of aggregate prior to its incorporation into 
HMA refer to 

Section 3-04

.

5-04.3(11)A 

Reject Work – General

Work that is defective or does not conform to Contract requirements shall be rejected. 
The Contractor may propose, in writing, alternatives to removal and replacement of 
rejected material. Acceptability of such alternative proposals will be determined at the 
sole discretion of the Engineer.

5-04.3(11)B 

Rejection by Contractor

The Contractor may, prior to acceptance sampling and testing, elect to remove any 
defective material and replace it with new material. Any such new material will be 
sampled, tested, and evaluated for acceptance.

5-04.3(11)C 

Rejection Without Testing (Mixture or Compaction)

The Engineer may, without sampling, reject any batch, load, or section of Roadway that 
appears defective. Material rejected before placement shall not be incorporated into 
the pavement.

No payment will be made for the rejected materials or the removal of the materials unless 
the Contractor requests the rejected material to be tested. If the Contractor requests 
testing, acceptance will be by Statistical Evaluation, and a minimum of three samples 
will be obtained and tested. When uncompacted material is required for testing but 

Page 5-54 

Hot Mix Asphalt

not available, the Engineer will determine random sample locations on the roadway in 
accordance with WSDOT Test Method 

T 716

, take cores in accordance with WSDOT 

SOP 734

, and test the cores in accordance with WSDOT 

SOP 737

.

If the CPF for the rejected material is less than 0.75, no payment will be made for the 
rejected material; in addition, the cost of sampling and testing shall be borne by the 
Contractor. If the CPF is greater than or equal to 0.75, the cost of sampling and testing 
will be borne by the Contracting Agency. If the material is rejected before placement 
and the CPF is greater than or equal to 0.75, compensation for the rejected material 
will be at a CPF of 0.75. If rejection occurs after placement and the CPF is greater than 
or equal to 0.75, compensation for the rejected material will be at the calculated CPF 
with an addition of 25 percent of the unit Contract price added for the cost of removal 
and disposal.

5-04.3(11)D  Rejection – A Partial Sublot (Mixture or Compaction)

In addition to the random acceptance sampling and testing, the Engineer may also isolate 
from a mixture or compaction sublot any material that is suspected of being defective 
in relative density, gradation or asphalt binder content. Such isolated material will not 
include an original sample location. The Contracting Agency will obtain a minimum 
of three random samples of the suspect material and perform the testing. When 
uncompacted material is required for testing but is not available, the Engineer will select 
random sample locations on the roadway in accordance with WSDOT Test Method 

T 716

, take cores samples in accordance with WSDOT 

SOP 734

, and test the material in 

accordance with WSDOT 

SOP 737

The material will then be statistically evaluated as an 

independent lot in accordance with 

Section 1-06.2(2)

.

5-04.3(11)E 

Rejection – An Entire Sublot (Mixture or Compaction)

An entire mixture or compaction sublot that is suspected of being defective may be 
rejected. When this occurs, a minimum of two additional random samples from this sublot 
will be obtained. When uncompacted material is required for the additional samples but 
the material has been compacted, the Contracting Agency will take and test cores from 
the roadway as described in 

Section 5-04.3(11)D

The additional samples and the original 

sublot will be evaluated as an independent lot in accordance with 

Section 1-06.2(2)

.

5-04.3(11)F 

Rejection - A Lot in Progress (Mixture or Compaction)

The Contractor shall shut down operations and shall not resume HMA placement until 
such time as the Engineer is satisfied that material conforming to the Specifications can 
be produced when:
1.  the Composite Pay Factor (CPF) of a mixture or compaction lot in progress drops 

below 1.00 and the Contractor is taking no corrective action, or

2.  the Pay Factor (PF

i

) for any constituent of a mixture or compaction lot in progress 

drops below 0.95 and the Contractor is taking no corrective action, or

3.  either the PF

i

 for any constituent (or the CPF) of a mixture or compaction lot in 

progress is less than 0.75.

Hot Mix Asphalt 

5-04

5-04.3(11)G  Rejection – An Entire Lot (Mixture or Compaction)

An entire lot with a CPF of less than 0.75 will be rejected.

5-04.3(12) Joints

5-04.3(12)A 

HMA Joints

5-04.3(12)A1  Transverse Joints

Conduct operations such that the placement of the top or wearing course is a continuous 
operation or as close to continuous as possible. Unscheduled transverse joints will be 
allowed, but the roller may pass over the unprotected end of the freshly laid HMA only 
when the placement of the course is discontinued for such a length of time that the 
HMA will cool below compaction temperature. When the Work is resumed, cut back the 
previously compacted HMA to produce a slightly beveled edge for the full thickness of 
the course.

Construct a temporary wedge of HMA on a 50H:1V where a transverse joint as a result 
of paving or planing is open to traffic. Separate the HMA in the temporary wedge from 
the permanent HMA upon which it is placed by strips of heavy wrapping paper or other 
methods approved by the Engineer. Remove the wrapping paper and trim the joint to a 
slightly beveled edge for the full thickness of the course prior to resumption of paving.

Waste the material that is cut away and place new HMA against the cut. Use rollers or 
tamping irons to seal the joint.

5-04.3(12)A2  Longitudinal Joints

Offset the longitudinal joint in any one course from the course immediately below by 
not more than 6 inches nor less than 2 inches. Locate all longitudinal joints constructed 
in the wearing course at a lane line or an edge line of the Traveled Way. Construct a 
notched wedge joint along all longitudinal joints in the wearing surface of new HMA 
unless otherwise approved by the Engineer. The notched wedge joint shall have a vertical 
edge of not less than the maximum aggregate size nor more than ½ of the compacted lift 
thickness, and then taper down on a slope not steeper than 4H:1V. Uniformly compact 
the sloped portion of the HMA notched wedge joint.

On one-lane ramps a longitudinal joint may be constructed at the center of the traffic 
lane, subject to approval by the Engineer, if:
1.  The ramp must remain open to traffic, or
2.  The ramp is closed to traffic and a hot-lap joint is constructed.

a.  Two paving machines shall be used to construct the hot-lap joint.
b.  The pavement within 6 inches of the hot-lap joint will not be excluded from 

random location selection for compaction testing.

c.  Construction equipment other than rollers shall not operate on any 

uncompacted HMA.

Page 5-56 

Hot Mix Asphalt

When HMA is placed adjacent to cement concrete pavement, construct longitudinal joints 
between the HMA and the cement concrete pavement. Saw the joint to the dimensions 
shown on Standard Plan A-40.10 and fill with joint sealant meeting the requirements of 

Section 9-04.2

.

5-04.3(12)B 

Bridge Paving Joint Seals

5-04.3(12)B1  HMA Sawcut and Seal

Prior to placing HMA on the bridge deck, establish sawcut alignment points at both 
ends of the bridge paving joint seals to be placed at the bridge ends, and at interior 
joints within the bridge deck when and where shown in the Plans. Establish the sawcut 
alignment points in a manner that they remain functional for use in aligning the sawcut 
after placing the HMA overlay.

Submit a Type 1 Working Drawing consisting of the sealant manufacturer’s application 
procedure.

Construct the bridge paving joint seal as specified in the Plans and in accordance 
with the detail shown in the Standard Plans. Construct the sawcut in accordance with 

Section 5-05.3(8)

Apply the sealant in accordance wit

Section 5-05.3(8)B

 and the 

manufacturer’s application procedure.

5-04.3(12)B2  Paved Panel Joint Seal

Construct the paved panel joint seal in accordance with the requirements specified in 

Section 5-04.3(12)B1

 and the following requirement:

1.  Clean and seal the existing joint between concrete panels in accordance with 

Section 

5-01.3(8)

 and the details shown in the Standard Plans.

5-04.3(13)  Surface Smoothness

The completed surface of all courses shall be of uniform texture, smooth, uniform as to 
crown and grade, and free from defects of all kinds. The completed surface of the wearing 
course shall not vary more than ⅛ inch from the lower edge of a 10-foot straightedge 
placed on the surface parallel to the centerline. The transverse slope of the completed 
surface of the wearing course shall vary not more than ¼ inch in 10 feet from the rate of 
transverse slope shown in the Plans.

When deviations in excess of the above tolerances are found that result from a high place 
in the HMA, correct the pavement surface by one of the following methods:
1.  Remove material from high places by grinding with an approved grinding machine, or
2.  Remove and replace the wearing course of HMA, or
3.  By other method approved by the Engineer.

Correct defects until there are no deviations anywhere greater than the allowable 
tolerances.

Hot Mix Asphalt 

5-04

Deviations in excess of the above tolerances that result from a low place in the HMA 
and deviations resulting from a high place where corrective action, in the opinion of the 
Engineer, will not produce satisfactory results will be accepted with a price adjustment. 
The Engineer shall deduct from monies due or that may become due to the Contractor 
the sum of $500.00 for each and every section of single traffic lane 100 feet in length in 
which any excessive deviations described above are found.

When concrete pavement is to be placed on HMA, the surface tolerance of the HMA 
shall be such that no surface elevation lies above the Plan grade minus the specified 
Plan depth of concrete pavement. Prior to placing the concrete pavement, bring any 
such irregularities to the required tolerance by grinding or other means allowed by the 
Engineer.

When utility appurtenances such as manhole covers and valve boxes are located in the 
Traveled Way, pave the Roadway before the utility appurtenances are adjusted to the 
finished grade.

5-04.3(14)  Planing Bituminous Pavement

Plane in such a manner that the underlying pavement is not torn, broken, or otherwise 
damaged by the planing operation. Delamination or raveling of the underlying pavement 
will not be construed as damage due to the Contractor’s operations. Pavement outside 
the limits shown in the Plans or designated by the Engineer that is damaged by the 
Contractor’s operations shall be repaired to the satisfaction of the Engineer at no 
additional cost to the Contracting Agency.

For mainline planing operations, use equipment with automatic controls and with sensors 
for either or both sides of the equipment. The controls shall be capable of sensing the 
grade from an outside reference line, or a mat-referencing device. The automatic controls 
shall have a transverse slope controller capable of maintaining the mandrel at the desired 
transverse slope (expressed as a percentage) within plus or minus 0.1 percent.

Remove all loose debris from the planed surface before opening the planed surface to 
traffic. The planings and other debris resulting from the planing operation shall become 
the property of the Contractor and be disposed of in accordance with 

Section 2-03.3(7)C

or as otherwise allowed by the Contract.

5-04.3(15)  Sealing Pavement Surfaces

Apply a fog seal where shown in the Plans. Construct the fog seal in accordance with 

Section 5-02.3

. Unless otherwise approved by the Engineer, apply the fog seal prior to 

opening to traffic.

5-04.3(16)  HMA Road Approaches

Construct HMA approaches at the locations shown in the Plans or where staked by the 
Engineer, in accordance with 

Section 5-04

.

Page 5-58 

Hot Mix Asphalt

5-04.4 Measurement

HMA Cl. ___ PG ___, HMA for ___ Cl. ___ PG ___, and Commercial HMA will be measured 
by the ton in accordance with 

Section 1-09.2

with no deduction being made for the 

weight of asphalt binder, mineral filler, or any other component of the HMA. If the 
Contractor elects to remove and replace HMA as allowed by 

Section 5-04.3(11)

, the 

material removed will not be measured.
Roadway cores will be measured per each for the number of cores taken.
Crack Sealing-LF will be measured by the linear foot along the line of the crack.
Soil residual herbicide will be measured by the mile for the stated width to the nearest 
0.01 mile or by the square yard, whichever is designated in the Proposal.
Pavement repair excavation will be measured by the square yard of surface marked prior 
to excavation.
Asphalt for fog seal will be measured by the ton, as provided in 

Section 5-02.4

.

Longitudinal joint seals between the HMA and cement concrete pavement will be 
measured by the linear foot along the line and slope of the completed joint seal.
HMA sawcut and seal, and paved panel joint seal, will be measured by the linear foot 
along the line and slope of the completed joint seal.

Planing bituminous pavement will be measured by the square yard.
Temporary pavement marking will be measured by the linear foot as provided in 

Section 8-23.4

.

Water will be measured by the M gallon as provided in 

Section 2-07.4

.

5-04.5 Payment

Payment will be made for each of the following Bid items that are included in the 
Proposal:

“HMA Cl. ___ PG ___”, per ton. 
“HMA for Approach Cl. ___ PG ___”, per ton.
“HMA for Preleveling Cl. ___ PG ___”, per ton.
“HMA for Pavement Repair Cl. ___ PG ___”, per ton.
“Commercial HMA”, per ton.
The unit Contract price per ton for “HMA Cl. ___ PG ___”, “HMA for Approach Cl. ___ 
PG ___”, “HMA for Preleveling Cl. ___ PG ___”, “HMA for Pavement Repair Cl. ___ PG 
___”, and “Commercial HMA” shall be full compensation for all costs, including anti-
stripping additive, incurred to carry out the requirements of 

Section 5-04

 except for 

those costs included in other items which are included in this Subsection and which 
are included in the Proposal.
“Crack Sealing-FA”, by force account.

Hot Mix Asphalt 

5-04

“Crack Sealing-FA” will be paid for by force account as specified in 

Section 1-09.6

For the purpose of providing a common Proposal for all Bidders, the Contracting 
Agency has entered an amount in the Proposal to become a part of the total Bid by 
the Contractor.
“Crack Sealing-LF”, per linear foot.
The unit Contract price per linear foot for “Crack Sealing-LF” shall be full payment 
for all costs incurred to perform the Work described in 

Section 5-04.3(4)A

.

“Soil Residual Herbicide ____ ft. Wide”, per mile, or
“Soil Residual Herbicide”, per square yard.
The unit Contract price per mile or per square yard for “Soil Residual Herbicide” 
shall be full payment for all costs incurred to obtain, provide and install herbicide in 
accordance with 

Section 5-04.3(4)B

.

“Pavement Repair Excavation Incl. Haul”, per square yard.
The unit Contract price per square yard for “Pavement Repair Excavation Incl. Haul” 
shall be full payment for all costs incurred to perform the Work described in 

Section 

5-04.3(4)C

 with the exception, however, that all costs involved in the placement of 

HMA shall be included in the unit Contract price per ton for “HMA for Pavement 
Repair Cl. ___ PG ___”, per ton.
“Asphalt for Fog Seal”, per ton.
Payment for “Asphalt for Fog Seal” is described in 

Section 5-02.5

.

“Longitudinal Joint Seal”, per linear foot.
The unit Contract price per linear foot for “Longitudinal Joint Seal” shall be full 
payment for all costs incurred to construct the longitudinal joint between HMA and 
cement concrete pavement, as described in 

Section 5-04.3(12)B

.

“HMA Sawcut And Seal”, per linear foot.
The unit Contract price per linear foot for “HMA Sawcut And Seal” shall 
be full payment for all costs incurred to perform the Work described in 

Section 5-04.3(12)B1

.

“Paved Panel Joint Seal”, per linear foot.
The unit Contract price per linear foot for “Paved Panel Joint Seal” shall  
be full payment for all costs incurred to perform the Work described in 

Section 5-04.3(12)B2

.

“Planing Bituminous Pavement”, per square yard.
The unit Contract price per square yard for “Planing Bituminous Pavement”  
shall be full payment for all costs incurred to perform the Work described  
in 

Section 5-04.3(14)

.

“Temporary Pavement Marking”, per linear foot.
Payment for “Temporary Pavement Marking” is described in 

Section 8-23.5

.

Page 5-60 

Hot Mix Asphalt

“Water”, per M gallon.
Payment for “Water” is described in 

Section 2-07.5

.

“Job Mix Compliance Price Adjustment”, by calculation.
“Job Mix Compliance Price Adjustment” will be calculated and paid for as described 
in 

Section 5-04.3(9)B6

 and 

5-04.3(9)D1

.

“Compaction Price Adjustment”, by calculation.
“Compaction Price Adjustment” will be calculated and paid for as described in 

Section 5-04.3(10)C3

.

“HMA Core – Bridge”, per each. 
The unit Contract price per each for “HMA Core – Bridge” shall be full payment 
for all costs, including traffic control, associated with taking HMA density cores in 
pavement that is on a bridge deck.
“HMA Core – Roadway”, per each.
The unit Contract price per each for “HMA Core – Roadway” shall be full payment 
for all costs, including traffic control, associated with taking HMA density cores in 
pavement that is not on a bridge deck.
“Cyclic Density Price Adjustment”, by calculation.
“Cyclic Density Price Adjustment” will be calculated and paid for as described in 

Section 5-04.3(10)B

.

Cement Concrete Pavement 

5-05

5-05 

Cement Concrete Pavement

5-05.1 Description

This Work shall consist of constructing a pavement composed of cement concrete on a 
prepared Subgrade or base in accordance with these Specifications and in conformity with 
the lines, grades, thicknesses, and typical cross-sections shown in the Plans or established 
by the Engineer.

5-05.2 Materials

Materials shall meet the requirements of the following sections: 
 Cement 

9-01

 

Fine Aggregate 

9-03

 

Coarse Aggregate 

9-03

 

Combined Aggregate 

9-03

 

Joint Filler 

9-04.1

 

Joint Sealants 

9-04.2

 

Corrosion Resistant Dowel Bars 

9-07.5(2)

 

Tie Bars 

9-07.6

 

Concrete Patching Material 

9-20.

1

 

Curing Materials and Admixtures 

9-23

 

Water 

9-25

 

Epoxy Resins 

9-26

Cementitious materials are considered to be the following: portland cement, blended 
hydraulic cement, fly ash, ground granulated blast furnace slag, and microsilica fume.

5-05.3 

Construction Requirements

5-05.3(1)  Concrete Mix Design for Paving

The Contractor shall provide a concrete mix design for each design of concrete specified 
in the Contract. The Contractor shall use ACI 211.1 as a guide to determine proportions. 
Concrete strength, placement, and workability shall be the responsibility of the 
Contractor. Following approval of the Contractor’s proposal, all other requirements of 

Section 5-05

 shall apply.

1.  Materials – Materials shall conform to 

Section 5-05.2

. Fine aggregate shall conform 

to 

Section 9-03.1(2)

, Class 1. Coarse aggregate shall conform t

Section 9-03.1(4)

AASHTO grading No. 467. An alternate combined gradation conforming to 

Section 

9-03.1(5)

 may be proposed, that has a nominal maximum aggregate size equal to or 

greater than a 1½-inch sieve.

 

Fly ash, if used, shall not exceed 35 percent by weight of the total cementitious 
material, shall conform t

Section 9-23.9

 and shall be limited to Class F with a 

maximum CaO content of 15 percent by weight.

Page 5-62 

Cement Concrete Pavement

 

Ground granulated blast furnace slag, if used, shall not exceed 30 percent by weight 
of the total cementitious material and shall conform to 

Section 9-23.10

. When both 

ground granulated blast furnace slag and fly ash are included in the concrete mix, 
the total weight of both these materials is limited to 35 percent by weight of the 
total cementitious material. As an alternative to the use of fly ash, ground granulated 
blast furnace slag and cement as separate components, a blended hydraulic cement 
that meets the requirements of 

Section 9-01.2(1)B

 Blended Hydraulic Cements may 

be used.

 

The water/cement ratio shall be calculated on the total weight of cementitious 
material. Cementitious materials are those listed in 

Section 5-05.2

. The minimum 

cementitious material for any mix design shall be 564 pounds per cubic yard.

2.  Submittals – The Contractor’s submittal shall include the mix proportions per 

cubic yard, test results from beams and cylinders, and the proposed sources for all 
ingredients including the fly ash. The mix shall be capable of providing a minimum 
flexural strength of 650 psi at 14 days. Evaluation of strength shall be based on 
statistically analyzed results of five beam specimens made according to WSDOT 

T 808

 and tested according to WSDOT 

T 802

 that demonstrate a quality level of 

not less than 80 percent analyzed in accordance with 

Section 1-06.2(2)D

. In addition 

the Contractor shall fabricate, cure, and test five sets of cylinders, for evaluation of 
28-day strengths, according to FOP for AASHTO T 22 and FOP for AASHTO T 23 
using the same mix design as used in fabrication of the beams.

 

Mix designs submitted by the Contractor shall provide a unique identification 
for each proposal and shall include test data confirming that concrete made 
in accordance with the proposed design will meet the requirements of these 
Specifications and the 28-day compressive strength result. Test data shall be from 
an independent testing lab or from a commercial concrete producer’s lab. If the test 
data is developed at a producer’s lab, the Engineer or a representative may witness 
all testing.

3.  Mix Design Modifications – The Contractor may initiate adjustments to the 

aggregate proportions of the approved mix design. An adjustment in both the fine 
and coarse aggregate batch target weights of plus or minus 200 pounds per cubic 
yard will be allowed without resubmittal of the mix design. The adjusted aggregate 
weights shall become the new batch target weights for the mix design.

4.  Conformance to Mix Design – Cement and coarse and fine aggregate weights shall 

be within the following tolerances of the batch target weights of the mix design:

Concrete Batch Weights

Cement

+5%

-1%

Coarse Aggregate

+ 2%

- 2%

Fine Aggregate

+ 2%

- 2%

 

If the total cementitious material weight is made up of different components, these 
component weights shall be within the following tolerances:

Cement Concrete Pavement 

5-05

a.  Cement weight plus 5 percent or minus 1 percent of that specified in the mix 

design.

b.  Fly ash and ground granulated blast furnace slag weight plus or minus 5 percent 

of that specified in the mix design.

c.  Microsilica weight plus or minus 10 percent of that specified in the mix design.
 

Water shall not exceed the maximum water specified in the mix design.

 

The Contractor may initiate minor adjustments to the approved mix proportions 
within the tolerances noted above without resubmitting the mix design.

The Contractor shall notify the Engineer in writing of any proposed modification. A new 
mix design will designate a new lot.

5-05.3(2) Consistency

The materials shall be mixed with sufficient water to produce a stiff concrete which will 
hold its shape when deposited upon the Subgrade. Concrete placed during wet weather 
must be mixed with sufficient water to produce a very stiff mixture. The consistency 
shall be such that separation of the mortar from the coarse aggregate will not occur in 
handling.

The water/cementitious material ratio, by weight, shall not exceed 0.44. When slip-form 
paving equipment is used, the Contractor shall further control concrete consistency to 
ensure that edge slump conforms to the requirements of 

Section 5-05.3(11)

.

5-05.3(3) Equipment

Equipment necessary for handling materials and performing all parts of the Work shall 
conform to the following requirements:

5-05.3(3)A 

Batching Plant and Equipment

1.  General – The batching plant shall include bins, weighing hoppers, and scales for the 

fine aggregate and for each size of coarse aggregate. If cement is used in bulk, a bin, 
hopper, and separate scale for cement shall be included. The weighing hoppers shall 
be properly sealed and vented to preclude dusting during operation. The batching 
plant shall be equipped with a suitable batch counter that cannot be reset, which will 
correctly indicate the number of batches proportioned.

2.  Bins and Hoppers – Bins with adequate separate compartments for fine aggregate 

and for each size of the coarse aggregate shall be provided in the batching plant.

5-05.3(3)B 

Mixing Equipment

1.  General – Concrete may be mixed at a batching plant or wholly or in part in truck 

mixers. Each mixer shall have attached in a prominent place a manufacturer’s plate 
showing the capacity of the drum in terms of volume of mixed concrete and the 
speed of rotation of the mixing drum or blades.

Page 5-64 

Cement Concrete Pavement

2.  Batching Plant – Mixing shall be in an approved mixer capable of combining the 

aggregates, cement, and water into a thoroughly mixed and uniform weight within 
the specified mixing period.

 

Mixers shall be cleaned at suitable intervals. The pickup and throw-over blades in the 
drum shall be repaired or replaced when they are worn down ¾ inch or more. The 
Contractor shall have available at the jobsite a copy of the manufacturer’s design, 
showing dimensions and arrangements of the blades in reference to original height 
and depth, or provide permanent marks on blades to show points of ¾ inch wear 
from new conditions. Drilled holes ¼ inch in diameter near each end and at midpoint 
of each blade are recommended.

3.  Truck Mixers and Truck Agitators – Truck mixers used for mixing and hauling 

concrete, and truck agitators used for hauling plant-mixed concrete, shall conform to 
the requirements of 

Section 6-02.3(4)A

.

4.  Nonagitator Trucks – Bodies of nonagitating hauling equipment for concrete shall 

be smooth, mortar-tight, metal containers and shall be capable of discharging the 
concrete at a satisfactory controlled rate without segregation. Covers shall be 
provided when needed for protection. Plant-mixed concrete may be transported 
in nonagitated vehicles provided that concrete is in a workable condition when 
placed and:
a.  discharge is completed within 45 minutes after the introduction of mixing water 

to the cement and aggregates, or

b.  discharge is completed within 60 minutes after the introduction of mixing water 

to the cement and aggregates, provided the concrete mix temperature is 70°F 
or below during placement, or

c.  discharge is completed within 60 minutes after the introduction of mixing 

water to the cement and aggregates, provided the mix contains an approved set 
retarder at the manufacturer’s minimum dosage rate.

5-05.3(3)C 

Finishing Equipment

The standard method of constructing concrete pavement on State Highways shall be 
with approved slip-form paving equipment designed to spread, consolidate, screed, 
and float-finish the freshly placed concrete in one complete pass of the machine so a 
dense and homogeneous pavement is achieved with a minimum of hand finishing. On 
other roads and on WSDOT projects requiring less than 1,000 square yards of cement 
concrete pavement or requiring individual placement areas of less than 1,000 square 
yards, irregular areas, intersections, and at locations inaccessible to slip-form paving 
equipment, cement concrete pavement may be placed with approved placement and 
finishing equipment utilizing stationary side forms. Hand screeding and float finishing 
of cement concrete pavement may only be utilized on small irregular areas as allowed 
by the Engineer.

 

 

 

 

 

 

 

Content      ..     59      60      61      62     ..